Api 570 Sec 6&7
Api 570 Sec 6&7
Correct
Points: 1/1
Per API 570, a one-time, temporary extension of a piping inspection due date is called:
Question 2 Correct
Points: 1/1
To ensure equipment integrity, all piping systems and pressure-relieving devices shall be
Question 3 Correct
Points: 1/1
Regarding future Inspection interval determination by the Inspector, which of these
statements is not correct (False) according to the API 570 code?
Question 4 Correct
Points: 1/1
After each inspection or significant change in operating conditions, the
Question 5 Correct
Points: 1/1
For class 1 piping , the risk based inspection (RBI ) assessment should be reviewed and
approved at intervals not to exceed
Your Answer Correct Answer
5 years 5 years
Question 6 Incorrect
Points: 0/1
if RBI methods are not used , visual external inspections of piping shall be conducted at
intervals of no more than
10 years for a Class 2 line 5 years for a Class 1 or Class 2 line
Question 7 Correct
Points: 1/1
What is the recommended maximum inspection interval for injection point thickness
measurements?
Question 8 Incorrect
Points: 0/1
Deadlegs in a piping system should be:
Eliminated whenever Inspected at the same time interval as the rest of the
possible piping system
Question 9 Correct
Points: 1/1
Inspection intervals shall be reviewed and adjusted (How often) per API 570?
Question 11 Incorrect
Points: 0/1
In addition to thickness measurement intervals by Class (also Injection Points & S/A),
Table 1 also contains recommended maximum inspection intervals for external
inspection:
By Class or ½ RL, use lesser value By Class (RL value applies when less than table)
Question 12 Correct
Points: 1/1
For Piping in non-continuous service, inspection intervals can be based on the number of
years of actual service that the vessel operated, not calendar years, provided that all of
the following precautions are taken EXCEPT:
Question 13 Correct
Points: 1/1
For a class 1 piping in non-continuous service (operates for 8 months in every year and is
placed under a nitrogen purge each time after being idled for summer for 4 months),
what are maximum possible Thickness measurements inspection intervals (assume NO
RBI)?
Question 15 Correct
Points: 1/1
Per API 570, inspection of Category D Fluid Service piping is:
Question 16 Correct
Points: 1/1
A piping circuit containing hydrocarbons is located within the boundary limits of an
operating unit. The hydrocarbons, if released, would evaporate slowly. According to API
standard 570, what classification should this piping receive?
Question 17 Correct
Points: 1/1
Listed below are several examples of a CLASS 1 piping system. Which one does not
belong ?
Question 18 Correct
Points: 1/1
Of the three classification of piping systems, which includes the majority of unit
processes and selected off-site piping ?
Question 19 Correct
Points: 1/1
Class 3 piping is described as being in services
Question 20 Correct
Points: 1/1
During inspection for CUI, an insulated austenitic SS, Class 1 piping system operating at
300°F (150°C) would require what percentage of follow-up exams at areas of damaged
insulation?
Question 21 Correct
Points: 1/1
Piping systems that are known to have a remaining life of over ……….or that are
adequately protected against external corrosion need not be included for the NDE
inspection recommended in Table 2
Question 22 Correct
Points: 1/1
During inspection, you found CUI with a damaged insulation; the piping was class II, the
allowed percentage of insulation remove is
Question 23 Correct
Points: 1/1
What is the minimum thickness measurement interval for CUI?
Question 24 Correct
Points: 1/1
For Class 3 piping systems, the examination for corrosion under insulation (CUI) should
include at least __________ percent of all suspect areas?
Question 25 Correct
Points: 1/1
For Class 2 piping, the extent of CUI inspections on a system operating at – 45 F will be
Question 26 Correct
Points: 1/1
Inspection of small-bore piping (SBP) that is part of a Class 3 and Class 4 secondary
process system is:
Question 27 Correct
Points: 1/1
Small bore piping (SBP) that is Class I shall be inspected
Your Answer Correct Answer
To the same requirements as primary To the same requirements as primary
process piping process piping
Question 28 Correct
Points: 1/1
Threaded connections associated with machinery and subject to fatigue damage should
be inspected :-
Question 29 Correct
Points: 1/1
If an inspector finds threaded small bore piping (SBP) associated with machinery and
subject to fatigue damage, he should :-
Question 30 Correct
Points: 1/1
Pressure-relieving devices should be inspected, tested and maintained in accordance with
?
Question 31 Correct
Points: 1/1
For Pressure-relieving Devices PRDs tested and repaired ,Each repair organization shall
have
Question 33 Correct
Points: 1/1
What is the maximum interval of pressure relief device testing in typical process service?
Question 34 Correct
Points: 1/1
When a pressure-relieving device is found to be heavily fouled or stuck, or when a PRD
fails an as received pop test,
Question 35 Correct
Points: 1/1
The inspection interval for all pressure-relieving devices is determined by________.
