Module No. 5. Construction Methods and Operation
Module No. 5. Construction Methods and Operation
Prepared by:
Assoc. Prof. CRISPIN S. LICTAOA CE, MSManEng
Civil Engineering Department
PRESENTATION OUTLINE
Introduction
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
modern design, whilst civil engineering works can be completely divorced from any
COLLEGE OF ENGINEERING
such building.
Civil engineering deals with the design, construction and maintenance of the physical
and natural built environment, including works such as bridges, roads, canals, and
dams.
Civil engineering takes place on all levels: in the public sector from municipal through
to federal levels, and in the private sector from individual homeowners through to
international companies.
DEFINITION
CONSTRUCTION METHODS
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
All these stages require not only vision and thought, but also the most important thing is
organization.
On signing the contract, the contractor will use the data from the preliminary planning
stage to establish and set up an appropriate organization.
This organization will include layout of the site: access road (for sites limited to water: the
use of barges , temporary jetties, conveyors etc.)
Method used in civil engineering works depends on the types of civil engineering to be
carried out. The two most common method: - critical path analysis techniques - bar
charts.
By producing the work programme, the most suitable method of carrying out the many
different operations in civil engineering can be determined.
ORGANIZATION AND WORKING METHOD TO
CIVIL ENGINEERING INDUSTRY
Most buildings (both residential and commercial) are built around a frame that
CIVIL ENGINEERING DEPARTMENT
Framing typically falls into two categories – heavy framing and light framing – with light
framing used in the majority of residential buildings.
Light framing is typically done using dimensional lumber or light-gauge steel, with
the building’s structural skeleton of wood or steel components assembled piece by
piece.
OTHER CONSTRUCTION METHODS
Masonry (building with individual stones or bricks held together by
CIVIL ENGINEERING DEPARTMENT
mortar).
COLLEGE OF ENGINEERING
Far and away the most common way to build a home is using “platform”
or “stick” framing, also known as “stick-built”.
With this building method the platform or foundation is built first, followed
by the walls of the first level of the home (created with vertical pieces of
lumber), and then an additional platform for the second-story floor with
the walls of the second-story anchored into the second platform.
COMMONLY-USED RESIDENTIAL CONSTRUCTION METHODS
Steel Framing
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
Concrete
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
Concrete
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
Volumetric Construction
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
Hybrid Construction
Procedures for each of these fields are generally the same, even when
applied to different projects,such as buildings, dams, or airports. However,
the relative importance of each field is not the same in all cases.
CONSTRUCTION OPERATION
During construction site preparation, boundary line pillars are also to be fixed on the
ground or as directed by the authority. All of these will help you to prepare a site for
starting the construction process.
CONSTRUCTION OPERATION
Erection
CIVIL ENGINEERING DEPARTMENT
Establishing that the foundations are suitable and safe for erection to commence.
Lifting and placing components into position, generally using cranes but sometimes by jacking.
To secure components in place bolted connections will be made, but will not yet be fully
tightened. Bracings may similarly not be fully secured.
Aligning the structure, principally by checking that column bases are lined and level and
columns are plumb. Packing in beam-to-column connections may need to be changed to allow
column plumb to be adjusted.
Bolting-up which means completing all the bolted connections to secure and impart rigidity to
the frameon site, and it can be a significant project cost
CONSTRUCTION OPERATION
Concrete Placing
CIVIL ENGINEERING DEPARTMENT
Concrete is placed in its final position before the cement reaches its
initial set and concrete is compacted in its final position within 30
minutes of leaving the mixer and once compacted it should not be
disturbed.
CONSTRUCTION OPERATION
Concrete Placing
CIVIL ENGINEERING DEPARTMENT
For locations where direct placement is not possible and in narrow forms
suitable drop and Elephant Trunks to confine the movement of concrete
is provided.
Asphalt Paving
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
The coats are then allowed to cure before the actual paving resume.
The purpose of having these coats is to prevent any slippage between
the surface and overlay during or after the compaction.
CONSTRUCTION OPERATION
Asphalt Paving
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
After that, the block can be removed and paving can start. As soon as
the haul truck arrives at the job site, the paving inspector must check
that the asphalt delivered must be in a satisfactory condition.
CONSTRUCTION OPERATION
Asphalt Paving
CIVIL ENGINEERING DEPARTMENT
COLLEGE OF ENGINEERING
The paving inspector usually check for these criteria listed below:
1.blue smoke - blue smoke indicate that the mix is too hot.
2.stiff appearance
3.mix slumped in truck.
4.lean, dull appearance - this indicates that the mix has insufficient
asphalt.
5.rising steam - too much moisture.
6.segregation.
7.contamination.
CONSTRUCTION OPERATION
CIVIL ENGINEERING DEPARTMENT OPERATION AND MAINTENANCE
COLLEGE OF ENGINEERING
When the constructed structures are completed and turned over to the
project owner, they are the operated and maintained. Allied to these
activities are repairs, rehabilitation and redevelopment and expansion.
CIVIL ENGINEERING DEPARTMENT Construction Methods and Project Management
COLLEGE OF ENGINEERING