BOQ Ashuganj Rev2
BOQ Ashuganj Rev2
BOQ Ashuganj Rev2
Assist work
Pending
Pending
Pending
Pending
Note:
1 The unit rate covers all old equipment demolition work, there is no extra charge w
2 The unit rate covers all direct work, indirect work, contingencies, overhead, prof
3 The manpower rates includes small tools.
4 Equipment rates includes operators, servicing, fuels, lubricants, maintenance, rep
5 The equipment rates will be paid to the number of operating hours.
6 Hand tools are all included in the manhours rates of the above.
7 This time is only composed of the hours of working at the appointed place.
8 The time of transportation or the time on the way to the appointed area inside or
9 Materials supplied by the subcontractor shall cover installation costs.
ction Materials 人工及施工设备
Amount
Remarks
BDT
appointed place.
ppointed area inside or the site are not be measured.
lation costs.
Project: 通用版
Work Title:安装工作
Note:
Measurement of Category Number for Unit Price 分部分项工程量
Work Description(The work including, but is not limited to the following) 工
作内容包括如下,但不仅限于此
This item shall be applied to the fabrication and installation of supports and protection
for electrical works, such as conduit, cable duct, rack, tray,other minor parts etc. 本条
目适用于如导管,保护管,支架,桥架等材料的安装和制作
This work shall cover works as follows: 工作内容包括如下:
Measuring, leveling and centering 测量,找平以及中心定位
Prefabrication of such supports as follows by cutting, welding and other methods
用切割,焊接或者其他方法等预加工如下支架
Bracket 托架
Tray 托盘
Hanger 吊架
Conduit 导管
Cable duct 电缆保护管
Other supports to be fabricated 其他需要制作的支架
Painting or galvanized 喷漆或者镀锌
Installation and adjustment of support 支架安装和调整
Final check as per the technical documents 根据技术文件进行最终检查
Checking the elevation, center and other conditions of the foundation 检查基础的
标高中心定位等情况
Cleaning the foundation 基础清理
Setting liner 安装垫块
Setting rails 安装轨道
Equipments and materials shifting at site 设备和材料现场运输
Unpacking,visual inspection,cleaning 开箱,外观检查,清理
Confirm no damage on any equipment and parts 确认设备和附件没有任何损坏
Placing and setting of equipment 设备定位安装
Attaching and fixing all accessories 安装和固定所有附件
Alignment 对齐
Filtering and filling of oil 注油以及滤油
Remove rust and repair paint as per factory SV requirement 按照厂家要求除锈补
漆
Final check as per the technical documents 根据技术文件进行最终检查
This work shall include installation of all equipment of system, such as control,protect
panel/cabinet/MK box etc. 该工作包括系统所有设备的安装,如控制盘,保护盘/柜子/端
子箱等
This work shall cover as follows: 工作内容包括如下:
Checking foundation for elevation, center and other conditions 基础标高,中心定
位等条件检查
Cleaning the foundation 基础清理
Setting liner 垫块安装
Setting steel support 预埋件安装
Equipments and materials shifting at site 设备和材料现场运输
Installation of panel/cabinet, control desk/console 盘柜/控制台等安装
Fixing all accessories 紧固所有附件
Attaching instrument 附件安装
Terminal work between system equipments which are disconnected for
transportation 设备二次线连接工作(方便运输断开或者本体未完成的)
Calibration of panel instrument 表计仪表等校准
Hole making for panel when necessary
Extension/modification of existing panel if required 如需要按要求扩建和改造旧屏
柜
Function test of system 系统功能试验
Loop test 回路检查
Final check as per the technical documents 根据技术文件进行最终检查
Note:
t Price 分部分项工程量清单计价定义表
Volume of Quantity to Be
Remarks 备注
Measured 工程量计价规则
Number of equipments 数量
Number of equipments 数量
Number of equipments 数量
Number of equipments 数量