Ausgrid
Ausgrid
Ausgrid
Document No : NW000-S0087
Amendment No : 5
NETWORK Approved By : Head of AR&P
Approval Date : 04/12/2020
Minor amendments approved on 21/10/2021
ISSUE
For issue to all Ausgrid and Accredited Service Providers’ staff involved with the making of cable joints and terminations on low
voltage cables, and is for reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments on www.ausgrid.com.au.
Where this Standard is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document.
DISCLAIMER
As Ausgrid’s Standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at any
time. It is possible that conflict may exist between Standard documents. In this event, the most recent Standard shall prevail.
This document has been developed using information available from field and other sources and is suitable for most situations
encountered in Ausgrid. Particular conditions, projects or localities may require special or different practices. It is the responsibility of the
local manager, supervisor, assured quality contractor, accredited service provider and the individuals involved to make sure that a safe
system of work is employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for anything done or not done, as a result of this Standard.
All design work, and the associated supply of materials and equipment, must be undertaken in accordance with and consideration of
relevant legislative and regulatory requirements, latest revision of Ausgrid’s Network Standards and specifications and Australian
Standards. Designs submitted shall be declared as fit for purpose. Where the designer wishes to include a variation to a Network Standard
or an alternative material or equipment to that currently approved the designer must obtain authorisation from the Network Standard
owner before incorporating the variation to a Network Standard or alternative material into a design. All designers including external
designers authorised as Accredited Service Providers will seek approval through the approved process as outlined in NS181 Approval
of Materials and Equipment and Network Standard Variations. Seeking approval will ensure Network Standards are appropriately updated
and that a consistent interpretation of the legislative framework is employed.
Notes: 1. Compliance with this Network Standard does not automatically satisfy the requirements of a Designer Safety Report. The
designer must comply with the provisions of the Work Health and Safety Regulation 2017 (NSW - Part 6.2 Duties of designer of structure
and person who commissions construction work) which requires the designer to provide a written safety report to the person who
commissioned the design. This report must be provided to Ausgrid in all instances, including where the design was commissioned by or
on behalf of a person who proposes to connect premises to Ausgrid’s network, and will form part of the Designer Safety Report which
must also be presented to Ausgrid. Further information is provided in Network Standard (NS) 212 Integrated Support Requirements for
Ausgrid Network Assets.
2. Where the procedural requirements of this document conflict with contestable project procedures, the contestable project procedures
shall take precedent for the whole project or part thereof which is classified as contestable. Any external contact with Ausgrid for
contestable works projects is to be made via the Ausgrid officer responsible for facilitating the contestable project. The Contestable
Ausgrid officer will liaise with Ausgrid internal departments and specialists as necessary to fulfil the requirements of this Standard. All
other technical aspects of this document which are not procedural in nature shall apply to contestable works projects.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain, ambiguous or otherwise in need of
interpretation, the user should request Ausgrid to clarify the provision. Ausgrid’s interpretation shall then apply as though it was included
in the Standard, and is final and binding. No correspondence will be entered into with any person disputing the meaning of the provision
published in the Standard or the accuracy of Ausgrid’s interpretation.
KEYPOINTS
This Standard has a summary of content labelled “KEYPOINTS FOR THIS STANDARD”. The inclusion or omission of items in this
summary does not signify any specific importance or criticality to the items described. It is meant to simply provide the reader with a quick
assessment of some of the major issues addressed by the Standard. To fully appreciate the content and the requirements of the Standard
it must be read in its entirety.
This Network Standard specifies General requirements include: A large number of standard joints and Some additional requirements include;
Ausgrid's construction requirements for Use only approved materials terminations are detailed and in general
Low Voltage (LV) cable joints, Limits on number of UGOHS on a pole include: Testing of joints after installation in
terminations, and LV Underground to Mechanical protection of UGOHs accordance with NS161
Overhead (UGOH) Connections. The Other UGOH requirements LV cable joints of several generic All materials to be new and may be
following scope applies and risks Stripping dimensions and heatshrink types, eg straight through, lay on tees, purchased through Ausgrid stores
addressed include: technology etc.
Lubrication of stainless steel bolts and UGOH construction details
Only approved and currently in use set-screws Service and distribution pillar details
construction standards are Visually impaired persons Kiosk terminations
documented Disconnection link boxes
Due to changes in practice and Safety requirements include: Pot end details
mergers of earlier organisations there Lead exposure
may be existing non-compliant Asbestos
construction within Ausgrid’s supply
network.
All equipment and materials used to be
free of asbestos and asbestos related
materials.
Any variation from this standard must
be approved by Ausgrid prior to being
implemented.
Where to for more information? Where to for more information? Where to for more information?
Section 3, 4 Section 5 - 45 Section 46, 47
Where to for more information? Tools and Forms Tools and Forms Tools and Forms
Section 1, 2 None Annexures A and B None
Network Standard
NS127
Low Voltage Cable Joints and Terminations
Contents
PURPOSE .............................................................................................................................................. 7
SCOPE ................................................................................................................................................... 7
GENERAL REQUIREMENTS ................................................................................................................ 7
3.1 Approved products ..................................................................................................................... 7
3.2 Total number of Service UGOH connections on an Ausgrid pole .............................................. 7
3.3 Mechanical Protection of UGOHs .............................................................................................. 7
Customer (underground service) UGOHs ...................................................................... 7
LV Network UGOHs ........................................................................................................ 8
Existing LV UGOH covers .............................................................................................. 8
Cable Connection Bond for Metallic Covers ................................................................... 8
UGOHs on Ausgrid poles ............................................................................................. 10
Sub-transmission poles and UGOHs ............................................................................ 10
3.4 UGOHs on air break switch (ABS) poles .................................................................................. 11
3.5 UGOHs on substation poles (PTs) ........................................................................................... 11
3.6 Service UGOHs in excess of 200 amps ................................................................................... 11
3.7 Phase and neutral/earth connectors ........................................................................................ 11
3.8 Stripping dimensions ................................................................................................................ 11
3.9 Other requirements ................................................................................................................... 11
3.10 Lubrication of stainless steel bolts and set-screws .................................................................. 12
3.11 Consideration of Visually Impaired Persons............................................................................. 12
Location of Pillars ......................................................................................................... 12
Short Turret Pillars ........................................................................................................ 12
Contrast against Surrounding Surfaces ........................................................................ 12
Determining Luminance Contrast ................................................................................. 13
3.12 Field recording of network assets ............................................................................................. 13
SAFETY REQUIREMENTS ................................................................................................................. 14
4.1 Lead exposure .......................................................................................................................... 14
4.2 Asbestos ................................................................................................................................... 14
CONSTRUCTION OF UGOH SERVICE CABLE CONNECTIONS (LV1-14) ...................................... 15
UGOH CONSTRUCTION, BARE OH MAINS TO 240 AL4 XQ Z/SAC, 300 AL4 XQ Z/SAC OR
240 CU4 XQ Z CABLES (LV 1-43) ..................................................................................................... 19
UGOH CONSTRUCTION, SINGLE CIRCUIT OF LV ABC TO 240 AL4 XQ Z/SAC OR 300 AL4 XQ
Z/SAC CABLES (LV1-70).................................................................................................................... 22
UGOH CONSTRUCTION, DOUBLE CIRCUIT OF LVABC TO 240 AL4 XQ Z/SAC OR 300 AL4
XQ Z/SAC CABLES (LV1-44) ............................................................................................................. 25
UGOH CONSTRUCTION, SINGLE CIRCUIT OF LVABC TO 240 AL4 XQ Z/SAC OR 300 AL4 XQ
Z/SAC CABLES WITH FUSE SWITCH DISCONNECTOR (LV1-71) ................................................. 28
UGOH CONSTRUCTION, DOUBLE CIRCUIT OF LVABC TO 240 AL4 XQ Z/SAC OR 300 AL4
XQ Z/SAC CABLES WITH FUSE SWITCH DISCONNECTOR (LV1-46) ........................................... 31
UGOH CONSTRUCTION, BARE OH MAINS TO 240AL4 XQ Z/SAC OR 300AL4 XQ Z/SAC
CABLES WITH FUSE SWITCH DISCONNECTOR (LV1-5)............................................................... 34
PURPOSE
This Network Standard specifies Ausgrid's construction requirements for Low Voltage (LV) cable
joints, terminations and LV Underground to Overhead (UGOH) Connections.
