PO07218 Installation Requirements For Telecommunication Equipment On Evoenergy Assets
PO07218 Installation Requirements For Telecommunication Equipment On Evoenergy Assets
PO07218 Installation Requirements For Telecommunication Equipment On Evoenergy Assets
REQUIREMENTS FOR
THIRD PARTY ASSETS ON
EVOENERGY NETWORK
2022 • PO07218 • V2
CONTENTS
2022 • PO07218 • V2 2
1. PURPOSE AND SCOPE
1.1 Purpose
The purpose of this document is to outline the general requirements and considerations for third party
transmitting assets such as communications cables and radio frequency (RF) equipment on Evoenergy owned
structures.
These types of cables and equipment are generally installed to provide communication services, including but
not limited to, cable television (CATV), telephone and interactive data services. Communication cables are
both broadband and narrowband (self-supporting or integral bearer). Communication equipment will include
mobile phone cells, transmitters/receivers, and any other radio devices.
The requirements outlined are to mitigate the risk of radio frequency (RF) hazards to people, maintain access
to Evoenergy hardware, protect street appeal and to ensure adequate fixing and effective integration onto
Evoenergy structures.
1.2 Scope
The sections within the document outlines the design, installation, and operational and maintenance
requirements for third party organisations or individuals proposing to install communication devices and
associated hardware on Evoenergy overhead network structures. Also, the sections contain common
requirements for both cables and RF equipment as well as specific requirements for RF equipment.
The required documentation provided to Evoenergy in accordance with this document will support the
acceptance of a standard design for installation on Evoenergy assets.
Only 230/400V and or 11kV structures are within scope of this document. Underground network assets (such
as switching stations) and substation assets or 66kV and 132kV transmission assets are not considered
suitable for the attachment of third-party devices.
The standard design must cover the variables that could be proposed at any particular site. Site specific
applications and plans must be submitted and approved prior to the installation of any cable or equipment.
The equipment referred to in this document must operate between 3 kHz to 300GHz (Radiation Protection
Standard, series No 3) and that do not present ionising radiation hazards.
Clearances, pole loadings and all other conditions must also continue to meet the requirements of this standard
for the entire life cycle of the communication cable and equipment, including during maintenance and removal.
The requirements for working on telecommunication equipment installed on Evoenergy structures; or, working
on Evoenergy structures that have telecommunications equipment are outside the scope of this standard.
2022 • PO07218 • V2 3
2. REFERENCES
It is the responsibility of the communications designer to ensure the latest version of the appropriate standards
and drawings referred to in this standard is used in all designs and calculations.
2022 • PO07218 • V2 4
3. DEFINITIONS & ABBREVIATIONS
TABLE 3. DEFINITIONS AND ABBREVIATIONS
TERM DEFINITION
2CTW 2 Wire Twisted (1 phase) service
4CTW 4 Wire Twisted (3 phase) service
4WL 4 Wire Lateral (open wire 3 phase) service
AAAC All Aluminum Alloy Conductor
AAC All Aluminum Conductor
ABC Aerial Bundled Conductor
ACSR Aluminium Conductor Steel Reinforced
ACT Australian Capital Territory
ADSS All Dielectric Self-supporting (Communications cable—optical fibre)
AHD Australian Height Datum
Al Aluminium
Antenna Transmitter, such as a wire or grid, sometimes mounted within a tube or panel, that
emits and receives radio signals
Asset Owner Owner of the Third-Party Communications Assets
Authorised person A person with technical knowledge or sufficient experience who has been approved
and authorised in writing by the Company to perform the function requiring
authorisation.
BAZ Bushfire Abatement Zone
BCC Broadband Communication Cables
CATV Cable television, that is, television provided by means of Broadband cable.
CBL Calculated Breaking Load. In relation to a conductor, means the calculated minimum
breaking load determined in accordance with the relevant Australian/New Zealand
Standard.
CLAH Current-limiting Arcing Horn, or gapped surge arrester
Communications Communication hardware refers to the equipment associated with the transmitting
Hardware device excluding the antenna, namely, the power supply, isolation device and any
auxiliary equipment.
