BOQ Ashuganj Rev2

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 21

Price Schedule

Project Name:Ashuganj 132/33kv substation (Capacity Upgradation)


Unit Rate Schedule For Electrical Installation W
Sl. No. Description of work Unit Qty
序号 工作描述 单位 安装
1 Power Transformer (Replaced)
1.1 132/33kV, 80/120MVA, 3-phase Power transformer set 2
2 132 KV Switchgear
2.1 132KV XLPE Power cable(Replaced)
2.1.1 132KV XLPE Power cable (800mm2) m 120
2.1.2 132KV Outdoor type Cable Sealing End with Accessories nos. 6
3 33 KV Switchgear
3.1 33KV incomer bays (Replaced)
3.1.1 Vacuum Circuit Breaker, 2500A, 40KA set 2
3.1.2 Disconnector Switch without E/S, 2500A, 40KA set 4
3.1.3 Single Phase Current Transformer nos. 6
3.1.4 Single Phase voltage transformer nos. 6
3.1.5 Single Phase Surge Arrester nos. 12
3.1.6 Disconnector for Bus & line feeder set 1
4 Flexible Conductor for busbar, Jackbus,Jumper & equipment Connection with m 650
clamp, connector & insulator
4A Flexible Conductor for busbar, Jackbus,Jumper & equipment Connection with m
450
clamp, connector & insulator(Demolition)
4B 33kv Tube - shaped busbar Ø100/92(Replaced) m 126
5 Steel structures & cable tray
5.1 Gantry and beam ton 21.6
5.2 Equipment steel structure ton 3
5.3 Cable bracket, cable tray and other electrical support etc ton 2
5.4 Dismantle of steel structures ton 6
6 33kV XLPE Power Cable and accessories
6.1 Power cable XLPE-800mm² m 1107
6.2 Outdoor type Cable Sealing End with accessories nos. 24
7 Control, Protection and Metering
7.1 132 KV Circuits
7.1.1 Modification of existing Control panels for transformer bay sets 2
7.1.2 Tariff metering lot 1
7.2 33 KV Circuits
7.2.1 Control & Protection panels for incomer bay set 2
7.2.2 Tariff metering for incomer bay lot 1
7.2.3 Local control box, terminal box pcs 2
8 Multicore Cables(LV & control cable) mtr 5000
8A Multicore Cables(LV & control cable)(Dismantle) mtr 3000
9 Earthing and Lightning Protection
9.1 Earthing mesh and equipment earthing m 200
9.2 Grounding electrode Length =< 10 m m 50
9.3 Transformer neutral grounding set 2
9.4 Overhead ground wire mtr 60
10 DC System
10.1 Extension/Modification of DC Distribution board lot 1
11 LVAC System
11.1 Extension/Modification of LV Distribution board lot 1
12 Teleprotection, Telemetering & Communication System
12.1 Integration to SCADA/NLDC system. lot 1

13 Outdoor switchyard lighting, small power lot 0


14 Handing over the Dismantled Equipment & Materials
14.1 Handing over the Dismantled transformer(inside the substation) set 0
14.2 Handing over the Dismantled transformer(outside the substation) set 0
14.3 Handing over the Dismantled Equipment & Materials excluding transformer lot 0
(inside the substation)
14.4 Handing over the Dismantled Equipment & Materials excluding transformer lot 0
(outside the substation)
15 Testing & Commissioning(Assist work) lot 0
16 Testing & Commissioning (All inclusive) lot 1
17 Miscellaneous works if any lot 1

Sub Total Price


ical Installation Work
Unit Rate Amount Remark
安装 BDT 备注

Assist work

Boring about 120ft


Configuration and testing by GE
people
Pending

Pending
Pending
Pending

Pending

Such as vehicle support, snacks,


entertainment expense etc.
Price Schedule
Project: Ashuganj 132/33kv substation
Unit Rate Schedule For Labour & Construction Materials 人工
Qty Unit rate
SL NO. Description of Works
Unit Qty BDT
1 Labour 人工
1.1 Engineer 工程师 Manday 1
1.2 Supervisor 工头 Manday 1
1.3 Skilled Labour 大工 Manday 1
1.4 Unskilled Labour 小工 Manday 1
Construction Equipment and Materials
2 施工机具和材料

