Construction Project Quality Plan SAMPLE
Construction Project Quality Plan SAMPLE
Construction Project Quality Plan SAMPLE
The Project Quality Plan (PQP) for construction work is a written plan which serves as the basis for
the overall Project Quality Assurance System and identifies the quality requirements, methods to
achieve Project Quality objectives & continual improvements during the work execution.
This is different from a Company Quality Manual, which explains the quality policies and procedures
in general, but not with information specific to each project.
Construction PQP
Training Plan detailing the training given and who got it.
Essentials Elements
Project staff
As a part of the customer requirements, every contractor should have a designated quality
manager – the person in charge of the project’s quality control and quality assurance. Your client
wants to know who this person is and what his or her duties and responsibilities are in terms of
quality. In a way, include this information, as well as the person’s qualifications for the role, in
your quality plan.
Although the quality manager is in charge of the project’s overall quality control and quality
assurance, the project supervisors are in charge of the contractors’ daily field operations. Your
quality management plan should detail the duties and responsibilities of your supervisors.
Have an organization map to demonstrate the quality manager’s and supervisor’s independence.
Effective Communication
Do you intend to have a kick-off meeting as well as regular production meetings to address quality
issues? Will you be sending your client or customer files, test results, and forms? Then, as part of
your QC procedures, you should have a quality communications plan that outlines the expected
contact points with your client.
Controlling Non-conformances
Everyone knows that things go wrong in construction from time to time. How you will manage these
circumstances should be discussed in your plan. Make it clear how you’ll handle non-conformances
in order to maintain the project’s overall efficiency.
Parts of quality assurance are to make sure that the definition of controlling non-conformances
excludes regular corrections and punch items, otherwise, you’ll end up with a lot of unnecessary
paperwork.
Final Thoughts
Clients are curious about how you can handle work efficiently. You’ll comply with their specifications
by addressing project-specific, site-specific, and specific requirements in your project construction
quality plan.
Project construction quality control plan proposals, on the other hand, are restricted in scope. As a
result, make sure to devote time to creating and documenting the company’s quality control policies
and procedures.
Is there something I’m missing? If there is anything you can suggest, please leave a message for me.
I’d be delighted to hear from you.
COPY REFERENCE
DESIGNATION COMPANY
NO. INDICATOR
COPY
DESIGNATION COMPANY REFERENCE INDICATOR
NO.
(Name of
1. Project Director Company PD
Here)
(Name of
Technical
2. Company TM
Manager
Here)
(Name of
Construction
3. Company CM
Manager
Here)
(Name of
QA/QC
4. Company QA/QC (Site)
Engineer (Site)
Here)
(Name of
Manager
5. Company QAR
QA/QC
Here)
(Name of
Project
6. Company PE
Engineer
Here)
(Name of
7. Site Engineer Company SE
Here)
CONTENTS OF PQP
General
Amendment Record
QM-QAD / G2 01 2
Sheet
Controlled copyholders
QM-QAD / G3 01 3
of PQP
Controlled copyholders
QM-QAD / G4 of ITP & Method 01 4
statements
QM-QAD / G5 Contents 02 5
QM-QAD / G6 Declaration 01 7
Quality Management
System
Documentation
QM-QAD / 4.2.1 01 13
requirements
Management
Responsibility
Management
QM-QAD / 5.1 01 18
Commitment
Responsibility, authority
QM-QAD / 5.5 07 22
& communication
Resource management
Product Realization
Customer related
QM-QAD/ 7.2 01 33
processes
Control of monitoring
QM-QAD/ 7.6 01 37
and measuring devices
Measurement,
analysis, and
improvement
General, Customer
QM-QAD / 8.0 01 38
satisfaction
Monitoring and
QM-QAD / 8.2.3 measurement of 01 40
processes
Monitoring and
QM-QAD / 8.2.4 measurement of 01 40
product
Control of
QM-QAD/ 8.3 01 41
nonconforming product
Attachments
Corporate organization
Annexure – 1 01 43
chart
Project organization
Annexure – 2 01 45
chart
List of Method
Annexure – 3 01 46
statements
PD Project Director
FM Finance Manager
PM Project Manager
PE Project Engineer
HO Head Office
TM Technical Manager
PA Preventive Action
AM Accounts Manager
PO Purchase Order
HR Human Resource
MS Method Statement
SH Section Head
ADM Administration
TC Test Certificate
WO Work Order
1.2 Application: The content of this document shall be applicable to all works carried out by (Name
of Company Here) in connection with the above project. The scope/responsibility matrix is as per
Annexure -7