CSA Cross-sectional Area
Cu Copper
EMF Electromagnetic Field
Exclusion Zone The safe working distance that has to be achieved from an energised radio
frequency transmitter, which cannot be entered by any part of the body or metal
object.
GL Ground Level
HDC Hard Drawn Copper
HV High Voltage
2022 • PO07218 • V2 5
TERM DEFINITION
IBC Integrated bearer cable – an overhead cable used for telephone lines consisting of
a metallic supporting strand or strands and a variable number of metallic telephone
pairs
MEWP Mobile elevated working platform
Microwave Dish Dish-shaped transmitter device, used on some cells, that emits and receives radio
signals that allow the cell to communicate with the telecommunications carrier’s
network
Mobile Phone Cell Communications installation that communicates between mobile phones and the
telecommunications carrier’s network using radio signals
NENS National Electricity Network Safety codes, issued by ENA
OPGW Optical Ground Wire—an overhead earth wire with internal optical fibre/s
RF Radio Frequency
Radio transmitter A device used to send radio signals. Such transmitters have associated
communications hardware installed on the ground or the structure supporting the
antenna
SC/GZ Steel Conductor / Galvanized
SF Safety Factor, also Strength Factor
SL Street lighting
UG/OH Underground to overhead transition structure
UTS Ultimate Tensile Strength – the maximum mechanical load, which may be applied
to a conductor, beyond which failure occurs.
2022 • PO07218 • V2 6
4. DESIGN REQUIREMENTS
2022 • PO07218 • V2 7
If more information is required or non-conformances to this document or its referenced standards are identified,
notice will be provided in writing outlining the omissions. The Safety in Design Report must be then updated
outlining the amendments to the design.
Acceptance of the standard design does not allow the devices to be installed on Evoenergy structures until
site specific drawings are provided and approved.
2022 • PO07218 • V2 8
ATTRIBUTE VALUE
Structure type 11kV and 230/400 V pole structures.
Minimum Ground Temperature: 0°C (minimum ground temperature recorded at Canberra airport
at 100mm is 4°C)
Maximum Ground Temperature: 40°C
Typical Network Design Life 40 years
ATTRIBUTE VALUE
Maximum System Earth Fault Current
7kA- Specified in compliance to Fyshwick Zone Substation
(11kV Network)
Maximum System Short Circuit Duration 0.5 seconds (as extracted from PO07127 Distribution Earthing
(11kV network) Design and Construction Manual clause 6.8)
Maximum System Earth Fault Current
40kA (single 2MVA transformer 6% reactance)
(230/400V Network)
Maximum System Short Circuit Duration
(230/400V Network – Past the LV 0.2 Sec
Protection at distribution substations)
2022 • PO07218 • V2 9
The connected stay wire must have an insulator installed in series that meets the flash over requirements of
the highest voltage attached to the structure being stayed. Typically, Porcelain insulators are utilised on the
Evoenergy Network – to AS 3609
The correct stay insulator being installed mitigates the risk of transfer hazards from one circuit to another.
4.4.3 Restricted Structures and Locations
Complex structures are not deemed suitable for the installation of third-party assets.
Devices must not be installed above any Evoenergy network circuit- unless a site-specific exemption to this
requirement is granted.
Structures with the following attachments must be avoided;
Backyard Poles
Conductive Poles
Transmission Structures (33kV, 66kV, 132 kV)
Pole with Substation
Pole with automated switching equipment
Customer overhead services
Structures with other third-party assets installed
Structures which are stayed
Bare mains constructions with a tee off (double termination configuration)
Overhead mains to underground service mains connections (possibly suitable up to one 16mm²
underground service only)
Structures that are not considered appropriate are;
Low Voltage and or High Voltage mains underground to overhead connections (UG/OH)
Structures with surge arresters
Structures with network nominal system voltages above 11kV
Structures with any network switchgear (excluding service fuses)
Reinforced timber structures (nailed poles)
Condemned poles
Termite affected structures
Severely leaning structures
In proximity to future planned capital works- For example the removal of overhead mains.