SCOPE
Although there are many types of LV joints, terminations, and UGOH connections on Ausgrid's
reticulation system, only the approved construction standards currently in use are detailed in this
document. Construction details for joints, terminations, and UGOH connections which are not
covered in this standard should be sought from Ausgrid as required.
GENERAL REQUIREMENTS
3.1 Approved products
The specifications contained in this standard provide Ausgrid’s stockcode numbers for all approved
components. Alternative components must not be used unless specifically approved by Ausgrid.
Refer to Clause 47.0 Stores and Materials.
If the mechanical protection used on Customer LV UGOH cables is metallic, the metallic protection
cover shall be made of galvanised steel and shall be bonded to the neutral of the LV overhead
mains as illustrated in Figure 3.1, in accordance with Network Standard NS116.
Mechanical protection shall be of non-metallic material for Customer LV UGOH cables installed on
poles supporting an earth down lead that is part of a HV earthing system.
Mechanical protection between 2000mm below the lowest set of overhead conductors and the top
of the pole must be of non-metallic (non-conductive) material.
LV Network UGOHs
The required mechanical protection of LV Network UGOH cables between 3000mm above
groundline and 300mm below groundline should be of ‘U’ section construction with no side flanges
(side securing tabs are permitted) to minimise the surface area of the pole that is covered and help
prevent unauthorised climbing.
The following non-metallic UGOH cover is approved for use as mechanical protection of LV
Network UGOH cables:
If the mechanical protection used on LV Network UGOH cables is metallic, the metallic protection
cover shall be made of galvanised steel and shall be bonded to the neutral of the LV overhead
mains as illustrated in Figure 3.1, in accordance with Network Standard NS116.
Mechanical protection shall be of non-metallic material for LV Network UGOH cables installed on
poles supporting an earth down lead that is part of a HV earthing system.
Mechanical protection between 2000mm below the lowest set of overhead conductors and the top
of the pole must be of non-metallic (non-conductive) material.
If the metallic UGOH cover has a drilled hole in the cover (approximately 50mm from top of the
cover) to fix the 70mm² lug (stockcode H95851), using stainless steel M12 nut, spring washer, flat
washer and M12 x 20mm bolt, connect the neutral bond as shown above. Bolt head must be inside
the cover to avoid damage to the UGOH cable.
If there is no hole on the metallic cover, drill a hole of 13mm diameter 50mm from the top of the
cover and reapply cold galvanising paint (stockcode 176055). Then, connect the neutral bonding
cable as per above. Drilling of the hole shall be carried out before the UGOH cover is installed on
the pole to avoid any damages to the UGOH cable.
To drill a hole for the neutral bonding connection in an existing LV UGOH metallic cover installed
on a pole, the metallic cover shall be removed from the pole prior to drilling. This is to prevent any
damage to the LV UGOH cable.
It is recommended to install the neutral bond cable to the metallic cover before installing the cover
on the pole to avoid any damage to the UGOH cable.
A 70 mm² copper insulated cable (stockcode 60111) must be used to bond the LV UGOH cover to
the neutral. The following three tables shows the methods and Ausgrid stock codes which can be
used to connect the 70 mm² copper bonding cable to the OH neutral conductor. Each table shows
the different OH conductor type (LV ABC, bare aluminium and bare copper).
The 70mm² neutral bond cable (where no HV UGOH exists) must be separately saddled straight up
the pole using 12mm Galvanised double sided saddles (stockcode 176494) held in place using
self-drilling timber screws type 17 10G x 25mm (stockcode 184996) not more than 600mm apart.
Non-metallic mechanical protection (PVC Cover Strip stockcode 157552) should be placed within
2m below of the LV mains or streetlight wire.
Table 3.1 – Method to connect the bonding cable to LV ABC mains:
LV ABC 25 mm² 95 mm² 150 mm²
Connector See Note 1 below IPC IPC
Stock Code: 176580 Stock Code: 148387
Notes:
1. Insulation Piercing Connector (IPC) details: Sicame Australia Pty Ltd (Part No. TTD301XFA) or
Preformed Line Products Australia (Part No. D-K445).
2. Install two IPCs when connecting the bonding cable to LV ABC mains.
3. Make sure that the PVC insulated bonding cable is new when connecting to the LV ABC mains
using IPCs. If it is old and hard, it may prevent the teeth of the IPC connector making a sound
electrical connection and cause the connection to fail.
Table 3.2 – Method to connect the bonding cable to bare aluminium mains:
Bare Aluminium 5.5 – 14 mm diameter 6.5 – 15.5 mm diameter
Connector Bimetallic PG Clamp Bimetallic PG Clamp
Stock Code: H88013 Stock Code: 176491
Table 3.3 – Method to connect the bonding cable to bare copper mains:
Bare Copper Up to 70mm² 70 - 95 mm² 95 - 185 mm²
Connector Split Bolt Natural Stock Split Bolt Natural Stock Split Bolt Natural Stock
Code: 61374 Code: 61358 Code: 59139
4. Install two Split bolts when connecting the bonding cable to bare copper mains.
5. Bare overhead mains must be cleaned by application of a scratch brush to remove oxide
components before any electrical connection is made.
Road Road
Kerb Kerb
Minimise obstructions in this Area.
This Area to Existing UGOH This Area to
To enable future pole inspection. Pole Pole
be left free of be left free of
Neutral obstruction Neutral obstruction
axis for future axis for future
splinting of splinting of
pole. m pole.
50m
This Area to be
used for non ABS Restrict installation Customer UGOHs to be
separated by 50mm and to be Critical axis
wood poles. on ABS poles to this area (Direction of rated load)
Critical axis grouped to make use of the
(Direction of rated load) allotted area
Where no LV Network UGOH exists on the pole the first Customer UGOH will be placed on the
footpath side of the pole (or critical axis) in the allotted area. Where an LV Network UGOH exists
on a pole, the first Customer UGOH to be installed will be put adjacent to the LV network UGOH.
See the above figure.
All customers UGOHs on poles that include High Voltage construction, except ABS poles, are to be
connected on the non-climbing side of the pole.
• Cables and cable ends being worked on must be kept free of any damage or contamination
during the jointing process.
• Cables and cable cores must not be bent tighter than the manufacturers’ specified minimum
internal bending radii either during the jointing process or after they have been set in position.
Completed joints and the first 500 mm of each associated cable must be kept straight when set
in position.
• All components involved in joints and terminations (including cable components) which will
come into contact with either mastic tape or adhesive sealants must be thoroughly cleaned and
degreased prior to the application of these sealing agents. Cleaning must only be done using
lint-free cloth.
• Heatshrink tubing must be positioned correctly, and properly and evenly shrunk, free of voids
and must not be damaged due to overheating. Heatshrink components with adhesive sealant
coatings must provide effective sealing against moisture ingress when installed.
• The specified overlapping distances between various heatshrink tubing and cable components
must always be adhered to.
• Where polyurethane resin is specified for filling joints, the polyurethane resin shall be used in
accordance with the manufacturer’s instructions.
• Completed joints and terminations must be allowed to either cool down or set before they are
subjected to any mechanical load.
