Drilling 2
Drilling 2
Onshore (land) rigs are all similar, but offshore rigs are of five basic types - each of which is
designed to suit specific offshore environment.
EDC Rig 5
1.
2.
The barge rig is most often a flat-bottomed vessel with a shallow draft, equipped with a derrick and
other necessary drilling equipment. It is usually towed to the location and then has its hull filled with
water which allows it to rest on the bottom, providing a solid support for drilling activities.
2 ASSR
Drilling Engineering
A submersible rig is a larger version of a posted barge and is capable of working in water depths of
18 ft to 70 ft (5.5 m to 2.14 m). Often the hull of a submersible rig
will have steel floats or "bottles" that can be filled with water (ball lasted) to help stabilize the vessel
on bottom.
This is a self-elevating drilling rig, designed to operate in depths from 30 ft t 350 ft (9 m to 107 m).
After being towed to the location (or in some cases being self propelled), the legs are lowered by
electric or hydraulic jacks until they rest on the seabed and the deck is level, supported perhaps 60 ft
(18 m) above the waves. Most jack-up rigs have three to five legs, and are either vertical or slightly
angled for stability.
The chief disadvantages of the jack-up are its vulnerability when being jacked up or relocated, but as
a class, they are cheaper than other mobile rigs. Nearly half of the world's fleet of offshore rigs in
service is the jack-up type, some of which are large, self-propelled Units.
These are floating drilling rigs consisting of hulls or caissons, which carry a number of vertical
stabilizing columns, support a deck with derrick, and associated drilling equipment. Semi-
submersible drilling rigs differ principally in their displacement, hull configuration, and the number
of stabilizing columns. Most modem type have a rectangular deck, a few are cruciform shaped, others
pentagon shaped, while some of the smaller rigs have a triangular deck.
The semi-submersible is very stable because its center of gravity is low in water. It can operate in
deeper water than a jack-up rig.
Drill ships are most often utilized for extremely deep-water drilling locations. A "floater" like the
semisubmersible, a drillship must maintain its position at the drilling location by anchors and
mooring lines, or by computer-controlled dynamic positioning equipment
3 ASSR
Drilling Engineering
5 ASSR
Drilling Engineering
Is a tapered tower made of steel which serves to suspend the
drill string or casing strings or place drill pipe stands during housing operations (round trips).
The draw-works
Is the main item of any drilling rig. It serves as the power control center of the rig. The power plant of
the rig supplies motive power to the hoisting drum, permitting reeling and unreeling of the drilling line
from the hoisting drum.
6 ASSR
Drilling Engineering
Crown block
The crown block Is mounted on the top of the derrick. it is the stationary block of the block and tackle
system. Crown Block contains a number of sheaves on which is wound the drilling line. The crown
block provides a means of taking the drilling line from the hoisting drum to the travelling block.
The travelling block is the moving block of the system and suspended from the loops of the wire rope
which passes over all the sheaves of the two blocks one after another. a diamond-shaped block
containing a number of sheaves which is always less than those in the crown block.
The rotary system is intended for transmitting the rotary to the drill string to which lower end a
drilling bit is attached. The rotary system consists of:
The Rotary Table
The rotary table Is situated in the center of the derrick floor, its function is to rotate the drill string in
the process of drilling and serve as a support for the drill string while round trips are being made.
The Swivel
Swivel is probably the most ingenious element of the drilling rig. While drilling is in progress, the
swivel is suspended from the hook and suspends the whole weight of the drill string. It permits free
rotation of the drill string and serves as the passageway for the drilling fluid from the hose lo the
drill string, which is rotated.
The Kelly
Is the first section of pipe below the swivel the outside section of the Kelly is squared or hexagonal.
Drill pipe
Is the major portion of drill string, it is specified by its outer diameter, weight per foot, steel grade&
range length.
7 ASSR
Drilling Engineering
Drill collar
Is the lower section of drill string it is a heavy thick wall steel tubular.
Drill bit
Is used to disintegrate the rock, Types is (mechanical bit and polycrystalline diamond bit)
Top drive
In the top drive system Power swivel or power-sub installed just below a conventional swivel can be
used to replace the Kelly, Kelly bushing & rotary table Drilling rotation is achieved through
hydraulic motor incorporate in the power swivel or power sub.