Structures located in environmentally sensitive environments such as water catchment areas or restricted
areas in National Parks are not suitable for third party device installations.
4.4.4 UG/ OH Poles – Special Situation
Electricity cables rising up the pole do not pose any particular problem for the attachment of a steel catenary
cable to the pole. To provide additional protection however, a non-conductive section guard is to be fitted to
Evoenergy UG/OH cables centred on the BCC attachment point. This work must be carried out by Evoenergy
personnel with all costs at the communications carrier’s expense. For these poles, a clearance of 150 mm from
parts with single insulation or covering must be maintained.
4.4.5 Structures with third party assets installed
Where a structure currently is encumbered by the attachment of items not owned by Evoenergy, the owner of
the proposed installation must consult with the owner of the installed asset.
The owner of the installed hardware must agree and be satisfied that their implemented processes and
procedures manage the risks associated with the proposed installation.
Written permission from the third-party asset owner for each site which they are affected must be provided to
Evoenergy.
2022 • PO07218 • V2 10
4.5 Structural Certification
Structural certification must be provided to confirm adequacy of all components and fixings configured as per
the proposed designs. Where components are used in multiple arrangements, the certification of the most
burdensome configuration should be assessed.
Understanding the maximum allowable resultant forces applied on proposed structures as below, will allow a
limit of applicability to be established for the proposed designs. The structure details below are the weakest
structures installed on the Evoenergy network- this is a conservative approach; however most proposed
configurations are expected to be physically small and will likely comply. Meaning when site specific
applications are lodged the main considerations to confirm structural adequacy will be conductor loadings
(including third party cables) applied to the structure to determine the resultant forces onsite. Confirmation of
an adequate foundation must also be confirmed. Where the proposed design does not comply with the basic
limits of applicability further investigation can occur to assess the adequacy of the structure on site- for example
considering the actual strength of the installed pole.
TABLE 6. TYPICAL POLE ATTRIBUTES
STRUCTURE STRENGTH MATERIAL DIMENSION ASSUMED ASSUMED
LENGTH RATING GROUND TO AUSTRALIAN FOOTING DEPTH-
(UNBURIED) TOP OF STANDARDS COMPACTED
PROPOSED ROAD BASE
INSTALLATION
9.5m 4kN Timber 7000mm AS7000 1600mm
AS1720.1-1997*
9.5m 4kN Composite AS7000
Fibre
9.5m 4kN Concrete AS7000
AS 4065
12.5m 5kN Timber 8500mm AS7000 2000mm
AS1720.1-1997*
12.5m 5kN Composite AS7000
Fibre
12.5m 5kN Concrete AS7000
AS 4065
*AS1720.1 is referenced as the most recent edition does not completely align with AS7000 (as per AS7000
appendix F).
Where specific information is required for currently installed apparatus on the network, a request in writing for
such information should be made directly to Evoenergy.
Site specific requests for information should be made through the Consumer Engagement team. Please call
132 386 and ask to speak with a Consumer Engagement team member.
Strength reduction factors as outlined in AS7000 table 6.2 must be observed. This requirement must be noted
in the safety in design report.
4.6 Aesthetics
Evoenergy is aware that its overhead electricity network will be implicated in any adverse community reaction
due to the addition of communication infrastructure and accordingly, the telecommunications owner and
Evoenergy staff involved in this exercise are to ensure the completed network is as aesthetically pleasing as
possible.
The communication cable owner must obtain the required approvals from the relevant authority and inform the
residents before proceeding with the installation of any communications equipment. Evoenergy must be
provided this information prior to any works commencing.
2022 • PO07218 • V2 11
4.7 Design Constraints – Cables and RF Equipment
4.7.1 Allowable Devices
Devices in compliance with the PO07173 Evoenergy Service and Installation Rules are permitted. The
installation must be deemed suitable for an unmetered supply (known as type 7 devices). Conditions and
approvals as outlined in the Evoenergy Service and Installation Rules apply to un-metered supplies. Electricity
meters must not be installed on Evoenergy structures
4.7.2 Proposals with more than one antenna
Designs that require more than one antenna and are located with 2000mm of any Evoenergy owned circuit
must be installed on standoff brackets. The circumference of the pole must be a maximum 25% covered with
directly attached devices or brackets in this area.