• The polyurethane resin in the completed joint must be allowed to set before applying
mechanical load to it or energising the joint. This is normally two hours.
• The three active cable cores shall be coloured red, white (or uncoloured) and blue. The neutral
core shall be coloured black.
• The completed joint if direct buried, shall be surrounded in soft bedding material up to a depth
of 100 mm above the joint. The bedding material must comply with the requirements of NS130.
Location of Pillars
Designers shall give consideration to visually impaired persons when determining the location of
pillars. Where possible, pillars shall be installed outside of pedestrian thoroughfares and within the
restrictions specified by NSW Streets Opening Coordination Council, “Guide to Codes and
Practices for Streets Opening”.
SAFETY REQUIREMENTS
4.1 Lead exposure
When working with lead during the cable jointing process, the persons performing the works must
comply with the controls in their SWMS and the Work Health and Safety (WHS) Regulation 2017
for working with lead and lead products. Ausgrid workers are to comply with the additional
requirements of the controls for lead in the Ausgrid WHS management system. Other workers must
comply with any additional controls within their WHS management system. For detailed guidance
on lead controls refer to WHS Regulation 2017 Part 7.2 Lead.
Any lead waste from the jointing process must be disposed of through a waste facility licenced to
receive Hazardous Waste. For additional guidance on managing hazardous waste refer to NS174C
Environmental Handbook for Construction and Maintenance.
4.2 Asbestos
Asbestos has been used within the Ausgrid network and the known locations of asbestos products
used in the underground network are listed in the GIS. For Ausgrid workers the asbestos
information in the GIS can be accessed via Network Viewer. For other workers the GIS information
is available via the Dial-Before-you-dig service. All other identified asbestos products are listed in
the Ausgrid Asbestos Register. Ausgrid workers can access the Asbestos Register from their
mobile devices or a copy of the site information can be downloaded from the register by their
supervisor. For other workers a copy of site information can be obtained from their Ausgrid point of
contact for the works.
The requirements for working with asbestos on the Ausgrid network are listed in NS211. Ausgrid
workers working with or in the vicinity of Asbestos must comply with the additional requirements for
working with asbestos in the Ausgrid WHS management system. Other workers must comply with
the controls in their SWMS and the NSW Code of Practice How to safely remove asbestos.
All materials and equipment used for construction of Ausgrid’s assets are to be free from Asbestos
and or Asbestos related products. Suppliers are expected to comply with the Work Health and
Safety Act 2011 (NSW) together with the Work Health and Safety Regulation 2017 (NSW) and
confirm in writing that all products supplied to Ausgrid contain no Asbestos related materials.
Notes:
1. 300mm of the cable cover is to be installed below ground line.
2. Insulation piercing connectors shall either have a grease filled cap fitted to seal the service
cable core ends; or the end of the service cable shall be sealed with UV inhibited
heatshrink cap.
5. The PVC-covered copper cable shall have a core conductor in which all conductors shall
be circular stranded plain annealed copper complying with the requirements of AS1125,
and the insulation shall be black V-90, and shall be UV stabilised by the addition of a
minimum of 1% carbon black. The insulation thickness shall comply with the requirements
of Section 6 of AS/NZ 5000.1 and be marked V-90 UV.
6. All heatshrink components are packaged into a single kit. Refer to item 7 for details.
8. Single phase UGOH construction shall only be used for street lighting or special services
only (eg Telstra/Optus). Where single core cables are used, they must be installed in
flexible conduit for the entire length along the pole.
Notes:
1. 300mm of the cable cover is to be installed below ground line.
2. Bi-metallic tee clamps must be used if the overhead conductors are aluminium.
3. The underground cable must be clamped at intervals not exceeding 1500 mm.
5. All heatshrink components are packaged into a single kit. Refer to Item 9 for details.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the multicore cable termination are packaged as a
single kit. Refer to Item 7 for details.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single
kit. Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the
lug barrel.
4. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink
the sleeve down starting at the glove fingers and working towards the four core cable.
5. The heatshrink components required for the multicore cable termination are packaged as a
single kit. Refer to item 7 for details.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. Refer to NS125 for the installation requirements of the fuse switch disconnector.
3. The heatshrink components required for the multicore cable termination are packaged as a
single kit. Refer to item 7 for details.
4. Abrade the cable sheath to the dimensions shown in General Arrangement and Figure 9.2
– Detail C: Cable Termination Details.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single
kit. Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the
lug barrel.
4. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink
the sleeve down starting at the glove fingers and working towards the four core cable.
5. Refer to NS 125 for the installation requirements of the fuse switch disconnector.
6. The heatshrink components required for the multi-core cable termination are packaged as
a single kit. Refer to item 7 for details.
7. Abrade the cable sheath to the dimensions shown in Figures 11.1 and 11.2.
8. Cut the tails of ABC long enough to be transferred over to any 2x95LVABC that is later
installed on the pole.
9. If the Bare OH mains are a double circuit (for example, 8x66 HDCU) then connect one set
of ABC tails to each circuit. An additional bonding cable is not required. Refer to LV 1-7 for
a description of how to connect to the OH mains.
10. The enclosed fuse switch disconnector should be installed so that it is in the correct
position when the bare mains are replaced with LV ABC. The specified dimension of
550mm assumes that the lower circuit of 95ABC will be installed 250mm below the king
bolt of the cross-arm, which is then 300mm above the fuse switch disconnector, which is
the correct position as per LV 1-46.
11. A UV resistant cable tie should be used to mechanically connect the ABC tail to the Bare
Mains within 150mm of the IPC.
Notes:
1. 300mm of the cable cover is to be installed below ground line.
2. Bi-metallic tee clamps must be used if the overhead conductors are aluminium.
3. The underground cables must be clamped at intervals not exceeding 1500 mm.
4. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 12.1.
5. Pre-heat the compression lug before placing the heatshrink sleeve over the cable. Shrink
the sleeve starting from the cable end. Apply additional heat to the sleeve and the palm of
the lug until a bead of mastic appears around the top of the sleeve.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 13.1.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single kit.
Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the lug
barrel.
4. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink the
sleeve down starting at the glove fingers and working towards the single core cable.
5. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 14.1.
6. All measurements are in millimetres (mm) unless marked otherwise.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 15.1.
3. Refer to NS125 for the installation requirements of the fuse switch disconnector.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single kit.
Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the lug
barrel.
4. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 16.1.
5. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink the
sleeve down starting at the glove fingers and working towards the single core cable.
6. Refer to NS125 for the installation requirements of the fuse switch disconnector.
7. All measurements are in millimetres (mm) unless marked otherwise.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single
kit. Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the
lug barrel.
4. Abrade the cable sheath and the cable insulation to the dimensions shown on Figure 17.1.
5. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink
the sleeve down starting at the glove fingers and working towards the single core cable.
6. Refer to NS 125 for the installation requirements of the fuse switch disconnector.
7. Cut the tails of ABC long enough to be transferred over to any 2x95LVABC that is later
installed on the pole.
8. If the Bare OH mains are a double circuit (for example, 8x66 HDCU) then connect one set
of ABC tails to each circuit. An additional bonding cable is not required. Refer to LV 1-7 for
a description of how to connect to the OH mains.
9. The enclosed fuse switch disconnector should be installed so that it is in the correct
position when the bare mains are replaced with LV ABC. The specified dimension of
550mm assumes that the lower circuit of 95ABC will be installed 250mm below the king
bolt of the cross-arm, which is then 300mm above the fuse switch disconnector, which is
the correct position as per LV 1-48.
10. A UV resistant cable tie should be used to mechanically connect the ABC tail to the Bare
Mains within 150mm of the IPC.
Notes:
1. Cover the bolted connection area with fibreglass tape to keep it free from any adhesives
flowing from item 5.