Usually a drilling rig is provided with two slush pumps. Their function is to circulate drilling fluid in
the process of drilling. The heart of the circulating system is the mud pumps. There are two types of
pumps used in the oil industry: Duplex and Triplex.
The prime movers and transmissions are necessary to provide motive power for all the mechanics of
the rig, the hoisting system, the rotary system and the mud pumps.
Consists of mud pits and tanks, an auxiliary pump and mechanisms for mixing, chemical treatment
and solids controls of the drilling fluid (a mud hopper, a shaker, a hydro cyclone etc.)
The well monitoring equipment system use devices to display different parameters and factors that
must be measured continuously during the drilling operations that are:
Types of BOP:
Annular preventer
Stop the flow from the well using arming of synthetic rubber that contract in the fluid passage in
annulus.
Ram preventer
Have two packing elements on opposite sides that close by moving toward to each other (pipe
ram, blind ram shear ram)
9 ASSR
Drilling Engineering
loads are either
Dead load of derrick itself.
Vertical loads: Dead load of the load supported by the C/B.
Live and impact load
Note, Use maximum dead load capacity of a derrick equal to the heaviest casing column, an
For well #1
1. Derrick selection:
the maximum casing capacity; is the capacity of the last casing string
Effective weight= weight in air *buoyancy factor
Buoyancy factor B.F = 1 – γm / γsteel = 1 – (10 / 65.5) = 0.84733
For 7'' Wc = (23*920+20*3972) * 0.84733 =85241.398 1b“The max.”
By add length 35 %;
Maximum derrick load = 1.35 * 85241.398 = 115075.887 lb.
Note for wind load
Wind load Lw = 0.004 V2, lb / ft2 and V = 50 mph
Wind load = 0.004 * (50)2 * 510 ft2 (for rig class 8A) = 5100 lb.
From rotary drilling handbook page (12) from A Complete Well Planning
the derrick specifications Approach N. J. Adams
Derrick size No. 18 A
Derrick size No. 12 Height 136 ft
Height 94 ft Base square 30 ft
Base square 30 ft Casing capacity 300000 lbs
Water table opening 5.5 ft Pipe size 5 in
Casing
10 ASSRcapacity 300000 lb Total length 8900 ft
Pipe weight 22.5 lb/ft
Pipe set back capacity 150000 lb
Wind load area 510 ft2
Drilling Engineering
2. Selection of the wellhead (BOP)
The safest procedure for designing preventer pressure ratings is to ensure that the preventer
can withstand the worst pressure condition possible. This condition occur when all drilling
fluids have been evacuated from the annulus and only low density from fluids such as gas
remain, so,
a- Maximum formation pressure = .499*4892 = 2441.108 psi.
b- Determine minimum hydrostatic pressure assume only gas density = 1 ppg
Phmin= 0.052 * 1 * (4892) = 254.38 psi.
The experience should dictate that 80 % design factor would be unexpected eventualities.
Working pressure = resultant pressure * 0.8= (Pfmax. – Phmin) * 0.8= 1750.2 psi
Using the API designations at 3000 psi working pressure.
For flanges two types :
Size 13 3/8
Outside diameter 26.5
Diameter of raised face 18
Total thickness 4.94
Large diameter of hob 18.94
Small diameter of hob 16.69
2.2 For bolts :
Selection of (BOP):
11 ASSR
Drilling Engineering
Use Cameron ram type BOP, Operating Data:
3. Kelly selection:
Find the maximum d/s weight:
D/S max. = Wb max. + Wd/p max. + Wd/c max.
Where,
Wb, Bit weight (assume: 86 lbs.)
Fc, factor to compensate fraction (1.35)
D/P + DC + HWDP = (3722*21.35) +(630*49.3) +(540*103.77) = 166559.5 lbs.
12 ASSR
Drilling Engineering
D/S = (86 +166559.5) * 1.35 * 0.84733 = 190625.037 lb.
