0% found this document useful (0 votes)
23 views3 pages

Techo-Commercial Queries

The document discusses technical queries regarding an engineering project for creation of gas dehydration unit facilities at Tripura assets. It lists 9 queries around project documentation, procurement process, and engineering details that require clarification from the client.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views3 pages

Techo-Commercial Queries

The document discusses technical queries regarding an engineering project for creation of gas dehydration unit facilities at Tripura assets. It lists 9 queries around project documentation, procurement process, and engineering details that require clarification from the client.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

CLIENT PROJECT EPC CONTRACTOR

OIL AND NATURAL GAS CREATION OF GDU FACILITIES AT MULTITEX FILTERATION


CORPORATION LIMITED TRIPURA ASSETS ENGINEERING LIMITED

TECHNO-COMMERCIAL QUERIES

Page 1 of 3
Revision: Rev 00
CLIENT PROJECT EPC CONTRACTOR

OIL AND NATURAL GAS CREATION OF GDU FACILITIES AT MULTITEX FILTERATION


CORPORATION LIMITED TRIPURA ASSETS ENGINEERING LIMITED

1. Introduction
This document has been created to know some more details regarding the
instrumentation detail engineering work for project “ CREATION OF GDU FACILITIES
AT TRIPURA ASSETS”.

2. TECHNO-COMMERCIAL QUERIES
Based on our review of submitted document and requirement of techno-commercial
offer, following queries need to be answered.

S.no Description Reply


1. P&ID legend sheet to be shared for review of
Provided P&ID .

2. We request to submit a sample RFQ , to know the


details of attachments required to submit with RFQ
3. As per the mail, we understand that MTO will be
extracted from hook up drawings only. Kindly
confirm.
4. Kindly confirm that type of instrument decided by
us or by company.
5. All the input detail shall be provided in instrument
process data sheet or we have to refer PMS, design
basis, contract document, hazardous area
classification layout and SIL report etc.
6. Kindly share the level-1 detail engineering
schedule.

Page 2 of 3
Revision: Rev 00
CLIENT PROJECT EPC CONTRACTOR

OIL AND NATURAL GAS CREATION OF GDU FACILITIES AT MULTITEX FILTERATION


CORPORATION LIMITED TRIPURA ASSETS ENGINEERING LIMITED

7. All template and formats shall be provided by


ANG. Kindly confirm.

8. All input and reference documents shall be


provided by ANG during detail engineering.

9. Document approval time cycle and


communication protocols to be shared for
reference.

Page 3 of 3
Revision: Rev 00