Construction Cost Estimating
Construction Cost Estimating
Construction Cost Estimating
Duroja BSCE 4B
October 07, 2022
6. What are the three (3) primary categories of classifying estimates? Give details
- The three primary categories of classifying estimates are:
Design Estimates: These estimates, prepared during a project’s pre-design and design
phases, start with an order of magnitude estimate, or screening estimate, which
determines which construction methods and types are most feasible. Next comes the
preliminary estimate, or conceptual estimate, which you base on the schematic design.
Then comes the detailed estimate, or definitive estimate, which you base on design
development. The last of the design estimates is the engineer’s estimate, which you base
on the construction documents. A simple template can help give an initial assessment of
costs involved in a project.
Bid Estimates: Contractors prepare bid estimates when bidding to construct the project.
Contractors will draw from a number of data points to prepare their estimates, including
direct costs, supervision costs, subcontractor quotes, and quantity take-offs. (We’ll look
at these in more detail shortly.)
Control Estimates: Prepared after one signs a contractor agreement and before
construction gets under way, the control estimate functions as a baseline by which you
assess and control actual construction costs. The control estimate also allows contractors
to plan ahead to meet upcoming costs and determine the project’s cost to completion.
7. What are the four (4) step process that are used in creating a bill of quantities? Give details.
- The four (4) step process that are used in creating a bill of quantities are:
Taking-Off Quantities: Working from the construction documents, a quantity surveyor
will measure the tasks and items of work in a project. This requires scaling dimensions
from drawings. One will record these in standard units such as area, volume, or length.
For example, you can quantify excavation in cubic meters and steel supports in linear
feet. It’s important to follow one of the standard methodologies, such as the New Rules
of Measurement. The surveyor will list the number of each item in the project.
Squaring: Next, the quantity surveyor multiplies the dimensions of the component into
square area and multiplies this by the number of times this work item occurs in the
construction, thus getting the total dimensions, length, volume, and area as applicable.
Abstracting: Abstracting is the collecting and ordering of the squared dimensions.
Similar tasks and components are grouped together. Once you have taken off and squared
all items and have obtained total dimensions, they must be merged. You make deductions
for any voids or openings in the building, such as stairs.
Billing: This last step simply involves presenting item descriptions and quantities in a
structured format, the bill of quantities. You usually present these in a hierarchy for
group, subgroup, and work section. (Examples include substructure, earthwork, and site
clearance.)
9. Give several primary factors that influences on the construction cost.
One of the primary factors that influences cost is the building site. Waterlogged soils,
previous construction, geological formations and the nature of the rock, native animal
species, and the presence of historical or natural heritage sites are just a few of the things
that can affect materials and labor requirements, delay the issuance of permits, and
increase the time needed to complete the project. Similarly, the location of the
construction site relative to economic centers can also be significant. Contractors may
have to transport workers and materials for a long distance if the site is remote. In a
bustling urban area, the wages may be higher. Furthermore, regulatory requirements may
be stricter, and hence more expensive to fulfill or comply with, at some construction sites
than at others. Lastly, certain construction sites require the completion of feasibility or
impact studies, which are likely to prove expensive.
Time-related aspects can also affect costs significantly. Chief among these is the project
schedule, as a compressed, labor-intensive schedule will incur higher costs and rush
charges. Shorter projects, especially those with significant penalties for the contractor’s
failure to complete the project on time, are also likely to have more expensive insurance.
Also, with a project that you expect to take years to complete, you will almost certainly
have to consider fluctuating market conditions and inflation. Finally, owners inviting bids
may notice seasonal variations in bid amounts, since contractors are busier at some times
of the year than at others.
The size and complexity of the project are other major influences on cost estimates.
Larger, more prestigious projects may attract more reputable contractors, or there may
simply be few firms capable of handling the project. Either of these scenarios can
escalate project costs.
The quality of plans and specifications are also vital factors, as is the contractor’s
relationship with the project engineer. Construction documents that hint at imprecision
will almost certainly result in higher bids from contractors who want to err on the side of
safety. On the other hand, the project engineer’s reputation can swing costs the other
way, since contractors will know that plans drawn by a reputable engineer are less likely
to result in efficiency losses.
Some other factors that affect the project cost include whether a government or quasi-
governmental agency commissions or funds the project, a circumstance which may
require additional paperwork and reporting. Some large projects require the completion
of a value-engineering review before bidding commences. Value engineering, which
examines the function-to-cost ratio of a project, aims at making the design as cost
efficient as possible.
14. What is the most common way of working out labor calculations? How this to be done?
- The most common way of working out labor calculations is to use labor units. These set
out how long it takes to install each and every component across the entire project, from laying
out the foundations to building walls, installing sections of circuit on the MEP side, and the time
taken to install each individual fixture and fitting. This requires a detailed quantitative take-off to
be completed first, which will set out the requirements for each part of the job. This can then be
used in conjunction with labor rates for the different aspects of the job to produce a detailed
labor cost estimate. Still, it’s not as simple as multiplying hours required by hourly rates. There
are labor overheads and ‘non-productive’ hours to be taken into account, as well as numerous
factors that can affect the costs, such as weather, illness, site conditions, and other means of
productivity loss.