4. Swivel selection:
Maximum swivel rated dead load capacity
= Bit + D/P + D/C + HWDP + Kelly
=190625.037 + 688.3
=191313.337 lbs
Use Rotary Drilling Handbook page 147,
Swivel specifications
Depth capacity 5000 ft
Main bearing dia. 16 1/2 "
Fluid passage dia. 3 in
Bail pin dia. 22 in
Net approximate weight 3030 lb
5. Hook selection
a- For total hook load during drilling,
Max. weight =Drill String wt. + Kelly+ Swivel wt.
= 190625.037 + 688.3 + 3030 = 194343.3375 lb
b- For total hook load during casing,
13 ASSR
Drilling Engineering
H. L = wt. of heaviest casing in mud = 3030 + 85241.398 =
88271.398 lbs =40 ton
So, Hook specification
H-6(composite Handbook) Rated load 100 tons & Weight 5310lbs
14 ASSR
Drilling Engineering
1-Consider the maximum tension in the line in pounds,
which expected for the drilling operation
FL = 30473.517 lb
Multiply this tension by (2) as safety factor to obtain the safe ultimate strength of the
required cable =60947.034 lb
From Drilling Data Handbook, select the cable which has the closest ultimate strength and
has the suitable diameter for hoisting sheaves.
Select 6 * 19 classification wire rope, bright (UN coated) or Drawn-Galvanized wire
independent wire rope core.
From Drilling Data Handbook
Nominal diameter Approximate mass, Extra improved Improved plow
lb / ft plow steel steel
1 in 1.85 79600 lb 89800 lb
15 ASSR
Drilling Engineering
7. Ton-mile:
Is a measure of the usage of the hoisting cable.
Ton mile calculations:
Drilling line is maintained in good conditions by following a - scheduled Slip-and Cut
program, slipping the d/line involves loosing the dead line anchor and placing a few feet of
new line in service from the storage reel.
Max.Ton mile during tripping:
16 ASSR
Drilling Engineering
Tr = {4892*18.09*(91+4892) +
4*4892*(10708+ .5*(37675.34+15295.23))}/10560000
= 110.68 ton-mile
17 ASSR
Drilling Engineering
Total length of the rope for wrapping N layers
L=N*l*n
Where,
N=A/d
n = no. of coils in one layer=B/d
L = average length of one coil=Π*(D+a)/12 ft
A B
L * * ( D A) *
d 12 d
L=K*(A + D) *A*B
K: constant depending on the rope diameter, equal to
K 0.04
12 * d 2
L = 0.04*25*57*(32+25) = 3249 ft
18 ASSR
Drilling Engineering
From bit record Select circulation rate 540 gpm
and the hole depth is 4892 ft
For pressure losses during circulation.
∆ PT = ΔPS + ΔPIDP+ ΔPIDP + ΔPIDP + ΔPBIT + ΔPODP+ ΔPODC + ΔPOHW + ΔPIHW
Where
∆ PT : Total pressure loss, psi
ΔPS : Total pressure loss in surface connection, psi
Vc=
ρm∗ID
19 ASSR
Drilling Engineering
Where
Vc Critical velocity (ft / sec.)
PV Plastic viscosity (11c.p)
ρm mud density (10 ppg)
ID inside diameter of drill pipe = 4.276in
Y.P yield point 14
Where
V
: Actual velocity (average velocity) ft/sec.
Q: flow rate gpm
IDc : inside diameter of drill pipe inch.
