Testrano 600
Testrano 600
Testrano 600
Author
Brandon Dupuis | Brandon.Dupuis@omicronenergy.com
Logan Merrill | Logan.Merrill@omicronenergy.com
Fabiana Cirino | Fabiana.Cirino@omicronenergy.com
Date
August 06,2019
Application Area
Transformer testing with PTM
Keywords
PTM guide
Version
v 1.0
Document ID
Abstract
This application note is a step-by-step guide for users creating a test plan in the PTM software for
electrical diagnostic testing of power transformers. Important settings and tips for obtaining a good
measurement are highlighted in the guide for each major test associated with the TESRANO 600.
General information
OMICRON electronics GmbH, including all international branch offices, is henceforth referred to as
OMICRON.
The product information, specifications, and technical data embodied in this Application Note
represent the technical status at the time of writing and are subject to change without prior notice.
We have done our best to ensure that the information given in this Application Note is useful, accurate
and entirely reliable. However, OMICRON does not assume responsibility for any inaccuracies which
may be present.
OMICRON translates this Application Note from the source language English into a number of other
languages. Any translation of this document is undertaken for local requirements, and in the event of
a dispute between the English and a non-English version, the English version of this note shall
govern.
All rights, including translation, reserved. Reproduction of any kind, for example, photocopying,
microfilming, optical character recognition, and/or storage in electronic data processing systems,
requires the explicit consent of OMICRON. Reprinting, wholly or partly, is not permitted.
© OMICRON 2019. All rights reserved. This Application Note is a publication of OMICRON.
DANGER
Death or severe injury caused by high voltage or current if the respective
protective measures are not complied with.
Only experienced and competent professionals that are trained for working in high voltage or high
current environments may implement this Application Note. Additionally, the following qualifications
are required:
• Authorized to work in environments of energy generation, transmission or distribution, and
familiar with the approved operating practices in such environments.
• Familiar with the five safety rules.
• Good knowledge/proficient in working with the TESTRANO 600 and Electrical Diagnostic
Testing of Power Transformers.
Perform Measurements
In addition to providing a step-by-step guide for using PTM, the intention of this document is to also
help the user develop good testing practices, which can help increase the accuracy and quality of the
measurements performed, as well as decrease the likelihood of making safety related mistakes.
The home screen of the PTM software is shown in Figure 2, and can be used to complete the
following tasks,
Connect the OMICRON equipment to the laptop via an Ethernet cable
Access the PTM Database via the “Manage” option
Create a new test plan
A new test plan can be created either by clicking the “New guided job” or “Manage” button; however,
the “New guided job” button is a more direct way of creating a new test plan and allows the user to
bypass the data manager. Therefore, to create a new test plan for a power transformer, select the
“New guided job” button.
Once a new job is created, the user will have access to the five main sections of the PTM software,
which include, the “overview”, “location”, “asset”, “tests”, and “report” section. The five sections can
be found on the left panel of PTM (see Figure 3). The user should complete these sections in order
from top to bottom, as shown in Figure 3.
Start
Finish
Figure 3: PTM Left Panel- Workflow
NOTICE
It is important that the “Asset” section of the software is completed from top-to-bottom. The
“Asset” section may change based on a previous selection so it is important to enter the
information accurately, and in order.
Once the main transformer nameplate information is complete, notice that the “Asset” section
expands into 5 tabs, including the “Transformer”, “Bushings”, “Tap Changers”, “Surge Arresters”, and
“DGA Trending” sections, as highlighted in Figure 7. It is recommended that the first four sections are
completed from left-to-right, starting with the “Transformer” section. The “DGA Trending” tab
automatically documents results of available oil analysis tests in the PTM database for the associated
asset.
1 2 3 4 5
Remain in the “Transformer” section and scroll down to the “Winding configuration” section. The
winding configuration section is critical to PTM, and will heavily influence the test plan. By entering
the correct winding configuration and vector group of the transformer you would like to test, the PTM
software will provide the correct connection diagrams for the available tests.
For example, if the asset you would like to test is a 3-phase, two-winding, DYn1 transformer, then the
vector group shown in Figure 9 would be selected. If you are unsure of the correct vector group,
visually match the vector group on the nameplate of the transformer to the options provided below.
