Saudi Aramco is developing an Engine Manufacturing Factory in Ras Al Khair, Saudi Arabia to produce engines and pumps for the maritime industry. The factory will be located within the King Salman Global Maritime Industries Complex and consist of 14 buildings. It will have an annual production capacity of 30 two-stroke engines, 235 four-stroke engines and 160 marine pumps. An environmental impact assessment report must be developed and approved by the National Center for Environmental Compliance and Royal Commission.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
487 views6 pages

Project Scope-Eia

Saudi Aramco is developing an Engine Manufacturing Factory in Ras Al Khair, Saudi Arabia to produce engines and pumps for the maritime industry. The factory will be located within the King Salman Global Maritime Industries Complex and consist of 14 buildings. It will have an annual production capacity of 30 two-stroke engines, 235 four-stroke engines and 160 marine pumps. An environmental impact assessment report must be developed and approved by the National Center for Environmental Compliance and Royal Commission.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Saudi Aramco

EIA-Scope of Work Engine Manufacturing Factory (EMF)

Saudi Aramco

SCOPE OF WORK FOR


Developing of Environmental Impact Assessment report for Engine
Manufacturing Factory

Revision 00o. 15

Page 1 of 6

Saudi Aramco: Company General Use


Saudi Aramco
EIA-Scope of Work Engine Manufacturing Factory (EMF)

Table of Contents

1.0 INTRODUCTION ................................................................................................................................ 3


1.1 Project Objective ................................................................................................................... 3
1.2 Project Location .................................................................................................................... 3
2.0 PROJECT DATA .................................................................................................................................. 5
3.0 DESCRIPTION OF SCOPE OF WORK .................................................................................................. 6
4.0 APPENDICES: -................................................................................................................................... 6

Page 2 of 6

Saudi Aramco: Company General Use


Saudi Aramco
EIA-Scope of Work Engine Manufacturing Factory (EMF)

1.0 INTRODUCTION

1.1 Project Objective


The purpose of the proposed facility is to localize maritime industry, Saudi Aramco would like to
manufacture 2-Stroke, 4-Stroke engines and Marine pumps in King Salman International Complex
for Maritime Industries & Services, located in Ras Al-Khair. The primary objective of the facility is
to produce an annual production capacity of 30 two-stroke engines, 235 four-stroke engines and
160 marine pumps.

1.2 Project Location


The Engine Manufacturing Factory proposed location is inside the Maritime Yard Complex in Ras
Al-Khair, the East Coast of Saudi Arabia, approximately 80 kilometers to the north of Jubail
Industrial City, as indicated layout of MY with EMF.
Engine Manufacturing Factory location in relation to Maritime Yard Location in Figure (1) & (2).

Figure (1): Engine Manufacturing Factory location in relation to Maritime Yard Location.

The facility is to be located within the King Salman Global Maritime Industries Complex. The
Manufacturing Factory consists of below buildings/shops:
1. 2-Stroke Engine Shop
2. 4-Stroke Engine Shop
3. Marine Pump Shop
4. Fabrication Shop
5. Store House
6. Paint Shop

Page 3 of 6

Saudi Aramco: Company General Use


Saudi Aramco
EIA-Scope of Work Engine Manufacturing Factory (EMF)

7. Main Substation Building


8. Multifunction Office Building
9. Multi-Purpose/Production Building
10. Guard House(x2)
11. Electrical Room
12. Search Building
13. Solid Waste Transfer Station
14. Gate 2 Service Building

ENGINE
MANUFACTURING
FACTORY (EMF)

Figure (2): Engine Manufacturing Factory location in relation to Maritime Yard Location.

Page 4 of 6

Saudi Aramco: Company General Use


Saudi Aramco
EIA-Scope of Work Engine Manufacturing Factory (EMF)

2.0 PROJECT DATA

Project's data
Region Eastern Province

City Ras Al Khair

Area of the facility 150,000 m2

Land Ownership Saudi Aramco

Description of the activity Manufacture of internal combustion engines


and parts thereof

Components of the project 14 Buildings

Coordinates

(Latitude) Transverse coordinate 327561.48

(Longitude) Longitudinal coordinate 3043506.71

The perimeter of the facility

North 308 meters

South 308 meters

East 500 meters

West 500 meters

Request data

Approval Services EIA Approval

Project Type Industrial

Project Facilities 14 Buildings

Energy Resources Saudi Electricity Company

Water Sources King Salman International Complex for


Maritime Industries

The amount of liquid waste in the facility Less than 10 tons

The amount of solid waste in the facility Less than 100 tons

Page 5 of 6

Saudi Aramco: Company General Use


Saudi Aramco
EIA-Scope of Work Engine Manufacturing Factory (EMF)

3.0 DESCRIPTION OF SCOPE OF WORK


a) CONTRACTOR scope of work includes development of the Environmental Impact
Assessment (EIA) report. CONTRACTOR to follow the new regulation which mandates
Saudi Aramco to submit and secure EIAs approval based on the requirements of National
Center for Environmental Compliance (NCEC) and through an NCEC’s certified consultant
(refer to below link):
https://ncm.gov.sa/Ar/EService/Pages/QualifiedServices.aspx
b) CONTRACTOR to follow the guidelines mentioned in the Letter (Appendix-A) from
Environmental Coordination Division (ECD) on the recent guidelines for EIA submittal and
approval. Ministry of Energy has established a new regulation in relation to EIA submittals
and approval path forward. The new regulation was developed jointly with the National
Center for Environmental Compliance (NCEC).
c) CONTRACTOR to include the approval fee for the NCEC and Royal Commission ,if any in
their bid quotation.
d) CONTRACTOR to Coordinate and following up with NCEC & Royal Commission till the final
EIA approval of the project is received.
e) CONTRACTOR to provide the estimated completion time for final EIA report.

4.0 APPENDICES: -
A. Letter from Environmental Coordination Division for Environmental Impact Assessment New
Approval Mechanism/Regulations.
B. Letter from Ministry of Energy (In Arabic)

Page 6 of 6