24.5∗540
¿ 2
=723.6 ft /minute
4.276
8.91∗10−5∗10 0.8∗5401.8∗110.2∗3722
∆ P IDP= =261.97 psi
4.2764.8
20 ASSR
Drilling Engineering
2 nd
. calculate the actual velocity that is expressed as:
24.5∗Q
−¿= 2
¿
I Dc
V
24.5∗540
−¿= 2
=2613.3 ft /minute ¿
2.25
V
D- ΔPIHW: Total pressure loss inside the heavy weight drill pipe, psi
8.91∗10−5∗10 0.8∗5401.8∗110.2∗630
∆ P IDhw = =243 psi
3 4.8
21 ASSR
Drilling Engineering
Annular losses
E- ΔPODpipe: total pressure loss outside drill pipe and cased hole :
Vc=
ρm∗IDe
V
−¿= 2
8.921 −5
2
¿
=242.37 ft/minute
2200∗11∗242.37 2200∗14
∆ PODP = + =41.27 psi
60000∗(8.921−5) 2
225∗(8.921−5)
F-ΔPODpipe: total pressure loss outside drill pipe and heavy weight drill pipe in open hole
1st. Using the following calculation, calculate the critical velocity,
Vc=
ρm∗IDe
22 ASSR
Drilling Engineering
Vc=97∗11+97 √ 112+ 6.2∗10 ¿ ¿ ¿= 317.89 ft/minute
2nd. calculate the actual velocity that is expressed as:
24.5∗Q
−¿= 2 2
¿
D hole −ODpipe
V
24.5∗540
V
−¿= 2
8.5 −5
2
¿
=280 ft/minute
2152∗11∗280 2152∗14
∆ PODP = + =47.27 psi
60000∗(8.5−5) 225∗(8.5−5)
2
Total pressure drop around drill pipe and heavy weight drill pipe = 88.546 psi
V
−¿= 2
8.5 −6.25
2
¿
=399 ft/minute
23 ASSR
Drilling Engineering
8.91∗10−5∗100.8∗5401.8∗110.2∗540
∆ P oDc=
¿¿
√ [ ]
2
13
Dequ . = 3 × =1.41 inch
16
2
540 ×10
∆ P BIT = =2 18.73 psi
7430 ×0.95 2 ×1.412
1732.61 × 540
H.P= = 545 .86 hp
1714
pump horse power
The brake horse power=
ηmech
24 ASSR
Drilling Engineering
545.86
The brake horse power= =642.19 hp
0.85
BHP
the rated horse power for the prime mover engine= ×1.4
ηO
642.33
the rated horse power for the prime mover engine= ×1.4 = 1033.4 h p
0.87
So, we are supposed to use two pumps to give the needed horse power in the manner
that one on operations and one standby
For well #2
1. Derrick selection:
the maximum casing capacity; is the capacity of the last casing string
Effective weight= weight in air *buoyancy factor
Buoyancy factor B.F = 1 – γm / γsteel = 1 – (10.5 / 65.5) = 0.8385
For 7'' Wc = (23*920+20*3760) * 0.8385 =80797.86 1b“The max.”
By add length 35 %;
Maximum derrick load = 1.35 * 80797.86 = 109077.11 lb.
from A Complete Well Planning
From rotary drilling handbook page (12)
Approach N. J. Adams
the derrick specifications
Derrick size No. 18 A
Derrick size No. 12 Height 136 ft
Height 94 ft Base square 30 ft
Base square 30 ft Casing capacity 300000 lbs
Water table opening 5.5 ft Pipe size 5 in
Total length 8900 ft
Casing capacity 300000 lb
Pipe weight 22.5 lb/ft
Pipe set back capacity 150000 lb Wind load area 510 ft2
Note for wind load
Wind load Lw = 0.004 V2, lb / ft2 and V = 50 mph
Wind load = 0.004 * (50)2 * 510 ft2 (for rig class 8A) = 5100 lb.
25 ASSR
Drilling Engineering
The safest procedure for designing preventer pressure
ratings is to ensure that the preventer can withstand the worst pressure condition possible.
This condition occur when all drilling fluids have been evacuated from the annulus and only
low density from fluids such as gas remain, so,
a- Maximum formation pressure = .499*4700 = 2345.3 psi.
b- Determine minimum hydrostatic pressure assume only gas density = 1 ppg
Phmin= 0.052 * 1 * (4700) = 244.4 psi.
The experience should dictate that 80 % design factor would be unexpected eventualities.
Working pressure = resultant pressure * 0.8= (Pfmax. – Phmin) * 0.8= 1680.72 psi
Using the API designations at 3000 psi working pressure.
For flanges two types :
Size 13 3/8
Outside diameter 26.5
Diameter of raised face 18
Total thickness 4.94
Large diameter of hob 18.94
Small diameter of hob 16.69
Selection of (BOP):
Use Cameron ram type BOP, Operating Data:
3. Kelly selection:
Find the maximum d/s weight:
D/S max. = Wb max. + Wd/p max. + Wd/c max.
Where,
Wb, Bit weight (assume: 86 lbs.)
Fc, factor to compensate fraction (1.35)
27 ASSR
Drilling Engineering
D/P + DC + HWDP = (3530*21.35) +(630*49.3)
+(540*103.77) = 162460.3 lbs.