Question 36 Correct
Points: 1/1
If a RBI assessment is not performed, what is the greatest possible time period allowed by
API 510 between testing of pressure relieving devices?
Question 37 Correct
Points: 1/1
What should the frequency of inspection for pressure relief devices be based on?
Question 38 Correct
Points: 1/1
Here is the thickness data for a specific CML. Calculate the Corrosion Rate in ipy?
Question 39 Correct
Points: 1/1
Here is the thickness data for a specific CML. Calculate the Corrosion Rate in ipy?
Question 40 Incorrect
Points: 0/1
Here is the thickness data for a specific CML. Calculate the Corrosion Rate in ipy?
Question 42 Incorrect
Points: 0/1
For a Class 2 pipe circuit, the controlling Corrosion Rate is 0.006 ipy and the Remaining
Corrosion Allowance is 0.096”. Determine the Intervals for the Thickness Measurement
and External Inspections.?
Question 43 Correct
Points: 1/1
Here is the data For a Class 2 pipe circuit. Determine the Interval and Next Inspection
Date for the Thickness Measurement
Question 44 Incorrect
Points: 0/1
A piping system installed in January 1993 (initial thickness 0.320 in.)
In January 2004, a thickness of 0.200 in. was recorded just prior to a change of service in
the piping system as reported to the Corrosion Specialist by the Inspector, who was told
to expect a significant decrease in the corrosion rate. The next thickness in January 2009
measured 0.180 inches. What corrosion rate shall be used for this line and, given this
information, the Retirement thickness of 0.150 inches will be reached on:
Corrosion rate almost 9 MPY & retirement Corrosion rate of 4 MPY & retirement
thickness will be reached by June 2012 thickness will be reached by July 2016
Question 45 Correct
Points: 1/1
For a class 1 piping in non-continuous service (operates for 8 months in every year and is
placed under a nitrogen purge each time after being idled for summer for 4 months),
what are maximum possible thickness measurement and external inspection intervals
(assume NO RBI)?
Question 46 Correct
Points: 1/1
long term(L.T) and short term (S.T) corrosion rates should be compared in order to:
Question 47 Incorrect
Points: 0/1
What is the purpose of comparing the long-term and short-term corrosion rates of piping?
.as part of determining the required thickness as part of the data assessment
Question 48 Incorrect
Points: 0/1
Long-term and short-term corrosion rates should be compared to see which results in the
shortest remaining life as part of the data assessment. Who is responsible to select the
corrosion rate that best reflects the current process?
Piping Engineer after consultation with Authorized Inspector after consultation with
the Corrosion Engineer a Corrosion Engineer
Question 49 Incorrect
Points: 0/1
Thickness measurement readings on a piping system indicate that a corrosion rate has
increased. The Inspector’s most appropriate response is to:
Recalculate the piping circuit average Recalculate the inspection interval of the
corrosion rate system
Question 50 Correct
Points: 1/1
What is the formula for ST Corrosion Rate?
Question 51 Correct
Points: 1/1
The table below shows the years of operation and corresponding wall: thickness of a Class
1 piping system.
For a minimum required thickness of 0.380 inch ( 9.652 mm) , the shortest remaining life
of the piping system is :
Question 52 Correct
Points: 1/1
A piping system installed in January 1993 (initial thickness 0.320 in.)
In January 2004, a thickness of 0.200 in. was recorded just prior to a change of service in
the piping system as reported to the Corrosion Specialist by the Inspector, who was told
to expect a significant decrease in the corrosion rate. The next thickness in January 2009
measured 0.180 inches. What corrosion rate shall be used for this line and, given this
information, the Retirement thickness of 0.150 inches will be reached on:
Question 54 Correct
Points: 1/1
The recommended maximum inspection interval for the thickness measurement for an
injection point circuit is :
Question 55 Correct
Points: 1/1
use the given information below!
This data is given for a Class 2 piping system … Remaining Life = 16 Yrs
Thickness = 0.36 in. (Insp results) … Corrosion Rate = 10 mpy
. When is the next thickness measurement inspection due (using the information above)?
Question 56 Incorrect
Points: 0/1
use the given information below!
This data is given for a Class 2 piping system … Remaining Life = 16 Yrs
Thickness = 0.36 in. (Insp results) … Corrosion Rate = 10 mpy
.When will the next external inspection be due (using the given information above)?
