Practice Notes For Quantity Surveyors - Procurement Strategy
Practice Notes For Quantity Surveyors - Procurement Strategy
Practice Notes For Quantity Surveyors - Procurement Strategy
NOTES
FOR
QUANTITY
SURVEYORS
Procurement
Strategy
Contents
CONTENTS
Page
Preface 1
1. Introduction 2
2. Procurement Strategy 3
3. Choose Relationship Models 5
4. Decide Contract Types 17
Disclaimer
All parties must rely exclusively upon their own skill and judgment when making
use of this document. Neither The Hong Kong Institute of Surveyors, Association of
Consultant Quantity Surveyors nor any of the committee members and any other
contributor assumes any liability to anyone for any loss or damage caused by any
error or omission, whether such error or omission is the result of negligence or any
other cause. Any and all such liability is disclaimed.
Preface
PREFACE
The Practice Notes are not intended to promulgate a standard of practice, but rather
to produce some basic guidelines for the following core practices:
The members of the Working Committee who prepared the Practice Notes for the
Procurement Strategy are:
1
Introduction
1. INTRODUCTION
1.1 Selecting the correct procurement strategy is one of the most important
decisions for the Employer. It is this decision which establishes the risk
allocation and management for the construction project required by the
Employer.
1.3 After that the Employer should, through its consultants, start preparing the
tender documents for the construction project.
1.4 The relationship models and contract types described here are the most
common models and types. In actual practice, the actual procurement
strategy adopted may be a hybrid of the different relationship models and
contract types to take their best advantageous features suiting the particular
need of a project. There are also less common models and types such as:
serial contracting, build-operate-transfer and its many variances, prime
contracting, framework agreement, private finance initiative, public-private
partnership, integrated project delivery, partnering, etc. some of which have
become more popular these days.
2
Procurement Strategy
2. PROCUREMENT STRATEGY
2.3 Accordingly, the selection process should therefore provide a best-fit solution,
which is acceptable in terms of the identified criteria and acceptable allocation
of risks.
2.4 The common factors that should be taken into account in deciding what
procurement strategy to use include the following:
Factors to Examples
Consider
Time • The Employer may require the project to be completed
quicker than normal
• There is sufficient time for a full specification (Drawings
and/or Employer’s requirements) to be systematically
developed
Cost • The Employer may require cost certainty with limited
exposure to cost increases
• There is a desire for the Employer to transfer complete risk
as much as possible to the Contractor
Quality • The Employer may require a high-quality building
irrespective of costs
• The project may involve complicated buildability issues
which may benefit from having a contractor involved in the
design stage
2.5 The reality is that although the three most important considerations
are usually cost, time and quality, the business of construction project
procurement invariably calls for some compromise or conscious balancing
of these priorities. There is a need for careful balancing of priorities in which
adequate thinking time and careful thought are required.
3
Procurement Strategy
2.6 Furthermore, with growing awareness of the complexities associated with
delivering an end product that optimizes the Employer’s various needs and
objectives, the following factors are required to be considered:
(b) Responsibility – Need for single contractual link for project execution?
(c) Professional Responsibility – Need for the design team to report to the
Employer?
2.7 There are also minor factors such as dispute avoidance, safety, health,
environment, social responsibility, innovation, tax management, import and
export restrictions, etc. that may affect the appropriate choice of procurement
strategy.
4
Choose Relationship Models
3. CHOOSE RELATIONSHIP MODELS
3.1 There are the following three key models commonly adopted:
(a) Traditional (or sequential) model in which at least in theory design and
construction are seen as separate elements
(b) Integrated model in which design and construction are carried out by
the Contractor
3.2 A diagrammatic illustration showing the above three models is shown below:
Relationship Models
Traditional Management
Integrated
(Sequential) Oriented
3.3 This is the typical design-bid-build model commonly used in Hong Kong.
3.4 Under this model, the Employer engages the consultants for design, cost
control, and contract administration, and that the Contractor is responsible
for carrying out the works.
3.5 In some cases, the Employer will select some of the sub-contractors to be
engaged by the Contractor (variously referred to as named, nominated,
or pre-selected). In such cases the Contractor is still required to take full
responsibility for their performance.
5
Choose Relationship Models
3.6 A diagrammatic illustration showing the arrangement of this model is shown
below:
Employer
Main Contractor
3.7 The advantages of adopting the traditional (or sequential) model are as follows:
(c) The Employer and the consultants are fully in control over the design
and the quality of the project.
(d) Compared with other procurement approaches, the tender prices are
usually more competitive.
(e) There is certainty of cost, to the extent that the construction cost is
known before work begins, even if it has to be adjusted during the
construction period as provided for in the contract.
