This document provides details of Anjali Swain's broiler farming project with 6,500 birds reared in 1,100-bird fortnightly batches. The total capital cost is Rs. 10.04 lakh including construction of poultry sheds, equipment, day-old chicks and feed. Recurring costs are estimated over 6 years with an annual surplus ranging from Rs. 2.27 lakh to Rs. 5.89 lakh. Cash flow projections show the internal rate of return is above 50%. A bank loan of Rs. 8 lakh will be repaid in equal annual installments of Rs. 1.33 lakh over 6 years at 10.5% interest.

Uploaded by

MANAS KUMAR SAHU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
129 views6 pages

Project Report of A BROILER FARMING

This document provides details of Anjali Swain's broiler farming project with 6,500 birds reared in 1,100-bird fortnightly batches. The total capital cost is Rs. 10.04 lakh including construction of poultry sheds, equipment, day-old chicks and feed. Recurring costs are estimated over 6 years with an annual surplus ranging from Rs. 2.27 lakh to Rs. 5.89 lakh. Cash flow projections show the internal rate of return is above 50%. A bank loan of Rs. 8 lakh will be repaid in equal annual installments of Rs. 1.33 lakh over 6 years at 10.5% interest.

Uploaded by

MANAS KUMAR SAHU
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT REPORT

BROILER FARMING

ANJALI SWAIN
Proprietor
College Square, Jobra, Cuttack-3
POULTRY PROJECT (BROILER)
OF SHRI ANJALI SWAIN
AT:College Square, Jobra, Cuttack-3
(6,500 Birds, 1100 FORTNIGHTLY BATCH

CAPITAL COST:
A.NON-RECURRING EXPENDITURE:- UNITS COST IN Rs./UNIT TOTAL

I Poultry Shed for 6,500 6,500 80 5,20,000


birds @ 1 sq.ft.per bird for

B.OTHER CAPITAL EXPENDITURE

I Water Supply ( Motor+ Tank + Pipes) 10,000

II Equipments @ Rs. 10 per bird 65,000

TOTAL CAPITAL EXPENDITURE I 5,95,000

RECURRING COST CAPITALISED FOR 5 BATCHES

I Cost of day old chicks 6,500 15 97,500

ii Cost of concentrate
feed @ 3.6 kg/bird 23,400 10 2,34,000

iii Misc.Expenditure, such as, 6,500 12 78,000


Elec.,Vaccines, Insur.,Medic.,etc.

TOTAL RECURRING COST II 4,09,500

TOTAL PROJECT COST I + II 10,04,500

MARGIN @ 20% 2,00,900

AGRIL. LOAN FROM BANK 8,03,600

Or Say 8,00,000
BATCH SCHEDULE YEAR
1 2 3 4 5 6
1.NO OF BATCHES INTRODUCED 27 29 29 29 29 29
2.BROODER@GROWER WEEKS 202 231 231 231 231 231
3.NO OF BATCHES SOLD 23 29 29 29 29 29
ASSUMPTIONS :

1. Construction Period- 3 Weeks


2. Rearing ( Brooding & Growing ) period- 8 weeks
3. Clearing Period of each shed between 2 batches-1 week

Cost of Chick Rs.15


Cost of feed per kg Rs.10 Feed consumed per Batch in kg 3,960
Consumption of feed per bird in kg 3.6
Sale price per kg in Rs. 39
Avg.Wt.of Broiler in kg 1.6
Price per bird 62.4
RECURRING COST

ITEMS Nos per Rate in No of YEAR 1 2 3 4 5 6


Batch Rs. Batches
1. Cost of day old chicks 1,100 15 As per 4,45,500 4,78,500 4,78,500 4,78,500 4,78,500 4,78,500
2. Total Feed Cost @ 3.6 1,100 10 Batch 10,69,200 11,48,400 11,48,400 11,48,400 11,48,400 11,48,400
kg/bird Schedule
3. Misc. expenditure 1,100 5 in Sheet-1 1,48,500 1,59,500 1,59,500 1,59,500 1,59,500 1,59,500

TOTAL RECURRING COST 16,63,200 17,86,400 17,86,400 17,86,400 17,86,400 17,86,400

RECURRING COST NET OF CAPITALISED COST 12,53,700 17,86,400 17,86,400 17,86,400 17,86,400 17,86,400

Nos per Rate in No of YEAR 1 2 3 4 5 6


INCOME Batch Rs. Batches
1. Sale of Broilers per batch 1,100 62.4 As per 18,53,280 19,90,560 19,90,560 19,90,560 19,90,560 19,90,560
2. Sale of Manures 1,100 0.5 Batch 14,850 15,950 15,950 15,950 15,950 15,950
3. Sale of Gunny bags 53 5 Schedule 7,128 7,656 7,656 7,656 7,656 7,656
4. Depreciated Value of Assets in Sheet-1 2,12,000
5. Value of closing stock of birds 1,49,600
TOTAL INCOME 18,75,258 20,14,166 20,14,166 20,14,166 20,14,166 23,75,766
SURPLUS 6,21,558 2,27,766 2,27,766 2,27,766 2,27,766 5,89,366
SURPLUS FOR REPAYMENT PURPOSE 6,21,558 2,27,766 2,27,766 2,27,766 2,27,766 5,89,366
VALUE OF CLOSING STOCK