Question 57 Incorrect
Points: 0/1
Measurements from inspection of Class 3 pipe reveal actual metal thickness of 0.350
inches. Calculated minimum thickness is 0.250 inches. If the corrosion rate is 0.0025
inches/year, the NEXT thickness measurement inspection is due in
Question 58 Correct
Points: 1/1
A piping system installed in January 1993 had an initial thickness of 0.32 inch . In January
2004, a thickness of 0.20 inch was recorded just prior to a change of service on the piping
system. The thickness measurement in January 2009 was 0.18 inch . The retirement
thickness of 0.15 inch will be Met in :
Question 59 Incorrect
Points: 0/1
An NPS 12 carbon steel standard pipe in Class 2 service, designed to operate at 450 psig
and 500°F (260°C) with an allowable stress of 20 ksi, has a thickness at inspection of 0.280
inches (7.1 mm). What is the maximum interval for the next thickness measurement
inspection (assume no RBI, E=1.0, Corr. rate = 25 MPY)?
Question 60 Incorrect
Points: 0/1
The fluid in a process is changed, which results in the piping system being reclassified as a
Class 1 piping system. The previous thickness measurement interval was 6 years. Given
the following:
ØMeasured thickness: 0.240 inch.ØRequired thickness: 0.192 inch.ØAnticipated corrosion
rate based on similar service: 0.008 inch per year.
If RBI is not considered, what should the new thickness measurement interval be?
Question 62 Correct
Points: 1/1
For a class 1 piping in non-continuous service (vessel working 6 months only per year),
When is the next Thickness Measurements for a piping last inspected on May 2005?
Question 63 Correct
Points: 1/1
For a class 1 piping in non-continuous service (operates for 6 months in every year and is
placed under a nitrogen purge each time after being idled), what are maximum possible
thickness measurement and external inspection intervals (assume NO RBI)?
Question 64 Correct
Points: 1/1
A class 2 piping has been in non-continuous service for 15 years. During this time, it has
been filled three times, for two years at a time, and then Thickness Measurements
conducted. The last Thickness Measurements determined that the vessel had a remaining
life of nine years. When is the next Thickness Measurements due?
A default corrosion rate of 10 mils Published data on piping systems in comparable
per year service
Question 66 Correct
Points: 1/1
For newly installed piping systems , the interval for the first thickness measurement is
established by :
Question 67 Correct
Points: 1/1
Service conditions have been changed for one the piping. Determining the probable rate
of corrosion from which the remaining wall thickness at the time of the next inspection
can be
Question 68 Correct
Points: 1/1
If the corrosion rate for a piping system cannot be determined by similar service, initial
thickness measurements should be taken within:
Question 70 Correct
Points: 1/1
Service conditions have been changed for one the piping. Rate of corrosion has to
determined no longer than
Question 71 Correct
Points: 1/1
Following a significant change in operating condition:
Question 72 Incorrect
Points: 0/1
If RBI is not being used, the interval between piping inspections shall reviewed when
changing service from:
Question 73 Incorrect
Points: 0/1
A piping system has an assumed corrosion rate of 0.010 inch per year. An inspection
shows an actual short term corrosion rate of 0.021 inch per year The proper course of
action would be to:
Question 74 Incorrect
Points: 0/1
Evaluation of record of the previous inspection reveals that thickness reading and the
resulting calculation of corrosion rate were inaccurate . The rate to be used for the next
period shall?
Not be changed to actual rate found until rate is Be changed to agree with the actual
confirmed at the next inspection corrosion rate found
Question 75 Correct
Points: 1/1
For repaired or in-kind replacement piping, the corrosion rate shall be established based
on _____
Question 76 Correct
Points: 1/1
Question 77 Correct
Points: 1/1
Which of these MAWP values is correct for a piping system NPS 10, ASTM A106 Gr. B
Seamless pipe, designed at 300°F, latest UT = 0.30 inches, observed corrosion rate = 0.020
inches per year, and the next inspection is to be in 5 years?
Your Answer Correct Answer
372 psig 372 psig
Question 78 Correct
Points: 1/1
When the maximum allowable working pressure (MAWP) is recalculated for the continued
use of a piping system, the wall thickness to be used is the:
Question 79 Correct
Points: 1/1
What wall thickness is used to recalculate MAWP for continued use of a piping system?
Question 80 Correct
Points: 1/1
Which of these may be assumed for maximum allowable working pressure (MAWP)
calculations (unknown materials)?
Question 81 Correct
Points: 1/1
if a piping system is made up of unknown materials and computations must be made to
determine the minimum thickness of the pipe, what can the inspector or the piping
engineer do t establish the minimum thickness?
Question 82 Correct
Points: 1/1
Which of these MAWP values is correct for a piping system designed at 380 psig at 700°F,
having A53 Gr. B seamless pipe, NPS= 18 inch , latest UT = 0.28 inches, observed corrosion
rate = 0.005 inches per year, and the next inspection is in 4 years?
