Construction Cost Estimate

Quantity Cost
1 Bricks Bricks 20 / sq ft 5000/ per Thousand 40,000 200,000
2 Sand Sand 1 Truck/ 167 Sq. ft 5000 /Truck (350 cub ft) 12 60,000
3 Crush Crush 0.6 Cubic feet / sq ft 10000 6 60,000
4 Steel Steel 1.35 kg / sq ft 3 ton @ 60000 2,700 180,000
5 Cement Cement 1 Bag / 3.07 sq ft 340/ Bag 651 221,498
6 Mud
7 Shuttering for Roof
8 Tiles for Front 65.03 Sqm for 10 Marla 425/ Sq m
9 Grills Grills 160 sq ft for 5 Marla; 160 Sq ft for
7 Marla and 280 sq ft for 10 Marla
150/ Sq ft
10 Glass Glass 140 sq ft for 5 Marla; 140 sq ft for
7 Marla and 250 sq ft for 10 Marla
30/ Sq ft
11 Lamination Lamination 12 sheets for 5 Marla
House; 16 Sheets for 7 Marla and 18 for
10 Marla
1025/ Sheet
12 ChipBoard Chip Board 66 sheets for 5 Marla
House; 74 Sheets for 7 Marla and 74
sheets for 10 Marla
700/ Sheet
13 Ply Ply 12 sheets for 5 Marla House; 17
Sheets for 7 Marla and 19 sheets for 10
Marla House
210/ Sheet
14 Wood Wood 242 Sq ft for 5 Marla; 296 Sq ft
for 7 Marla and 296 Sq ft for 10 Marla
House
15/ Sq Ft
15 Gate 150 /Sq ft
16 Flooring For the whole covered area 35/ Sq ft
17 Bathrooms flooring for 4 bathrooms 450/ Sq m
18 Doors (16) 80/ Sq ft
19 Civil Work
20 Elecrification
21 Sanitation
22 Paint
23 Carpenter
24 Glass Work
TotaI Cost 721,498
10 MarIa
MateriaI 721,498
Labour @ 200 per sqft 400,000
Land 2,100,000
MisceIIaneous 200,000
TotaI 3,421,498
Per Sqr Feet Cost - 561
(Labour+Material)