Erection Method Statement - Birla White (Gotan)
Erection Method Statement - Birla White (Gotan)
Erection Method Statement - Birla White (Gotan)
For
Ultratech Cements
At
1.0 Scope
This Method statement describes the methodology to be followed for the following activities:
Requirements
To carry out the above activities in the stipulated manner as explained in this method statement, the
following are to be provided by the customer.
Well compacted and leveled ground to be made available to us for storage of PEB materials and for
painting area. Proper approach has to be given from the storage area to the building.
The area inside the building to be made good with PCC or well compacted before starting of
erection to enable the crane and scaffolding movement inside the building.
Sufficient compacted area, all round the building, to be made available for scaffolding to do the
cladding. Mobile scaffolds/ Suspended platform will be used for doing the cladding and hence the
area has to be level
One point for Power supply at the yard and 2-3 at site to be arranged.
2|Page
Work Method Statement PEBS / WMS/ 01
The required material, accessories, crane, tools, tackles and safety equipments will be checked once
again for availability and ready to be used prior to starting of lift.
All tools and equipment used for installation shall have test certificates and calibration certificates, as
required. The concerned PEBS Pennar project personnel / Project Manager or competent person will
check the certificates before using the equipments on site.
3|Page
Work Method Statement PEBS / WMS/ 01
2.3 Slings
All slings shall be inspected each day prior to their use. This includes chain, wire rope and
synthetic slings and their attachments, i.e. master links, alligators, clips, hooks, quick-alloys etc.
In lifting operations, protect slings from abuse. Protect slings by padding sharp corners, and never
jerk the load. Jerking may triple the load on the sling.
2.4 Scaffolds
Scaffolds installed separately must be fixed to static structure at a minimum space of 1.5m and
every upper scaffold frame must be fixed to the below scaffold by steel rod or scaffold tubing in a
safe method.
Scaffolds must always be placed on a firm ground position and foot bases always supported by
adequate wood planks.
All scaffolds shall be installed with ladders, and a platform at every floor level. At each ladder
anchor points, an appropriate wire ‘tie-off’ shall be used to tighten.
4|Page
Work Method Statement PEBS / WMS/ 01
Anchor bolts are to be set in accordance with PEBS Pennar’s issued ‘FOR COSTRUCTION ANCHOR
BOLT PLAN’. The Following procedure shall be adopted by the Civil Contractor for Setting of the
Anchor Bolt
Mark the grid lines as indicated in anchor bolt setting plan on the reference pillars and check whether
foundation is square with the help of Theodolite or Total Station. Ensure following points are kept in
mind during setting of anchor bolts at site:
1. Ensure rigidity of shuttering and reinforcement and make sure cover blocks are in place.
2. Place the anchor bolts in respective templates. Mark centerlines on template
3. Check the level and projection of threaded portion of anchor bolts; it can adjusted by adjusting nut
below and above the template.
4. All anchor bolts should be located in concerned templates, check distances and diagonal. Nail
template to outer formwork.
5. Verticality of anchor bolts can be maintained by tying it to reinforcement; if required it can be also
tack welded with reinforcement.
6. Before pouring concrete re-check the elevations of anchor bolts using the level instrument and
ensure that the nuts are tight.
7. During concreting ensure that concrete surface under template is rough and level.
8. Remove the template after setting of concrete and clean the protruded portion of anchor bolts and
apply the grease to threads and cover it with hessian cloth to protect it from dust.
9. The gap below the base plates should be grouted by civil contractor after completing the plumbing,
alignment and bolt tightening of building.
10. Anchor bolts shall be set perpendicular to the theoretical bearing surface; threads shall be
protected from falling of free concrete and nuts shall run freely on the threads.
11. The projection of anchor bolts from the theoretical bearing surface shall strictly follow the drawing.
5|Page
Work Method Statement PEBS / WMS/ 01
1. Upon receipt of material, the materials controller will match the packing lists and shall verify the
consignment.
2. Lifting Nylon belts with suitable SWL shall be used for unloading the material to minimize the
damage to the painted surface. Else proper packing will be provided if steel slings are used for
offloading to avoid painting damages.
3. The Material will be stored in a firm and dry area.
4. The material shall be stored above ground level with proper packing.
5. The materials shall be stacked in locations according to the building/areas, and should be at a
lifting position adjacent to the area to be erected. This is to facilitate the sorting and delivery during
the erection.
6. The materials shall be stored separately, above ground level on timber packing. They shall not be
stacked directly on top of each other but must be separated thick timber, and shall not be stacked
in contact with other steel components and must be separated by a minimum gap.