Question 83 Incorrect
Points: 0/1
Which of these MAWP values is correct for a piping system designed at 380 psig at 700°F,
having A53 Gr. B seamless pipe, latest UT = 0.28 inches, observed corrosion rate = 0.005
inches per year, and the next inspection is in 4 years?
Question 84 Incorrect
Points: 0/1
Determine UT thickness Inspection Interval (Class 2 pipe) per API 570 rules and then
determine the MAWP of corroded pipe given: Design pressure/temp = 500 psig/500°F for
A106 Gr B, Pipe = NPS 20 Sch. 40, with a baseline UT thickness in 2003 of .560 inches, and in
2008 of .530 inches, and in 2013 of .500 inches … The Corrosion rate = .006 or 6 MPY, and
you must assume a 10 year interval proposed for purpose of the MAWP calculation!
UT inspection interval = 10 years for UT inspection interval = 10 years for class
class 2 piping, and the calculated MAWP = 2 piping, and the calculated MAWP = 722
494 psi psi
Question 85 Correct
Points: 1/1
A piping system has the following characteristics:
Pipe description : NPS 10 , A106 Gr. B , Outside diameter of pipe , D: 10 ¾ Inches
Allowable stress:- 20,000 psi , Longitudinal weld efficiency, E=1
Thickness Determined Inspection:- 0.300 inches,
Observed Corrosion Rate: 0.020 inches, Next Planned Inspection : 5years
Question 86 Incorrect
Points: 0/1
An older section of pipe of unknown material was inspected and found to have a
thickness of 0.189”. The pipe is NPS 8 and appeared to originally be standard wall
thickness. The system operates at 300°F. What is the current maximum allowable working
pressure?
Question 87 Incorrect
Points: 0/1
Determine the minimum required thickness for a NPS 2, ASTM A106, Grade B, pipe
designed for 100 psig @ 100 °F., D = 2.375 in., S = 20,000 psi, E = 1.0 (since seamless), Y = 0.4.
0.007 in 0.07 in
Question 88 Incorrect
Points: 0/1
Determine the minimum required thickness for a 14 NPS, ASTM A106, Grade B, pipe
designed for 600 psig @ 100 °F, D = 14 in., S = 20,000 psi, E = 1.0 (seamless), Y = 0.4
0.107 in 0.208 in
Question 89 Incorrect
Points: 0/1
What is the minimum required thickness, given the design conditions below for an
existing piping system in a local refinery?
Given: Design Pressure & Temp = 600 psig @ 500°F, ASTM A-106 Gr. B, Pipe is 18 NPS and
the structural minimum design thickness for the 18 NPS system = .270 inches
Question 90 Incorrect
Points: 0/1
What is the minimum required thickness for an NPS 4 piping system (API 5L Gr. A25 ERW)
that operates at 525 psi at 400°F, and has a corrosion allowance of 0.062 inches?
Question 91 Incorrect
Points: 0/1
What is the minimum required thickness including corrosion allowance for an NPS 4
piping system (API 5L Gr. A25 ERW) that operates at 525 psi at 400°F, and has a corrosion
allowance of 0.062 inches?
Question 92 Incorrect
Points: 0/1
Calculate the retirement thickness of a 10 " gate valve. The valve will operate at a
pressure of 500 psig and a temperature of 600 F. The stress allowed is 7,000 psi and E = 1.0
(since seamless),
Question 93 Incorrect
Points: 0/1
In pipe caps, corroded areas evidenced by local thinning:
Question 94 Correct
Points: 1/1
During a routine inspection, you notice a bulge in a pressure vessel that is attached to a
piping. Your immediate action is
Question 95 Correct
Points: 1/1
When unexpected movement of the piping system is observed, what should the inspector
do to evaluate the problem?
Question 96 Correct
Points: 1/1
During an inspection, you find that the pipe shoes have moved off the main supports and
are hanging on the beams preventing the line returning to its cold position. What would
be the most appropriate action for you to take?
Question 97 Incorrect
Points: 0/1
Piping stress analysis is done during the system's original design. How can the inspector
make use of stress analysis information?
An inspector cannot use this It can be used to concentrate inspection efforts at
information. It is only meaningful to a locations most prone to fatigue or creep damage,
piping engineer. and to solve vibration problems.
Question 98 Correct
Points: 1/1
According to API 570, owner/user shall maintain piping records that are:
Question 99 Correct
Points: 1/1
Inspection reports shall document the:
Question 100 Incorrect
Points: 0/1
The owner/user shall maintain appropriate permanent and progressive records of each
piping system covered by API 570 for all of the following items EXCEPT:
Results of thickness measurements & other tests, inspections, Fitness for service
repairs (temp/permanent), alterations, or rerating. Design assessment plans and
information and piping drawings may be included strategies
Question 101 Correct
Points: 1/1
Computer based systems are useful for storing data relating to which of the following?