5 Marla House Detail Estimation 2017
5 Marla House Detail Estimation 2017
5 Marla House Detail Estimation 2017
PROFIT/LOSS
Material 2,385,242 127,750 83,217
Labor 302,466 ‐ ‐
Subcontracto 650,075 ‐ ‐
Other 226,000 ‐ ‐
3,563,784 127,750 83,217
Contract 3,450,000
Alternates 97,050
3,547,050
(16,734)
66,483
ITEMS QUANTITY UOM UNIT COST BUDGET ORDERED UNIT COST % COMP EQUATED ACTUAL DIFFERENCE PROFIT/LOSS
BRICKS 62,000 EA 8.2 508,400 14,000 7.30 23% 114,800 102,200 12,600 55,800
CEMENT 703 BAGS 550 386,650 50 511 7% 27,500 25,550 1,950 27,417
SAND 2,990 CF 28 83,720 ‐ 0% ‐ ‐ ‐
CRUSH 1,860 CF 75 139,500 ‐ 0% ‐ ‐ ‐
BRICK BLAST 600 CF 32.5 19,493 ‐ 0% ‐ ‐ ‐
LAND FILL 6,073 CF 10 60,734 ‐ 0% ‐ ‐ ‐
BRICK TILES 3,105 SF 7 21,732 ‐ 0% ‐ ‐ ‐
POLYTHENE 1,422 SF 6 8,534 ‐ 0% ‐ ‐ ‐
BITUMEN 1,487 SF 8 11,896 ‐ 0% ‐ ‐ ‐
JUMBOLON 926 SF 94 87,053 ‐ 0% ‐ ‐ ‐
STEEL 2,941 KGs 82 241,123 ‐ 0% ‐ ‐ ‐
BATH/KITCHEN TILES 842 SF 112 94,248 ‐ 0% ‐ ‐ ‐
FLOOR TILES 1,496 SF 93 139,128 ‐ 0% ‐ ‐ ‐
TOUGH TILES 273 SF 25 6,820 ‐ 0% ‐ ‐ ‐
MARBLE 242 SF 180 43,560 ‐ 0% ‐ ‐ ‐
Plumbing PPRC Pipes 1 LS 40000 40,000 ‐ 0% ‐ ‐ ‐
Plumbing Conc Pipes 1 LS 5000 5,000 ‐ 0% ‐ ‐ ‐
Plumbing Grey Misc 1 LS 5000 5,000 ‐ 0% ‐ ‐ ‐
Electrical Grey Pipes 1 LS 15000 15,000 ‐ 0% ‐ ‐ ‐
Electrical Grey Boxes 1 LS 5000 5,000 ‐ 0% ‐ ‐ ‐
Electrical Grey Misc 1 LS 5000 5,000 ‐ 0% ‐ ‐ ‐
Gas Pipes 1 LS 10000 10,000 ‐ 0% ‐ ‐ ‐
Distribution Box 1 EA 15,000 15,000 ‐ 0% ‐ ‐ ‐
3/29 Wire 14 Coil 1,600 22,400 ‐ 0% ‐ ‐ ‐
7/36 Wire 2 Coil 4,800 9,600 ‐ 0% ‐ ‐ ‐
7/29 Wire 9 Coil 3,200 28,800 ‐ 0% ‐ ‐ ‐
Main Wire 1 Coil 4,000 4,000 ‐ 0% ‐ ‐ ‐
Low Voltage 1 Coil 4,000 4,000 ‐ 0% ‐ ‐ ‐
Wash Basin 4 EA 6000 24,000 ‐ 0% ‐ ‐ ‐
WC 4 EA 10000 40,000 ‐ 0% ‐ ‐ ‐
Mirrors 4 EA 1000 4,000 ‐ 0% ‐ ‐ ‐
Vanities 4 EA ‐ ‐ 0% ‐ ‐ ‐
Bath Accessories/Taps 4 EA 8000 32,000 ‐ 0% ‐ ‐ ‐
Bracket Fans 1 EA 1,500 1,500 ‐ 0% ‐ ‐ ‐
Ceiling Fans 6 EA 3,000 18,000 ‐ 0% ‐ ‐ ‐
Exhaust Fans 5 EA 2,000 10,000 ‐ 0% ‐ ‐ ‐
Exterior Lights 3 EA 1,000 3,000 ‐ 0% ‐ ‐ ‐
Main Gate Lights 2 EA 1,500 3,000 ‐ 0% ‐ ‐ ‐
Power Socket 36 EA 500 18,000 ‐ 0% ‐ ‐ ‐
Power Switches 8 EA 500 4,000 ‐ 0% ‐ ‐ ‐
Switch Board 16 EA 500 8,000 ‐ 0% ‐ ‐ ‐
Telephone Outlet 2 EA 500 1,000 ‐ 0% ‐ ‐ ‐
TV Outlet 2 EA 500 1,000 ‐ 0% ‐ ‐ ‐
Vanity Lights 6 EA 1,000 6,000 ‐ 0% ‐ ‐ ‐
