16-Nov-21 Project Updates
Structural Working in progress. To be given as committed on 20 th Nov,21. (Bilal sb)
Parking’s are being calculated and 150 nos are to be kept for retail. The Court Heights Architecture IFC of Sales office to be provided when 3d of ceilings are finalized. (Arch dept working on it). Beam issue of Sales office needs to be discussed with Rameez and AVP. Structure: Bilal sb First Floor Slab is being casted of Sales office. Electrical: Eleken Block masonry on ground floor has started of Sales office. Mechanical: SEM QS dept uploaded all Mechanical and Electrical quantities of Sales office. Drawings of Sales office uploaded in Software.
Meeting to be held regarding master planning of TCIP on 17 th Nov,21.
Latest drawings shared with Eleken and SEM for marking all their services for meeting, 16-Nov,21. Provide parking on plot for visitors. The Court Provide Parking Plaza for visitors. Provide Park near gate 2 with provision of parking’s. Industrial Park Working drawing of Sales office received on 11th Nov 21. Working drawings of sales office sent for structure to Bilal sb on 11 th Nov,21. Structure: Bilal sb New Layout shared with FND for quote on 16-Nov-21. Electrical: Eleken Bore Holes of Soil test completed. Mechanical: SEM Soil Test reports awaited. Fly ash (Backfilling) quotation from vendors awaited. Meeting with JT partners done on 15th Nov,21. JT Partner will come to Pakistan for face-to-face meeting. The Court Pile Tender floated on 4th November,21. Skyscraper Al Ghazi had meeting with noman sb on 15th Nov,21. Al Ghazi shared quotation on 16th Nov,21. Structure: Mushtaq sb Share details with Al Ghazi regarding whole building. Electrical: SMC Harisnco had meeting with Talha on 15th Nov,21 regarding piling and main building. Mechanical: SMC Covered area was shared with Harisnco for quotation of Main Building. Harisnco shared revised quotation with/without electricity. Comparative statement in progress. Followup CES for work and give references for work not in their scope. Afaaq(National Boring), Abid(National Boring), Atlas to share revised quotation. SMC shared updated drawings of Plumbing, Drainage, Fire on 16 th Nov,21. SMC will share updated drawings of HVAC and Electrical on 25 th Nov,21. Lux levels go ahead to be given by ASA for main building. Façade Lighting decision to be taken. ASA to give go ahead on piling as Column Layout plan shared with ASA on 13 th Nov,21. Vetting given to Beg Associates on 13th Nov,21. Beg Associates replied that not to reduce the number of piles and provide reaction marking on piles on 16 th Nov,21. M&B to share latest survey plan. QS checking Ali Interiors bill Drawings updated till today in software. 100 KVA generator needed due to load shedding. Eleken shared proposal as per K-Electric for decision of sub-station on 15 th Nov,21. The Court Regency Elevator required at site which will be dismantled and used at other sites too. Alfa contract Aluminum with Tahir. Structure: Alliance Kone (Farooq)to talk regarding fire lift. Electrical: Eleken TCR elevation to be finalized. (Mr. Iqbal sb and Mr. Wajahat) Mechanical: SEM Checking of Bill – 37th Running bill- TMC. Checking of BBS – Podium 2. Drawings updated till today in software.
The Court Twin
Towers Swimming Pool issue resolved at 1st Floor. Structure: Bilal sb Checking of 24th Running Bill – TMC. Electrical: Eleken Mechanical: SEM