The 25% coverage is not a requirement where devices are positioned more than 2000mm from Evoenergy
network hardware. It is preferred where 2000mm clearance can be maintained to Evoenergy assets that the
transmitters are installed directly to the structure with no brackets.
4.7.3 Radio frequency public hazard mitigation
All proposed installations must not impose an RF hazard to the public. Installations must meet or exceed the
requirements outlined in the ATMA document RF Safety Compliance Program-Process and Site Safety
Documents (RFSCP Manual Two).
The carrier must identify that all proposed installations will satisfy these requirements on both construction
drawings and the safety in design report.
4.7.4 Antenna/ Transmitter minimum dimension to ground
The standard design must identify the minimum dimension from the bottom of the installed antenna to ground
at an ideal site. Antennas must be installed with the centre of propagation path being horizontally level
At 5 m above ground line in a public area (non-sensitive) the exposure level at any point must not be greater
than those allowable to the general public under the ARPANSA Radiation Protection Series Publication No3.
(5m requirement is recommended in the AMTA RF safety compliance program site safety documents)
Propagation paths above private property with exposure levels above those allowable for the general public
(ARPANSA) must be at least 10m above ground line (RFSCP V2).
Where there is likelihood of a person standing above ground line within the plume of the device, the minimum
dimension must be from that point. For example, the top of a colour bond fence, bench or a roof structure
within the plume area should be considered as the ground line.
4.7.5 Antennas in proximity to trees and vegetation
The proposed microcell installation should not extend non occupational limits (according to APARNSA) into
trees or vegetation. Where this is unavoidable the tree owner must consent to the condition. A letter supporting
the consent must be provided to Evoenergy with the proposed installation application.
2022 • PO07218 • V2 12
4.7.8 Aerial Splices
All splices must be located in an underground pit. No splices must be installed on the overhead network, due
to the additional load placed on poles/structures, visual impact of splicing equipment and impediment to access
for maintenance and operation of the Evoenergy distribution network.
2022 • PO07218 • V2 13
4.8.3 Electrical single line diagram
An electrical single line diagram of the proposed components must be provided. The single line diagram
must include the entire installation from the Evoenergy network boundary (service connection point).
The position of the isolation switch on the single line diagram must isolate all sources of supply including any
battery power sources.
Industry standard symbols must be used for all diagrams. A legend must be provided identifying the
symbology utilised.
4.8.4 Drawing Governance
All provided drawings must incorporate basic drawing governance principles. The drawings must identify;
A unique drawing number,
Sheet number
A revision number and revision table- the amendment table must identify any changes between
revisions
Drawing title
Approvals register- drawn and date approved as minimum entries
4.8.5 Plume diagrams
Each proposed transmitting device in the configurations depicted must be provided to Evoenergy. The plume
diagrams must identify;
A dimensioned vertical and horizontal profile
Overlayed coloured plumes must identify the areas that are deemed to be above general public and
occupational exposure levels (ARPANSA- RPS3).
Each plume diagram must be dimensioned in mm – identifying the width of the plume at the widest
point and the distance from the transmitter to the end of the plume
The plume diagram must show the position of the isolation switch in relation to the propagation path.
A separate plume diagram must be provided showing the minimum ground clearance at the time the tilt switch
activates, isolating the device.
5. INSTALLATION REQUIREMENTS
2022 • PO07218 • V2 14
deemed acceptable. The ladder must be able to be rested 1000mm below the Evoenergy network components
see drawings 390-024, 390-023, 390-022 for component placement requirements.
5.1.2 Mobile elevated work platform access requirements.
The mobile elevated work platform access window for circuits above 1kV is increased to allow Evoenergy Live
High Voltage Work practices to be observed. Live work practices require workers to insulate secondary points
of contact. It is not appropriate for Live Workers to insulate third party devices, as such the devices must be
located no closer than 1800mm to any circuit operating above 1kV.
