Team Assignment 2 Group 3
Team Assignment 2 Group 3
1
Certificate of originally
This is to certify that this assignment submitted by group 3 is an outcome of our independent and
original work. We have duly acknowledged all the references from which the ideas and extracts
have been taken. We have given credit to all sources of information used in our assignment by
including citations and contacts in the APA format. The project is free from plagiarism and has
2
Introduction
One of the most critical measures that have been considered before the start of the project
is risk management. This process must be done carefully before starting and during the project.
After defining the project in the previous report, including determining scope, objectives,
according to the limitations and nature of each part of the work break down structure, project
risks should be defined and managed to prevent the occurrence or response timely. Due to the
technical nature of the project and the study of potential risks and using the past experiences of
the project execution team, some of the most critical internal and external risks have been
identified. Then, in the next step, each risk is evaluated in terms of probability of occurrence and
the degree of impact, and the results are used to develop risk response. Although the project
executive team tries to prevent risks, a contingency plan is developed to respond to the risks at
the time of an occurrence. Risk management budgeting has also been done using project
budgeting data.
Risk Identification
Risk breakdown structure and risk profile have been conducted for having a more
comprehensive understanding of risk and the consequences of failure. The risk breakdown
structure is aligned with the previous project plan, which includes a more detailed illustration of
the risk component. The following paragraph will identify the key internal and external risks, and
3
Risk Breakdown Structure
Based on the work breakdown structure (Appendix 1) in the previous project plan, the
risk breakdown structure has been conducted; two external risks and three internal risks will be
illustrated in detail. For the external risks, there might be constant changes in the codes and
policies related to security systems and work standards, which will make an impact on the design
approval process with the whole installation plan and pre-installation (Cather, Morris &
Wilkinson, 2001), if during our project the industrial standard and codes changed so the design
might not be approved, and more adjustment will be needed (Angel et al., 2001). In addition, if
the market price is fluctuated, which will influence the consistency of the budget (Elleuch,
Hachicha & Chabchoub, 2014). The project might redesign to adapt to the new market price and
control the budget, and for the installation process, the selected facilities might cause different
costs. Thus, the installation will also take the risk for this reason.
For the internal risks, the employee who ignores the safety code and gets injured from the
technical operation will be the key risks that impact the installation process; if there are any
unexpected injuries, the schedule might be delayed, and there is a risk that affects the employee
arrangement (Schofield et al., 2015). Another internal risk is the possibility that caused by
communication when there is any process that needs the cross-department collaboration; there
might be the risk in the coordination and miscommunication, this will also impact the efficiency
of the whole project (Liu et al., 2021). The last internal risk is that there might exist a gap
between the design and actual installation situation; when processing the wiring, there have the
possibility of error because the wiring is very complex and experienced construction workers are
needed, if there is any mistake in this process there will impact on the schedule and waste of
4
Figure 1
Risk Breakdown structure
Risk Profile
A risk profile is a set of questions that address the project's traditional sources of
uncertainty. These questions have been designed and refined based on prior experience of a
similar project (Gray & Larson, 2011). The risk profile is prepared and maintained in the project
office under the supervision of the project manager. This profile, which is an essential source for
risk management during the project, is based on past experiences and will be reviewed during the
project if necessary.
5
Table 1
Management
Risk profile
Does the project leader have effective management skills and overview concepts within
the project?
Coordination
Is there any member responsible for the cross-function coordinating the resource and
employee?
Design
Does the installation plan have a realistic design and align with optimistic assumptions?
Work Environment
Budget
Testing
Schedule
Are the project arrangement with a reasonable period and acceptable slack?
Resource
Quality
Staffing
6
Risk Assessment
In the previous part, the internal and external risks of the project were identified. The
important issue in risk management is that the impact and probability of the risks are not the
same. Therefore, risks should be rated and prioritized based on the probability and the degree of
impact so that response can be taken at the appropriate time (Cervone, H.F., 2006).