2. The heatshrink components required for the bolted connection are packaged as a single
kit. Refer to item 5 for details.
3. Position the base of the glove body level with the interface between the lug palm and the
lug barrel.
4. Position the end of the heatshrink sleeve level with the base of the glove fingers. Shrink
the sleeve down starting at the glove fingers and working towards the four core cable.
5. Refer to NS 125 for the installation requirements of the fuse switch disconnector.
6. Abrade the cable sheath to the dimensions shown in Figures 19.1 and 19.2.
7. Cut the tails of ABC long enough to be transferred over to any 2x95LVABC that is later
installed on the pole.
8. If the Bare OH mains are a single circuit (for example, 4x98 HDCU) then connect both set
of ABC tails to the circuit. Refer to LV 1-5 for a description of how to connect to the OH
mains.
9. The enclosed fuse switch disconnector should be installed so that it is in the correct
position when the bare mains are replaced with LV ABC. The specified dimension of
550mm assumes that the lower circuit of 95ABC will be installed 250mm below the king
bolt of the cross-arm, which is then 300mm above the fuse switch disconnector, which is
the correct position as per LV 1-49.
10. A UV resistant cable tie should be used to mechanically connect the ABC tail to the Bare
Mains within 150mm of the IPC.
11. Buy in from TE Connectivity Part No H16036 or from Legend Power Systems Part No
CAL240LB-12.
12. The conductor of the 240 CU4 XQ Z cables must be rounded with rounding dies (S/C
182051) before being inserted into the crimp lug.
Note: The arrangement above is shown with the front half of the lug cover removed to show
internal details. Service cables must be installed with lug cover fully assembled. See
Figure 20.4 for a fully assembled arrangement.
Notes:
1. Ausgrid will not provide any training for the installation of the Legend Power Systems URD
pillars. Please refer to Business Development Manager at Legend Power Systems if training is
required.
2. Refer to NS130 for the installation requirements of the pillar base.
3. The pillar base is backfilled with sand and has a 40mm deep sand/cement mix (20:1)
4. PVC sheaths of all cables must be terminated 25mm above the surface of the sand/cement
mix.
5. Refer to Figure 20.3 for service conduit stub details (if applicable).
6. The top of the pillar base is to be a minimum of 50 mm above the ground level.
7. The cable cores should be cut at a height of 390mm from the top of the pillar base.
8. If it is necessary to remove and reinstall the lug once it is installed; a new lug shall be used.
The conductor shall be cut below the indentations and stripped to the required length.
9. The cables shall be centred within the pillar once they are connected.
Notes (cont.):
10. The lug covers shall be arranged so that a minimum of 25mm clearance is maintained between
any part of the lug cover and inner edge of the pillar base (Refer to Figure 20.2) allowing the
turret to be fitted clear of the lug covers.
11. Fit the turret over the connections and ensure it sits in its correct position with the securing
holes aligned without applying any force to the turret. Reposition the cables if necessary.
CAUTION
Incorrect installation of the turret (ie using the securing bolts to force
it into position) will lead to premature failure.
Notes (cont.):
12. A conduit stub shall be installed in accordance with Figure 20.3 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
• Only use conduit 90 degree large sweep bends as any sharper angle will impede cable
entry.
• The upper end of the conduit stub shall extend 50 mm above the sand/cement mix and be
placed 50 mm clear of the inside edge of the pillar base.
• The conduit stubs are to extend a minimum of 200 mm outside the footprint of the pillar
base on the property side of the pillar and shall be capped at both ends using conduit caps
of the appropriate size.
• The minimum cover for the conduit stub shall be 500 mm.
• The PVC service cable sheath must be terminated 10mm above the end of the conduit
stub.
Note: The arrangement above is shown with the front half of the lug cover removed to show
internal details. Service cables must be installed with lug cover fully assembled. See
Figure 21.4 for a fully assembled arrangement.
Notes:
1. Ausgrid will not provide any training for the installation of the Legend Power Systems URD
pillars. Please refer to Business Development Manager at Legend Power Systems if
training is required.
3. The pillar base is backfilled with sand and has a 40mm deep sand/cement mix (20:1)
4. PVC sheaths of all cables must be terminated 25mm above the surface of the
sand/cement mix.
5. Refer to Figure 21.3 for service conduit stub details (if applicable).
6. The top of the pillar base is to be a minimum of 50 mm above the ground level.
7. The cable cores should be cut at a height of 390mm from the top of the pillar base.
8. If it is necessary to remove and reinstall the lug once it is installed; a new lug shall be
used. The conductor shall be cut below the indentations and stripped to the required
length.
9. The cables shall be centred within the pillar once they are connected.
Notes (cont.):
10. The lug covers shall be arranged so that a minimum of 25mm clearance is maintained
between any part of the lug cover and inner edge of the pillar base (Refer to Figure 21.2)
allowing the turret to be fitted clear of the lug covers.
11. Fit the turret over the connections and ensure it sits in its correct position with the securing
holes aligned without applying any force to the turret. Reposition the cables if necessary.
CAUTION
Incorrect installation of the turret (ie using the securing bolts to force
it into position) will lead to premature failure.
Notes (cont.):
12. A conduit stub shall be installed in accordance with Figure 21.3 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
Note: The heatshrink tubing on the distributor cables ends 25mm above the pillar base.
Notes:
1. Refer to NS130 for the installation requirements of the pillar base.
2. The pillar base is backfilled with sand and has a 40 mm deep sand/cement mix (20:1).
3. PVC sheaths of all distributor cables must be terminated 200 mm below ground level
4. Refer to Figure 22.4 for service conduit stub details (if applicable).
5. The top of the pillar base is to be a minimum of 50 mm above the ground level.
6. Up to 6 service cables can be connected in each block - 4x70mm² and 2x50mm².
7. The 3-way bolted block connector (186235) is suitable for both 2-way and 3-way applications
8. The cables shall be centred within the pillar once they are connected.
Notes (cont.):
9. The core terminals (Refer to Figure 22.2 and Figure 22.3) are staggered with two cores at
450mm and two cores at 310mm from the turret base, allowing the turret to be fitted clear of
the core terminals.
10. Fit the turret over the connections and ensure it sits in its correct position with the securing
holes aligned without applying any force to the turret. Reposition the cables if necessary.
CAUTION
Incorrect installation of the turret (i.e. using the securing bolts to force
it into position) will lead to premature failure.
Notes (cont.):
11. A conduit stub shall be installed in accordance with Figure 22.4 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
• Conduit stubs shall be 40 mm or 50 mm diameter for 100 amp services and 80 mm diameter
for 200 amp services and comply with NS130. All services shall be assumed to be 100 amp
unless otherwise specified.
• Only use conduit 90 degree large sweep bends as any sharper angle will impede cable entry.
• The upper end of the conduit stub shall extend 50 mm above the sand/cement mix and be
placed 50 mm clear of the inside edge of the pillar base.
• The conduit stubs are to extend a minimum of 200 mm outside the footprint of the pillar base
on the property side of the pillar and shall be capped at both ends using conduit caps of the
appropriate size.
• The minimum cover for the conduit stub shall be 500 mm.
• The PVC service cable sheath must be terminated 10mm above the end of the conduit stub.
• 185mm² stranded copper conductor, XLPE insulated, PVC sheathed, single core cables
(185 CU1 XQ Z);
• 240mm² four core, stranded copper conductor, XLPE insulated, PVC sheathed cables (240
CU4 XQ Z);
• 240mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (240
AL4 XQ Z/SAC);
• 300mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (300
AL4 XQ Z/SAC)
Note that if all distributor cables are solid-sector aluminium (240 AL4 XQ Z/SAC or 300 AL4 XQ
Z/SAC), then use arrangement LV1-82, CMPBL2EA or CMPBL3EA as appropriate.