5.1.3 Portable platforms
Where cables are vertically installed on a structure, they must allow a portable platform to be utilised.
To allow the platform chain to be positioned on the pole the cables should be installed 35mm off the pole
between 800mm to 1200mm below the LV crossarm. This will form a bridge for the chain to pass under the
conduits.
2022 • PO07218 • V2 15
5.2.3 Clearances to other third-party assets
Where third party assets are installed on the structure the asset owner of the proposed device must determine
in consultation with the third-party hardware owner the required clearances. The clearances must be in
compliance with relevant Australian Standards including AS7000. The existing third-party hardware owner
must be satisfied their implemented policies and procedures control the hazards of the proposed installation.
All street light conductors must be at minimum regarded as bare or covered conductors as outlined in this
document- regardless of the requirements identified by the asset owner.
5.2.4 Midspan Clearances
Midspan clearances between communication cables and the electrical infrastructure are to be determined
under worst case operating conditions.
Clearances where a telecommunication cable is installed below electrical conductors are to be determined
with the electrical network at maximum operating temperature and the communication cable at 5°C.
For ADSS cables installed above low voltage networks, where approval is given, a 0.1 m mid-span clearance
must be maintained with both circuits at 5°C.
Crossing of communication cables between electrical network conductors is not permitted.
5.2.5 Mains Ground Clearance
Mains ground clearances must be as per AS/NZS 7000. If any locations are identified where clearances are
not as per the latest standards, the designer must determine if any remediation work to the existing overhead
conductors will provide suitable ground and mid-span separation clearances to allow installation of
communication assets. Works to be considered covers all available options including conductor re-tensioning,
service main alterations and the replacement of the Evoenergy pole. The proposed remediation work is to be
submitted to Evoenergy at the design stage for approval.
5.2.6 Service Cables
The minimum separation between service cables and conductive aerial communications conductors is as per
Evoenergy drawing 390-018. Communication providers are not allowed to connect any cables to LV cross-
arms.
Generally, Evoenergy aerial service cables are attached to the pole below LV mains. These cables are usually
insulated; however, the minimum clearance between overhead service mains and aerial communication
conductors is 600 mm.
The following situations, however, will require attention by those installing the communications cables if it is
anticipated that BCC staff will be required to work within 500 mm of such wiring:
If there is exposed live metal, such as uninsulated connectors between mains and aerial service cables, those
installing the communications cable must cover the exposed metal with an Evoenergy approved insulating
tape and a weatherproofing tape.
If the insulation on the service cables has deteriorated to the point that conductors are exposed, the overhead
service to the customer will need to be replaced with a multi- core aerial bundled conductor. This type of
insulation failure must be reported to Evoenergy immediately for remedial work.
If the number of services taken from a pole is large, and/or the connections between service conductors and
the mains are untidy, the aerial service cables may impact upon the desired BCC location. The standard
Evoenergy notification and outage processes to be followed to allow Evoenergy to carry out any remedial work.
2022 • PO07218 • V2 16
TABLE 9. MINIMUM INSULATION LEVELS
REQUIREMENT
ATTRIBUTE
Insulation Rating 3kV A.C (AS3100 & AS3560.1) Working voltage
3kV insulation requirement is rationalised by accepting the insulation from the structure to the low voltage
circuit on a LV ABC construction is approximately 3kV. The insulation level is made from the cables 1kV rating
and the insulation properties of the applied clamp (AS3100).
The safety in design report must identify the adequacy of the proposed hazard mitigation measures. The
proposed mitigations will be specific to the design and may include standoff insulators, insulating plates, double
insulated conductors and the use of conduits. Sound engineering rationale or testing must substantiate any
claims of insulation performance.
In the case of the installation being electrically connected to a low voltage circuit not on the same structure
additional mitigation maybe required to limit risk to the connected low voltage circuit. This may include surge
protection installed at the Third Party owned micro pillar.
5.3.2 Basic Insulation impulse Level (BIL)
Evoenergy has installed non-conductive and conductive poles (steel reinforced concrete) in the electricity
distribution systems. Hazardous voltages can be present on all types of poles during abnormal system
conditions including, but not limited to; equipment failure, earth faults, weather conditions, etc.
