CS01 - Create Material BOM
CS01 - Create Material BOM
Organization/Area:
Responsibility:
Plant Maintenance Status
Work Instruction
Purpose
Use this procedure to create Material BOM.
Trigger
Perform this procedure when you want to create Material BOM.
Prerequisites
All the details related to BOM like Material No, BOM Usage, Plant, Item Category etc. should be known.
Menu Path
Use the following menu path to begin this transaction:
Logistics Plant Maintenance Management of Technical Objects Bill of Material Material BOM
Create
Transaction Code
CS01
Helpful Hints
CS01 is the SAP transaction code for creating Material BOM.
A maintenance bill of material (BOM) is a complete, formally structured list of the components
making up a technical object or an assembly.
Field values can be queried using the F4 help wherever available. This can be done either by placing
the cursor in the field and pressing F4, or by clicking on the match code that appears next to
the field.
You can click on a field and press F1 to view the Field help. This allows you to understand the field
and decide what contents should be entered.
Responsibility:
Plant Maintenance Status
Procedure
Enter the T-Code CS01 and click on icon to create Material BOM.
You can also double click on the menu “Create” as highlighted in the below screenshot to create
Material BOM.
Responsibility:
Plant Maintenance Status
We can search the Material no. for which BOM has to be created by clicking on the input help icon
Enter the Plant (1I01) and Click on continue icon . This opens the following screen.
Responsibility:
Plant Maintenance Status
Responsibility:
Plant Maintenance Status
Enter the Planning Plant as “1i01” & BOM Usage as “4 Plant maintenance”.
Responsibility:
Plant Maintenance Status
The description of the fields for the above screen is given below:
Valid From Specifies the start date for the validity 28.04.2014
period of an object
Valid To End of validity period of an object. 31.12.9999
Responsibility:
Plant Maintenance Status
Note the Material BOM created message at the bottom of the screen as marked above.
Result
You have successfully created the Material BOM.