Set 1

Question 1: Correct
Select the correct Scrum team accountabilities defined in Scrum. (Choose the best
answer)

Developers, Scrum Master, Product Owner

(Correct)

Engineers, Business Analyst, Product Owner

Stakeholders, Scrum Master, Project Manager, Product Owner

Product Manager, Business Analyst, Developers, Stakeholders

Explanation
The Scrum Framework only recognizes these three accountabilities. However, other
accountabilities may be needed to help the team build the most valuable product
possible.
Question 2: Correct
Which of these tools is mandatory for the Product Owner to use? (Choose the best
answer)

Release burnup chart.


Burndown chart.

Version control.

Project Gantt chart.

All answers above apply.

None of the answers apply.

(Correct)

Explanation
The Product Owner can use any tool, method, or practice that he/she finds fit for
him/her to make the best decisions possible. However, none of them are mandatory.
Question 3: Correct
Scrum has an accountability called “Project Manager.”

True

False

(Correct)
Explanation
The Scrum Framework only recognizes these three accountabilities. However, other
accountabilities may be needed to help the team build the most valuable product
possible.
Question 4: Correct
Which statement best describes Scrum? (Choose the best answer)

A clearly defined methodology that determines the software development


processes

A manual methodology for defining best practices for software development.

A clearly defined and predictable process that follows the principles of Computer
Science.

Scrum is a lightweight framework that helps people, teams and organizations


generate value through adaptive solutions for complex problems.

(Correct)

Explanation
Scrum is a lightweight framework that helps people, teams and organizations generate
value through adaptive solutions for complex problems as stated in the Scrum Guide.
Question 5: Correct
When could the Developers cancel the Sprint? (Choose the best answer)

When the availability of the Product Owner is less than expected.


When the requirements for the work to be done become unclear or not
understood.

They can't. Only the Product Owner can cancel the Sprint.

(Correct)

When the Sprint Backlog is determined to be unachievable.

When too many impediments occur.

Explanation
Only the Product Owner has the power to cancel the Sprint. This usually happens when
the Sprint Goal becomes obsolete.
Question 6: Correct
The Scrum Master is no longer needed when teams become self-managed.

True

False

(Correct)

Explanation
It is False, as he is still necessary; however, the Scrum Master will spend less time with
the Developers in this case.
Question 7: Correct
Scrum is based on which of the following? (Choose the best answer)

Defined process.

Complex process.

Empiricism.

(Correct)

Hybrid model.

Explanation
Scrum addresses complex problems in complex environments and asserts that
knowledge comes from experience and from decisions based on what is known. What is
known can only be discovered in hindsight.
Question 8: Correct
How often should Scrum team membership change? (Choose the best answer)

Frequently, in order to share knowledge.

As needed, while taking into account a short-term reduction in productivity.


(Correct)

Never, as it conflicts with the Scrum process.

As needed, as long as it doesn’t impact productivity.

Explanation
The same team doesn't need to stay together, although it must be understood that any
changes to the team will impact how they work together.
Question 9: Correct
Every Scrum team should include Developers that have the competencies and skills
needed to deliver a Done Increment in a Sprint.

True

(Correct)

False

Explanation
Developers are self-managed and cross-functional.
Question 10: Correct
Who must ensure that the work done for a Product Backlog item conforms to the
Definition of Done? (Choose the best answer)

The test team.


The Scrum team.

The Scrum Master.

The Product Owner.

The Developers.

(Correct)

Explanation
The whole Scrum Team must create a Definition of Done appropriate for the product.
However, the Developers are those who do the work, so they should make sure that the
produced work has the agreed standards. Developers are accountable for the quality of
the Product Backlog items and it's their responsibility to conform to the Definition of
Done.
Question 11: Correct
Who is accountable for knowing the most about the progress towards a business
objective or a release and also being able to clearly explain the alternatives?
(Choose the best answer)

The Product Owner

(Correct)


The Release Manager

The Developers

The Scrum Master

The Development manager

Explanation
The Product Owner needs to make sure that he keeps the Developers updated with
what the clients & stakeholders need. The Scrum Master is there to coach him/her on
how to do it.
Question 12: Correct
What are the Developers responsible for? (Choose the best answer)

Writing User Stories and ordering the Product Backlog.

Reporting productivity and selecting the Sprint timebox.

Organizing the work required to meet the Sprint Goal and resolving internal team
conflicts.

(Correct)
Explanation
They need to be focused on the Sprint Goal. They create the Sprint Backlog, instill
quality by adhering to a Definition of Done, adapting their plan each day toward the
Sprint Goal and holding each other accountable as professionals.
Question 13: Correct
Cross-functional teams are specialized for working on specific system components
(e.g. design, database, back-end, front-end).

True

False

(Correct)

Explanation
Cross-functional teams have all the skills and competencies needed to deliver end-to-
end work.
Question 14: Correct
Which of the following is required in Scrum? (Choose the best answer)

Sprint Retrospective

(Correct)

All Developers answering the three questions at the Daily Scrum

Sprint Burndown Chart


User Stories

All answers above apply.

None of the answers apply.

Explanation
Sprint Retrospective is mandatory in the Scrum Guide, whereas the rest of the options
are not mandatory.
Question 15: Correct
What is the recommended size for a Scrum team? (Choose the best answer)

Typically 10 or fewer members

(Correct)

Minimal 5

7 plus or minus 2

3 to 9
Explanation
Typically 10 or fewer people are needed as the Scrum team is small enough to remain
nimble and large enough to complete significant work within a Sprint.
Question 16: Correct
Who manages the progress of work during a Sprint? (Choose the best answer)

The Scrum Master knows who will be his back-up whenever he is unavailable. This
saves the organization time and money, and the Developers will know who to
request tasks from.