Notes:
1. The conductor of the 240 CU4 XQ Z cables must be rounded with rounding dies (S/C
182051) before being inserted into the crimp lug.
2. Only one service active is to be connected into each hole of the termination block (9). This
service terminal block also allows for 70mm² copper compacted conductor to be installed.
3. Only one service neutral is to be connected into each hole of the termination block (9). If
additional neutral connections are required another termination block may be connected to
the spare dropper cable.
5. The hole centres in the distributor and service bar (6) for the distributor cable is to be
430 mm from the top of the pillar base.
6. The top of the service termination block (9) is to be 330 mm from the top of the pillar base.
7. Refer to Figure 23.3 for service conduit stub details (if applicable).
Notes (cont.):
8. Refer to NS130 for the installation requirements of the pillar base.
9. The pillar base is backfilled with sand and has a 40 mm deep sand/cement mix (20:1).
10. PVC sheaths of multicore cables must be terminated 25 mm above the surface of the
sand/cement mix.
11. The top of the pillar base is to be a minimum of 50 mm above the ground level.
Notes (cont.):
12. A conduit stub shall be installed in accordance with Figure 23.3 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
• 240mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (240 AL4
XQ Z/SAC)
• 300mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (300 AL4
XQ Z/SAC)
• 240mm² four core, stranded copper conductor, XLPE insulated, PVC sheathed cables
(240 CU4 XQ Z)
• 185mm² stranded copper conductor, XLPE insulated, PVC sheathed, single core cables (185
CU1 XQ Z).
Notes:
1. Link kit (including Activating Links and Tee Operating Handle) is available on stockcode
178071. The link kit must be constructed in accordance with the installation instructions
supplied.
2. The terminal screws must be tightened with a torque wrench to the tension specified in the
following table:
3. Neutral connections are made using the 6 hole termination block (10). Only one service
neutral is to be connected into each hole of the termination block. If additional neutral
connections are required another termination block may be connected to the neutral bar.
4. Only one service active is to be connected per hole. The service terminal block also allows
for a 70mm² copper compacted conductor in the middle terminal to be installed.
5. The initial designed number of services must not exceed the number specified in NS110
Design and Construction Standard for Underground Residential Subdivisions, i.e. four
100 amp 3-phase services per link pillar. The maximum number of services connected to
each side of the pillar shall not exceed:
Notes (cont.):
6. Refer to NS130 for the installation requirements of the pillar base.
7. The pillar base is backfilled with sand and has a 40 mm deep sand/cement mix (20:1).
8. PVC sheaths of all cables must be terminated 25 mm above the surface of the
sand/cement mix.
9. Refer to Figure 24.3 for service conduit stub details (if applicable).
10. The top of the pillar base is to be a minimum of 50 mm above the ground level.
Notes (cont.):
11. Each distribution cable must be terminated into the link modules on the side at which the
cable enters the pillar.
12. A conduit stub shall be installed in accordance with Figure 24.3 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
• 240mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (240 AL4
XQ Z/SAC)
• 300mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (300 AL4
XQ Z/SAC)
• 240mm² four core, stranded copper conductor, XLPE insulated, PVC sheathed cables (240 CU4
XQ Z)
• 185mm² stranded copper conductor, XLPE insulated, PVC sheathed, single core cables (185
CU1 XQ Z).
Note: The heatshrink tubing on the 4-core cable, ends 25mm above the pillar base. The cable
sheath of the single core cables end 10mm below the terminals.
2. Training in the installation of this link pillar must be completed prior to installing. Training
for Ausgrid staff can be arranged by emailing [email protected]. ASPs are to
directly contact the supplier of this pillar (TE Connectivity) on email [email protected] to
arrange training.
3. The terminal screws must be tightened with a torque wrench to the tension specified in the
following table:
4. Service neutral connections are made by crimping an M8 compression lug onto the service
neutral conductor and terminating it on to the neutral bar. Only one neutral allowed per
bolted connection.
5. Only one service active is to be connected per hole. Service actives to be terminated into
the service tunnels integrated with the link panel assembly prior to utilising the three-hole
termination blocks.
6. The initial designed number of services must not exceed the number specified in NS110
Design and Construction Standard for Underground Residential Subdivisions, i.e. three
100amp 3-phase services. The maximum number of services connected to the pillar shall
not exceed:
Notes (cont.):
7. Refer to NS130 for the installation requirements of the pillar base.
8. The pillar base is backfilled with sand and has a 40 mm deep sand/cement mix (20:1).
9. PVC sheaths of all cables must be terminated 25 mm above the surface of the
sand/cement mix.
10. Refer to Figure 25.3 for service conduit stub details (if applicable).
11. The top of the pillar base is to be a minimum of 50 mm above the ground level.
Notes (cont.):
12. A conduit stub shall be installed in accordance with Figure 25.3 for each cable that has not
been initially laid prior to the installation of the pillar noting the following:
• Conduit stubs shall be 40 mm or 50 mm diameter for 100 amp services and 80mm
diameter for 200 amp services and comply with NS130. All services shall be assumed to
be 100 amp unless otherwise specified.
• Only use conduit 90 degree large sweep bends as any sharper angle will impede cable
entry.
• The upper end of the conduit stub shall extend 50 mm above the sand/cement mix and
be placed 50 mm clear of the inside edge of the pillar base.
• The conduit stubs are to extend a minimum of 200 mm outside the footprint of the pillar
base on the property side of the pillar and shall be capped at both ends using conduit
caps of the appropriate size.
• The minimum cover for the conduit stub shall be 500 mm.
• The PVC service cable sheath must be terminated 10mm above the end of the conduit
stub.
13. As the distributor cables hold the link panel in place, all three (3) distributor cables must be
installed during the construction of this pillar.
Notes:
1. Complete panel is available on stockcode 180223.
50 mm
Sand/cement mix Cable
40 mm 50 mm
Ground level
Sand backfill
Min
500 mm
Pillar base cover
10
Figure 26.3 – Pillar Base Details
Notes (cont.):
2. Refer to NS130 for the installation requirements of the pillar base.
3. The pillar base is backfilled with sand and has a 40 mm deep sand/cement mix (20:1).
4. PVC sheaths of all cables must be terminated 25 mm above the surface of the
sand/cement mix.
5. The top of the pillar base is to be a minimum of 50 mm above the ground level.
• 185mm² stranded copper conductor, XLPE insulated, PVC sheathed, single core cables
(185 CU1 XQ Z);
• 300mm² stranded copper conductor, XLPE insulated, PVC sheathed, single core cables
(300 CU1 XQ Z);
• 240mm² four core, stranded copper conductor, XLPE insulated, PVC sheathed cables (240
CU4 XQ Z);
• 240mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (240
AL4 XQ Z/SAC);
• 300mm² four core, solid aluminium conductor, XLPE insulated, PVC sheathed cables (300
AL4 XQ Z/SAC).
1. Pre-heat the compression lug before placing the heatshrink sleeve over the cable.
2. Shrink the sleeve starting from the cable end.
3. Apply additional heat to the sleeve and the palm of the lug until a bead of mastic appears
around the ends of the sleeve.
Figure 27.2 – Application of Heatshrink on Single Core Cables
Notes:
1. PVC sheaths of all cables must be terminated 200 mm above ground level.
Notes:
1. The conductor of the 240 CU4 XQ Z cables must be rounded with rounding dies (S/C
182051) before being inserted into the crimp lug.
Notes:
1. When the colour of the cable sheath does not correctly identify the cable, coloured
heatshrink tubing or coloured PVC tape shall be used to correctly identify the cable. Colour
coded for reference only.
2. Cable termination boots will be supplied with the switch.
3. Insert the cable tie through the holes in the cable termination boots and make a loose loop.
Note: Do not tighten the cable tie at this stage.