D/S = (86 +162460.3) * 1.35 * 0.8385 = 183998.347 lb.
From standard specifications of Kelly selection
Square Kelly 2.5 “
4. Swivel selection: Lower pin connection (size & style) NC 26 C 2 3/8 IF
Maximum swivel rated dead load Inside diameter 1.25
capacity Outside diameter 2.5
Minimum recommend casing O. D. 6 5/8
= Bit + D/P + D/C + HWDP + Kelly Internal pressure @ yield stress. 153.1
=183998.347 + 688.3 Tensile yield. 185000 daN
The Kelly weight 688.3 lb
=184686.65 lbs
Use Rotary Drilling Handbook page 147,
Swivel specifications
Depth capacity 5000 ft
Main bearing dia. 16 1/2 "
Fluid passage dia. 3 in
Bail pin dia. 22 in
Net approximate weight 3030 lb
5. Hook selection
a- For total hook load during drilling,
Max. weight =Drill String wt. + Kelly+ Swivel wt.
= 183998.347 + 688.3 + 3030 = 187716.64 lb
b- For total hook load during casing,
H. L = wt. of heaviest casing in mud = 3030 + 80797.86 = 83827.86 lbs = 39 ton
So, Hook specification
H-6(composite Handbook) Rated load 100 tons & Weight 5310lbs
6. Hoisting system selection:
For maximum traveling block load:
28 ASSR
Drilling Engineering
From Rotary Drilling Handbook page 140,
API working load strength 100 tons
No. of sheaves 4
Sheave diameter 36 inches
Line size 1 1/8 inch,
Overall length 69.5 inch
Weight with no hook 5470 lb
Thickness 20.75 inch
Clevis width 8 1/2 inch
Length with hook 204,314 inches
Hook length 191/2 inch
Hook width 30 1/2 inch
29 ASSR
Drilling Engineering
From Drilling Data Handbook
Nominal diameter Approximate mass, Extra improved Improved plow
lb / ft plow steel steel
1 in 1.85 79600 lb 89800 lb
7. Ton-mile:
30 ASSR
Drilling Engineering
Is a measure of the usage of the hoisting cable.
Ton mile calculations:
Drilling line is maintained in good conditions by following a - scheduled Slip-and Cut
program, slipping the d/line involves loosing the dead line anchor and placing a few feet of
new line in service from the storage reelMax.Ton mile during tripping:
31 ASSR
Drilling Engineering
Ton mile during casing,
32 ASSR
Drilling Engineering
n = no. of coils in one layer=B/d
L = average length of one coil=Π*(D+a)/12 ft
A B
L * * ( D A) *
d 12 d
L=K*(A + D) *A*B
K: constant depending on the rope diameter, equal to
K 0.04
12 * d 2
L = 0.04*25*57*(32+25) = 3249 ft
From bit record Select circulation rate 540 gpm and the hole depth is 4700 ft
For pressure losses during circulation.
∆ PT = ΔPS + ΔPIDP+ ΔPIDP + ΔPIDP + ΔPBIT + ΔPODP+ ΔPODC + ΔPOHW + ΔPIHW
Where
∆ PT : Total pressure loss, psi
33 ASSR
Drilling Engineering
ΔPS : Total pressure loss in surface connection,
psi
ΔPIDP : Total pressure loss inside the drill pipe, psi
ΔPIDP : Total pressure loss inside drill collar, psi
ΔPBIT : Total pressure loss in bit, psi
ΔPODP: Total pressure loss in the outside of drill pipe, psi
ΔPODC: Total pressure loss in the outside of drill collar, psi
ΔPOHW: Total pressure loss in the outside the heavy weight drill pipe, psi
ΔPIHW: Total pressure loss inside the heavy weight drill pipe, psi
Where
Vc Critical velocity (ft / sec.)
PV Plastic viscosity (11c.p)
ρm mud density (10.5 ppg)
ID inside diameter of drill pipe = 4.276in
Y.P yield point 14
34 ASSR
Drilling Engineering
97∗11+ 97 √11 +8.2∗10 .5∗4.276 ∗14
2 2
Vc = = 345.38 ft/min
10.5∗4.276
Where
V
: Actual velocity (average velocity) ft/sec.