Once the desired vector group is selected, click the “ok” button in the lower right-hand corner to
confirm.
Please note that from the software’s perspective, there is a major difference between a Y-
winding (wye winding with no accessible neutral) and a Yn-winding (wye winding with an
accessible neutral). To prevent the software from populating the incorrect test plan, please
make sure that the vector diagram you select accurately represents the transformer you
would like to test.
Once the “winding configuration” section is complete, scroll down to the “Ratings” section.
Once the “Ratings” section is complete, scroll down to the “Impedances” section.
To compare the measured leakage reactance values to the nameplate (factory) short-circuit impedance, the
following information is required, and can typically be found on the nameplate of the transformer,
*Leakage Reactance Z (%)
*Base Power
*Base Voltage
*OLTC and/or DETC position (when applicable)
Once the “Impedances” section is complete, scroll down to the “Others” section.
Once the “Transformer” nameplate information is complete, scroll up to view the tabs located at the
top of the “Asset” section. If the transformer has bushings that you would like to test, please click the
“Bushings” tab (highlighted in Figure 13) to begin populating the nameplate information of the
bushings. Otherwise, proceed to the next section.
Note, for the “Asset type”, selecting the “With test tap” option will
set the output voltage to 500V for a C2 power factor test for that
particular bushing. If the “With potential tap” option is selected,
the output voltage for the C2 power factor test will be 2000V.
Next, scroll to the right to view more bushing nameplate fields, as shown in Figure 15.
Finally, scroll to the right to view the final bushing nameplate fields, as shown in Figure 16.
If the transformer you would like to test has a de-energized and/or load tap changer, click on the “Tap
changers” tab in the “Asset” section, as shown in Figure 17. If the transformer you would like to test
does not have a tap changer, then please proceed to the next section.
As an example, let’s say that you would like to test a transformer that has the following tap changer
configuration,
> Load Tap Changer (OLTC): 16R-16L located on the low-voltage winding
> No-Load Tap Changer (DETC): 1-5 located on the high-voltage winding
Then, the “Tap Changers” section would be populated as shown in Figure 18.
NOTICE
Once the Tap Changer information is complete, click the “Transformer” tab and scroll down
to the leakage reactance section. Then, populate the OLTC and/or DETC position that the
factory short-circuit impedance test was performed on (most likely the nominal tap
positions).
If the transformer has surge arresters that you would like to test, click on the “Surge arresters” tab in
the “Asset” section, as shown in Figure 19. Note, the surge arrester nameplate information is only
required if you would like to perform a watts loss test on the surge arresters. Otherwise, entering the
arrester information is for documentation.
To enter the nameplate information for one or more surge arresters, click the box next to the surge
arrester that you would like to add to the test plan.
Input the following critical information to correctly perform a watts loss test by using PTM,
The number of individual units in the surge arrester stack
The rated line-to-ground voltage of the surge arrester(s)
The test voltage for the arrester. We recommend that the test voltage does not
exceed 20% of the rated line-to-ground voltage for each arrester.
The DGA Trending Tab documents all available “Oil Analysis” tests in PTM associated with the asset.
This tab is only available if the license has been purchased. It is only populated if at least two oil
analyses are available for the asset. It assesses DGA results using interpretation methods such as
Duval’s triangles or gas ratio methods according to IEEE C57.104 and IEC60599.
List of all available tests that can be performed on This column is the current “Test Queue” This column
this transformer, based on the nameplate information and corresponds to the tests shown in represents global
entered in the Asset section. The tests shown the left panel of the PTM software. test settings that
depend on the test set selected. can be applied to
To remove a test from the “Test Queue”, specific tests. For
If you would like to add one or more tests to the “Test click the “X” to the right of the name of example, the
Queue”, simply click the plus (“+”) symbol to the right the test you would like to remove. temperatures
of the test you would like to add. entered below
The tests in the “Test Queue” can be
can be used to
Tests that have a yellow star to the left of their name arranged in any order that you would like.
temperature
(e.g. “Surge Arrester Watt Losses H” shown in Figure Simply click and drag the name of the
correct the power
21) are tests that are highly recommended, but not test you would like to move up or down
factor
currently in the “Test Queue”. the “Test Queue”.
measurements.
