Ms Scaffolding
Ms Scaffolding
METHOD STATEMENT
FOR
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 1 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
Table of Content
1.0 Purpose……………………………………... 3
2.0 Scope……………………………………....... 3
3.0 Definitions…………………...…………....... 3
5.0 Responsibility………………..…………....... 4
8.0 Safety………………………………...……….12
9.0 Attachments………………………………….13
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 2 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
1. PURPOSE
This method statement describes the procedure and resources required to do
erecting and dismantling of all temporary elevated work platform scaffolds to be
used for finishing work of porta cabins and relevant work in Zuluf Project.
This method statement summarizes suggested method of executing works safely
within any constraints. This method statement offers advice and guidance to the
personnel involved in this activity to:
2. SCOPE
This Method Statement covers the scaffolding works and Lifeline installation,
including installation, maintenance and modification for use by JGC within Zuluf
project and finally the dismantling after the scaffold is no longer required by JGC.
2.2.1. All delivery of scaffold materials shall be placed and properly stacked
at the designated storage area on site and barricaded with safety
signage
2.2.2. All excess and unused material during erection must be return
immediately and properly stacked at the designated storage area on
site and close out relevant work permit.
2.2.3. Dismantling - All dismantled scaffold material which will not be use
immediately for another approved purposed must be returned
immediately to the designated storage area and housekeeping &
proper waste management must be observed at all time and close
out relevant work permit.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 3 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
3. DEFINITIONS
4. APPLICABLE DOCUMENTS
5. RESPONSIBILITIES
5.2. HSE Manager / Supervisor – To ensure that all safety requirements have
been followed on all scaffold activities, uses and alteration of scaffolds. He
should ensure that all scaffold supervisors and inspectors are attended the
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 4 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
5.3. Scaffold Inspector – having valid ID for Saudi Aramco Certified Scaffold
Inspector. He shall visually inspect and check all components of complete
scaffold system before signing the green or yellow tag system for safe work.
He shall monitor and record the status of scaffolds into his registration
logbook.
5.4. Manpower used for building scaffolding shall consist of but not limited as
follows:
6.1. Scaffold materials shall be check by scaffold supervisor before and after each
work. Defective materials shall be painted with orange paint and segregates.
All identified defective materials shall be immediately removed from project
site to avoid reused.
6.2. Tools and equipment’s shall be in good condition, verified and checked by
responsible Safety Officer on monthly basis and shall be colour coded before
use at construction site.
6.3. Tools & Equipment will consist of but not limited as below:
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 5 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 6 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 7 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
7.3.2. Safety Tool Box meeting –Safety tool box meeting shall be
carried out by Scaffold Supervisor/Foreman to discuss all risk
hazards and necessary precaution needed to prevent any type of
accident.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 8 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
7.3.7. Provide and secure ties placed spacing equal to 4 times of base
width tightly connected into equipment (grating platform supports
or pipe support) by using pair of girder clamps.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 9 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
7.4.1. Securing Working Permit – Work permit shall be sign out and
placed into designated permit box and comply with SAPO
approved contractor CSSP, SACSM, GI 8.001, GI 2.100 and other
relevant Saudi Aramco Standards.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 10 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
7.4.12. JGC Supervisor shall ensure that all excess Tower Type scaffold
materials shall be return and properly stacked at their designated
storage location immediately, and performed housekeeping and
close out relevant work permit.
7.5.1. Dismantling Guard rails – Guard rails shall be removed from the
standards at all boarded levels.
7.5.3. Dismantling Tie Tubes – Tie tubes shall be removed after the
removal of ladders.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 11 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
8. SAFETY
8.2. Lifeline – Lifeline use for scaffold shall be made of scaffold tubes
connected by means of pair girder couplers into steel structural columns
capable of supporting load 5,000 lbs. Lifeline shall be designed by certified
Engineer having degree on Structural / Civil Engineering. And approved by
contractor (JGC) / Company (SA).
8.3. Securing Working Permit – Working permit shall be sign out and placed
into designated permit box and comply with SAPO approved contractor
CSSP, SACSM, GI 8.001, GI 2.100 and other relevant Saudi Aramco
Standards.
8.4. Identify all possible risk hazards – Job Safety Assessment has to filled-
up to identify all risk hazard and preventions. Risk hazard has to be
discussed at Tools Box Meeting to all scaffolders and supervisors.
8.6. All necessary scaffold materials, Hand tools and equipment shall be in
good condition and inspected for safe use.
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 12 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
8.7. All scaffolders must wear their PPE’s and Complete Safety Full Body
Harness at all times when working on scaffolding. Scaffolder shall be
equipped with trauma strap along with full body harness while erection and
dismantling of scaffolding.
8.9. Scaffolding fittings like couplers must be kept inside container box and
must not be stacked directly on the ground. Scaffold Pipes and wood
planks must be segregated and placed properly inside stack piles.
8.11. AURCO Supervisor shall ensure proper housekeeping before, during and
after commencement of all activities and ensure waste management
8.13. AURCO Supervisor shall always look for the welfare of everyone
8.14. JGC shall prioritized Safety requirements specific for this activity
8.15. JGC Safety Supervisor shall keep Jobsite Safety Logbook and keeping of
Training records & Competency of personnel specific to this activity which
shall be made available for anytime inspection of SAPO Representative
9. ATTACHMENTS
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 13 of 14
Zuluf Temporary Facilities
Reference No: LI-0-887-TF9 Mechanical Works Rev: 00
Document Title: Method Statement For Scaffold Installation / Modification / Dismantling And Lifeline
Document Number: V-3200-TF9-A-1020
This document has been prepared by Attiq Ur Rehman Contracting Company for JGC
It contains information that is Confidential and such information is intended to be for the exclusive use of the individual or entity named above.
It shall be neither shown to third parties nor used for purposes other than those for which it has been disclosed.
Page 14 of 14