True/False Questions
1. Process costing is used in those situations where many different products or servicesare
produced each period to customer specifications.
Answer: False
Answer: False
Answer: True
4. In a job-order cost system, indirect labor is assigned to a job by using the labor time
ticket as a source document.
Answer: False
Answer: False
6. The fact that one department may be labor intensive while another department is
machine intensive may explain in part the existence of multiple predetermined
overhead rates in larger companies.
Answer: True
7. If a company closes any under- or overapplied overhead to the Cost of Goods Sold
account, then Cost of Goods Sold will be credited if manufacturing overhead is
overapplied for the period.
Answer: True
8. The following entry would be used to record the transfer of material from the
storeroom to production if 80% of the material was direct material and 20% was
indirect material:
Work in Process................................ 40,000
Manufacturing Overhead .................. 10,000
Raw Material........................ 50,000
Answer: True
9. If a job is not completed at the end of the year, then no manufacturing overhead cost
should be applied to that job.
Answer: False
10. When raw materials are purchased, they are recorded as an expense.
Answer: False
Answer: False
12. The entire difference between the actual manufacturing overhead cost for a period andthe
applied manufacturing overhead cost is typically closed to the Work In Process account.
Answer: False
13. If the actual manufacturing overhead costs for a period exceed the manufacturing
overhead costs applied, then overhead would be considered to be overapplied.
Answer: False
14. When the predetermined overhead rate is based on the level of activity at capacity, the
overhead underapplied may be called the Cost of Unused Capacity and treated as a period
expense.
Answer: True
15. The absorption cost approach is so named because it provides for the absorption of all
manufacturing costs, fixed and variable, into units of product.
Answer: True
16. Which of the following industries would be most likely to use a process costing
system?
A) Ship builder
B) Movie studio
C) Oil refinery
D) Hospital
18. Emco Company uses direct labor cost as a basis for computing its predetermined
overhead rate. In computing the predetermined overhead rate for last year, the
company misclassified a portion of direct labor cost as indirect labor. The effect of this
misclassification will be to:
A) understate the predetermined overhead rate.
B) overstate the predetermined overhead rate.
C) have no effect on the predetermined overhead rate.
D) cannot be determined from the information given.
20. The operations of Kalispell Company resulted in overapplied overhead for the month
just completed. Which of the following journal entries can be correct if Kalispell
allocates under- or overapplied overhead among accounts?
25. On the Schedule of Cost of Goods Manufactured, the final Cost of Goods
Manufactured figure represents:
A) the amount of cost charged to Work in Process during the period.
B) the amount of cost transferred from Finished Goods to Cost of Goods Sold during
the period.
C) the amount of cost placed into production during the period.
D) the amount of cost of goods completed during the current year whether they were
started before or during the current year.
26. Under a job-order costing system, the peso amount transferred from Work in Process
to Finished Goods is the sum of the costs charged to all jobs:
A) started in process during the period.
B) in process during the period.
C) completed and sold during the period.
D) completed during the period.
29. A job order cost system uses a predetermined overhead rate based on estimated
activity and estimated manufacturing overhead cost. At the end of the year,
underapplied overhead might be explained by which of the following situations?
32. Blackwood Co. uses a predetermined overhead rate based on direct labor cost to apply
manufacturing overhead to jobs. The predetermined overhead rates for the year are
200% for Department A and 50% for Department B. Job 123, started and completed
during the year, was charged with the following costs:
Dept. A Dept. B
Direct materials ............................. P25,000 P5,000
Direct labor.................................... ? P30,000
Manufacturing overhead................ P40,000 ?