When communication equipment is installed on:
Conductive poles, equipment must be insulated to a minimum of
2022 • PO07218 • V2 17
Termination insulators must be of approved 32kV polymeric long-rod construction.
Insulator pins must be approved by Evoenergy and be a nominal 22kV rated.
Mechanical protection (conduit, U guard or similar) is required to protect telecommunications cables that run
up the pole where a ladder or pole platform may be placed for work on the pole, its equipment or mains.
This is required from 500 mm below the highest electricity mains on the pole to at least 2500 mm below the
lowest electricity mains on the pole.
2022 • PO07218 • V2 18
5.6.1 Labelling requirements – Cables
The BCC owner must at each pole, clearly identify the cable by an Evoenergy approved sign. Where a sign
is installed for this purpose, it must comply with the following requirements:
Up to a six (6) letter word or acronym identifying the owner of the cable only
A clear code to indicate the nature of the cable, NC for a non-conductive cable, and C for a
conductive cable
Mounting of signs will be according to the methods set out in Table 10. Attachment using cable ties
is not acceptable. Attachment to poles to be approximately 100mm below the cable
The sign material must be aluminium sheet with an edge sealer
Reflective Class 2 individual numbers and letters, 30 mm high, are required.
The sign must not impact any works to be carried out on Evoenergy assets by Evoenergy staff.
5.6.2 Labelling requirements – RF equipment
Suitable signage must be provided to alert workers to the presence of an RF hazard. The signage must be
placed in a position that optimises the chance of the sign being seen by an attending worker. The sign must
be positioned where exposure levels are deemed safe for the general public.
A sample acceptable sign is presented in appendix A.
The sign must be suitably fixed to the structure below the isolation switch assembly. The sign must be UV
resistant. The sign must be replaced if missing or becomes difficult to read. The sign must be large enough
and positioned to allow a person to read whilst standing on the ground.
The sign must meet the following requirements
Have wording in bold and large font ‘Transmitting Antenna RF Hazard Above This Point’
Have wording ‘Isolation switch system installed. Do not proceed above this point until the antenna is
isolated and verified non-active’.
If RFNSA registered- have wording ‘Consult RFNSA Website- www.rfnsa.com.au’
2022 • PO07218 • V2 19
POLE MATERIAL TELECOMMUNICATIONS CABLING TELECOMMUNICATIONS
TYPE HARDWARE
Timber Support Bracket attached with bolts. Attached by 12mm x 75mm long
These fixtures must be UV stabilised and not be galvanised coach bolts.
affected by temperature cycle brittleness
Fibre-Reinforced Support Bracket attached with stainless steel Attached by stainless steel straps.
Composite (FRC) straps.
These fixtures must be UV stabilised and not be
affected by temperature cycle brittleness
Steel Support Bracket attached with stainless steel Attached by stainless steel straps.
straps. (kingbolt hole not available) (where a kingbolt hole is not
These fixtures must be UV stabilised and not be available)
affected by temperature cycle brittleness
Concrete Support Bracket attached with stainless steel Attached by stainless steel straps.
straps. (kingbolt hole not available) (where a kingbolt hole is not
These fixtures must be UV stabilised and not be available)
affected by temperature cycle brittleness
Other Information Catenary must be isolated from HV Conductive All metallic equipment must be
Poles with an insulator capable of withstanding either hot dipped galvanised or
the Pole's EPR under all weather and pollution treated by other Evoenergy
conditions – with the following specs: approved methods to prevent
Wet power frequency withstand voltage of corrosion.
28kV for 1 minute; The attachment brackets, clamps,
Dry power frequency withstand voltage of ancillary hardware and equipment
28kV for 1 minute; must not interfere with existing
Lightning impulse withstand voltage of installation and the Operations.
95kV; The attachment brackets, clamps,
Flashover distance > 120mm; ancillary hardware and equipment
Creepage distance > 230mm; must also be able to be detached
Cantilever strength of 6 kN. from the Pole with the use of
The catenary must be attached to timber Poles standard hand tools.
via an insulator where that Pole carries a HV
earth conductor down the Pole, i.e. cable
screen, switch earth, surge arrester earth etc.