Q: flow rate gpm
IDc : inside diameter of drill pipe inch.
24.5∗540
¿ 2
=723.6 ft /minute
4.276
35 ASSR
Drilling Engineering
D- ΔPIHW: Total pressure loss inside the heavy weight drill pipe, psi
Vc=
ρm∗ID HW
8.91∗10−5∗10.5 0.8∗5401.8∗110.2∗630
∆ P IDhw = =252.68 psi
3 4.8
Annular losses
36 ASSR
Drilling Engineering
E- ΔPODpipe: total pressure loss outside drill pipe and cased hole :
Vc=
ρm∗IDe
V
−¿= 2
8.921 −5
2
¿
=242.37 ft/minute
2305∗11∗242.37 2305∗14
∆ PODP = + =43.24 psi
60000∗(8.921−5) 225∗(8.921−5)
2
F-ΔPODpipe: total pressure loss outside drill pipe and heavy weight drill pipe in open hole
1st. Using the following calculation, calculate the critical velocity,
97 PV + 97 √ pv +6.2 ¿ ρm∗De ∗YP
2 2
Vc=
ρm∗IDe
37 ASSR
Drilling Engineering
2 . calculate the actual velocity that is expressed as:
nd
24.5∗Q
−¿= 2 2
¿
D hole −ODpipe
V
24.5∗540
V
−¿= 2
8.5 −5
2
¿
=280 ft/minute
1855∗11∗280 1855∗14
∆ PODP = + =60.18 psi
60000∗(8.5−5) 225∗(8.5−5)
2
Total pressure drop around drill pipe and heavy weight drill pipe = 103.42 psi
24.5∗540
V
−¿= 2
8.5 −6.25
2
¿
=399 ft/minute
38 ASSR
Drilling Engineering
−5 0.8 1.8 0.2
8.91∗10 ∗10.5 ∗540 ∗11 ∗540
∆ P oDc=
¿¿
Assume a cone bit has 3 nozzles of size 13/16, in. withbit nozzle co-efficient C = 0.95
2
Q × ρm
∆ P BIT = 2 2
7430 ×c × Dequ .
√ [ ]
2
13
Dequ . = 3 × =1.41 inch
16
2
540 ×10
∆ P BIT = =2 18.73 psi
7430 ×0.95 2 ×1.412
∆P × Qac
H.P=
1714
1790.15 × 540
H.P= = 563 . 99 hp
1714
39 ASSR
Drilling Engineering
563.99
The brake horse power= =663.517 hp
0.85
BHP
the rated horse power for the prime mover engine= ×1.4
ηO
663.517
the rated horse power for the prime mover engine= ×1.4 = 1067.7 h p
0.87
So, we are supposed to use two pumps to give the needed horse power in the manner
that one on operations and one standby
ASSRD.E.F
C. / B.load
40
max .equavelantlegload
( N 2) * T
Drilling Engineering
D.E.F.= (8 + 2) / (8 + 4) = 83.33 %
D.E.F. = (N + 2) / (N + 6) = 71.4 %
41 ASSR
Drilling Engineering
R=
∑ Ri∗H i
∑ Hi
Where, Ri :isthe penetration rate∈theith section∈the formation
H i :isthe section drilled∈the formation
WELL#1
MOGHRA
870 207 870 663 59 59
DABAA
2380 870 2300 1430 59 58.088742
42 ASSR
Drilling Engineering
Avg.
ROP
(FT/ Averagr ROP In Each Formation
HR)
Unit Drilled
70
60
50
40
30
20
10
0
A " " " "
HR AA NI
A AN "D "E "F "G IA
B O M R /R R AR
OG DA LL O A/ A A/ A /R AH
M O KH B
AP
WELL#2
Lithology Form. Depth Depth Drilled ROP Avg.ROP
Depth In Out Section
MOGHRA 870
180 499 319 49.1 62.326957
DABAA 2380
870 2305 1435 73.7 72.185099
43 ASSR
Drilling Engineering
Avg.80
ROP
(FT/HR) Averagr ROP In Each Formation Unit
70
Drilled
60
50
40
30
20
10
0
A " " " "
HR AA IA AN "D "E "F "G IA
B ON M /R R R AR
G DA L O A/ A/ /R AH
M
O OL KH A A B
AP
For every depth interval, the bit rotating time is determined as:
i=j
T CJ=∑ t i
i=1
5000
DEPTH (FT)
4000
3000
2000
1000
44 ASSR
Drilling Engineering
WELL#2
0 10 20 30 40 50 60
5000
4500
4000
3500
DEPTH (FT)
3000
2500
2000
1500
1000
500
0
Ts D
Tt 2
L
* 60
s
Where,
Tt : Tripe time , hrs
Ts : Time for pull one stand, 4 min.
