EPCC Sludge Processing Equipment Schedule

The document outlines an equipment deployment schedule for a project involving processing sludge from a wastewater treatment plant. It lists various types of transportation and equipment needed each month from July 2021 through October 2022, including vehicles, air compressors, welding generators, cranes, and more. The total equipment needs are calculated for each category on a monthly basis.

Uploaded by

MDhana Sekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
296 views2 pages

EPCC Sludge Processing Equipment Schedule

The document outlines an equipment deployment schedule for a project involving processing sludge from a wastewater treatment plant. It lists various types of transportation and equipment needed each month from July 2021 through October 2022, including vehicles, air compressors, welding generators, cranes, and more. The total equipment needs are calculated for each category on a monthly basis.

Uploaded by

MDhana Sekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No.

:T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

EQUIPMENT DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22

1
A TRANSPORT & EQUIPMENT (TOCO)
1 TRANSPORT & GENERAL 1 1
SALOON CAR 1 12 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PICK-UP 2 12 1 1 1 2 2 2 2 1
BUS 25 SEATER 2 12 1 1 1 2 2 2 2 1
BUS 66 SEATER 2 12 1 1 1 2 2 2 2 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 8 1 1 1 1 1 1 1 1

2 EQUIPMENT WORKS 1 1
AIR COMPRESSOR 300 ~ 450 CFM 1 1 1
FORKLIFTER 5 TON 1 1 1
CRANE 50 TON 1 1 1
CRANE 450 TONS 1 0.5 1

3 PIPING WORKS (FAB & ERECTION) 1 1


AIR COMPRESSOR 300 ~ 450 CFM 2 11.0 1 1 1 2 2 1 1 1 1
TRAILER FLAT BED 40 FT 1 4.8 0.3 0.3 0.3 1 1 1 1
WELDING GENERATOR DIESEL 400 AMP 6 30.0 2 4 4 6 6 4 2 2
POWER GENERATOR 50 KVA 1 5.0 1 1 1 1 1
WINCH WITH PULLEY & MAN BASKET 2 4.0 2 2
CRANE 30 TON 1 8.0 1 1 1 1 1 1 1 1
WATER TANKER 1 1.0 1
VACCUM TANKER 1 1.0 1

4 E&I WORKS 1
MANLIFT 1 1.0 1
TOTAL TRANSPORT & EQUIPMENT (TOCO) 127 1 1 1 1 1 1 9 11 11 19 22 21 16 10 1
B TRANSPORT & EQUIPMENT - SUBCONTRACTORS
1

1 SCAFFOLDING/PAINTING 1 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 2 1 1
AIR COMPRESSOR 350 CFM 1 2 1 1
200 LTR BLASTING POT / POWER GUN 1 2 1 1
AIRLEES SPRAY MACHINE/CONVENTIONAL SPRAY GUN 1 2 1 1

2 CIVIL & STUCTURAL WORKS 1 1


Crane 30 Tons 1 3 1 1 1
Tipper-18m³ 1 3 1 1 1
Shovel 1 3 1 1 1
Plate compactor 1 1 1
Concrete Mixer 1 3 1 1 1
BOOM TRUCK 1 3 1 1 1
TRAILER 1 2 1 1
Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No. :T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

EQUIPMENT DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
TOTAL TRANSPORT & EQUIPMENT- SUBCONTRACTORS 27 5 6 7 4 4

TOTAL "A + B" = 154 1 1 1 1 1 1 14 17 18 19 22 21 20 14 1