4. Slide the cable termination boot over each cable/core to expose the cable lug.
5. Unbolt the front busbar extension. Securely fasten the cable lug to the switchgear palm.
Fasten the rear cable lugs first.
Note: Lubricate the thread as detailed in Clause 3.10. Wipe all excess anti-seize off the
thread after tightening.
6. Slide the cable termination boots of the rear terminations over each one of the terminations.
Ensure that the top of the cable termination boot is touching the bottom of the distributor strips
and that there is no exposed metal showing. Secure the cable ties and cut off the excess tie
ends.
7. Fix the front extension busbar back in position. Securely fasten the cable lug to the switchgear
palm. Slide the cable termination boot. Secure the cable tie and cut off the excess tie end.
Items for 'Double Circuit 800Amp Distributor Strips' are the same as ‘Single Circuit 400Amp
Distributor Strips’. Refer to the relevant Table 27.1 (A, B, C or D) above for item descriptions.
3. Slide the cable termination boot over the two cables/cores of the same phase to expose the
cable lugs. Repeat for the remaining two phases.
6. Slide the cable termination boot over each of the two rear cable terminations. Ensure that
the top of the cable termination boots are touching the bottom of the distributor strip and that
there is no exposed metal showing.
Note: If the MDI secondary wiring is installed at the base of the distributor strip (see
photo below), ensure that the cable tie does not become entangled in the MDI
secondary wiring and put undue pressure on the insulation of the MDI secondary
wiring when the cable tie is secured.
7. Secure the cable ties and cut off the excess tie ends.
8. Secure the front busbar extension to the distributor strip palm using the M16 set screw,
torque to 80Nm.
11. Secure the cable tie and cut off the excess tie end.
12. Install the polycarbonate cover.
• where it is possible to visually trace the entire length of cable from the pot end to the
source of supply, or
• where it is possible to visually trace the entire length of cable from the pot end to the tee
joint to which the pot ended section of cable is connected. Additionally, it shall be possible
to identify the cables connected to the other two legs of the tee joint using cable
identification equipment.
When pot ends are to be direct buried, the pot end shall be located as close as practicable to
either:
• the tee joint to which the pot ended section of cable is connected.
This requirement is to minimise future civil works for the purposes of cable identification.
If it is intended to join cable to the pot ended section of cable in the future, sufficient cable length
shall be left to allow for the pot end to be replaced with a straight through joint.
The Neutral Bonding Cables for Multicore PILC Pot End are identified below:
Table 28.2 – Material list
Notes:
1. For 500 Cu1 XQ Z replace the small cable end cap included in the kit with a large cable
end cap available on stockcode 62067.
2. Additional components are required for a Multicore PILC pot end kit (stockcode: 178611).
The components are available direct from TE Connectivity by requesting the following:
28.4 Requirements
The following requirements must be satisfied when constructing a pot end:
(a) The cable cores must not be bent tighter than the manufacturer’s specified minimum internal
bending radius during the construction process.
(b) The pot end shall be constructed in accordance with the installation instruction supplied in the
kit.
(c) The kit components and the prepared cable ends must be kept free of foreign matter and must
not be damaged during the construction process.
(d) All components involved in the pot end (including cable components) which will come into
contact with either mastic tape or adhesive sealants must be thoroughly cleaned and
degreased prior to the application of such sealing agents. Cleaning must only be done using
lint-free cloth.
(e) Heatshrink tubings must be properly and evenly shrunk, free of voids, and must not be
damaged from overheating. Heatshrink components with adhesive sealant coatings must
provide effective sealing against moisture ingress when installed.
(f) The completed pot end must be allowed to cool down before applying mechanical load to it.
(g) The completed pot end if direct buried, shall be surrounded in soft bedding material up to a
depth of 100 mm above the pot end. The bedding material must comply with the requirements
of NS130.
29.1 Cold Pour Resin Joint Kits (only for solid sector aluminium cables)
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
29.3 Requirements
The following requirements must be satisfied when constructing a heatshrink straight through joint
for four core sector cables:
(a) The joint shall be constructed in accordance with the installation instruction supplied in the
joint kit.
(b) The cable cores must not be bent tighter than the manufacturer’s specified minimum internal
bending radius during the jointing process.
(c) The joint kit components and the prepared cable ends must be kept free of foreign matter and
must not be damaged during the jointing process.
(d) All components involved in the joint (including cable components) which will come into contact
with either mastic tape or adhesive sealants must be thoroughly cleaned and degreased prior
to the application of such sealing agents. Cleaning must only be done using lint-free cloth.
(e) Heatshrink tubings must be properly and evenly shrunk, free of voids, and must not be
damaged from overheating. Heatshrink components with adhesive sealant coatings must
provide effective sealing against moisture ingress when installed.
(f) The completed joint must be allowed to cool down before applying mechanical load to it.
(g) The completed joint if direct buried, shall be surrounded in soft bedding material up to a depth
of 100 mm above the joint. The bedding material must comply with the requirements of
NS130.
30.1 Requirements
The following requirements must be satisfied when constructing a heatshrink straight through joint
for four core sector cables:
(a) The joint shall be constructed in accordance with the installation instruction supplied in the
joint kit.
(b) The cable cores must not be bent tighter than the manufacturer’s specified minimum internal
bending radius during the jointing process.
(c) The joint kit components and the prepared cable ends must be kept free of foreign matter
and must not be damaged during the jointing process.
(d) All components involved in the joint (including cable components) which will come into
contact with either mastic tape or adhesive sealants must be thoroughly cleaned and
degreased prior to the application of such sealing agents. Cleaning must only be done using
lint-free cloth.
(e) Heatshrink tubings must be properly and evenly shrunk, free of voids, and must not be
damaged from overheating. Heatshrink components with adhesive sealant coatings must
provide effective sealing against moisture ingress when installed.
(f) The completed joint must be allowed to cool down before applying mechanical load to it.
(g) The completed joint if direct buried, shall be surrounded in soft bedding material up to a
depth of 100 mm above the joint. The bedding material must comply with the requirements of
NS130.
(h) The 240 CU4 XQ Z cables must rounded with rounding dies (S/C 182051) before being
inserted into the crimp link.
Notes:
1. Any aluminium links are supplied pre-pasted - extra jointing paste is not required.
2. Scratch brush the outside strands of any aluminium conductor and immediately fit the link
onto the conductor.
3. Compression links are marked with crimping position and required die size.
4. The joints shall be constructed in accordance with installation instruction supplied in the
joint kit.
5. If 240 CU4 XQ Z is being used, the conductor must be rounded with rounding dies (S/C
182051) before being inserted into the crimp link.
Table 32.2 – Straight Through Transition Joint Kits for Single Core Cables
Notes:
1. The neutral connector is included in the neutral joint kit.
2. One earthing kit is sufficient to bond the sheaths of four single core PILC cables. All four
tinned copper braids are bolted together using a M12 x 35mm SS bolt (stockcode 45021),
two M12 SS flat washers (stockcode 49429), one SS spring washer (stockcode 143859)
and M12 SS nut (stockcode 8987).
Table 32.3 – Straight Through Joint Kits for Single Core PILC Cables
Straight Through Joints Joint Kit Earthing Kit Connector
Cable Type Cable Type Stockcode Stockcode Stockcode
185 mm² Cu1 PL Z 185 mm² Cu1 PL Z 152306 152330 150250
300 mm² Cu1 PL Z 300 mm² Cu1 PL Z 152306 152330 80929
32.1 Requirements
In addition to the requirements of Clauses 3.7, 3.8 and 3.9 the following requirements must be
satisfied when constructing a heatshrink straight through joint for single core cables:
(a) The joints shall be constructed in accordance with the installation instruction supplied in the
joint kit.