(f) As the Employer appoints the consultants to advise on cost issues, the
Employer retains cost control over the project.
6
Choose Relationship Models
3.8 The disadvantages of adopting the traditional (or sequential) model are as follows:
(b) The design liability for permanent work rests on the consultants
engaged by the Employer.
(e) The Contractor depends heavily upon the necessary information and
instructions from the consultants being issued on time. There is a risk
of claims if they are delayed.
3.9 Under this model, the Employer appoints a Contractor to design and construct
the works, as opposed to a traditional or sequential model, where the
Employer appoints the consultants to design the project and then a contractor
is appointed to construct the works.
3.10 Design and build approach fall under this model. It involves the appointment
of a single contractor through either tendering or negotiation for delivering the
entire project to fulfil the requirements of the Employer including employing the
Contractor’s own design team. This arrangement will require tender documents
outlining the Employer’s requirements to be prepared by the Employer. These
are usually in the form of a design brief, building functional requirements, area
requirements, service performance criteria and finishes standard, etc.
3.11 There is single point responsibility placed on the Contractor to deliver within
the time and price to the quality expected.
3.12 However, there is little flexibility for making changes which can be both costly
and have programme implications. Once the parameters are set there is little
opportunity to make material changes. It therefore requires discipline and
understanding of the Employer’s expectations at the outset.
3.13 The tenderer is required to submit its design and pricing in the form of a
Contractor’s Proposal for evaluation and subsequent award. The tender
process will be longer, when compared with the traditional or sequential
model, because of the time required for the tenderer to prepare the design
and the time for the Employer to conduct tender assessment.
7
Choose Relationship Models
3.14 Although the tendering period may be longer, the design and build
arrangement is regarded as a fast-track strategy given that the Contractor can
start work on site before all detailed design is completed.
Employer
Main Contractor
Quantity Quantity
Architect Engineer
Surveyor Surveyor
3.16 The advantages of adopting the integrated model (design and build
approach) are as follows:
(a) From the Employer’s perspective, this approach provides a single point
of responsibility and without having to appoint separately the design
consultants to undertake and complete the design. Management of
the design consultants is diverted to the Contractor.
(b) This approach may appear to offer a quick start on site as the detailed
design will be undertaken by the Contractor. Furthermore, part of the
design process can be deferred to a later stage after the appointment
of the Contractor.
(d) There can be lesser project management input from the Employer
should the Contractor be considered trustworthy.
8
Choose Relationship Models
(f) There is greater certainty of cost at award of contract subject to few
subsequent changes of the Employer’s requirements. However, any
significant changes in the Employer’s requirements will affect the
contract sum.
3.17 The disadvantages of adopting the integrated model (design and build
approach) are as follows:
(b) The Employer lacks control over the detailed aspects of design;
however, this might be acceptable where the broad lines of the
scheme are satisfactory and the detail relatively less important.
(f) The Employer may lose control over design if the brief is not clearly
developed.
(g) This approach does not allow much flexibility in design changes or
changes in Employer’s requirements after the contract is awarded.
(h) The higher tendering costs and the higher design risks to the
Contractor are reflected in the tender prices.
9
Choose Relationship Models
(j) There is no design review unless separate consultants are employed
as independent design checker for supervision of quality.
3.18 Under the management contracting, the works are constructed by a number
of different works contractors who are sub-contracted under a Management
Contractor engaged by the Employer.
3.20 The Employer initially appoints the consultants to undertake feasibility and
costing and perhaps outline design.
10
Choose Relationship Models
3.24 The Management Contractor bears responsibility for the construction
works without actually carrying out any of the works. Having said that, the
Management Contractor will be responsible for the provision of the site
management and preliminaries items including providing temporary works
and facilities for the project and providing buildability advice to the design
team.
(b) Either a percentage or lump sum for its management, supervision and
the like, plus
(c) Costs of carrying out site works and contractors’ design and other
services (by itself or works contractors).
3.26 A competitive tendering element is retained for the works contracts, which
usually account for most of the overall prime cost of the project. Tenders for
works packages will normally be on a lump sum basis. The work package
contracts are executed between the work packages contractors and the
Management Contractor.
3.27 The prime cost of all works contractors is monitored against the estimated
prime cost and therefore the Employer retains the cost risk on the
project unless incurred due to the default of the Management Contractor.
Accordingly, cost certainly is not achieved until all works contractors have
been appointed.
3.28 Much of the detailed design work can be left to proceed in parallel with the
site operations for some work packages, thus reducing the time needed
before the project starts on site. Indeed, a great deal of detailed design will
need to be left to specialist works contractors or suppliers.
3.29 All design work will not be completed before the first works contractor
starts work although the design necessary for the first works package must
be completed. As design is completed, subsequent works packages are
tendered for and let.