Ceiling Lights 9 EA 750 6,750 ‐ 0% ‐ ‐ ‐
Wall Lights 19 EA 750 14,250 ‐ 0% ‐ ‐ ‐
Kitchen Sink + Mixture 1 EA 2,000 2,000 ‐ 0% ‐ ‐ ‐
3'x7' Single Door/Frame 1 EA 4,500 4,500 ‐ 0% ‐ ‐ ‐
3' 6"x7' Single Door/Frame 3 EA 4,500 13,500 ‐ 0% ‐ ‐ ‐
2' 6"x7' Single Door/Frame 5 EA 4,000 20,000 ‐ 0% ‐ ‐ ‐
3'x7' Single Door/Frame 2 EA 5,000 10,000 ‐ 0% ‐ ‐ ‐
4' x 7' Double Door/Frame 1 EA 9,500 9,500 ‐ 0% ‐ ‐ ‐
Main Door Hardware 1 EA 2,000 2,000 ‐ 0% ‐ ‐ ‐
Primary Door Hardware 5 EA 1,500 7,500 ‐ 0% ‐ ‐ ‐
Secondary Door Hardware 6 EA 1,000 6,000 ‐ 0% ‐ ‐ ‐
Closet Hardware 4 EA 1,000 4,000 ‐ 0% ‐ ‐ ‐
Kitchen Cabinet Hardware 1 EA 2,000 2,000 ‐ 0% ‐ ‐ ‐
Paint ‐ Interior Ceilings 1428 SF 10 14,280 ‐ 0% ‐ ‐ ‐
Paint ‐ Exterior Ceilings 174 SF 10 1,740 ‐ 0% ‐ ‐ ‐
Paint ‐ Interior Walls 4846 SF 10 48,460 ‐ 0% ‐ ‐ ‐
Paint ‐ Exterior Walls 1440 SF 10 14,400 ‐ 0% ‐ ‐ ‐
Paint ‐ Gate 130 SF 10 1,300 ‐ 0% ‐ ‐ ‐
Paint ‐ Grill for Windows 200 SF 10 2,000 ‐ 0% ‐ ‐ ‐
Paint ‐ 3'x7' Single Door/Frame 126 SF 10 1,260 ‐ 0% ‐ ‐ ‐
Paint ‐ 3' 6"x7' Single Door/Fram 130 SF 10 1,300 ‐ 0% ‐ ‐ ‐
Paint ‐ 2' 6"x7' Single Door/Fram 175 SF 10 1,750 ‐ 0% ‐ ‐ ‐
Paint ‐ 4' x 7' Double Door/Frame 56 SF 10 560 ‐ 0% ‐ ‐ ‐
Paint ‐ Stair/Terrace Railing 130 SF 10 1,300 ‐ 0% ‐ ‐ ‐
2,385,242 142,300 127,750 83,217
ACTIVITY QUANTITY UOM PRODUCTION DAYS COST/DAY TOATL COST % COMP EQUATED ACTUAL DIFFERENCE PROFIT/LOSS Laborer Mason Laborer Cost Mason Cost Total
Layout 1.00 1,500 1,500 0% ‐ ‐ ‐ 1 600 1,500 1,500
Shanty
Dig Foundations 1.00 7,200 7,200 ‐ ‐ ‐ 12 600 1,500 7,200
Dig UG Water Tank 1.00 1,200 1,200 ‐ ‐ ‐ 2 600 1,500 1,200
UG Water Tank 1.00 2,100 2,100 ‐ ‐ ‐ 1 1 600 1,500 2,100
Dig Septic Tank 1.00 1,200 1,200 ‐ ‐ ‐ 2 600 1,500 1,200
Septic Tank 1.00 2,100 2,100 ‐ ‐ ‐ 1 1 600 1,500 2,100
Foundations 15000 bricks 2000 7.50 4,200 31,500 ‐ ‐ ‐ 2 2 600 1,500 4,200
Backfill 1.00 2,400 2,400 ‐ ‐ ‐ 4 600 1,500 2,400
DPC 1.00 2,100 2,100 ‐ ‐ ‐ 1 1 600 1,500 2,100
Walls 34800 bricks 2500 13.92 4,200 58,464 ‐ ‐ ‐ 2 2 600 1,500 4,200
Window/Door Lintels 2.00 4,200 8,400 ‐ ‐ ‐ 2 2 600 1,500 4,200
Stairs 3.00 4,200 12,600 ‐ ‐ ‐ 2 2 600 1,500 4,200
Slabs 4.00 3,900 15,600 ‐ ‐ ‐ 4 1 600 1,500 3,900
Roof Parapet 2100 bricks 2000 1.05 4,200 4,410 ‐ ‐ ‐ 2 2 600 1,500 4,200