Note:
1 The unit rate covers all old equipment demolition work, there is no extra charge w
2 The unit rate covers all direct work, indirect work, contingencies, overhead, prof
3 The manpower rates includes small tools.
4 Equipment rates includes operators, servicing, fuels, lubricants, maintenance, rep
5 The equipment rates will be paid to the number of operating hours.
6 Hand tools are all included in the manhours rates of the above.
7 This time is only composed of the hours of working at the appointed place.
8 The time of transportation or the time on the way to the appointed area inside or
9 Materials supplied by the subcontractor shall cover installation costs.
ction Materials 人工及施工设备
Amount
Remarks
BDT

per day 8 hours


per day 8 hours
per day 8 hours
per day 8 hours

ere is no extra charge will be pay it.


ngencies, overhead, profit, insurance, duties and taxes etc.

icants, maintenance, repairs etc.

appointed place.
ppointed area inside or the site are not be measured.
lation costs.
Project: 通用版
Work Title:安装工作

Work Definition and Measurement of Category Number


Item Work 项目名称 Unit 单位

Steel Structural Works 钢结构工程


Gantry & Beam 龙门架,大梁 tons

Equipment Support 设备支架 tons

Fabrication and installation of support and tons


protection for Electrical Work 电气设备支架,
桥架加工及安装等

Power Transformer 电力变压器 sets


AIS HV Equipments 空气绝缘高压设备 sets

GIS HV Equipments 气体绝缘封闭式高压开关 sets


设备

Aluminium Conductor 铝绞线 m


Power Cable and Termination 电力电缆及终端 m/sets

LV Equipments 低压设备 sets

Multicore Lv Power & Control Cables 低压电缆 m


,控制电缆
Earthing and Lightning Protection 接地及防雷 m
保护

Outdoor switchyard lighting, small power 户外 m/sets


照明,小电源系统等
Testing & Commissioning 试验及送电 lot

Note:
Measurement of Category Number for Unit Price 分部分项工程量
Work Description(The work including, but is not limited to the following) 工
作内容包括如下,但不仅限于此

This item covers installation works except prefbrication as follow: 工作内容包括如下:

Preparation of foundation 准备基础


Field inspection 现场检查
Ground assembling work 地面组装工作
Placing and aligning of steel structure 钢结构布置与校直
Bolting or welding if necessary 必要时用螺栓或者焊接
Minor modification work adjustment and anchor bolt hole enlargement 局部修改,
调整以及地脚螺栓孔扩大
Touch-up painting on damaged portion 损坏部分补漆
Final check as per the technical documents 根据技术文件进行最终检查

This item shall be applied to the fabrication and installation of supports and protection
for electrical works, such as conduit, cable duct, rack, tray,other minor parts etc. 本条
目适用于如导管,保护管,支架,桥架等材料的安装和制作
This work shall cover works as follows: 工作内容包括如下:
Measuring, leveling and centering 测量,找平以及中心定位
Prefabrication of such supports as follows by cutting, welding and other methods
用切割,焊接或者其他方法等预加工如下支架
Bracket 托架
Tray 托盘
Hanger 吊架
Conduit 导管
Cable duct 电缆保护管
Other supports to be fabricated 其他需要制作的支架
Painting or galvanized 喷漆或者镀锌
Installation and adjustment of support 支架安装和调整
Final check as per the technical documents 根据技术文件进行最终检查

This work shall cover as follows: 工作内容包括如下:

Checking the elevation, center and other conditions of the foundation 检查基础的
标高中心定位等情况
Cleaning the foundation 基础清理
Setting liner 安装垫块
Setting rails 安装轨道
Equipments and materials shifting at site 设备和材料现场运输
Unpacking,visual inspection,cleaning 开箱,外观检查,清理
Confirm no damage on any equipment and parts 确认设备和附件没有任何损坏
Placing and setting of equipment 设备定位安装
Attaching and fixing all accessories 安装和固定所有附件
Alignment 对齐
Filtering and filling of oil 注油以及滤油
Remove rust and repair paint as per factory SV requirement 按照厂家要求除锈补

Final check as per the technical documents 根据技术文件进行最终检查

This works shall include installation of all equipment 这项工作应包含所有设备的安装


This work shall cover as follows: 工作内容包括如下:
Checking foundation for elevation, center and other conditions 检查基础标高,中
心定位等情况
Cleaning the foundation 基础清理
Setting liner 安装垫块
Setting anchor bolt 安装地脚螺栓
Equipments and materials shifting at site 设备和材料现场运输
Unpacking,visual inspection,cleaning 开箱,外观检查,清理
Confirm no damage on any equipment and parts 确认设备和附件没有任何损坏
Assembling and placing of substation equipment,include all equipment and
accessaries installation,such as Breaker, disconnector, PT, CT, LA, PI etc 设备定
位及组装,包括所有设备和附件的安装,如断路器,隔离开关,电压互感器,电流
互感器,避雷器,支柱绝缘子等
Fixing all accessories 紧固所有附件
Modification of exsiting support for installation work if necessary 如有需要,对现有
的安装支架进行修改
Alignment 对齐
Terminal work between system equipments which are disconnected for
transportation 设备二次线连接工作(方便运输断开或者本体未完成的)
Mechanical and electrical properties drive debugging etc 机电性能传动调试等
Final check as per the technical documents 根据技术文件进行最终检查