BATCH NO AGE NO OF BIRDS VALUE PER BIRD TOTAL VALUE

169 6 1,100 46.5 51,150


170 4 1,100 36.5 40,150
171 3 1,100 31.5 34,650
172 1 1,100 21.5 23,650

TOTAL 1,49,600
CASH FLOW & FINANCIAL ANALYSIS

ITEMS 1ST YR 2ND YR 3DR YR 4TH YR 5TH YR 6TH YR

PROJECT COST 10,04,500

RECURRING COST NET OF


CAPITALISED COST 12,53,700 17,86,400 17,86,400 17,86,400 17,86,400 17,86,400
TOTAL COST 22,58,200 17,86,400 17,86,400 17,86,400 17,86,400 17,86,400

BENEFIT 18,75,258 20,14,166 20,14,166 20,14,166 20,14,166 23,75,766


SURPLUS (3,82,942) 2,27,766 2,27,766 2,27,766 2,27,766 5,89,366
GROSS SURPLUS
D.F. @ 15% 0.869565 0.756144 0.657516 0.571753 0.497177 0.432323
PV @ 15% D.F. (3,32,993) 1,72,224 1,49,760 1,30,226 1,13,240 2,54,796
NPV @ 15% D.F 4,87,253
D.F. @ 20% 0.833333 0.694444 0.578704 0.482253 0.401878 0.334898
PV @ 20% D.F. (3,19,118) 1,58,171 1,31,809 1,09,841 91,534 1,97,377
NPV @ 20% D.F 3,69,614
D.F. @ 25% 0.8 0.64 0.512 0.4096 0.32768 0.262144
PV @ 25% D.F. (3,06,354) 1,45,770 1,16,616 93,293 74,634 1,54,499
NPV @ 25% D.F 2,78,459
D.F. @ 30% 0.769231 0.591716 0.455166 0.350128 0.269329 0.207176
PV @ 30% D.F. (2,94,571) 1,34,773 1,03,671 79,747 61,344 1,22,102
NPV @ 30% D.F 2,07,067
D.F. @ 35% 0.740741 0.548697 0.406442 0.301068 0.223014 0.165195
PV @ 35% D.F. (2,83,661) 1,24,975 92,574 68,573 50,795 97,360
NPV @ 35% D.F 1,50,616
D.F. @ 40% 0.7144286 0.510204 0.364431 0.260308 0.185934 0.13281
PV @ 40% D.F. (2,73,585) 1,16,207 83,005 59,289 42,349 78,274
NPV @ 40% D.F 1,05,540
D.F. @ 45% 0.689655 0.475624 0.328017 0.226218 0.156013 0.107595
PV @ 45% D.F. (2,64,098) 1,08,331 74,711 51,525 35,534 63,413
NPV @ 45% D.F 69,416
D.F. @ 50% 0.666667 0.444444 0.296296 0.197531 0.131687 0.087791
PV @ 50% D.F. (2,55,295) 1,01,229 67,486 44,991 29,994 51,741
NPV @ 50% D.F 40,146

SO IRR IS MORE THAN 50 %


REPAYMENT SCHEDULE

Total Financial Outlay 10,04,500


Bank loan 8,00,000
Rate of Interest 10.50%
Repayment Period in years 6
Annual Repayment 1,33,333

1st yr 2nd yr 3rd yr 4th yr 5th yr 6th yr

Loan disbursed 8,00,000


Loan outstanding at the
beginning of the year 8,00,000 6,66,667 5,33,333 4,00,000 2,66,667 1,33,333

Annual Principal Repayment 1,33,333 1,33,333 1,33,333 1,33,333 1,33,333 1,33,333

Interest Repayment 84,000 70,000 56,000 42,000 28,000 14,000

Total Repayment 2,17,333 2,03,333 1,89,333 1,75,333 1,61,333 1,47,333

Gross Surplus (3,82,942) 2,27,766 2,27,766 2,27,766 2,27,766 5,89,366

Net Surplus 4,17,058 24,433 38,433 52,433 66,433 4,42,033

DSCR 1.12 1.20 1.30 1.41 4.00

AVERAGE DSCR 1.37