1.0 Introduction To Construction Management 1
1.0 Introduction To Construction Management 1
CONSTRUCTION
MANAGEMENT
INTENDED LEARNING OUTCOMES:
• DELIVERABLES
• KEY DATES
• COMPLETION CRITERIA DKCEP
• EXPECTATIONS
• POTENTIAL RISKS
PARAMETERS TO DETERMINE WHAT TASKS TO
INCLUDE IN YOUR PROJECT
DELIVERABLES
KEY DATES
PARAMETERS TO DETERMINE WHAT TASKS TO
INCLUDE IN YOUR PROJECT
PPCC
PRECONSTRUCTION
CSDC
PRECONSTRUCTION
Conceptual design:
- Very important for the owner.
- During this stage the owner hires key consultants including the designer
and project manager, selects the project site, and establish a conceptual
estimate, schedule, and program.
- The owner must gather as much information as possible about the project.
- The most important decision is to proceed with the project or not.
PRECONSTRUCTION
Schematic design:
- During this phase, the project team investigates alternate design solutions,
materials and systems.
- Completion of this stage represents about 30% of the design completion
for the project.
PRECONSTRUCTION
Design development:
- Designing the main systems and components of the project.
- Good communication between owner, designer, and construction manager
is critical during this stage because selections during this design stage affect
project appearance, construction and cost.
- This stage takes the project from 30% design to 60% design.
PRECONSTRUCTION
Contract documents:
- Final preparation of the documents necessary for the bid package such as
the drawings, specifications, general conditions, and bill of quantities.
- All documents need to be closely reviewed by the construction manager
and appropriate owner personnel to decrease conflicts, and changes.
- With the contract documents are almost complete; a detailed and complete
cost estimate for the project can be done.
PROCUREMENT PHASE
(BIDDING AND AWARD PHASE)
- Transition from design and construction to the actual use of the constructed
facility.
- In this stage, the management team must provide documentation, shop drawings,
as-built drawings, and operation manuals to the owner organization.
- The as-built drawings are the original contract drawings adjusted to reflect all the
changes that occurred.
- Assessment of the project team’s performance is crucial in this stage for avoiding
mistakes in the future.
- Actual activity costs and durations should be recorded and compared with that
was planned. This updated costs and durations will serve as the basis for the
estimating and scheduling of future projects.
MAJOR TYPES OF CONSTRUCTION PROJECTS
RISI
MAJOR TYPES OF CONSTRUCTION PROJECTS
- Examples of design professionals are architects, engineers, and design consultants. The
major role of the design professional is to interpret or assist the owner in developing the
project’s scope, budget, and schedule and to prepare construction documents.
- The construction professionals are the parties that responsible for constructing the project.
- The project manager is the individual charged with the overall coordination of the entire
construction program for the owner. These include planning, design, procurement, and
construction.