GM FMEA Done
GM FMEA Done
PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval, In Process Sampling Test
Inner Diameter Ø 50.8 / 51.2 mm 1 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rejection Increases,
More 8 2 2 32
Assembly Problems Incorrect Programing,Incorrect Set up of Set up Approval,In Process
Ø 95.000 / 95.040 Sampling Test
Inner Diameter
mm
2 ▼ Fixture,loose Mounting/Clamping,Faulty Tool Inspection,Operator
Every lot
Rework Increases, Travel , Tool Wear Monitoring,SPC
Less 7 2 2 28
Assembly Problems
Rework Increases,
More 6 2 5 60
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 110.7 / 111.3 Sampling Test
Outer Diameter 3 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
mm Every lot
Rejection Increases, , Tool Wear
Less 5 2 5 50
Assembly Problems
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 229.00 / 232.00 Sampling Test
Inner Diameter 4 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
mm Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rework Increases,
More 8 2 2 32
Assembly Problems Incorrect Programing,Incorrect Set up of Set up Approval,In Process
Ø 271.30 / 271.40 Sampling Test
Outer Diameter 6 ▼ Fixture,loose Mounting/Clamping,Faulty Tool Inspection,Operator
mm Every lot
Rejection Increases, Travel , Tool Wear Monitoring,SPC
Less 7 2 2 28
Assembly Problems
Rework Increases,
More 6 2 5 60
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 275.5 / 276.5 Sampling Test
Outer Diameter 7 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
mm Every lot
Rejection Increases, , Tool Wear
Less 5 2 5 50
Assembly Problems
Rework Increases,
More 6 2 5
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 296.7 / 297.3 Set up Approval,In Process Sampling Test
Outer Diameter 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 60
mm Inspection,Operator Monitoring, Every lot
Rejection Increases, , Tool Wear
Less 5 2 5
Assembly Problems
Rejection Increases,
Less 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 16.50 / 18.00 mm 9 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 6 60
Assembly Problems
1 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rework Increases,
Less 6 Incorrect Programing,Incorrect Set up of 2 7 84
Assembly Problems Set up Approval , Sampling Test
Chamfer 13 Fixture,loose Mounting/Clamping,Faulty Tool Travel
1.5 X 45° Rejection Increases, Program Controlled Every lot
More 5 , Tool Wear 2 7 70
Assembly Problems
Rework Increases,
Less 6 Incorrect Programing,Incorrect Set up of 2 7 84
Assembly Problems Set up Approval , Sampling Test
Chamfer 17 Fixture,loose Mounting/Clamping,Faulty Tool Travel
0.5 X 45° Rejection Increases, Program Controlled Every lot
More 5 , Tool Wear 2 7 70
Assembly Problems
Rework Increases,
Less 6 Incorrect Programing,Incorrect Set up of 2 7 84
Assembly Problems Set up Approval , Sampling Test
Chamfer 1.0 X 45° 22 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Rejection Increases, Program Controlled Every lot
More 5 , Tool Wear 2 7 70
Assembly Problems
2 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 4.7 / 6.2 mm 26 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,In Process Sampling Test
Depth 12.5 / 12.7 mm 28 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 5 60
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,In Process Sampling Test
Chamfer Depth 1.4 / 1.6 mm 29 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 5 50
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,In Process Sampling Test
Depth 6.80 / 7.20 mm 30 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval, In Process Sampling Test
Depth 61.9 / 62.1 mm 31 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
3 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval, In Process Sampling Test
Depth 41.9 / 42.1 mm 32 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 7.8 / 8.2 mm 33 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 33.70 / 34.30 mm 34 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 17.3 / 17.8 mm 35 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,In Process Sampling Test
Width 15.3 / 15.7 mm 36 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
4 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Ream Depth 9.80 / 10.20 mm 42 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Drill Depth 13.80 /14.20 mm 44 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 117.7 / 118.3 Set up Approval , Sampling Test
Inner Diameter 46 Fixture,loose Mounting/Clamping,Faulty Tool Travel