The total manufacturing costs associated with Job 123 should be:
A) P135,000
B) P180,000
C) P195,000
D) P240,000
Source: CPA, adapted
During the month, Fisher Company's Work in Process inventory account was credited
for P120,500, which represented the Cost of Goods Manufactured for the month. Only
one job remained in process on May 31; this job had been charged with P9,600 of
applied overhead cost. The amount of direct materials cost in the unfinished job would
be:
A) P10,600
B) P16,700
C) P12,800
D) P23,400
34. At the beginning of the year, manufacturing overhead for the year was estimated to be
P477,590. At the end of the year, actual direct labor-hours for the year were 29,000
hours, the actual manufacturing overhead for the year was P472,590, and
manufacturing overhead for the year was overapplied by P110. If the predetermined
overhead rate is based on direct labor-hours, then the estimated direct labor-hours at
the beginning of the year used in the predetermined overhead rate must have been:
A) 29,300 direct labor-hours
B) 28,987 direct labor-hours
C) 28,993 direct labor-hours
D) 29,000 direct labor-hours
Answer: A Level: Hard LO: 3,5,8
35. At the beginning of the year, manufacturing overhead for the year was estimated to be
P670,700. At the end of the year, actual direct labor-hours for the year were 36,200
hours, the actual manufacturing overhead for the year was P665,700, and
manufacturing overhead for the year was overapplied by P22,100. If the predetermined
overhead rate is based on direct labor-hours, then the estimated direct labor-hours at
the beginning of the year used in the predetermined overhead rate must have been:
A) 35,037 direct labor-hours
B) 35,300 direct labor-hours
C) 36,200 direct labor-hours
D) 33,874 direct labor-hours
Answer: B Level: Hard LO: 3,5,8
36. At the beginning of the year, manufacturing overhead for the year was estimated to be
P670,530. At the end of the year, actual direct labor-hours for the year were 29,400
hours, the actual manufacturing overhead for the year was P665,530, and
manufacturing overhead for the year was underapplied by P27,550. If the
predetermined overhead rate is based on direct labor-hours, then the estimated direct
labor-hours at the beginning of the year used in the predetermined overhead rate must
have been:
A) 30,900 direct labor-hours
B) 29,400 direct labor-hours
C) 30,670 direct labor-hours
D) 31,939 direct labor-hours
Answer: A Level: Hard LO: 3,5,8
37. Bradbeer Corporation uses direct labor-hours in its predetermined overhead rate. At
the beginning of the year, the estimated direct labor-hours were 17,500 hours. At the
end of the year, actual direct labor-hours for the year were 16,000 hours, the actual
manufacturing overhead for the year was P233,000, and manufacturing overhead for
the year was underapplied by P15,400. The estimated manufacturing overhead at
thebeginning of the year used in the predetermined overhead rate must have been:
A) P249,375
B) P217,600
C) P228,000
D) P238,000
39. Braaten Corporation uses direct labor-hours in its predetermined overhead rate. At the
beginning of the year, the estimated direct labor-hours were 14,100 hours. At the end
of the year, actual direct labor-hours for the year were 13,500 hours, the actual
manufacturing overhead for the year was P291,100, and manufacturing overhead for
the year was underapplied by P7,600. The estimated manufacturing overhead at the
beginning of the year used in the predetermined overhead rate must have been:
A) P286,100
B) P296,100
C) P298,816
D) P283,500
40. Cribb Corporation uses direct labor-hours in its predetermined overhead rate. At the
beginning of the year, the estimated direct labor-hours were 17,900 hours and the total
estimated manufacturing overhead was P341,890. At the end of the year, actual direct
labor-hours for the year were 16,700 hours and the actual manufacturing overhead for
the year was P336,890. Overhead at the end of the year was:
A) P22,920 underapplied
B) P17,920 overapplied
C) P17,920 underapplied
D) P22,920 overapplied
42. Crick Corporation uses direct labor-hours in its predetermined overhead rate. At the
beginning of the year, the estimated direct labor-hours were 14,400 hours and the total
estimated manufacturing overhead was P355,680. At the end of the year, actual direct
labor-hours for the year were 15,200 hours and the actual manufacturing overhead for
the year was P350,680. Overhead at the end of the year was:
A) P24,760 underapplied
B) P24,760 overapplied
C) P19,760 underapplied
D) P19,760 overapplied
43. Dagger Corporation uses direct labor-hours in its predetermined overhead rate. At the
beginning of the year, the total estimated manufacturing overhead was P423,870. At
the end of the year, actual direct labor-hours for the year were 19,400 hours,
manufacturing overhead for the year was underapplied by P5,650, and the actual
manufacturing overhead was P418,870. The predetermined overhead rate for the year
must have been closest to:
A) P21.59
B) P20.76
C) P21.30
D) P21.85
45. Dafoe Corporation uses direct labor-hours in its predetermined overhead rate. At the
beginning of the year, the total estimated manufacturing overhead was P221,100. At
the end of the year, actual direct labor-hours for the year were 14,400 hours,
manufacturing overhead for the year was overapplied by P21,500, and the actual
manufacturing overhead was P216,100. The predetermined overhead rate for the
yearmust have been closest to:
A) P15.01
B) P17.73
C) P15.35
D) P16.50
46. Juanita Corporation uses a job-order cost system and applies overhead on the basis of
direct labor cost. At the end of October, Juanita had one job still in process. The job
cost sheet for this job contained the following information:
An additional P100 of labor was needed in November to complete this job. For this
job, how much should Juanita have transferred to finished goods inventory in
November when it was completed?