The Product Owner

The Team Leader

The Developers

(Correct)

Explanation
The Developers are self-managed, thus deciding how to manage their own progress.
Question 17: Correct
Which of the following best describes a Product Owner? (Choose the best answer)

Development requirements.


Value optimizer.

(Correct)

Team leader.

Go-between for the Developers and stakeholders.

Explanation
This is the way that a Product Owner should order the Product Backlog.
Question 18: Correct
What might be a valid reason for abnormally cancelling a Sprint? (Choose the best
answer)

When the Developers discover that it cannot meet their Sprint commitments.

When the work becomes too difficult for the Developers.

When the sales department discovers features that add more value than the
current work being done.

When the Sprint Goal becomes obsolete.

(Correct)
Explanation
The Product Owner has the power to cancel the Sprint if the Sprint Goal becomes
obsolete.
Question 19: Correct
A high performing Scrum team will have frequent Release Sprints.

True

False

(Correct)

Explanation
There are no special Sprints. All Sprints are structured to produce potentially shippable
product Increments.
Question 20: Correct
Which of the following actions is appropriate for a Scrum Master at the Daily
Scrum? (Choose the best answer)

Make sure each member has the opportunity to answer all three questions.

Leading the Daily Scrum.

Teaching the Developers to keep the Daily Scrum timeboxed to 15 minutes or less.

(Correct)

Updating the Scrum board.

All answers above apply.

None of the answers apply.

Explanation
The Scrum Master should make sure that the Daily Scrum takes place and is completed
within the timebox. However, the Scrum Master doesn't need to be present.
Question 21: Correct
How is a cross-functional Scrum team defined? (Choose the best answer)

Cross-skilled Developers can do all the work necessary to deliver a shippable


Increment at the end of the Sprint.

(Correct)

A team that consists of engineers, testers, business analysts, technical architects


and functional managers.

A group of full-stack Developers shared across multiple teams.


A team of skilled Developers that can effectively multi-task on multiple Product


Backlog items at the same time.

Explanation
The objective of the Sprint is to produce a shippable Increment at the end of each Sprint
so that the team can effectively inspect and adapt accordingly.
Question 22: Correct
Which statement is correct regarding the length of the Sprints? (Choose the best
answer)

The length of all Sprints must be no more than one month and it is optimal to
have a consistent Sprint length.

(Correct)

The Sprint length depends on the forecasted development effort (amount of items
selected) during Sprint Planning.

The Sprint length is calculated by aggregating the time required to design, code
and test.

The Sprint Length is defined by the Scrum Master.

Explanation
All Sprints must be one month or less and it is optimal to have a consistent Sprint length
as stated in the Scrum Guide.
Question 23: Correct
What must the Developers do during the first Sprint? (Choose the best answer)

Create a potentially shippable product Increment that includes at least one piece
of functionality.

(Correct)

Analyze and estimate the requirements for the subsequent Sprints.

Create a project plan in order to map the functional development to Sprint dates.

Only design and develop the architecture and infrastructure.

Explanation
Sprints promote iterative and Incremental development.
Question 24: Correct
Who is accountable for engaging with stakeholders? (Choose the best answer)

The team leader

The business analyst


The project manager

The Developers

The Product Owner

(Correct)

Explanation
It's the Product Owner's responsibility to keep the stakeholders updated.
Question 25: Correct
Which statement best describes the responsibility of the Product Owner? (Choose
the best answer)

To optimize the value of the work being done by the Developers.

(Correct)

To manage the Developers.

To ensure that the work meets the commitments of the stakeholders.

To act as a go-between for stakeholders.


Explanation
The Product Owner is accountable for the flow of value that the Developers select to
work on.
Question 26: Correct
Which of the following are timeboxed events in Scrum? (Choose the best answer)

Sprint Planning

Daily Scrum

Sprint Review

Sprint Retrospective

All answers above apply.

(Correct)

None of the answers apply.

Explanation
All answers apply as stated in the Scrum Guide.
Question 27: Correct
What are typical Product Owner activities during Sprint 0? (Choose the best
answer)

To create a project plan based on the defined timeline.

Ensuring there is enough work to do for at least three Sprints.

To create User Stories based on the requirements document.

To allocate enough resources before starting Sprint 1.

There is no such thing as Sprint 0.

(Correct)

Explanation
There are no special Sprints. All Sprints are structured to produce potentially shippable
Product Increments. Sprint 0, Release Sprints or Integration Sprints are not supported in
Scrum.
Question 28: Correct
How often should the customer satisfaction be measured? (Choose the best
answer)

Annually

Quarterly

Daily

Frequently

(Correct)

Explanation
Frequently. This ensures the team is building the right thing at the right time. However,
too frequent changes may affect the team's working progress.
Question 29: Correct
What are the typical Scrum Master activities during a Sprint? (Choose the best
answer)

To monitor the progress of the Developers and assign tasks.

To cause the removal of impediments to the Scrum team’s progress.

(Correct)

To avoid conflicts and escalate to the line managers if conflicts occur.

Explanation
One of the benefits of self-managed teams is the ability to decide how to work best
together in order to produce a shippable Increment.
Question 30: Correct
The Scrum Master is responsible for the process in which Scrum is adopted and
enacted.

True

(Correct)

False

Explanation
The Scrum Master need to make sure that the Scrum is applied in the right way.