2022 • PO07218 • V2 20
Conduit saddles 50mm 12G Tec Screws Saddles must be correctly sized to the conduit being
installed
Ground line cable guard 50mm 12G Tec Screws Size of fixing screw must be compatible with item
or being secured.
Minimum 50mm M10 Drawings to specify dimension between fixings
coach screws
Items over 5kg, large or Minimum M12 Items being installed with through bolts must be a
hazardous items Galvanised with two flat minimum M12. Where through bolts are used
requiring fixing with washers and a spring rationale to the adequacy of the fixing must be
through bolts volute washer included in the Safety in Design report.
All loose sapwood on natural hardwood poles at the position where devices or hardware are to be installed
must be removed.
Sapwood must not be removed on CCA treated poles.
5.8.2 Other Poles (Concrete, steel, composite)
Proposed designs on concrete, steel or composite poles may incorporate the following:
Fixing methods must be adequate to support the device being installed. Design specific fixings are required to
be identified and certified for each method of installation.
The sole use of 16mm stainless steel strapping for items that are deemed large, over 5kg or pose RF hazards
is not suitable. Multiple 32mm S/S strapping or robust fabricated pole bands are required.
Concrete, steel and composite fibre poles must not be drilled.
TABLE 12. EQUIPMENT ATTACHMENT METHODS - OTHER POLES
Item to be installed Fixing method Further information
Conduits up to 50mm 16mm S/S strapping Safety in design report to validate the fixing of cables
requiring a conduit larger than 50mm
All cables must have mechanical protection where
strapping is in contact with the cable.
Fixings must not be spaced no further than 300mm
apart
2022 • PO07218 • V2 21
Ground line cable guard 16mm S/S strapping Spacing of fixings to be specified on drawings
Light and physically Minimum 2X 16mm S/S
small items (i.e. isolation strapping
switch)
Items over 5kg, large or Minimum 32mm S/S The safety in design report must provide rationale to
hazardous items strapping – installed with the adequacy of the fixing method.
a buckle that minimises
the risk of tearing the Hazardous items include any device that produces
buckle or strap exposure levels greater than those deemed safe for
the general population as defined in ARPANSA
Two straps to be Radiation Protection Series Publication No.3
installed per installation
2022 • PO07218 • V2 22
5.9 Power Supply and Isolation switch – RF Equipment
5.9.1 Power Supply
Where it is necessary to provide line power supplies to drive amplifiers and it need to be powered by the low
voltage electricity system, this will be subject to an Evoenergy supply agreement.
Any devices that are required for the cable TV network will need to be powered by the low voltage electricity
system and will be subject to a special supply agreement with Evoenergy.
It is critical that the location of these devices is recorded in the Evoenergy network data system. The
communication hardware and associated power supply equipment must be located:
Outside the vertical exclusion zone distance for the type of antenna installed
A minimum of 3.0m from the bottom of the equipment and ground. If this cannot be achieved, the
hardware may be installed lower, however, a clearance of 3.0m above the equipment is required.
5.9.2 Isolation switch Assembly
Evoenergy prefers device owners to provide an isolation switch with a similar interface to those already
accepted for installation. Figure 1 depicts an acceptable switch assembly.
The ‘isolation switch assembly’ refers to the complete assembly, the ‘isolation switch’ refers to the switch
component only.
2022 • PO07218 • V2 23
The isolation switch must be installed in such a position not to place the operator in a hazardous environment
whilst accessing the switch. The operator or worker must not be exposed to a hazard outside of the acceptable
exposure levels for the general public.
The switch must not place the operator at a heightened risk of being struck by a vehicle. Where applicable the
switch should be positioned;
On the footpath side of the structure (optimum)
To position the structure between the operator and the oncoming traffic in the nearest live lane
(acceptable)
Clear of the live lane with operator’s back to the traffic (only under special circumstances)
See Evoenergy drawing 390-025 for further details.