7. The sheeting material should be placed with a minimum 5 o slope to avoid a water pond.
The Painting of the structural steel will be carried out as per the paint manufacturers specification and
guidelines
6|Page
Work Method Statement PEBS / WMS/ 01
Planning the lifting operation is essential to ensure that the lift is carried out safely and efficiently. The
following points will always be considered:
Where the load is to be picked up from
Where the load is to be placed
What areas are to be passed over
Proximity of the other contractors workers
Any obstructions in the way
How the load is to be slung
How the slings are to be removed
How the crane driver will be directed
The weight of the load
The weather
A pre-lift meeting will be held before lifting any structure to ensure everybody at site
understands the lifting method or step for the erection of the entire building.
Prior to start of any lifting work, the location for positioning of the cranes and material
lay down at the erection area shall be identified.
The crane shall be positioned and out riggers set prior to lifting. Boom length, boom
angle, operating radius and safe lifting capacity shall be assessed as per crane load chart prior to
lifting being made.
Nylon belts or cloth slings or steel slings with suitable SWL shall be used for unloading/
lifting the materials. The load should be landed gently to ensure that it is not damaged, and that the
crane does not receive any shock loading.
The signaler must ensure that he is in a place of safety when receiving the load,
ensuring that he cannot be crushed between the load and a fixed object or pushed over an open
edge.
Webbing slings, or any sling made from synthetic fibers, will be examined before and
after every lift as they are vulnerable to being cut by sharp edges. If there is any sign of a cut or
fraying in the fabric, they should be taken out of use and examined by a competent person
Structural Stability
7|Page
Work Method Statement PEBS / WMS/ 01
The Erection of any element or assembly will start only if all necessary equipments and tackles on site,
to ensure that the stability is maintained at all times. Sufficient provision and appropriate use of
temporary guys will be made during all stages of erection to ensure the stability of all parts of the
structure as well as structure as a whole. Added care will be taken to ensure that all temporary guys are
appropriately attached and safely anchored.
The stability of effectiveness of all temporary guys and supports should be checked at the end of each
shift and re-assessed at the beginning of each shift before further erection work begins. Similarly, the
stability of erected steel work and temporary guys should be checked prior to work being stopped
because of adverse weather and again when work restarts.
Erection Sequence
Erection will start at a braced bay in order that a stable and self supporting portion of the structure can
first be erected, having the necessary internal or inbuilt restraint. Such a stable and self supporting
braced bay can then be used to stabilize and support subsequently erected steelwork. Until the braced
bay reaches the self supporting stage, some temporary support to the steelwork may be required.
Generally this will be in the form of guy wires.
Lifting of Columns
Columns & Columns along with the triangular segment will be erected by crane placed by
attaching nylon/ rope slings. Appropriate slings with suitable SWL will be chosen with due
consideration to shock load.
Rubber packing or wooden packing will be placed where slings are attached to column to avoid
cutting of slings by sharp edges of column.
Temporary guys will be attached to column at ground to avoid working at height.
Work men with necessary PPE will guide the column to position into anchor bolts and will
tighten all anchor bolts with necessary spanners.
Spanners will be tied with lanyard and will be attached to waist belt of workmen.
During tightening foreman will ensure that column erected in a plumb and level. To bring
column into level necessary shims will be placed below the base plate.
Crane load will released slightly to check stability of column before fully releasing.
8|Page
Work Method Statement PEBS / WMS/ 01
Work men in Metal scaffolding / ladder provided with fall back arrestor will remove slings.
9|Page
Work Method Statement PEBS / WMS/ 01
10 | P a g e
Work Method Statement PEBS / WMS/ 01
Foundation Inspection
The steelwork contractor shall inspect the prepared foundations and holding down bolts for position and
level not less than seven days before erection of steelwork starts. He shall then inform the employer if
he finds any discrepancies which are outside the deviations specified in this specification guide,
requesting that remedial work be carried out before erection commences.
true position
Vertical Wall
Deviation from exact position at steelwork support
point
∆ = ± 15 mm
∆ = + 45 mm
- 5 mm
∆ = ± 3 mm
11 | P a g e position in plan
and elevation
Work Method Statement PEBS / WMS/ 01
∆
Positions of column at base
Deviation of section centerline from the specified
position ∆
∆ = 10 mm
on main axes
∆ = ± H/600 or 5 mm
whichever is greater
Max = ± 25 mm ∆H
h=
Storey
Height
∆h
D
Deviation from the specified level
∆ = (D/1000) + 1mm
13 | P a g e
∆ = 10 mm
Work Method Statement PEBS / WMS/ 01
Deviation relative to next column on a line parallel to the grid line when measured at base or
splice level.
Specified Level
∆
Beam Level
∆ = ± 10 mm
∆ = 5 mm
14 | P a g e
Work Method Statement PEBS / WMS/ 01
∆ = ± 5 mm
Floor
Beam Alignment Level
h < 3m, ∆ = 5 mm
******
15 | P a g e