11
Choose Relationship Models
3.32 A diagrammatic illustration showing the arrangement of management
contracting is shown below:
Employer
Management
Contractor
(e) There is greater adaptability and flexibility for the Employer to defer
decisions on other works contracts which are considered less time
critical and to deal with changes in the Employer’s requirements, as
the later works contracts are tendered for well after the start on site.
12
Choose Relationship Models
(f) Changes can be accommodated provided those works contracts
affected have not been let and there is little or no impact on those
already let.
(g) All works contracts are tendered and procured competitively. The
Employer has the benefit in receiving competitive prices from the
market.
(c) There will be a lower degree of cost control as the design is less
advanced at commencement.
13
Choose Relationship Models
3.36 One of the key roles of the Construction Manager is to manage, plan and
control the work of the works contractors. The Construction Manager is
required to provide sufficient on-site management resources to co-ordinate
work package interfaces and to monitor progress of construction works.
3.37 The Construction Manager is a member of the project team to manage the
project. In other words, construction management is a relationship model
whereby the designers provide the design, works contractors deliver their
works packages and the Construction Manager manages the process,
advises on construction techniques and methods to improve buildability, and
defines and manages the work packages.
Employer Employer
Construction Management
Manager Contractor
3.39 The Construction Manager is usually the lead consultant, has a more positive
role than the Management Contractor.
3.41 On appointment, the Construction Manager will take over any preliminary
schedule and costing information already prepared and draw up a detailed
programme of pre-construction activities for the Employer to consider the
recommendation of the Construction Manager.
(a) The working relationship between the Employer and the works
14
Choose Relationship Models
contractors is maintained as there is a direct contractual relationship
between the Employer and each of the works contractors.
(d) The Employer has the ability to influence the selection of works
contractors.
(e) As the Employer has direct contracts and pays directly to the works
contractors, this could result in lower price, improved performance
and payment relationship.
(a) There will be increased administration role for the Employer as the
Employer needs to directly deal with the Construction Manager and
the many works contractors.
15
Choose Relationship Models
Summary
3.44 The table below indicates the typical use of these relationship models:
Management Ori-
Integrated
Traditional ented
Factor Objectives
(Sequential) Design & Con. Man.
Build Man. Con.
Note:
1. Management Contracting and Construction Management can be adopted if early contractor’s
involvement is desired.
2. Design and build can be adopted if specialist designers are to be engaged by the Contractor.
3. Design and build can be adopted if the Employer accepts a free-hand turnkey approach.
16
Decide Contract Types
4. DECIDE CONTRACT TYPES
4.1 After the relationship model has been established and confirmed, the second
step is to choose the contract type to be adopted.
4.2 The contract type described here is largely determined by the type of pricing
arrangement the Employer wishes to have with other concerned parties.
The detailed terms and conditions of the printed forms of contract for any
particular contract type chosen would require an approach that matches the
allocation of risks amongst the contracting parties. It has to provide the right
plan to protect the prioritised time, cost and quality in the desired project
outcome. The contract type selected should echo and give effect to the
relationship model chosen.
4.5 Under a lump sum contract, the Contractor is engaged to perform the works
on a lump sum basis, requiring the works to be completed for a fixed price.
The risk allocation is placed mainly on the Contractor as he will have to
complete the works within the agreed price even if it incurs higher costs to
deliver the same contents of the works.
4.6 The lump sum can be adjusted if there are post contract Employer’s
instructions or variation orders (usually issued through the Architect or
Engineer) resulting in additional costs. Therefore, it is common for the
Contractor to submit numerous claims purporting post contract variations, in
the hope of increasing the contract price.
4.7 There are two types of lump sum contracts – ‘With quantities’ and ‘Without
quantities’.
4.8 For the ‘With quantities’ lump sum contract, it is prepared based on
drawings, specification and Bills of Quantities.
17
Decide Contract Types
4.9 This type of contract is used where the design is sufficiently advanced to
prepare the bills of quantities.
4.10 The advantages of using ‘With quantities’ lump sum contract are as follows:
(a) Compared with the ‘Without quantities’ lump sum contract, bills of
quantities provide a common basis for competition.
(b) The use of bills of quantities facilitate tender analysis as the tenderers
are pricing under the same bills of quantities.
(c) The bills of quantities relieve the tenderers’ costs and risks in
measuring the quantities.
(d) The quantities and unit rates in the bills of quantities serve as basis for
assessing variations.
4.11 However, compared with the ‘Without quantities’ lump sum contract, it takes
more time for the quantity surveyors to prepare the bills of quantities.
4.12 For the ‘Without quantities’ lump sum contract, it is prepared based on
drawings and specification.