Once the test plan has been created, you are ready to begin testing! Use the left panel of PTM to
select the test which you would like to perform first. Note, the tests can be performed in any order
that you would like. In addition, you can add more tests to the “Test Queue” at any time by clicking on
the “Tests” tab and populating the desired tests (as shown in Figure 22).
Both the TESTRANO 600 and CP TD1 are required. Before beginning the overall power factor test,
please consider the following,
Properly isolate the bushing terminals from any cable, bus-bar, support insulator, surge
arrester, etc.
Properly ground the transformer tank, TESTRANO 600, and CP TD1
Short-circuit all high-voltage bushings, including the neutral (if applicable)
Short-circuit all low-voltage bushings, including the neutral (if applicable)
Short-circuit all tertiary bushings, including the neutral (if applicable)
Remove all in-service grounds from all the neutral bushings
Place the load tap changer in any off-neutral tap position (Note: when investigating a failure, it
is recommended to leave the LTC in the as-found position)
Clean and dry the surface of all bushings.
o If the bushings have a porcelain exterior, use Windex or Colonite
o If the bushings have a silicone exterior, use a clean, dry rag
Do not test under the following conditions to avoid bad test results
o Rain
o High-humidity situations
o Oil temperatures close to or below 5ºC
Once these considerations have been confirmed, connect the test set leads to the transformer by
using the connection diagram.
Ensure the HV cable is “in the clear”. The last two feet of the HV cable should not touch any
surface of the transformer ( transformer tank, the bushing surfaces, etc.)
Note, the connection diagram may change depending on which block of the power factor test you are
trying to complete (i.e. “Injection at X” vs “Injection at H”). Consider an overall power factor test on a
two-winding transformer. First, the user would perform an “Injection at H” test, as shown in Figure 23.
Once the “Injection at H” test is completed, the user would proceed to the “Injection at X” test and use
the test connections shown in Figure 24.
Once the test considerations and test connections have been verified for the overall power factor test,
scroll down to the “Settings and conditions” section to verify the proper test settings for the test.
To temperature correct the measured power factor values to 20°C, select the “Temperature
correction” option. Then, by using the dropdown box, select the temperature type (e.g. top
oil temp., average oil temp, etc…) that you would like to use for the correction. The
temperature correction factors are no longer supported by any standard. We
recommend not to temperature correct, as results may be misleading.
You must click “Calculate” to apply the correction factor to the measured test results.
We recommend that you click the “Use reference voltage” field, which will automatically
correct all power factor measurements to 10kV and unlock a few key features, such as the
cross-check feature.
Once the desired test settings have been confirmed, scroll down to the “Assessment” section.
NOTICE
Enabling the assessment feature
Please note that the assessment feature will only be available if the following conditions are met,
1. The insulating medium of the transformer has been selected in the “Asset – Transformer -
Others” section
2. The “Temperature correction” feature has been enabled (as shown in Figure 25)
Once the “Assessment” section has been completed, scroll down to the “Measurements” section.
NOTICE
Locked in asset data after performing measurement
Please note that once a measurement within this job has been performed many of the
fields within the “Asset” section will be locked and inaccessible. Therefore, it is critical that
all the “Asset” (i.e. the nameplate) information is correct before performing the first
measurement. In addition, please verify that the “Settings and conditions” section is correct
before performing the first measurement.
Once all measurements for the “Injection at H” section are complete, click on the measurement for
“row No. 4”, as highlighted in the following image. Once the proper test connections are made for the
“row No. 4” measurement, select the “Start all” option for the “Injection at X” test. If the “Start all”
option is not green, then the user must connect the TESTRANO 600 to their laptop before beginning
the test.
Once the power factor measurements are complete, perform the two “sanity checks” to verify the
validity of the test results. The two “cross check” features are enabled after checking “Use reference
voltage” box in the “Settings and conditions” section to correct the measured values to 10kV. The two
“sanity checks” that must be performed include,
• Cross check #1: calculated ICHL/ICLH vs measured ICHL/ICLH (see comments in Figure 27)
• Cross check #2: measured ICHL vs ICLH (see comments in Figure 27)
If either of the two sanity checks are not valid, then investigate the following possibilities, and repeat
the test,
• Poor test connection, poor ground connection, and/or poor test procedure
• Possible voltage sensitive defect within insulation (please repeat test and perform the voltage
sweep)
Both the TESTRANO 600 and CP TD1 are required. Before beginning the bushing C1 power factor
test, please consider the following,
Properly isolate the bushing terminals from any cable, bus-bar, support insulator, surge
arrester, etc.