Ls : Length of stand, 91 ft.
D : Drilled footage by one bit.
WELL#1 Depth (FT) Trip Time (HR) Total Trip Time (HR)
0 0 0
2300 3.3699634 3.3699634
4892 7.1677656
Total Trip Time VS Depth
10.537729 Total T.time (hr)
0
0 2 Trip 4Time Vs.6Depth 8 10
Trip Time (hr)
12
0 1 2 3 4 5 6 7 8
0
1000
1000
DEPTH (FT)
2000
2000
3000
DEPTH (FT)
4000
3000
5000
4000 6000
45 ASSR
5000
6000
Drilling Engineering
WELL#2
depth out (ft) trip time (hr) total trip time (hr)
0 0 0
499 0.731135531 0.73113553
2305 3.377289377 4.10842491
4529 6.635897436 10.744322
4700 6.886446886 17.6307692
0 1 2 3 4 5 6 7 8
0
1000
2000
DEPTH (FT)
3000
4000
5000
6000
0 2 4 6 8 10 12
0
1000
2000
DEPTH (FT)
3000
4000
5000
6000
46 ASSR
Drilling Engineering
2.15 Intelligent well completion
The intelligent well completions being installed today have relatively simple capabilities. Intelligent well
completion systems (ICS) integrate reservoir sensors and remotely controllable inflow and outflow devices
deployed permanently in the wellbore. The immediate benefits of such system arise from minimization of
interventions needed to ascertain critical changes and alter downhole flow conditions, particularly in
offshore operations and subsea developments.
The Intelligent Well Completion of tomorrow will have significantly enhanced capabilities such as the
following namely:
Sensors and flow control devices in the
lateral’s branches Downhole separation of
water from oil. Also, the ability of reinjection
the water downhole Detection of water
encroachment
Detection and / or prevention / removal of
sand, scale, or corrosion
Three- phase flow measurement
Infinitely variable choke
Fiber optics developments for various uses including communication as well as distributed measurement
of temperature and pressure
Higher temperature capability
Downhole power source
Downhole seismic sources and / or receivers to provide in-well
vertical seismic profiles (VSP) or cross-.
In this case an obvious decrease in ROP might be an indication of bit balling. There are some steps the
driller follows in case of bit balling:
Rise the string few feet from the bottom and circulate.
Mechanically jar the string to clean the bit.
If the previous steps didn`t work the entire string must be pulled and the drilling bit must be cleaned
at surface.
To avoid bit balling a low weight on bit is recommended for hard formations and special additives are
added to the drilling mud to prevent shale swelling
Mud sticking caused by the mud dehydration in the annuals. Also, foreign fluids may contaminate
the mud changing its properties and possible sticking.
Friction sticking occurs when there is relatively small clearance between drill pipe outer diameter
and hole diameter.
49 ASSR
Drilling Engineering
Key seat sticking some indications are Pipe is moving up
when it becomes stuck. Pipe is stuck at an (OD) enlargement in the drill string. Drill string is stuck at
the top of the drill collars. Circulation of drilling mud is not affected.
Differential sticking occurs when the drill pipe come in contact with the mud cake in the wall. A
differential pressure between mud hydrostatic pressure and formation pressure causes a force on the
pipe keeping it stuck to the walls.an indication of this type is the drill string not moving up or down
especially while making a connection. Jarring is a good solution for these cases.