A) P1,330
B) P500
C) P1,230
D) P1,730
It is estimated that 10,000 direct labor hours will be worked during the year. The
predetermined overhead rate will be:
A) P3.90
B) P5.90
C) P6.80
D) P9.10
The company closes out the balance in the Manufacturing Overhead to Cost of Goods
Sold at the end of the year. In the journal entry to close out the balance, the company
would:
A) debit cost of goods sold for P2,000
B) credit cost of goods sold for P2,000
C) credit cost of goods sold for P7,000
D) debit cost of goods sold for
P7,000Answer: C Level: Hard LO:
4,5,8
49. Rio Manufacturing Company uses a job order cost system. At the beginning of
February, Rio only had one job in process, Job #594. The direct costs assigned to this
job at that time were P800 of materials and P650 of labor. Job #594 was finished
during February incurring additional direct costs of P120 for materials and P370 for
labor. Job #595 was started and finished during February. The direct costs assigned to
this job were P310 for materials and P190 for labor. Job #596 was started during
February but was not finished by the end of the month. The direct costs assigned to
this job were P740 for materials and P300 for labor. Rio applies manufacturing
overhead to its products at a rate of 200% of direct labor cost. What is Rio's cost of
goods manufactured for February?
A) P2,440
B) P3,750
C) P4,860
D) P6,500
50. Serenje Manufacturing Company produces nameplates and uses a job-order cost
system. The following amounts relate to nameplate production for the month of June:
52. Sargent Company applies overhead cost to jobs on the basis of 80 percent of direct
labor cost. If Job 210 shows P10,000 of manufacturing overhead cost applied, how
much was the direct labor cost on the job?
A) P12,500
B) P11,000
C) P8,000
D) P10,000
53. In the Vasquez Company, any over- or underapplied overhead is closed out to Cost of
Goods Sold. Last year, the company incurred P27,000 in actual manufacturing
overhead cost, and applied P29,000 of overhead cost to jobs. The beginning and
ending balances of Finished Goods were equal, and the Company's Cost of Goods
Manufactured for the year totaled P71,000. Given this information, Cost of Goods
Sold, after adjustment for any over- or underapplied overhead, for the year must have
been:
A) P98,000
B) P73,000
C) P71,000
D) P69,000
Including the items listed above, the debits to the Manufacturing Overhead account
totaled P245,000 for the year. Credits to the account totaled P240,000 for the year.
Based on this information, if all entries had been made correctly during the year the
Manufacturing Overhead account would have been:
A) overapplied by P4,000
B) overapplied by P12,000
C) underapplied by P5,000
D) overapplied by P2,000
Answer: D Level: Hard LO: 7,8
55. Compute the October cost of direct materials used if raw material purchases for the
month were P30,000 and the inventories were as follows:
Beginning Ending
Direct materials ............................. P7,000 P4,000
Work in Process............................. P6,000 P7,500
Finished goods............................... P10,000 P12,000
If the company allocates the underapplied overhead among Cost of Goods Sold and
the appropriate inventory accounts based on the amount of overhead applied during
the year in the accounts, Cost of Goods Sold after allocation will be:
A) P790,000
B) P820,000
C) P810,000
D) P780,000
Beginning Ending
Direct materials inventory ......................... P9,000 P7,000
Work in process inventory ........................ P17,000 P31,000
Finished goods inventory .......................... P10,000 P15,000
58. The total costs added to Work in Process during the year were:
A) P206,000
B) P162,000
C) P176,000
D) P182,000
59. If Omar Company applies overhead to jobs on the basis of direct labor hours and Job 3
took 120 hours, how much overhead should be applied to that job?
A) P960
B) P360
C) P528
D) P288
Answer: B