Assign 3 Soln
Assign 3 Soln
3-2 – 3-3
Overhead Personal time Hourly
Name Hours Total direct labour cost
rate rate rate
Nadia 60 1.75 1.1 20 $2310
John 80 1.55 1.12 40 $5555.2 (Answer John)
Saba 80 1.75 1.1 36 $5544
Kumar 40 1.55 1.12 20 $1388.8
Project total = $14,798 (Answer $14,800 closest)
3-4 – 3-6 Need to find both T1 and b, given that T2 = 28.6 = Tinit 2b and T3 = 28.2 = Tinit 3b
b
T2 28.6 2 28.6 2 0.006117
or log b log or b 0.03474
T3 28.2 3 28.2 3 0.17609
Total labour hours to produce first four units = 29.3 + 28.6 + 28.2 + 27.9 = 114 hours.
3-6 Total labour costs = 114 * $18 = $2052 Answer $2050 is closest
3-10 Taking into account the 12% increase in cost due to construction in winter conditions gives the
following order of magnitude estimate of the water treatment in Ureka