Topic 8 - Earthworks
Topic 8 - Earthworks
A. AREA COMPUTATIONS
TYPES OF CROSS-SECTIONAL AREA OF ROAD EARTHWORKS:
Natural Ground Line
1. CUT AREA
Area to be excavated or cut
Road Pavement
DL DR
C
hL 1 1 hR
1 1
m B/2 B/2 n
B
(width of pavement)
Cross-section notes:
+𝐡𝐋 +𝐡𝐑
+𝐂
−𝐃𝐋 +𝐃𝐑
2. FILL AREA
Road Pavement
Area of backfill or fill
B
(width of pavement) Natural Ground Line
m B/2 B/2 n
1.5 C 1.5
hL 1 1 hR
`
`
DL DR
Cross-section notes:
−𝐡𝐋 −𝐡𝐑
−𝐂
−𝐃𝐋 +𝐃𝐑
B
Road Pavement (width of pavement)
Natural Ground Line
m B/2 B/2 n
CUT 1 hR
1
C
1.5 FILL
hL 1
DL DR
Cross-section notes:
−𝐡𝐋 +𝐡𝐑
−𝐂
−𝐃𝐋 +𝐃𝐑
where:
C = Center Height
hR = side height right
= y-coordinates at right
hL = side height left Note:
= y-coordinates at left Side Slopes:
DR = distance out right For Cut = 1H: 1V
= x-coordinates at right For Fill = 1.5H: 1V
DL = distance out left
= x-coordinates at right
B = base
= width of the pavement
B. VOLUME COMPUTATIONS
𝐀𝟏 + 𝐀𝟐
𝐕=[ ]𝐋
A2 𝟐
Where:
A1, A2 = Cross-sectional Areas of end sections
A1 L L = distance between the two areas.
Solution:
Station 11 + 020m:
18m 16m
A2 A3
6m
3.8m 4m
A1 A4
10m 10m
20m
AREA COMPUTATIONS:
From,
𝟏
𝐀= (𝐛 × 𝐡) Area by TRIANGLES
𝟐
1 1
A1 = (10)(3.8) = 19. 00 m2 A3 = (6)(16) = 48. 00 m2
2 2
1 1
A2 = (6)(18) = 54. 00 m2 A4 = (10)(4) = 20. 00 m2
2 2
ATOTAL = 141.00 m2
Station 11 + 040m:
22m 16m
6m A2
4m A3
A1 3m
A4
10m 10m
20m
1 1
A1 = (10)(6) = 30. 00 m2 A3 = (4)(16) = 32. 00 m2
2 2
1 1
A2 = (4)(22) = 44. 00 m2 A4 = (10)(3) = 15. 00 m2
2 2
ATOTAL = 121.00 m2
VOLUME by END-AREA METHOD
𝐀𝟏 + 𝐀𝟐
𝐕=[ ]𝐋
𝟐
141 + 121
V=[ ] 20
2
Solution:
Station 10 + 120m:
DL DR Thus,
−𝟓. 𝟎 +𝟒. 𝟎
+𝟑. 𝟎
+𝟏𝟕. 𝟓𝟎 +𝟏𝟓. 𝟓𝟎
5m A2
1 A3 1 4m
3m
2 A1 A4 2
m 7.5m 7.5m n
15m
SOLVING FOR DL AND DR: AREA COMPUTATIONS:
From slope formula, also, From,
𝐯𝐞𝐫𝐭𝐢𝐜𝐚𝐥 1 4m 𝟏
𝐬= = 𝐀= (𝐛 × 𝐡) Area by TRIANGLES
𝐡𝐨𝐫𝐢𝐳𝐨𝐧𝐭𝐚𝐥 2 n 𝟐
𝐧= 𝟖𝐦
1 1
A1 = (7.5)(5) = 18. 75 m2 A3 = (3)(15.50) = 23. 25 m2
2 2
So, thus,
1 1
1 5m DL = 7.5 + 10 = 𝟏𝟕. 𝟓𝟎 𝐦 A2 = (3)(17.50) = 26. 50 m2 A4 = (7.5)(4) = 15. 00 m2
= 2 2
2 m
DR = 7.5 + 8 = 𝟏𝟓. 𝟓𝟎 𝐦
𝐦 = 𝟏𝟎 𝐦 ATOTAL = 83.50 m2 (cut)
15m
Thus,
m 7.5m 7.5m n
−𝟒. 𝟎 −𝟗. 𝟎
−𝟓. 𝟎
A1 −𝟏𝟓. 𝟓𝟎 +𝟐𝟓. 𝟓𝟎
4m 2 A4
1 5m
A2 2
A3 1 9m
DL DR
Road Pavement
3m
CUT
FILL
5m
1.5 FILL 1m
5m 1 A1
DL DR
SOLVING FOR DL AND DR: AREA COMPUTATIONS:
From slope formula, also, From,
𝐯𝐞𝐫𝐭𝐢𝐜𝐚𝐥 1 4m 𝟏
𝐬= = 𝐀= (𝐛 × 𝐡) Area by TRIANGLES
𝐡𝐨𝐫𝐢𝐳𝐨𝐧𝐭𝐚𝐥 1 n 𝟐
𝐧= 𝟒𝐦
1 1
A1 = (4)(5) = 10.00 m2 (fill) A3 = (1.5)(9) = 23. 25 m2 (cut)
2 2
So, thus,
1 1
1 5m DL = 5 + 7.5 = 𝟏𝟐. 𝟓𝟎 𝐦 A2 = (1)(1.50) = 0. 75 m2 (cut) A4 = (5)(4) = 10. 00 m2 (cut)
= 2 2
1.5 m
DR = 5 + 4 = 𝟗. 𝟎𝟎 𝐦
𝐦 = 𝟕. 𝟓 𝐦 ACUT = 34.00 m2 AFILL = 10.00 m2
Station 5 + 380m:
10m
Thus,
m 5m 5m n
−𝟓. 𝟎 −𝟕. 𝟎
−𝟔. 𝟎
A1 −𝟏𝟐. 𝟓𝟎 +𝟏𝟓. 𝟓𝟎
5m 1.5 A4
1 6m
A2 1.5
A3 1 7m
DL DR
Road Pavement
4m
CUT
FILL
7m
PRACTICE PROBLEM:
4. From the given cross-section notes, compute the volume of earthworks between the two stations. Width of roadway is 20m.
Use End-Area Method. Complete the cross-section notes at each station.