F 8.4 PU 03 - PRF Supplier Audit Check Sheet - EMF
F 8.4 PU 03 - PRF Supplier Audit Check Sheet - EMF
F 8.4 PU 03 - PRF Supplier Audit Check Sheet - EMF
0
not filled in
18 0 1 2 fout
fout fout
How to fill it in?
Please fill in the Process Audit worksheet first.
The Summary score will be calculated automatically, but you have to fill in manually Conclusion and Comments.
Purchase 86.0%
Production 94.5%
Logistics 93.3%
F/8.4/PU/03 , 02 ,30.03.2021
General Information
Audit Date 1/20/2022
Location Ambattur
Scope Plating
Yahoo! Mail'
Email <[email protected]
Phone 9941652413
Assessment:
For further Information Please Refer to the Current Supplier Profile Form.
F/8.5/PU/03 , 02 , 30.03.2021
Supplier Audit Data
Supplier: Electro Platers & Metal Finishers Date Of Audit: 20/01/2022
Check
# Questions (tick)
Score Comments Proof
What are the results of the last audit conducted by the certified external
3 body? R 10
Last audit conducted by external agencies and 3 minor NC' s
are raised and all the nc's are closed
###
Audit report, observations, non conformities, time scale to solve
Are actual quality results and key performance indicators (KPI's) Quality Results and Production Performances Are Measured
5
measured and communicated to all personnel on a regular basis?
What are these communication methods (display boards, posters, white R 10
and Communicated to All Personnel Using Display Board .
MRM Conducted Once in Six Months Evidenced. Last MRM on
boards)? Oct'21 report evidenced
10
Is the available measuring equipment sufficient to measure the produced
products effectively. R 10
XRF Spectrometer Available, Used To Measured Products
Coating Thickness And Alloy Content .
Has an adequate calibration program been implemented? Calibration status of Measuring and monitoring equipment
11 Calibrations traceable to internationally recognized standards, R 10 system ref LIS/D/ 08 rev.10 dt 15.11.2021 evidenced,
identification methods, procedures. calibration frequency once in year.
Are statistical techniques used, such as CP/ CPK/ Gauge R&R etc.?
12 Look for U 10 NA
records.
Are open engineering issues addressed with an appropriate action plan? Production process taken after getting approval from customer,
17 Especially important for running change issues. How is it ensured that R 10 defined in quality procedure Customer related process QP/08
engineering issues are finalised before actual production takes place? rev.01 dt 12.09.2018
Does the Supplier have a System for managing & Storing Customer
19
Supplied Documents.
Aspects to check: measurement first sample, registration release, R 10
Customer supplied documents are recorded in External Origin
documents LIS/D/8 Rev.10 dt 05.07.2021.
methods to check, criteria of acceptance.
PFMEA & Control Plan Available For All Product , Control Plan
PFMEA & Control plans for all component/ product?
21 Work instructions for production? R 10
Evidenced For The Part Ball Pin Forging Knuckle Fork Clutch
Release CP/QA/PRF 20 41 01 0533 Rev.No 01 Date.01-04-
Acceptance criteria and procedures for rejects?
2021 Evidenced.
Is sufficient machinery in place to carry out current production? Yes Sufficient Machinery is Available in place, List Of
22
Does the machinery in use meet the specifications of the product? R 10
Machineries LIS/D/09 Rev.No.09 Date.15-10-2020 Evidenced.
Are all personnel sufficiently trained and certified for their assigned Skill Matrix verified for the employees EMFPL / R / 04 reviewed
29
function?
How is it ensured that only competent personnel are working in the R 8
periodically, displayed in shop floor evidenced.
1)Training records , Training needs & Effectiveness monitoring
specified job role? Is there a training plan? system to be implement and followed .
Are work instructions made available for production and tooling, and are
they known by operators? Work instruction displayed near work area. Ref. WI/PROD/20
Check that they are in compliance with product requirements/ process work instruction barrel loading rev.no.01 date.11-01-2020
32
control plans. Do they adequately detail how to perform the operations R 10
evidenced. Operators Are Trained Product/Process Knowledge
and what to inspect? Is there clear evidence that the instructions have Training Record Available.
been checked on latest revision prior to production issue?
41
Does the supplier work on a FIFO system?
Check how they monitor dates and control sequence of usage. R 10
FIFO System Followed based on batch code, date of receipt
and records are maintained accordingly
Tag & Packing label with lot code system followed For
45 How is traceability of finished products controlled? R 8
Traceability Of Finished Products
P 01 P 02 P 03 P 04
P 05 P 06 P 07 P 08
P 09 P 10 P 11 P 12
P 13 P 14 P 15 P 16
P 17 P 18 P 19 P 20
P 21 P 22 P 23 P 24
P 25 P 26 P 27 P 28
620700179.xlsx
Photo's Audit
P 29 P 30 P 31 P 32
P 33 P 34 P 35 P 36
P 37 P 38 P 39 P 40
P 41 P 42 P 43 P 44
P 45 P 46 P 47 P 48
P 49 P 50 P 51 P 52
P 53 P 54 P 55 P 56
620700179.xlsx
Photo's Audit
P 57 P 58 P 59 P 60
P 61 P 62 P 63 P 64
P 65 P 66 P 67 P 68
P 69 P 70 P 71 P 72
P 73 P 74 P 75 P 76
P 77 P 78 P 79 P 80
P 81 P 82 P 83 P 84
620700179.xlsx
Photo's Audit
P 85 P 86 P 87 P 88
P 89 P 90 P 91 P 92
P 93 P 94 P 95 P 96
P 97 P 98 P 99 P 100
620700179.xlsx
Opportunities For Improvement
Electro Platers & Metal Finishers
Item for Improvement nr: 1 Date:
Department:
Situation:
Page 10 of 13
Revision Date
00 02-06-2018
01 11/4/2020
00 3/30/2021
620700179.xlsx
Change Details
New Release
Scope , Type,Need & Frequency Added
Check Sheet Review and Updated
620700179.xlsx
Wire Processing
Plating
ED Coating
Geomet Coating
Phosphating
Heat Treatment
Machining / Sloting
620700179.xlsx