(b) The earthing kit to bond the sheaths of four single core PILC cables together shall be
constructed in accordance with SPJ-AUG-ERT-300-01-R0 Earthing instruction for application
on metallic sheathed LV cables.
(c) Use a wire brush to abrade the surface of the aluminium conductors prior to terminating into
the connectors.
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
• Four core, stranded conductor, paper insulated, lead sheathed, polymeric oversheathed,
armoured and unarmoured cables to four core, solid aluminium conductor, XLPE insulated,
PVC sheathed cables.
• Four core with reduced neutral, stranded conductor, paper insulated, lead sheathed, polymeric
oversheathed, armoured and unarmoured cables to four core, solid aluminium conductor,
XLPE insulated PVC sheathed cables.
S/C 58305
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
3. The Neutral Connection can only be a weak back ferrule (stockcode 63834).
4. 35mm² tinned copper earth braid available direct from TE Connectivity Part No EPPA 013-
5-1000.
5. 70mm² tinned copper earth braid available direct from TE Connectivity Part No EPPA 013-
9-1000.
6. 85mm² tinned copper earth braid available direct from TE Connectivity Part No EPPA 013-
5-1000 for the 35mm² braid and EPPA 013-6-1000 for the 50mm² braid.
34.1 Requirements
In addition to the requirements of Clauses 3.7 and 3.9 the following requirements must be satisfied
when constructing a multicore transition joint:
The solid aluminium conductors must be abrasion tinned prior to sweating.
S/C 58305
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
Table 35.1 – Material List for Neutral Bond and Compression Link
Ausgrid
Item Description stockcode Qty required
1 Joint mould 181762 1
2 Resin 6 Litre tubs 75390 4
3 Foam tape 10m 39172 1
4 Clamping ring 181748 1
5 Core connectors (70-300mm²) 181745 3
6 Connector with 2 service tap-offs 181746 1
7 CR Insulation pad for phase connector 181752 3
8 CR Insulation pad for neutral connector 181761 1
9 Copper conductor 35mm² H118612 2m
10 35mm² Tinned Cu lug M10 73155 2
The following requirements must be satisfied when constructing the above mentioned straight
through joint:
(a) The joint shall be constructed in accordance with the Installation Instruction located in
Annexure A of this Network Standard.
(b) Wire brush the Aluminium conductors before inserting into the connectors.
(c) Ensure that the relevant General Requirements as specified in Clause 3.9 of this Network
Standard are met.
37.1 Requirements
The following requirements must be satisfied when constructing the above mentioned straight
through joint:
(a) The joint shall be constructed in accordance with the Installation Instruction located in
Annexure B of this Network Standard.
(b) Wire brush the Aluminium conductors before inserting into the connectors.
(c) Ensure that the relevant General Requirements as specified in Clause 3.9 of this Network
Standard are met.
• Three core stranded aluminium conductor, paper insulated, aluminium sheathed, PVC
oversheathed cables (CONSAC) to single core stranded copper, cross-linked polyethylene
insulated, PVC sheathed cables.
• Three core solid aluminium conductor, paper insulated, aluminium sheathed, PVC
oversheathed cables (CONSAC) to single core stranded copper, cross-linked polyethylene
insulated, PVC sheathed cables.
Ausgrid’s stockcodes of approved straight through joint kits for single core cables are provided in
the table below.
Table 38.1 – Four-to-One Transition Joint Kits for CONSAC cables
Table 38.2 – Neutral Bonding Cable for Four-to-One Transition Joints for CONSAC cables
38.1 Requirements
In addition to the requirements of Clauses 3.7, 3.8 and 3.9 the following requirements must be
satisfied when constructing a heatshrink four-to-one straight through joint:
(a) The joint shall be constructed in accordance with the installation instruction supplied in the
joint kit.
(b) Use a wire brush to abrade the surface of the aluminium conductors prior to terminating into
the connectors.
• Four core, stranded conductor, paper insulated, lead sheathed, polymeric oversheathed,
armoured and unarmoured cables to single core stranded copper, cross-linked polyethylene
insulated, PVC sheathed cables.
• Four core with reduced neutral, stranded conductor, paper insulated, lead sheathed, polymeric
oversheathed, armoured and unarmoured cables to single core stranded copper, cross-linked
polyethylene insulated, PVC sheathed cables.
Ausgrid’s stockcodes of approved straight through joint kits for single core cables are provided in
the table below.
Table 39.1 – Four-to-One Transition Joint Kits for PILC cables
39.1 Requirements
In addition to the requirements of Clauses 3.7, 3.8 and 3.9 the following requirements must be
satisfied when constructing a heatshrink four-to-one straight through joint:
The joint shall be constructed in accordance with the installation instruction supplied in the joint kit.
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
Notes:
1. Joint mould omitted for clarity.
2. Vinyl mastic tape (stockcode: 69807) is applied with the ends left unsealed to allow the
resin to flow around the connector.
Note: Apply a 5mm thick layer of sand/cement mix on top of the sand bedding prior to installing
the concrete slabs.
1. Abrade the cable sheath and the cable insulation to the dimensions shown.
2. Pre-heat the compression lug before placing the heatshrink sleeve over the cable.
3. Shrink the sleeve starting from the cable end.
4. Apply additional heat to the sleeve and the palm of the lug until a bead of mastic appears
around the ends of the sleeve.
Notes:
1. Disconnection link box is available on stockcode 180181 and comes complete with activating
links, link covers, tee operating handle, foam tubes, bell housing, circuit numbers, circuit
number housings, cable trough covers and sand barriers.
2. The dimensions of the disconnection link box are 470mm wide x 720mm long x 410mm high.
3. The threads of the stainless steel studs shall be lubricated with Nickel anti-seize grease
(stockcode 177212) prior to tightening. Wipe off any excess anti-seize after the nuts have
been tightened.
4. Cable connections to be tighten to a torque of 45Nm.
The link box shall be positioned so that when facing the link box and the building line “1” is in the
bottom left corner followed by “2”, “3”, and “4” in a clockwise direction. See drawing below.
Figure 43.4 – Cast Iron lid and the bolts provided with the pit frame
Note: Use string lines to determine the pavement height and then adjust the bolts provided with
the pit frame to ensure that the cast iron lid is level with the pavement surface.
The Cast Iron lid shall be infilled with concrete.
• four core stranded copper, cross-linked polyethylene insulated, PVC sheathed cables to four
core stranded copper, cross-linked polyethylene insulated, PVC sheathed cables.
• four core stranded copper, cross-linked polyethylene insulated, PVC sheathed cables to three
core stranded copper, cross-linked polyethylene insulated, copper helically wound concentric
wire neutral, PVC sheathed cables.
• four core stranded copper, cross-linked polyethylene insulated, PVC sheathed cables to single
core stranded copper, PVC insulated, PVC sheathed cables.
• transition joint from four core stranded copper, cross-linked polyethylene insulated, PVC
sheathed cables to three core solid sector aluminium paper insulated, metal sheathed,
polymeric oversheathed cables.
Ausgrid’s stockcodes of approved straight through joint kits for service cables are provided in the
table below.
Table 44.1 – Straight Through Joint Kits for Service Cables
*The neutral insulating sleeve for the ceander cable is to be cut to length from 40m roll (stockcode
177751).
Table 44.2 – Neutral Bonding Cable for Multicore PILC Service Cable
44.2 Requirements
In addition to the requirements of Clauses 3.7, 3.8 and 3.9 the following requirements must be
satisfied when constructing a heatshrink straight through joint for service cables:
(a) The joints shall be constructed in accordance with the installation instruction supplied in the
joint kit.
