Assign 3 Soln

The document provides solutions to engineering assignment problems 3-1 through 3-10. It includes calculations for direct labor costs, time estimates using an exponential decay model, and adjustments for factors like capacity, inflation, and location to estimate the total cost of a water treatment project.

Uploaded by

Guangjun Ou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views2 pages

Assign 3 Soln

The document provides solutions to engineering assignment problems 3-1 through 3-10. It includes calculations for direct labor costs, time estimates using an exponential decay model, and adjustments for factors like capacity, inflation, and location to estimate the total cost of a water treatment project.

Uploaded by

Guangjun Ou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ENGR 301 Assignment 3 solution

3-1 Price now = $89,500 (207.6/163.6) = $113,570.90 Answer $113,000 is closest

3-2 – 3-3
Overhead Personal time Hourly
Name Hours Total direct labour cost
rate rate rate
Nadia 60 1.75 1.1 20 $2310
John 80 1.55 1.12 40 $5555.2 (Answer John)
Saba 80 1.75 1.1 36 $5544
Kumar 40 1.55 1.12 20 $1388.8
Project total = $14,798 (Answer $14,800 closest)

3-4 – 3-6 Need to find both T1 and b, given that T2 = 28.6 = Tinit 2b and T3 = 28.2 = Tinit 3b
b
T2 28.6  2   28.6  2 0.006117
   or log   b log  or b   0.03474
T3 28.2  3   28.2  3  0.17609

3-4 Tinit = 28.6/2b = 28.6/2–0.03474 = 29.3 hours Answer 29.3 is closest

3-5 T50 = 29.3 * 50–0.03474 = 25.6 hours Answer 25.5 is closest

T4 = 29.3 * 4–0.03474 = 27.9 hours

Total labour hours to produce first four units = 29.3 + 28.6 + 28.2 + 27.9 = 114 hours.

3-6 Total labour costs = 114 * $18 = $2052 Answer $2050 is closest

3-7 – 3-10 as given below

3-7 Adjustment for capacity based on the exponential law:

Factor is: (50/60)0.67 = (0.833)0.67 = 0.885 Answer 0.90 is closest

3-8 Adjustment for inflation leads to the cost in 2007 dollars:

Factor is: (1.04)6 = 1.265 Answer 1.27 is closest

3-9 Adjustment for location index:

Factor is: 1.24/1.17 = 1.06 Answer 1.07 is closest


Typical cost excluding the additional cost due to poor site conditions in Vancouver

$50 million – $3 million = $ 47 million

($47 million) (50/60)0.67 (1.04)6 (1.24/1.17) = $55.781 million

Adjustment for the additional filter at Ureka plant gives

$55.781 million + $4 million = $59.781 million

3-10 Taking into account the 12% increase in cost due to construction in winter conditions gives the
following order of magnitude estimate of the water treatment in Ureka

($59.781)(1+0.12) = $66.955 million Answer $65 million is closest