mm Program Controlled Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 135.5 / 136.5 Set up Approval , Sampling Test
Inner Diameter 47 Fixture,loose Mounting/Clamping,Faulty Tool Travel
mm Program Controlled Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 149.0 / 151.0 Set up Approval , Sampling Test
Inner Diameter 48 Fixture,loose Mounting/Clamping,Faulty Tool Travel
mm Program Controlled Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rejection Increases,
More 6 2 7 84
Assembly Problems Incorrect Programing,Incorrect Set up of
Groove Inner Ø 229.5 / 230.5 Sampling Test
49 Fixture,loose Mounting/Clamping,Faulty Tool Travel Program Controlled
Diameter mm Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rejection Increases,
More 6 2 6 72
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 234.5 / 235.5 Set up Approval,In Process Sampling Test
Inner Diameter 50 Fixture,loose Mounting/Clamping,Faulty Tool Travel
mm Inspection,Operator Monitoring, Every lot
Rework Increases, , Tool Wear
Less 5 2 6 60
Assembly Problems
Rework Increases,
More 6 2 5 60
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 290.5 / 291.5 Sampling Test
Outer Diameter 51 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
mm Every lot
Rejection Increases, , Tool Wear
Less 5 2 5 50
Assembly Problems
5 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Set up Approval /
Incorrect Programing,Incorrect Set up of
Rejection Increases, CMM Report Sampling Test
Dimension 62.7 / 62.8 mm More / Less 67 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
Assembly Problems & Every lot
, Tool Wear
Program Controlled
Set up Approval /
Incorrect Programing,Incorrect Set up of
108.64 / 108.74 Rejection Increases, CMM Report Sampling Test
Dimension More / Less 68 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
mm Assembly Problems & Every lot
, Tool Wear
Program Controlled
Set up Approval /
Incorrect Programing,Incorrect Set up of
108.64 / 108.74 Rejection Increases, CMM Report Sampling Test
Dimension More / Less 69 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
mm Assembly Problems & Every lot
, Tool Wear
Program Controlled
Set up Approval /
Incorrect Programing,Incorrect Set up of
Rejection Increases, CMM Report Sampling Test
Dimension 134.7 mm More / Less 70 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
Assembly Problems & Every lot
, Tool Wear
Program Controlled
Set up Approval /
Incorrect Programing,Incorrect Set up of
Rejection Increases, CMM Report Sampling Test
Dimension 62.7 / 62.8 mm More / Less 71 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
Assembly Problems & Every lot
, Tool Wear
Program Controlled
6 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Set up Approval /
Incorrect Programing,Incorrect Set up of
125.45 / 125.55 Rejection Increases, CMM Report Sampling Test
Dimension More / Less 72 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 4 64
mm Assembly Problems & Every lot
, Tool Wear
Program Controlled
2
Incorrect Programing,Incorrect Set up of
Rejection Increases, Set up Approval,Operator Sampling Test
PCD Ø 74.00 mm More/Less 73 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 32
Assembly Problems Monitoring,In-Process Inspection Every lot
, Tool Wear
2
2
Incorrect Programing,Incorrect Set up of
Rejection Increases, Set up Approval,Operator Sampling Test
PCD Ø 251.00 mm More/Less 75 8 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 32
Assembly Problems Monitoring,In-Process Inspection Every lot
, Tool Wear
2
Set up Approval /
Incorrect Programing,Incorrect Set up of
Rejection Increases, CMM Report Sampling Test
Angle 13.50 ° More / Less
Assembly Problems
0 7 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2
& Every lot
8 112
, Tool Wear
Program Controlled
Set up Approval /
Incorrect Programing,Incorrect Set up of
Rejection Increases, CMM Report Sampling Test
0 73 ͦ30'± 10' More / Less 77 7 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 8 112
Assembly Problems & Every lot
, Tool Wear
Program Controlled
80
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
More 8 3
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,Operator Sampling Test
Tap M8 X 1.25 Fixture,loose Mounting/Clamping,Faulty Tool Travel 2 48
Monitoring,In-Process Inspection Every lot
, Tool Wear
Less Rework Increases 7 3
Rejection Increases,
More 8 2 2 32
Assembly Problems Incorrect Programing,Incorrect Set up of
Ø 5.974 / 5.988 Set up Approval , Sampling Test
0 82 Fixture,loose Mounting/Clamping,Faulty Tool Travel