Table 2 shows the level of impact of risk in the project. Each risk event is rated based on
a five-point scale which 5 means the level of impact is very high, and one means the impact of
the risk event is very low. Table 3 demonstrates the likelihood of risk events. We use the five-
point scale for evaluating the probability of the risk. Detection difficulty is a measure of how
Table 1
Risk Impact interpretation
After determining the indicators related to risk assessment, a risk assessment form has
been prepared. Table 4 shows the results of the assessments made and each risk's probable time
of occurrence. The risk assessment information helps to take preventive actions at the right time
Table 3
Risk assessment form
Detection
Code Risk event Likelihood Impact Risk effect When
Difficulty
Time, Cost and
1.3 Error in the wiring process 4 5 5 Wiring and installation
Quality
Ineffective internal
1 2 3 2 Time and scope Throughout the project
communication
Using the information of the risk assessment form and with three indicators of impact,
probability, and detection difficulty, we developed a risk severity matrix. As you can see in
Figure 2, the range of each project risk is specified in which the error in the wiring process is
considered as the significant risk of the project because the occurrence of this risk can cause cost
8
Figure 1
Risk Severity Matrix
Risk Major
5
Risk
Error in the
4 wiring
process
Likelihood
Impact
Response Development
The risk response matrix in the project can help the project team reduce risks and exploit
opportunities (Ben-Davis & Raz, 2001). We attempt to generate risk treatment options and
actions to use existing opportunities and reduce risks by planning risk responses. Table 5 shows
the Risk Response matrix of the project. According to the importance and impact of each threat,
9
which was determined in the risk assessment stage, the appropriate response and contingency
Table 5
Risk Response matrix
To find the proper estimation regarding contingency funds, there is a need to find an
accurate budget baseline. But the exact amount of five different types of risks related to different
activities is not available in the budgeting plan, which is assessed in the previous paper and is
shown in appendix 2. So, according to the risk assessment table, table 4, and the cost related to
risks that influence the contingency fund estimated in the chart below, the rate of probability of
each risk is computed. In addition, regarding the level of each risk, the impact of risks is
determined, and the total estimated contingency reserve is found in research from Usmani
10
Table 6
Contingency Fund Estimation
EMV
Risk Probability Impact
(Probability*Impact)
Change in codes and
8% 6,000 480
standards
Ineffective internal
15% 9,000 1,350
communication
Inconsistency of
23% 11,500 2,645
budget
Error in the wiring
31% 14,500 4,495
process
The total estimated contingency reserve 11,040
Total estimated cost according to budgeting in
40,758
Appendix 2
Total estimated contingency reserve and cost of the
51,798
project
Buffer Time
In this project, for having better risk management to protect the drawbacks of the delays
related to the probable risks and keep the project on track, extra time is added to estimating the
timeline. This time estimation is called buffer time, the same as a contingency fund, and is
closely related to the percent of likelihood of occurring risks in the project (Schragenhiem &
Ronen, 1989). This buffer-adjusted will not affect the project schedule. The baseline schedule is
predicted that the whole project will be done in 75 days (start date on 01.02.2022 and end date on
15.04.2022). Then, based on the whole impact rate, the extra time should be 20 days and added
to the main timetable. For finding the days that will allocate to each risk, in table 6, the buffer
Table 7
11
Buffer Time
Buffer Time (Based on
Risk Probability Impact
20 days)
Change in codes and standards 8% 12% 2.4
Ineffective internal communication 15% 18% 3.6
Ignoring safety codes 23% 18% 3.6
Inconsistency of budget 23% 23% 4.6
Error in the wiring process 31% 29% 5.8
Total estimated buffer time-days 20
After defining and assessing the risks and determining the risk response strategies of the
project, we prepared a risk register. The risk register is the foundation of the last stage of risk
management, which is risk control. Risk control includes implementing a risk response strategy,
monitoring start-up events, initiating contingency plans, and monitoring new risks (Kwak &
Stoddard, 2004). Table 5 shows the project risk register. The project manager and supervisors
monitor potential risks as the project progresses. Based on the background and experience of the
project execution team, many potential risks have been anticipated and controlled. Also, various
According to the company rules and organizational culture, all team members are obliged
to inform the project manager of any errors in the processes. Given that the quality of services
and commitment to schedule is a priority of the company, the timely and explicit announcement
of mistakes or potential risks is not punished, but denial and concealment are unacceptable. Risk
identification and assessment are constantly updated with new information based on the nature of
the project. Risk profiles should be tested to see if the initial responses are correct. Ongoing
12
meetings with project stakeholders, including executives and hotel managers, are held to review
that have been carefully done in this project. Each identified risk is assigned (or shared) by
mutual agreement of the owner, project manager, and executive team that has line responsibility
for the work package or segment of the project. It is best to have the line person responsible
approve the use of budget reserve funds and monitor their usage rate.