Properly ground the transformer tank, TESTRANO 600, and CP TD1
Ensure the bushings remain short circuited as in the Overall PF test
Remove all in-service grounds from all the neutral bushings
Clean and dry the surface of each bushing before testing
o If the bushings have a porcelain exterior, use Windex or Colonite
o If the bushings have a silicone exterior, use a clean, dry rag
Do not test under the following conditions to avoid bad test results
o Rain
o High-humidity situations
o Oil temperatures close to or below 5ºC
Confirm the Test Mode is UST-A (automatically configured by PTM)
Confirm the Test voltage does not exceed line-to-ground voltage rating of bushing
(automatically configured by PTM)
Remove one bushing tap cap at a time (i.e. only for the bushing currently under test)
Once these considerations have been confirmed, connect the test set leads to the apparatus by using
the connection diagram in PTM,
Place High-voltage lead on bushing center-conductor and Red-A lead on bushing test or
potential tap
Ensure the HV cable is “in the clear”. The last two feet of the HV cable should not touch any
surface of the transformer (transformer tank, the bushing surfaces, etc.)
Figure 28 shows the test connections for a C1 power factor test for the H1 bushing. Note, the
connection diagram may change depending on which bushings you are testing. Once the proper test
considerations and test connections have been confirmed, scroll down to the “Settings and
conditions” section.
Once the desired test settings have been confirmed, scroll down to the “Assessment” section.
NOTICE
Locked in Asset Data after performing measurement
Note, once a C1 power factor measurement has been completed, many of the “Settings
and conditions” fields will be locked and cannot be changed, so please verify that the
settings are correct before proceeding.
NOTICE
Please note that the assessment will only be available if the insulation type of the bushing
was selected in the “Asset - Bushings” section of the PTM software (see Figure 16).
Note, if the nameplate C1 power factor and capacitance values are entered in the “Asset - Bushings” section, then the
assessment will be performed by comparing the measured values to the nameplate values. However, if the nameplate values
are not available, the assessment will be performed by comparing the measured values to absolute limits.
Once the “Assessment” section is complete, scroll down to the “Measurements” section and select the
“Start” option for the measurement you would like to perform. For example, selecting the “Start”
option highlighted in Figure 31 would begin the H1 C1 power factor test. Note, if the “Start” option is
not green, then the user must connect their laptop to the TESTRANO 600 to begin the test.
Once all the bushing C1 Power Factor measurements are complete, the user should verify the validity
of the measurements, before proceeding to the next test. To help confirm the validity of the test
results consider the following,
• Are the capacitance values for each bushing > 200pF? Typically, the measured capacitance
for a bushing C1 power factor test is >200pF.
• Do the measured capacitance values compare well to the nameplate capacitance values?
They should compare well.
• Do the measured capacitance values of each bushing compare well to each other? (assuming
they are the same make, model, etc…) They should compare well.
If the measurements do not appear to be valid, then consider the following possibilities, and repeat
the test,
• Poor test connection, poor grounding, and/or poor test procedure (please see
considerations at the beginning of the section)
Both the TESTRANO 600 and CP TD1 are required. Before beginning the bushing C2 power factor
test, please consider the following,
Properly isolate the bushing terminals from any cable, bus-bar, support insulator, surge
arrester, etc.
Properly ground the transformer tank, TESTRANO 600, and CP TD1
Ensure the bushings remain short circuited as in the Overall PF test
Clean and dry the test tap area of each bushing before testing
Confirm the Test Mode is GSTg-A (automatically configured by PTM)
Confirm the correct test voltage for the C2 power factor test depending on whether the
bushing has a test (500V) or potential (2000V) tap.
Once these considerations have been confirmed, connect the test set leads to the apparatus
according to the connection diagram in PTM,
Place the High-voltage lead on test or potential tap of bushing. The high-voltage lead adapter
shown in Figure 32 should be used to help make the test connection to the bushing tap.