This works shall include installation of all equipment 这项工作应包含所有设备的安装

This work shall cover as follows: 工作内容包括如下:


Checking foundation for elevation, center and other conditions 检查基础标高,中
心定位等情况
Cleaning the foundation 基础清理
Setting liner 垫块安装
Checking base plate 检查预埋件
Make center line marking 标注中心线
Equipments and materials shifting at site 设备和材料现场运输
Unpacking,visual inspection,cleaning 开箱,外观检查,清理
Confirm no damage on any equipment and parts 确认设备和附件没有任何损坏
Assembling and placing of equipment,include all equipment and accessaries
installation,such as bushing,GIB,PT,ladder,platform etc 设备定位及组装,
包括所有设备和附件的安装,如套管,封闭式管母线,电压互感器,梯子,工作平
台等
Fixing all accessories 紧固所有附件
Alignment 对齐
Terminal work between equipment to LCC which are disconnected for
transportation 设备二次线连接工作(方便运输断开或者本体未完成的)
Mechanical and electrical properties drive debugging etc 机电性能传动调试等
Final check as per the technical documents 根据技术文件进行最终检查

This work shall cover as follows: 工作内容包括如下:


Assembling of bus with isulator string and strain clamp 耐张线夹,悬垂线夹与母线
间的组装
Assembling of jumper with equipment clamp 用设备线夹制作跳线
Placing and adjustment 安装和调整
Fixing of accessories 紧固附件
Connection of concerned equipment 设备间连接
Final check as per the Technical document and field inspection procedure 根据技
术文件和现场检查程序进行最终检查
This work shall cover as follows: 工作内容包括如下:

Excavation and backfilling of cable trench 电缆沟开挖和回填


Installation of cable protection slab 电缆保护板安装
Equipments and materials shifting at site 设备和材料现场运输
Laying cable and wire to cable routes 敷设电缆到指定路径
Routing cable and wire through conduit pipe, opening tube etc 电缆通过保护管或
者开孔敷设
Terminating and jointing cable and wire 终端制作
Clamping/binding/taping of cables and wires 电缆固定,绑扎等
Hanging and supporting at the required points 悬挂或者支撑制作
Setting of cable bracket at the required points 电缆支架安装
Marking identification bands for cables and wire 电缆标识带
Sealing of cable access at the required point with fire proof material and other 防
火材料密封孔洞
Excavation, backfilling and disposal of surplus soil when necessary (for U/G
cable) 如有需要,挖掘回填及处置剩余泥土
Maintenance & cleaning of cable trench after handing over from civil contractor 土
建移交后电缆沟的维护和清理
Uplifting and re-setting of cable trench cover 电缆盖板移动和复位
Marking rod installation at the required points 路径标志安装
Final check as per engineering specification and field inspection procedure 根据工
程规范和现场检查程序进行最终检查

This work shall include installation of all equipment of system, such as control,protect
panel/cabinet/MK box etc. 该工作包括系统所有设备的安装,如控制盘,保护盘/柜子/端
子箱等
This work shall cover as follows: 工作内容包括如下:
Checking foundation for elevation, center and other conditions 基础标高,中心定
位等条件检查
Cleaning the foundation 基础清理
Setting liner 垫块安装
Setting steel support 预埋件安装
Equipments and materials shifting at site 设备和材料现场运输
Installation of panel/cabinet, control desk/console 盘柜/控制台等安装
Fixing all accessories 紧固所有附件
Attaching instrument 附件安装
Terminal work between system equipments which are disconnected for
transportation 设备二次线连接工作(方便运输断开或者本体未完成的)
Calibration of panel instrument 表计仪表等校准
Hole making for panel when necessary
Extension/modification of existing panel if required 如需要按要求扩建和改造旧屏

Function test of system 系统功能试验
Loop test 回路检查
Final check as per the technical documents 根据技术文件进行最终检查

This work shall cover as follow: 工作内容包括如下:

