0% found this document useful (0 votes)
108 views2 pages

Disconnector Procedure

This document provides procedures for commissioning disconnect switches and earthing switches (DS/ES) at a site in Jakarta, Indonesia. It outlines preliminary checks to perform before energizing the supply voltage, including visual inspections, functional mechanical checks of the operating mechanism, and checks of limit switches and interlocks. It also describes electrical tests to conduct, such as functional checks of the operating mechanism, anti-condensation heater, auxiliary switches, and measurements of motor current according to the circuit diagram. The document is a procedure from PT. ABB Sakti Industri for commissioning DS/ES equipment.

Uploaded by

Hendra Laksmana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
108 views2 pages

Disconnector Procedure

This document provides procedures for commissioning disconnect switches and earthing switches (DS/ES) at a site in Jakarta, Indonesia. It outlines preliminary checks to perform before energizing the supply voltage, including visual inspections, functional mechanical checks of the operating mechanism, and checks of limit switches and interlocks. It also describes electrical tests to conduct, such as functional checks of the operating mechanism, anti-condensation heater, auxiliary switches, and measurements of motor current according to the circuit diagram. The document is a procedure from PT. ABB Sakti Industri for commissioning DS/ES equipment.

Uploaded by

Hendra Laksmana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Product Documentation GIS (PGHV DEPARTMENT)

abb On Site Test / SAT JAKARTA, INDONESIA

DS/ES PROCEDURE
COMMISSIONING

Doc. Kind Doc Title Doc No. Lang. Rev.

abb PT. ABB SAKTI INDUSTRI Procedure


DS/ES PROCEDURE
COMMISSIONING
03 Eng A

Page 1 of 2
Product Documentation GIS (PGHV DEPARTMENT)
abb On Site Test / SAT JAKARTA, INDONESIA

A. Before Energize supply ac/dc voltage (Preliminaries) on Mechanism Box;

1. Visual inspections for external damages.

2. Visual inspections of operating mechanism elements.

3. Functional mechanical check of operating mechanism (with hand crank) Close/Open.

4. Function check of limit swicth, interlock swicth (hand crank), position indication.

5. Check of interlocking with hand crank.

6. Check of key interlocking.

7. Visual check electrical plug connections (plugs) secured with screws.

B. ELECTRICAL TEST

1. Functional check of operating mechanism electrical CLOSE/OPEN.

2. Functional check of anti-condensation heater.

3. Check of auxiliary switch, optical check of electrical connections.

4. Functional check acc. to circuit diagram (planning standard).

5. Measurement of motor current at rated voltage.

Doc. Kind Doc Title Doc No. Lang. Rev.

abb PT. ABB SAKTI INDUSTRI Procedure


DS/ES PROCEDURE
COMMISSIONING
03 Eng A

Page 2 of 2