mm Program Controlled Every lot
Rework Increases, , Tool Wear
Less 7 2 2 28
Assembly Problems
Rejection Increases,
More 6 2 8 96
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Width 1.9/ 2.1 85 Fixture,loose Mounting/Clamping,Faulty Tool Travel Program Controlled
Every lot
Rework Increases, , Tool Wear
Less 5 2 8 80
Assembly Problems
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Sampling Test
Depth 7.9 / 8.1 mm 91 Fixture,loose Mounting/Clamping,Faulty Tool Travel Set up Approval
Every lot
, Tool Wear
8 of 12
Doc. No. PDC-EPD-F03
PROCESS FAILURE MODE AND EFFECTS ANALYSIS Rev. No. (Date) 00 (01/12/2017)
PFMEA Number 894172529 FMEA-MCD-01 Key Contact / Phone Name / Works / Dept Team Member Department
Rev. No. (Date) 00(01/01/14) Mr. Vibhor V. Jain CEO
Mr. Vibhor V. Jain CEO
Date (Originated) 1/1/2014 Mr. R.R. Sharma Head Quality
Part Number 894172529 Mr. Pradeep Garg G.M. Operation
Process Responsibility: Core Team
Part Name / Description GMI Flywheel Mr. Himanshu Duniwal Manager QMS
Material Grade FC 23 Key Date : 1-Jan-14 Mr. R S Shekhawat Manager - EPD
Rejection Increases,
Less 6 2 4 48
Assembly Problems Incorrect Programing,Incorrect Set up of
Set up Approval,Operator Sampling Test
Depth 17.80/18.20 mm 92 Fixture,loose Mounting/Clamping,Faulty Tool Travel
Monitoring,In-Process Inspection Every lot
Rework Increases, , Tool Wear
More 5 2 4 40
Assembly Problems
9 of 12
Hindustan Malleable Casting Works POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)
EICHER TRACTORS (A Unit of Tafe Motors and
Part Name FLY WHEEL CASING Customer PFMEA No. HMCW/TMTL-01 Rev. No. 0
Tractors Limited)
Part No. 9701 063 1 Key Dates Date 22/05/08 Date 22/05/08
RES. &
S. COMPONENT POTENTIAL FAILURE RECOM. ACTION
RPN
RPN
S C FAILURE EFFECTS FAILURE CAUSES O FAILURE PREVENTION FAILURE DETECTION D TARGET S O D
No. OR PROCESS FUNCTION MODES ACTION TAKEN
DATE
Visual Inspection of
Heat Codes Missing 6 Casting Rework & Punching Operator Negligence 4 Sampling Inspection 4 96
Patterns
CE
High 7 Lost in Properties Operator's Negligence 4 100 % Monitoring Sampling Test 4 112
Pouring
Temperature
Low 7 Lost in Properties Operator's Negligence 4 100 % Monitoring Sampling Test 4 112
Low
7 Casting Rejection Improper Composition 4 Inprocess Inspection Sampling Test 4 112
Hardness
Hardness
Test
High
7 Casting Rejection Improper Composition 4 Inprocess Inspection Sampling Test 4 112
Hardness
High
7 Casting Rejection Improper Composition 4 Inprocess Inspection 4508325 4 ###
Strength
Tensile
Strength
4508404 7 4507524 4508365 4 Inprocess Inspection 4508325 4 ###
O = Failure occurrence probability D = Failure detection probability Risk Priority Number RPN = S x O x D
To be filled if RPN>150 10 of 12
Hindustan Malleable Casting Works POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)
EICHER TRACTORS (A Unit of Tafe Motors and
Part Name FLY WHEEL CASING Customer PFMEA No. HMCW/TMTL-01 Rev. No. 0
Tractors Limited)
Part No. 9701 063 1 Key Dates Date 22/05/08 Date 22/05/08
RES. &
S. COMPONENT POTENTIAL FAILURE RECOM. ACTION
RPN
RPN
S C FAILURE EFFECTS FAILURE CAUSES O FAILURE PREVENTION FAILURE DETECTION D TARGET S O D
No. OR PROCESS FUNCTION MODES ACTION TAKEN
DATE
To be filled if RPN>150
I = Date of Implementation C = Classification S = Severity
11 of 12
Hindustan Malleable Casting Works POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA)
EICHER TRACTORS (A Unit of Tafe Motors and
Part Name FLY WHEEL CASING Customer PFMEA No. HMCW/TMTL-01 Rev. No. 0
Tractors Limited)
Part No. 9701 063 1 Key Dates Date 22/05/08 Date 22/05/08
RES. &
S. COMPONENT POTENTIAL FAILURE RECOM. ACTION
RPN
RPN
S C FAILURE EFFECTS FAILURE CAUSES O FAILURE PREVENTION FAILURE DETECTION D TARGET S O D
No. OR PROCESS FUNCTION MODES ACTION TAKEN
DATE
Excessive 7 Pitting over Surface More Blasting Time 4 Inprocess Inspection Visual Inspection 4 112
Poor 7 Loose Sand Less Blasting Time 4 Inprocess Inspection Visual Inspection 4 112
Poor 5 Increases Rework Improper Processing 5 Inprocess Inspection Visual Inspection 4 100
Dim. Oversize /
7 Increase Rework Improper Processing 3 Inprocess Inspection Sampling PDI 4 84
Inspection Undersize
Final
8
Inspection
Visual Casting
7 Casting Rejection Improper Processing 3 Inprocess Inspection Sampling PDI 4 84
Inspection Defects
O = Failure occurrence probability D = Failure detection probability Risk Priority Number RPN = S x O x D
To be filled if RPN>150
I = Date of Implementation C = Classification S = Severity
12 of 12