The remedy for this kind of trouble is usually a fishing job
A fast reaction should be taken to face this problem by adding chemical additives to the mud called loss
of circulation materials (LCM). If the (LCM) are not effective, cement is used to plug the zone entirely
then drilling will start through the cement passing the zone called Thief zone
b) Clay-particle swelling: occurs when water base filtrate enters the formation with existence of
water sensitive clay like smectite. The mineral adsorbs water and swells (its volume increases).
c) Saturation changes: occurs when mud filtrate enters the reservoir and causes some changes in
water saturation. The rock relative permeability certainly will change and production rate will be
affected.
50 ASSR
Drilling Engineering
d) Wettability changes: it is known that reservoir rocks are
originally water wet. While drilling with oil base mud, surfactants can reverse rock wettability to oil wet.
Lab studies showed that 90% of production can be lost this way.to avoid that minimum amount of
surfactant should be used.
e) Emulsion blockage: it is formed from the mixing of two immiscible fluids which forms a highly
viscous layer that blocks hydrocarbon flow. A mutual solvent is used to break down emulsions.
When choosing drilling mud, you should consider these factors to minimize the formation damage
during drilling:
fluid compatibility with the reservoir
presence of hydratable or swelling clays
Fractured formations and the possible reduction of permeability by invasion of materials into
the formation.
Hydraulic fracturing: pumping of special frac fluids at high pressure and high rate to break
down the rock forming fractures and channels to bypass near wellbore damaged area.
Underbalance drilling: a technique used to minimize mud filtrate and solid invasion from
drilling mud into formation.
Hole enlargement: occur as a result of drill string vibrations and may lead to
problems such as annular hole cleaning difficulty, change in Hole deviation,
problems during logging operations and reduce the quality of cement placement.
Hole closure: hole diameter gets smaller than expected and may lead to serious
problems like serious increase in torque and drag, increase of pipe sticking
situations and difficulty in casing landing.
52 ASSR
Drilling Engineering
straight hole. The degree of borehole deviation varies from location to
location. Drilling practices can create boreholes with doglegs or another irregularity in shape or
direction, which might be undetected until they restrict some operations.
It is common to find crookedness in vertical wells. But it is very common to have doglegs in directional
wells. The degree of crookedness is measured by the magnitude of doglegs and frequency. Causes of
crookedness can be:
Improper Weight on Bit: The most important reason for crookedness of a wellbore is the
high weight on bit (WOB).
Formation Dip: If the bit hits a subsurface rock layer with a dip greater than 45°, the bit
tends to be deflected down dip. If rock layer dip less than 45 °, the bit tends to be deflected up
dip.
Anisotropy: Bedding plane permeability anisotropy is common in natural fractures. Stress
anisotropy is greatest between overburden stress and horizontal stress in the bedding plane.
Inadequate Length of Drill Collars: Appropriate length of drill collars must be used in
order to ensure: weight on bit (WOB), BHA directional control, hole size integrity, drill string
clearance and drill string compressive and torsional loads.
No Stabilizer: stabilizer mechanically stabilizes the BHA in the borehole to avoid
unintentional sidetracking, vibrations, and ensure the quality of the hole being drilled.
Stabilizer placement is highly important to avoid drill string vibrations and to ensure safe
drilling.
In case the borehole is already crooked, the following remedial actions can be taken:
Plug Back and Sidetrack
Use Whip stock
Use Reamers
Torque and Drag: Drag is a force restricting the movement of the drill tools in directions
parallel to the well path. Torque is the force resisting rotation movement. Reducing drill string
weight reduces drag and torque at high quality of mud with appropriate chemical. Oil-based mud
is recommended because of its lubricating qualities.
53 ASSR
Drilling Engineering
Hole Cleaning: It is the difficulty of removing the
rock cuttings from the horizontal section of the well because cuttings tend to settle in the bottom
of the hole and allow mud to pass above without carrying them. High fluid velocities and
polymer muds are used for efficient hole cleaning and minimizing formation damage. also, oil-
based muds can control shale swelling.
Directional Control: Overcoming the force of gravity is a fundamental problem in directional
and horizontal drilling. The BHA section controls the hole trajectory but does not contribute to
WOB. So, this section should be kept as lightweight as possible to minimize torque and drag.
Anisotropy: Anisotropy affects horizontal wells different from vertical wells.
54 ASSR
Drilling Engineering
PRODUCTION CASING 54,000.00 USD
CEMENT & ADDITIVES 20,000.00 USD
447,863.00 USD
55 ASSR