Rev.No.
Date
Description
Issued by
Remarks
1.TITLE 2. SCOPE OF WORK 2.1 GENERAL DESCRIPTION 2.2 PLANT AND EQUIPMANT 2.3 WORK METHODOLOGY 3.HEALTH & SAFETY 4.MANPOWER
1.TITLE
AC Unit pipe installation and Drainage pipe insulation of AC split unitsfor office buildings.
2.SCOPE OF WORK
2.1 General Description This method of statement describes procedures forpipe installation and Drainage pipe insulation of AC split units. The aim of this work is to describe mechanical works associated with insulation of A/C drain pipe to ensure compliance with contract requirements approved shop drawings, materials, specification and quality control.
2) Piping connection 2.1)1). Measure the necessary length of the connecting pipe, and make it by the following way
a. Connect the indoor unit at first, then the outdoor unit. Bend the tubing in proper way. Do not harm them. For exact and perfect bending we have to use pipe bending machine. Be sure to use two wrenches simultaneously when you connect or disconnect the pipes.
b. The stop value of the outdoor unit should be closed absolutely (as original state). Every time you connect it, first loosen the nuts at the part of stop value, then connect the flare pipe immediately (in 5 minutes). If the nuts have been loosened for a long time, dusts and other impurities may enter the pipe system and may cause malfunction later. So please expel the air out of the pipe with refrigerant before connection. c. Expel the air after connecting the refrigerant pipe with the indoor unit and the outdoor unit. Then fasten the nuts at the repair-points. 2.2) Locate The Pipe a. Drill a hole in the wall (suitable just for the size of the wall conduit), then set on the fittings such as the wall conduit and its cover.
b. Bind the connecting pipe and the cables together tightly with binding tapes. Do not let air in, which will cause water leakage by condensation. c. Pass the bound connecting pipe through the wall conduit from outside. Be careful of the pipe allocation to do no damage to the tubing.
3) Additional charge
When the length of the one-way pipe is less than 8m, additional refrigerant charge after vacuuming is not necessary. When the length of one-way pipe is over 8m, the quantity to be added is as follows (unit in gram): Connective pipe length Less than 8m Over 8m Air purging method Use refrigerant of outdoor unit Use vacuum pump or refrigerant cylinder Additional amount of refrigerant to be charged
4)Pipe Clamps
After tapping to the refrigerant pipe and drain pipe(tapping refrigerant pipe drain pipe each other).Install the pipes with using clamp each up to 1 meter to 1.2 meter
Figure 1B
Cut the insulation tube according to the lengthwise (for big size pipe) Press together two surface firmly of joint
Figure 2B
Figure 3B
Other:
Required Personnel Protective Equipment:
conformity assesment procedure for risk
Safety Boots
Hard Hats
Safety Gloves
YES
YES
YES
If Require
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companys health and safety Policy.
4.Manpower
a. 1Supervizor b. 1 Foreman c. 3 Worker