The operator and the base of the ladder must never be positioned on a roadway to operate the isolation switch.
2022 • PO07218 • V2 24
6. OPERATIONAL AND MAINTENANCE REQUIREMENTS
6.1 Training
All persons working on Evoenergy poles near live mains must be Evoenergy authorised persons with
appropriate company accreditation for working on pole tops and with optic fibre cables.
The communications provider must ensure that all personnel working on Evoenergy poles for the attachment of
communications infrastructure would receive suitable training and familiarisation including but not limited to:
Evoenergy Electrical Safety Rules Working with fibre optic cables, NENS 04-
2006 safe working distances
Evoenergy Access Permit Requirements
Knowledge of the hazards associated with
Evoenergy Network Outage Notification stringing communication cables beneath
Lead Times energised electricity conductors
Identification of voltages and mains types Awareness and knowledge of this Standard
Knowledge of the hazards associated with
Any other required training
pole top work
Identification of suspect and condemned
poles
Required training can be obtained from industry training centre, including Evoenergy upon request and at an
appropriate charge.
2022 • PO07218 • V2 25
Where no alternative structure exists, a carrier may propose a different overhead construction of an Evoenergy
structure to be able to install their communications equipment. Any changes will be for the account of the cell
owner
6.3.2 Evoenergy Initiated Network Changes
Evoenergy reserves the right to change its structure at any time. In the situation where a cell owner’s
transmitters are attached to a structure, which needs to be modified, the cell owner must be notified and has
the responsibility to disassemble and remove the transmitter(s). The undergrounding of all electrical circuits
would normally require the removal of all associated poles; however, where the carrier requests, the pole
ownership may be transferred to that carrier.
6.3.3 Multiple Antenna
When installing additional antennas on a structure, it is the responsibility of the carrier to Negotiate with owners
of existing cells.
6.3.4 Pole Replacements
The agreements between various communication asset owners and Evoenergy define the process to be
followed by both Evoenergy and the communication asset owners’ staff. In general, Evoenergy staff are not
permitted to interfere with the communication asset owners’ equipment and cabling. The communication asset
owner will make arrangements for the relocation of their assets where reasonable notice of the proposed works
is given.
Evoenergy will notify the relevant telecommunications provider who must affix it as per the requirements of
this standard. Replacement poles will generally be installed in the same position as the previous poles.
The asset owner must meet any requirement for the replacement of a pole for either clearance requirements
or mechanical loadings due to the attachment of communication infrastructure, the cost of the pole replacement
and associated works. In addition, any requirement to straighten leaning poles prior to the attachment of
communication infrastructure must be the responsibility of the communication cable owner.
The conditions as stated in the agreements between various communication asset owners and Evoenergy set
out the process to be followed by both Evoenergy staff and the various communication asset owners’ staff.
6.3.5 Change of Pole ownership
If Evoenergy choose to remove an overhead section of overhead mains line and replace it with an underground
section the telecommunication has two options:
Asset owner can take ownership of the pole
Augment the telecommunications line underground
Any cost associated with the changes will be for the account of the communications owner.
Any upgrading of the network proposed by the asset owner must allow for any future proposal that Evoenergy
may have for that structure. Evoenergy’s right to install a structure on public land is dependent upon its use
for electricity distribution. Undergrounding of all electrical circuits may require removal of the pole or transfer
of its ownership to the carrier.
6.3.6 Pole Movement with Existing Communication Cables
The variable nature of ground conditions and pole footings may prevent their accurate assessment at the time
of assessing a pole’s suitability for carrying communication cables. All costs are to be borne by the
communication cable owner in the case where any corrective action is required to any infrastructure following
the installation of communications cables.
2022 • PO07218 • V2 26
safety in design report must be amended to demonstrate the adequacy of the design to relax the requirements.
Reports to demonstrate compliance to the inspection requirements must be provided to Evoenergy.
VERSION CONTROL
DOCUMENT CONTROL
2022 • PO07218 • V2 27
APPENDIX A – SIGNAGE
APPENDIX B – DRAWING 390-018
29
2022 • PO07218 • V2 29