Table 8
Risk Register
13
Persuasive Letter
My purpose in writing this letter as project manager of Feel safe company is to emphasize the
importance of the risk management plan in our project. By using a systematic procedure, we try
to manage the risk via identifying, assessing, and responding to all risks of the project, even
positive or negative.
There are various risks that can impact the results of our project. The most important
Cost
Expenses associated with events can have an effect on the budget of the project
Schedule
Performance
The risk is that a project will produce results that are not in keeping with its specifications.
Having a good project risk management plan helps us to understand how our project
might go in the wrong way. Developing alternative strategies for budget, schedule, and human
14
The management of risks must be done separately for each project within a program or portfolio.
It is possible for project managers to monitor and manage risks at the program level if they have
Our company may have many ongoing projects with different sizes and types that can
have various stakeholders. Program management facilitates the management of our projects.
With the plan, we can reduce the number of contingency fundings, focus help on the program's
most imperative risks rather than individual projects, and reduce costs by reducing risk at the
program level. Although project risk management can have costs, it is essential to note that it is
an investment. A profitable project with an effective risk management plan yields the benefits
outlined here.
We recommend that all projects with an estimated cost of more than $10,000 be
performed using this practice based on our research and past pieces of knowledge. Do not
Best Regards,
Ashkan Alavian
Project manager
15
Appendix 1
16
Appendix 2
Budgeting
17
References
Angel Del Brio, J., Fernández, E., Junquera, B., & José Vázquez, C. (2001). Joint adoption of
org.ezproxy.myucwest.ca/10.1080/09544120120075307
Ben-David, I., & Raz, T. (2001). An integrated approach for risk response development in
project
Business Administration.
Cather, H., Morris, R. D., & Wilkinson, J. (2001). Business Skills for Engineers and
Technologists. Newnes.
control. Tel Aviv University, Faculty of Management, Leon Recanati Graduate School of
Elleuch, H., Hachicha, W., & Chabchoub, H. (2014). A combined approach for supply chain risk
https://doi-org.ezproxy.myucwest.ca/10.1080/13669877.2013.815653
Gray, C.F. & Larson E.W. (2011). Project Management: The Managerial Process (5th ed. Or
Kwak, Y. H., & Stoddard, J. (2004). Project risk management: lessons learned from software
18
Liu, W., Zhao, H., Song, S., He, W., & Li, X. (2021). Coping with Loss Aversion and Risk
https://doi-org.ezproxy.myucwest.ca/10.3390/su13084364
Schofield, K. E., Alexander, B. H., Goodwin Gerberich, S., & Ryan, A. (2015). Management
Insurance Perspective. Journal of Safety, Health & Environmental Research, 11(1), 186–
194.
Usmani, F. (2012, February 16). Contingency Reserve vs. Management Reserve. PM Study
reserve-vs-management-reserve/
19