Place the Red-A lead on center-conductor of bushing
Ensure the HV cable is “in the clear”. The last two feet of the HV cable should not touch any
surface of the transformer (transformer tank, the bushing surfaces, etc.)
Figure 33 shows an example test connection for a C2 power factor test for the H1 bushing. Note, the
connection diagram may change depending on which bushings you are testing. Once the proper test
considerations and test connections have been confirmed, scroll down to the “Settings and
conditions” section.
Note, if the nameplate C2 power factor and capacitance values are entered in the “Asset” section, then the assessment will be
performed by comparing the measured values to the nameplate values. However, if the nameplate values are not available, the
assessment will be performed by comparing the measured values to absolute limits.
Once the “Assessment” section is complete, scroll down to the “Measurements” section and select the
“Start” option for the measurement you would like to perform. For example, selecting the “Start”
option highlighted in Figure 36 would begin the H1 C2 power factor test. Note, if the “Start” option is
not green, then the user must connect their laptop to the TESTRANO 600 to begin the test.
• Are the capacitance values for each bushing > 200pF? Typically, the measured capacitance
for a bushing C2 power factor test is >200pF.
• Do the measured capacitance values compare well to the nameplate capacitance values?
They should compare well.
• Do the measured capacitance values of each bushing compare well to each other? (assuming
they are the same make, model, etc…) They should compare well.
If the measurements do not appear to be valid, then consider the following possibilities, and repeat
the test,
• Poor test connection, poor grounding, and/or poor test procedure (please see
considerations at the beginning of the section)
Both the TESTRANO 600 and CP TD1 are required. Before beginning the bushing energized collar
test, please consider the following,
Properly isolate the bushing terminals from any cable, bus-bar, support insulator, surge
arrester, etc.
Properly ground the transformer tank, TESTRANO 600, and CP TD1
Clean and dry the surface of each bushing before testing
o If the bushings have a porcelain exterior, use Windex or Colonite
o If the bushings have a silicone exterior, use a clean, dry rag
Confirm the Test Mode is UST-A (automatically configured by PTM)
Once these considerations have been confirmed, connect the test set leads to the apparatus by using
the connection diagram in PTM,
Place the High-voltage lead on conductive collar. The high-voltage lead adapter shown in
Figure 32 should be used to help make the test connection to the collar.
Placed the conductive strap tightly around the bushing under test below the top skirt
Place the Red-A lead on center-conductor of bushing
Ensure the HV cable is “in the clear”. The last two feet of the HV cable should not touch any
surface of the transformer (transformer tank, the bushing surfaces, etc.)
Figure 37 shows an example test connection for an energized collar test on the H1 bushing.
Note, the connection diagram may change depending on which bushings you are testing. Once the
proper test considerations and test connections have been confirmed, scroll down to the “Settings and
conditions” section.
Once the correct test settings have been confirmed, scroll down to the “Measurements” section and
select the “Start” option for the measurement you would like to perform. For example, selecting the
“Start” option highlighted in Figure 39 would begin the H1 energized collar test. Note, if the “Start”
option is not green, then the user must connect their laptop to the TESTRANO 600 to begin the test.
NOTICE
Please note the energized collar test does not provide an automatic assessment. The
results of this test can be assessed by the following methods:
Comparing the measured current and watt losses of each bushing to each other
(assuming they are the same make, model, etc…)
Comparing the measured current and watt losses to previous test results
Ensuring the watts losses at 10kV is <100 mW
Both the TESTRANO 600 and CP TD1 are required. Before beginning the exciting current test, please
consider the following,
Remove all the shorting jumpers used previously in the power factor test (the exciting current
test is an “open circuit test” )
Follow the connection diagram, and pay close attention to the external ground leads that may
be required for certain winding configurations.
Figure 40 shows the test connection for the Phase-A measurement of a DYn1 transformer. Notice that
there are two external ground leads required (H2 and X0) to complete the measurement successfully.
However, keep in mind that these ground connections may change depending on the phase being
tested. Note, the connection diagram may change once another phase is selected.
Once the proper test connections have been made, scroll down to the “Settings and conditions”
section.
Once the correct test settings have been confirmed, scroll down to the “Measurements” section.
Select the phase that you would like to test and then click the “Start” option, which is highlighted in
Figure 42. If the “Start” option is not green, then the user must connect the TESTRANO 600 to their
laptop.