(b) Use a wire brush, to abrade the surface of the aluminium conductors. Apply jointing compound
with conductive zinc particles to all aluminium conductors. Use a different wire brush, to again
abrade the surface of the aluminium conductors prior to terminating into the connectors.
• where it is possible to visually trace the entire length of cable from the pot end to the
source of supply, or
• where it is possible to visually trace the entire length of cable from the pot end to the tee
joint to which the pot ended section of cable is connected. Additionally, it shall be possible
to identify the cables connected to the other two legs of the tee joint using cable
identification equipment.
When pot ends are to be direct buried, the pot end shall be located as close as practicable to
either:
• the tee joint to which the pot ended section of cable is connected.
This requirement is to minimise future civil works for the purposes of cable identification.
If it is intended to join cable to the pot ended section of cable in the future, sufficient cable length
shall be left to allow for the pot end to be replaced with a straight through joint.
45.4 Requirements
The following requirements must be satisfied when constructing a pot end:
(a) The cable cores must not be bent tighter than the manufacturer’s specified minimum internal
bending radius during the construction process.
(b) The pot end shall be constructed in accordance with the installation instruction supplied in the
kit.
(c) The kit components and the prepared cable ends must be kept free of foreign matter and
must not be damaged during the construction process.
(d) All components involved in the pot end (including cable components) which will come into
contact with either mastic tape or adhesive sealants must be thoroughly cleaned and
degreased prior to the application of such sealing agents. Cleaning must only be done using
lint-free cloth.
(e) Heatshrink tubings must be properly and evenly shrunk, free of voids, and must not be
damaged from overheating. Heatshrink components with adhesive sealant coatings must
provide effective sealing against moisture ingress when installed.
(f) The completed pot end must be allowed to cool down before applying mechanical load to it.
(g) The completed pot end if direct buried, shall be surrounded in soft bedding material up to a
depth of 100 mm above the pot end. The bedding material must comply with the
requirements of NS130.
ASPs may obtain approved materials and equipment items as listed in the AML from any source.
Where an ASP wishes to use alternative materials and equipment, application to have the materials
or equipment considered for approval is to be made in accordance with NS181. Alternatively,
where approved materials and equipment are held as stock in Ausgrid’s stores system, ASPs may
purchase them from Ausgrid. All enquiries and requests for quotations should be directed by email
to [email protected] and should include the appropriate stockcode numbers.
RELATED DOCUMENTS
All work covered in this document shall conform to all relevant Legislation, Standards, Codes of
Practice and Network Standards. Current Network Standards are available on Ausgrid’s Internet
site at www.ausgrid.com.au.
ASPs and other persons external to Ausgrid are responsible for sourcing the manufacturer’s
instructions and manuals.
DEFINITIONS
ABS Pole Air Break Switch Pole.
Accredited An individual or entity accredited by the NSW Department of Planning,
Service Provider Industry and Environment, in accordance with the Electricity Supply (Safety
(ASP) and Network Management) Regulation 2014 (NSW).
ASP/1, ASP/3 As defined in the current version of the NSW Department of Planning,
Industry and Environment – Accreditation of Providers of Contestable
Services – Scheme Rules.
Authorised A person with technical knowledge or sufficient experience who has been
Person approved as competent and is then authorised in writing by Ausgrid to
perform the function requiring authorisation on or near the company’s
electricity network. This definition holds for various forms of the word, eg
authorisation, authorise and authorised.
Authorised Work requiring specific permission in writing from Ausgrid to undertake
Work contestable design or work on or near its network. Refer to ES4 for further
information.
Client A Client is an individual or an entity which has responsibility for the design
and construction of the electricity reticulation installation, and who enters
into an agreement/contractual arrangement with accredited parties, for
developing the installation. A Client could be a developer, an Accredited
Service Provider or a customer.
Contestable Contestable Work is work such as the design, construction and installation
Work of electricity works, which are required to connect a customer’s installation
to an electricity network or relocate network assets. Customers are required
to fund the cost of contestable work and they have the choice of selecting
the ASP to carry out the work. The legislation relevant to contestable work is
the Electricity Supply (Safety and Network Management) Regulation 2014
(NSW).
Conventional A Street Lighting Standard with a planted-type base providing for the
Base Street installation of either side-entry or post-top luminaires.
Lighting
Standard
Customer A retail customer, or a real estate developer who requests (or on whose
behalf a request is made for) a new connection, connection alteration or
asset relocation.
Designer An Ausgrid employee, contractor to Ausgrid or authorised ASP/3 who is duly
qualified to produce design plans.
Direct Buried Cables installed underground whose outer surface is in direct contact with
Cables the general mass of the earth.
Distribution An enclosure consisting of a base and a cover, housing cable terminations
Pillar and forming part of the low voltage distribution network. Types of pillars
include link pillars, solid pillars. All distribution pillars have provisions for the
connection of services.
Distribution Side The side of the street on which low voltage distributor cables are installed.
Note: This only applies to single sided schemes.
Document Ausgrid employees who work with printed copies of document must check
Control the document repository regularly to monitor version control. Documents are
considered “UNCONTROLLED IF PRINTED”, as indicated in the footer.
Link Pillar A pillar incorporating links which serves as a switching point using
removable links.
Lot Boundary The dividing boundary line between adjoining lots and road reserve.
Low Voltage An electricity line rated at not more than 1000V AC which originates at the
(LV) Distributor low voltage end of a distribution substation and serves to convey electrical
energy to end users via their service mains. Low voltage distributors are
constructed in public roadways or through easements on private land.
Network A document, including Network Planning Standards, that describes the
Standard Company's minimum requirements for planning, design, construction,
maintenance, technical specification, environmental, property and metering
activities on the distribution and transmission network. These documents
are stored in the Network Category of the document repository and
available externally on Ausgrid’s website.
Pillar-Standard A steel street lighting column with an enlarged lower section which could
incorporate a link panel/bi-form connectors/tri-form connectors and
providing for the connection of services. Pillar-Standards are mounted on
ragbolt assemblies. Note: Pillar-standards are no longer a design /
construction option, although many will continue to operate on the network.
PT Pole A pole with a distribution transformer attached.
Remote Side The non-distributor side of the street.
Review date The review date displayed in the header of the document is the future date
for review of a document. The default period is three years from the date of
approval however a review may be mandated at any time where a need is
identified. Potential needs for a review include changes in legislation,
organisational changes, restructures, occurrence of an incident or changes
in technology or work practice and/or identification of efficiency
improvements.
Service Mains The electricity cable between the Point of Common Coupling and the
Connection Point as defined in the Service an Installation Rules of NSW.
Service Conduit A short length of service conduit installed between the distribution pillar and
Stub each of the adjoining lots within the subdivision.
Solid Pillar A pillar where the distributor cables are solidly connected using either bolted
lugs or mechanical connectors. Isolation of the distributor cables requires
removal of the connection bolts under load-free conditions.
Street The boundary line between the dedicated roadway and the allotment. This
Alignment is also known as the property alignment.
Street Lighting The customer (eg Local Council) responsible for providing street lighting,
Customer controlling the standard of lighting and responsible for the applicable Street
Lighting charges.
For dedicated roadways, the Street Lighting Customer is the Local Council
or TfNSW (Transport for NSW). For community land title developments, the
Street Lighting Customer is the Community Association responsible for that
particular development.
RECORDKEEPING
The table below identifies the types of records relating to the process, their storage location and
retention period.
Table 51.1 – Recordkeeping
Draft Copies of the Network Work Folder for Network Standards Unlimited
Standard during (HPRM ref. 2014/21250/309)
amendment/creation
* The following retention periods are subject to change eg if the records are required for legal
matters or legislative changes. Before disposal, retention periods should be checked and
authorised by the Records Manager.
DOCUMENT CONTROL
Document Owner : Head of Asset Risk & Performance