Laying cable and wire to cable routes 按要求敷设电缆


Connecting the cable and wire 电缆接线
Routing cable and wire through conduit pipe, opening tube etc. 电缆保护管等安装

Hole making for cable when necessary


Equipments and materials shifting at site 设备和材料现场运输
Name plate,cable number tube,Terminating and jointing cable and wire 电缆牌
,号码管,电缆接线和终端制作等
Clamping/binding/taping of cables and wires, construction materials supply 电缆绑
扎,相关材料供应
Hanging and supporting at the required points 电缆悬挂和支撑制作
Setting of cable bracket at the required points 电缆支架等安装
Marking identification bands for cables and wire 电缆标识带安装
Sealing of cable access at the required point with fire proof material and other 防
火材料等密封孔洞
Excavation, backfilling and disposal of surplus soil when necessary (for U/G
cable) 如有需要挖掘,回填以及处置剩余泥土
Maintenance & cleaning of cable trench after handing over from civil contractor 土
建移交后电缆沟的维护和清洁
Uplifting and re-setting of cable trench cover 沟盖板移动和复位
Marking rod installation at the required points 电缆路径标识
loop test 回路检查
Final check as per engineering specification and field inspection procedure 根据工
程规范和现场检查程序进行最终检查

This work shall cover as follow: 工作内容包括如下:

Laying cable or wire 电缆敷设


Connection to panels, electrical equipment grounding system 设备与地网连接
Routing cable and wire through conduit pipe, opening tube when necessary 必要
时通过保护管等敷设
Fabrication of busbar (cu plate) including cutting, making hole 母排制作,包括切
割或者打孔
Installation of busbar (cu plate) by anchor bolts or expansion bolts 地脚螺栓或者膨
胀螺栓安装母排
Terminating and jointing the wire by bolting, thermit welding 通过螺栓或者放热焊
接等方式连接
Clamping/binding/taping of wires 卡子,绑扎等固定地线
Hanging and supporting at the required points 悬挂或者支撑制作
Excavation, backfilling and disposal of surplus soil 开挖,回填及处置剩余泥土

Excavation for electrode and manhole 接地极和人孔等开挖打孔


Fixing plate and test terminal box in position 固定接地排和试验盒子到指定位置

Filling of ground resistance reducing materials, if required 如需要,按要求填充减


阻材料
Backfilling and disposal of surplus soil 剩余土壤回填和处理
Connection of rod to earth strips by bolting, thermit welding 通过螺栓和放热焊接连
接至接地极
Marking earth chamber and cover 接地井制作
Field test and final check as per engineering specification and field inspection
procedure 根据工程规范和现场检查程序进行现场测试和最终检查

This work shall cover as follows: 工作内容包括如下:

Setting anchor bolt and/or expansion bolts, supports or hanger 安装地脚螺栓,膨


胀螺栓,吊架,支架等
Assembling of fixtures including wiring 安装固定装置,包括布线
Installation of lighting pole including alignment for pole roadway fixture 灯杆安装,
包括固定夹具等
Setting of stanchion including adjustment as necessary by cutting or welding 支柱
安装包括切割焊接等进行调整
Fixing of location boxes 就地箱子固定
Installation of lighting fixtures including accessories 照明装配件等安装
Final check as per the engineering specification and field inspection procedure 根
据工程规范和现场检查程序进行最终检查
This work shall cover as follows: 工作内容包括如下:
All about the testing work, such as HV testing, LV testing, equipment testing,relay
configuration and protection testing. Etc. 所有关于测试工作,如高压测试,低压测
试,设备测试,继电器配置和保护测试等

All about the commissioning work 所有关于试运行的工作


All about the testing & commissioning report or completion documents 所有关于测
试和调试报告或竣工文件
Final check as per the technical documents and field inspection procedure 根据技
术文件和现场检查程序进行最终检查

Note:
t Price 分部分项工程量清单计价定义表
Volume of Quantity to Be
Remarks 备注
Measured 工程量计价规则

Work volume shall be measured as


net weight in accordance with
Drawings.Including joists, fasteners,
gusset plate, etc. 工作体积应按图纸
上的净重计量。包括托梁、扣件、扣
板等

Net weight of installation components


安装组件净重

Number of equipments 数量
Number of equipments 数量

Number of equipments 数量

Net installated length 长度


Net installated length and
equipments 长度和数量

Number of equipments 数量

Net installated length 长度


Net installated length 长度

Net installated length, Number of


equipments 长度和数量
lump-sum 总量

You might also like