Exterior Plumbing Work 1.00 2,100 2,100 ‐ ‐ ‐ 1 1 600 1,500 2,100
Water Barrier Roof 882 SF 0.50 2,400 1,200 ‐ ‐ ‐ 4 600 1,500 2,400
Insulation Roof 882 SF 0.50 2,700 1,350 ‐ ‐ ‐ 2 1 600 1,500 2,700
Landfill Roof 882 SF 1.00 1,200 1,200 ‐ ‐ ‐ 2 600 1,500 1,200
Tiles Roof 882 SF 200 4.41 2,100 9,261 ‐ ‐ ‐ 1 1 600 1,500 2,100
Landfill /Compaction 700 SF 2.00 2,400 4,800 ‐ ‐ ‐ 4 600 1,500 2,400
Brick Blast at Grey Floors 1700 SF 500 3.40 2,400 8,160 ‐ ‐ ‐ 4 600 1,500 2,400
PCC Grey Floors 1700 SF 1000 1.70 4,200 7,140 ‐ ‐ ‐ 2 2 600 1,500 4,200
Plaster Interior Walls 5000 SF 500 10.00 4,200 42,000 ‐ ‐ ‐ 2 2 600 1,500 4,200
Plaster Interior Ceilings 1425 SF 500 2.85 4,200 11,970 ‐ ‐ ‐ 2 2 600 1,500 4,200
Plaster Exterior 2150 SF 500 4.30 4,200 18,060 ‐ ‐ ‐ 2 2 600 1,500 4,200
Floor Tiles/Marble 1580 SF 150 10.53 2,100 22,120 ‐ ‐ ‐ 1 1 600 1,500 2,100
Bath/Kitchen Tiles 765 SF 100 7.65 2,100 16,065 ‐ ‐ ‐ 1 1 600 1,500 2,100
OH Water Tank 1.00 2,100 2,100 ‐ ‐ ‐ 1 1 600 1,500 2,100
Exterior Tough Tiles 248 SF 125 1.98 2,100 4,166 ‐ ‐ ‐ 1 1 600 1,500 2,100
‐ ‐ ‐ ‐ ‐ 600 1,500 ‐
‐ ‐ ‐ ‐ 600 1,500 ‐
92.30 302,466 ‐ ‐ ‐ ‐
ITEMS QUANTITY UOM UNITCOST BUDGET %COMP EQUATED
Windows 200 SF 450 90,000 0% Ͳ
Gate 67 SF 400 26,800 0% Ͳ
StairRailing 110 SF 120 13,200 0% Ͳ
TerraceRailing 20 SF 120 2,400 0% Ͳ
GrillforWindows 200 SF 120 24,000 0% Ͳ
Plumbing/GasGrey 1 LS 25,000 25,000 0% Ͳ
PlumbingFinish 1 LS 10,000 10,000 0% Ͳ
ElectricalGrey 1 LS 35,000 35,000 0% Ͳ
ElectricalFinish 1 LS 13,100 13,100 0% Ͳ
MillworkͲCabinets 310 SF 500 155,000 0% Ͳ
MillworkͲDFH 12 EA 500 6,000 0% Ͳ
PaintͲInterior 2674 SF 15 40,110 0% Ͳ
PaintͲExterior 1614 SF 15 24,210 0% Ͳ
PaintͲDFH 487 SF 15 7,305 0% Ͳ
PaintͲGrill/Railing 330 SF 15 4,950 0% Ͳ
PaintͲGate 130 SF 15 1,950 0% Ͳ
Shuttering 1 LS 20,000 20,000 0% Ͳ
MixingMachine 10 Days 8,000 80,000 0% Ͳ
Termite 1 LS 25,000 25,000 0% Ͳ
SteelBending 1 LS 3,000 3,000 0% Ͳ
SteelForming 1 LS 30,000 30,000 0% Ͳ
FlaseCeiling 145 SF 90 13,050 0% Ͳ
Ͳ 0% Ͳ
650,075 Ͳ
ITEMS QUANTITY UOM UNITCOST BUDGET %COMP EQUATED
Tools 1 LS 25,000 25,000 0% Ͳ
Rental 1 LS 25,000 25,000 0% Ͳ
Misc 1 LS 15,000 15,000 0% Ͳ
Supervision 6 LS 25,000 150,000 0% Ͳ
Transportation/Freight 1 10,000 10,000 0% Ͳ
PlumbingTest 1 1000 1,000 0% Ͳ
Ͳ 0% Ͳ
226,000 Ͳ