4.13 Again, this type of contract is used where the design is sufficiently advanced
and where the full extent and nature of works can be clearly defined based
on drawings and specification.
4.14 The advantages of using ‘Without quantities’ lump sum contract is that
the consultants’ work on taking-off quantities is saved. In other words, the
quantity risk is passed to the tenderers.
4.15 The disadvantages of using ‘Without quantities’ lump sum contract are as
follows:
(a) The cost to the tenderers of producing their own quantities will be
reflected in the tender prices which means the tenderers’ tendering
costs are increased.
18
Decide Contract Types
(d) As the tenderer is responsible for any errors it makes in taking off
from the drawings, the tenderer is likely to include high contingency
factors in its tender price.
Remeasurement Contract
4.16 For a remeasurement contract, the original works are tendered on estimated
approximate quantities from drawings multiplied by tendered rates. The
actual constructed works are re-measured and the works are valued based
on the tendered rates. The Employer thus takes the risk of the amount of
works to be done whilst the Contractor takes the risk of the adequacy of the
stated unit rates.
4.17 There are two types of remeasurement contract – ‘Schedule of Rates’ (with
no “calculated quantities”) and ‘Bills of Approximate Quantities’ (or ‘Bills of
Provisional Quantities’ or ‘Provisional Bills of Quantities’).
4.19 This type of contract is used where the works have not been fully detailed,
or the exact extent of the works based on a definite nature of works are
not known but will be carried out within a given period (e.g. maintenance
contract).
(a) Standard priced schedules can be used and the tenderers tender on
basis of percentage additions and commissions.
(b) The same standard schedule of rates can be used as a basis for
similar work at different times or in different locations.
19
Decide Contract Types
4.22 For the remeasurement contract based on bills of approximate quantities,
the works carried out are remeasured and priced at the rates stated under
the priced bills of quantities.
4.23 This type of contract is used where the design is not completed but an earlier
than normal start on site is required. However, the design should still be
sufficiently advanced to allow significant items to be measured in the bills of
approximate quantities.
(a) As the design is not required to be fully completed for the preparation
of bills of approximate quantities, there can be an overlap of design
and construction which results in a reduced overall project time.
(a) The items and quantities stated in the bills of approximate quantities
must bear reasonable resemblance to the works to be executed,
otherwise there will be a potential claim by the Contractor based on
missing items.
(b) There is less certainty of cost at the outset when compared with firm
bills of quantities.
(c) It encourages design to be put off to tomorrow for what could well
and better be decided today.
4.26 If cost-plus contract is adopted, the Contractor is paid based on the actual
costs incurred plus a lump sum or percentage fee for overheads and profit.
There is a need to carefully define exactly what the fee covers, with the
remainder being at cost.
20
Decide Contract Types
4.28 The advantages of using cost-plus contract are as follows:
(b) It relieves the Contractor’s pricing risks as he is paid the actual costs
incurred plus fee.
(c) There is a higher level of flexibility for design changes after during
construction.
4.30 U n d e r a t a r g e t c o s t a rr a n g e m e n t , t h e t a r g e t p r i c e i n c l u d e s t h e
Contractor’s estimate of the actual costs plus its fee. The target price
will be adjusted for any legitimate variations or instructions incurring
additional costs beyond the scope of risks borne by the Contractor.
4.31 Same as the cost-plus contract, the Contractor recovers the actual costs
incurred plus the fee but is capped to a certain amount (usually 10% of the
contract sum) so as to secure greater cost certainty for the Employer. In
addition, the Contractor is paid (or pays) its share of the difference between
the actual costs incurred plus the fee and the target price according to an
agreed formula. The Contractor’s gain share decreases as costs rise and may
end up with pain share (if the formula dictates this). Thus, the Contractor
and the Employer have a common interest in controlling costs as they share
the pain / gain.
4.32 A clear and unambiguous tender design brief together with a clearly defined
contractor’s design responsibilities are required for the Contractor to price
the works accordingly, thus ensuring a realistic target cost.
21
Decide Contract Types
4.33 A diagrammatic illustration showing the arrangement is shown below:
Pain
Gain Actual Share
Share Price
Target Target Employer
Price Price Pays
Actual Employer
Price Pays
4.34 The advantages of using target cost contract is similar to cost-plus contract
and with the following additional advantages:
(b) Both the Employer and the Contractor have motivation to save the
costs of construction.
(c) Both the Employer and the Contractor can contribute to management
of the risks.
4.35 The disadvantages of using target cost contract is also similar to cost-plus
contract and with the following additional disadvantages:
(a) Incorrect target setting can drive a focus on raising the target through
claims rather than suggesting innovative savings.
22
July 2021