The phase that you would like to test can be selected by clicking on the colored
indicator for each phase. Please note, the connection diagram will change once a
particular phase is selected.
To begin the test, click on the phase that you would like to measure, and then select
the “Start” option.
Only the TESTRANO 600 is required. Before beginning the turns-ratio test, please consider the
following,
This test utilizes the TESTRANO 600’s “one-time test connection”, so only one connection will
be necessary for the entire test.
Always run the TTR test before the DC winding resistance test since a magnetized core can
affect the results.
Fig. 43 shows the wiring diagram for a DYn1 transformer using the 3-phase test connection method.
Once the proper test connections have been made, scroll down to the “Settings and conditions”
section.
If a DETC and/or LTC was entered in the “Asset – Tap Changers” section, then
indicate which tap changer you would like to change during the turns-ratio
measurement. If a tap changer was not entered in the “Asset – Tap Changers” section
The default test voltage is 120V, then these fields require no action.
but can be manually changed. For example, let’s say that you would like to keep the DETC position fixed on position
Note, the maximum test voltage is 3, and test the LTC from 16R-16L, then the settings shown in Figure 44 should be
400V if the 3 x 400V Output mode selected.
is selected.
Note, once the measurement begins, the start and stop tap positions can only be
changed “on the fly” if the automatic tap control box is not selected.
Select the standard (IEEE or IEC) that you would like to use to
auto-assess your turns-ratio results.
Note, custom limits can be set by selecting the “Customer
specific limits” option.
Select the “Assess during measurements” option if you would like PTM
to assess your test results in real-time. If this feature is not enabled,
then the user will have to manually select the “Assess measurements”
option, once the test is complete.
Once the “Assessment” section is complete, scroll down to the “Measurements” section and select the
“Start” option. Note, if the “Start” option is not green, then the user must connect their laptop to the
TESTRANO 600 to begin the test.
Only the TESTRANO 600 is required. Before beginning the DC Winding Resistance test, please
consider the following,
This test utilizes the TESTRANO 600’s “one-time test connection”, so only one connection will
be necessary for the entire test. (Unless the single phase injection method is used)
The DC Winding Resistance Test should always be followed by the Demagnetization test.
NOTICE
Please note that the DC winding resistance test can be “stubborn” at times due to
difficulties with saturation of the core. The measurement can still be completed in a
reasonable amount of time if the test current is set correctly. A good guideline is to set the
test current between 10% and 15% of the rated winding current. This applies enough
current to easily saturate the core, without heating up the winding. Typically, we
recommend 5A for the H winding and 25A for the X winding, as long as current ratings of
the windings are not exceeded.
The TESTRANO’s “one-time test connection” for a DYn1 transformer is displayed in fig. 47.
Once the proper test connections have been made, scroll down to the “Settings and conditions”
section.
NOTICE
Compromised results possible if measurement not stable
Please note that it is critical that the resistance measurement stabilizes before the
measurement is recorded, so if the “Automatic result” feature is enabled (see Figure 48),
we recommend not changing the default setting of .01% for the “Tolerance R dev” any
higher than 0.05%.
Once the correct settings have been confirmed, scroll down to the “Assessment” section.
Select the standard (IEEE or IEC) that you would like to use to auto-assess your winding
resistance results. Note, custom limits can be set by selecting the “Customer specific
limits” option.
Select the “Assess during measurements” option if you would like PTM to assess your test
results in real-time. If this feature is not enabled, then the user will have to manually select
the “Assess measurements” option, once the test is complete.
Only the TESTRANO 600 is required. Before beginning the Demagnetization Test, please consider
the following,
This test utilizes the TESTRANO 600’s “one-time test connection”, so only one connection will
be necessary for the entire test.
This test is used to reduce the amount of residual magnetism in the transformer core, not to
analyze the health of the transformer. It is typically performed after events which magnetize
the core (i.e. after a DC Winding resistance test or if transformer taken out of service has
experienced a fault)
The test connection example shown in figure 51 displays the wiring diagram for a DYn1 transformer.
Once the proper test connections have been made, scroll down to the “Settings and conditions”
section. The demagnetization test should be run at the same
test current as the high-side DC winding resistance
test (below 15% of rated winding current).
Once the correct settings and test connections have been confirmed, scroll down to the
“Measurements” section and click “Start”. If the “Start” option is not green, then the user must connect
the TESTRANO 600 to their laptop.
Remanence: the residual magnetism remaining in the core after the test has been completed.
Initial remanence: the residual magnetism in the core when the test was started.
Only the TESTRANO 600 is required. The leakage reactance test consists of two test types, which
include,
• 3-Phase Equivalent Test: The purpose of this test is to reproduce the factory short-circuit
impedance value. Therefore, once the 3-phase equivalent measurement is performed,
the PTM software will automatically calculate and compare the measured field value to
the nameplate value. The factory short-circuit impedance value can typically be found on
the nameplate of the transformer, as shown in the example in Figure 54.
• Per-Phase Equivalent Test: The results from this test may not compare well to the
nameplate short-circuit impedance, but it is valuable because it helps isolate and test one
individual phase at a time, to identify a fault localized to one phase. The PTM software
will automatically compare the results among phases.
NOTICE
Please note that it is critical that the resistance and reactance of the shorting jumpers used
to short-circuit the secondary (or tertiary) of the transformer is negligible relative to the test
circuit. We recommend using a wire gauge of #4 or less. In addition, the length of the
shorting jumpers should be as short as possible from bushing terminal to bushing terminal.
Finally, the shorting jumpers should be solidly bonded to the bushing terminals, to avoid
creating additional resistance within the test circuit.
NOTICE
Please note that to compare the measured 3-phase equivalent value to the factory short-
circuit impedance, the DETC and/or LTC must be tested on the same tap position(s) as the
factory. Otherwise, the measured field values and nameplate values may not compare
well.
Please follow the connection diagram closely when changing between phases, and the two test types
outlined above.
An example wiring diagram for a 3-Phase Equivalent Test on a DYn1 transformer is shown in figure
55.
Once the proper test connections have been made, scroll down to the “Settings and conditions”
section.
NOTICE
Please note that to enable the leakage reactance auto-assessment, the following
conditions must be met,
The “Temperature correction” setting must be enabled as shown in Figure 56.
The DETC and/or LTC position(s) selected on the transformer must be identical to
the DETC and/or LTC position(s) entered to the “Asset – Transformer - Leakage
Reactance” section (Figure 11, 57).
The nameplate short-circuit impedance, base power, and base voltage must be
entered in the “Asset – Transformer - Leakage Reactance” section (shown in
Figure 11, 57).
Select the standard (IEEE or IEC) that you would like to use to auto-assess your leakage reactance results. Note,
custom limits can be set by selecting the “Customer specific limits” option.
Select the “Assess during measurements” option if you would like PTM to assess your test results in real-time. If this
feature is not enabled, then the user will have to manually select the “Assess measurements” option, once the test is
complete.
Once the “Assessment” section is complete, scroll down to the “Measurements: 3Ph equiv.” section.
When you are ready to begin the test, click the “Start” option.
NOTICE
Adjust the “Test current” (fig.56) depending on the measured impedance of the transformer. We
recommend performing the first measurement at a “Test current” of 1A, and monitoring the
measured voltage during the line-frequency (60Hz) test. We recommend that the measured
voltage at 60Hz is >50V. If the measured voltage is <50V, then increase the test current and
repeat the test until one of the following occurs,
• The measured test voltage is >50V (at 60Hz)
• The “Test current” has reached 5A
Once the 3-phase equivalent measurement is complete, please select the “Measurements: per-
phase” tab. Next, select the Phase-A measurement by clicking on the corresponding colored
indicator in the “Phase selection” menu, and observe the connection diagram to make the correct test
connections. An example of a per-phase equivalent test connection is shown in Figure 61. When you
are ready to begin the test, click the “Start” option next to the “Phase selection” menu as shown in
Figure 60. Repeat this procedure for the remaining phases (i.e. B and C), keeping in mind that the
connection diagram may be different for each measurement.
Once the measurement for all three phases is complete, the software will
calculate the average impedance of each phase, and then compare each phase
to the average. Typically, we recommend that all three phases compare to within
2% of the average, to pass the per-phase leakage reactance test.
© OMICRON
www.omicronenergy.com Subject to change without notice.