REINFORCED CONCRETE
DESIGN FOR CIVIL ENGINEERS
& CONSTRUCTION MANAGERS
STRUCTURAL DESIGN
Aim of Design
BS 8110 states that the aim of design is: To come up with a structure which is cost effective but
will, at the same time, perform satisfactorily throughout its intended life; that is the structure
will, with an appropriate degree of safety, be able to sustain all the loads and deformation of
normal construction and use and that it will have adequate durability and resistance to the
effects of fire and misuse.
REINFORCED CONCRETE
Reinforced concrete is a strong durable building material that can be formed into many varied
shapes and sizes. Its utility and versatility is achieved by combining the best properties of steel
and concrete.
Concrete Steel
Strength in tension Poor Good
Strength in Good Good but slender bars will
compression buckle
Strength in shear Fair Good
Durability Good Corrodes if unprotected
Fire resistance Good Poor – loses its strength rapidly
at high temperatures
Steel and concrete, as is seen in the table above are complementary to each other. When
combined, steel will provide the mix with tensile strength and some shear strength while
concrete will provide compressive strength, durability as well as good fire resistance.
Composite Action
The tensile strength of concrete is only 10% its compressive strength. In design, therefore, it is
assumed that concrete does not resist any tensile forces;it is the reinforcement that carries
these tensile forces and these are transferred by bond between the interface of the two
materials. If the bond is not adequate, the reinforcement will slip and there would be no
composite action.
It is assumed that in a composite section there is perfect bond such that the strain in the
reinforcement is identical to the strain in the concrete surrounding it.
2
Concrete
Concrete is composed of
Cement
Fine aggregate
Coarse aggregate
Water
Additives (optional)
A typical stress strain curve for concrete is as shown above. As the load is applied, the ratio
of stress and stain are at first linear (up to 1/3 of the ultimate compressive strength) i.e.,
concrete behaves like an elastic material with full recovery of displacement if load is
removed.The curve eventually becomes not linear because at this range concrete behaves
like a plastic. If the load is removed from concrete at this stage, there won’t be full recovery
of the material. A little deformation will also remain.
3
Steel
Stress strain Relationship
Mild steel
High yield steel
Mild steel behaves like an elastic material up the yield point where any further increase in
strain will not increase the stress. Beyond the yield point, steel becomes plastic and the
strain increases rapidly to the ultimate value.
High yield steel on the other hand shows a more gradual change from the elastic stage to
the plastic stage
Flexural Failure
This may happen in due to:
a) Under-reinforcement –tension failure
b) Over-reinforcement – compression failure
Tension Failure
If the steel content of the section is small (an under-reinforced concrete section), the steel
will reach its yield strength before the concrete reaches its maximum capacity. The flexural
strength of the section is reached when the strain in the extreme compression fiber of the
concrete is approximately 0.003, Fig. 1.10. With further increase in strain, the moment of
resistance reduces, and the bottom of the member will fail by lagging and cracking. This
type of failure, because it is initiated by yielding of the tension steel, could be referred to as
"tension failure." The section then fails in a "ductile" fashion with adequate visible warning
before failure.
4
FIGURE 1.10. Single reinforced section when the tension failure is reached.
Compression Failure
If the steel content of the section is large (an over-reinforced concrete section), the concrete
may reach its maximum capacity before the steel yields. Again the flexural strength of the
section is reached when the strain in the extreme compression fiber of the concrete is
approximately 0.003, Fig. 1.11. The section then fails suddenly in a "brittle" fashion by crushing
of the compression part if the concrete is not confined.There may be little visible warning of
failure.
FIGURE 1.11. Single reinforced section when the compression failure is reached.
These two behaviors show the importance of ensuring that the right amount of reinforcement
is provided in order to ensure that failure of one steel or concrete does not start before the
other. Failure of both steel and concrete should occur at the same time. This is known as
balanced failure.
5
Balanced Failure
At a particular steel content, the steel reaches the yield strength and the concrete reaches its
extreme fiber compression strain of 0.003, simultaneously, Fig. 1.12.
FIGURE 1.12. Single reinforced section when the balanced failure is reached.
6
DESIGN METHODS
Design of an engineering structure must ensure that
1. The structure remains safe under the worst loading condition
2. During normal working conditions the deformation of the members does not detract
from the appearance, durability or performance of the structure
1. Permissible stress method – ultimate strengths of the materials are divided by a factor
of safety to provide design stresses which are usually within the elastic range
Shortcomings – because it is based on elastic stress distribution, it is not
applicable to concrete since it is semi – plastic
– it is unsafe when dealing with stability of structures subject to
overturning forces
2. The load factor method–where working loads are multiplied by a factor of safety
Shortcomings – it cannot directly account for variability of materials due to
material stresses
It cannot be used to calculate the deflections and cracking at working conditions.
3. Limit state method–multiplies the working loads by partial factors of safety factors and
also divides the materials’ ultimate strengths by further partial factors of safety. It
overcomes the limitations of the previous methods by use of factors of safety as well as
materials’ factors of safety making it possible to vary them so that they may be used in
the plastic range for ultimate state or in the elastic range under working loads.
Limit States
The criterion for safe design is that the structure should not become unfit for use. i.e. it should
not reach a limit state during its design life.
Types of limit states
Ultimate limit state
Serviceability limit state
a) Ultimate limit state
This requires that the structure be able to withstand the forces for which it has been
designed
i) Deflection
ii) Cracking
7
Others are
i) Durability
ii) Excessive vibration
iii) Fatigue
iv) Fire resistance
v) Special circumstances
Characteristic strength is taken as the value below which it is unlikely that more than 5% of the
results will fall. This is given by
𝑓𝑘 = 𝑓𝑚 − 1.64𝑠
Characteristic Loads
Characteristic loads (service loads) are the actual loads that the structure is designed to carry.
8
Column – vertical members carrying primarily axial load but generally subjected to axial
load and moment
Walls – vertical plate elements resisting lateral or in-plane loads
Bases and Foundations – pads or strips supported directly on the ground that spread the
loads from the columns or walls so that they can be supported by the ground without
excessive settlement
SLABS
Slabs are reinforced concrete plate elements forming floors and roofs in buildings which
normally carry uniformly distributed loads. They are primarily flexural members
Types of Slabs
One way spanning slab
Two way spanning slab
Ribbed slab
Flat slab
Types of support
Fixed
Simply supported
9
GENERAL SLAB DESIGN PROCEDURE
Slab Sizing
Slab sizing majorly depends on the support conditions (cantilever, simply supported,
continuous)
For continuous,
𝑙𝑥
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2
36
For simply supported,
𝑙𝑥
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2
26
For cantilever,
𝑙𝑥
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2
10
The most suitable concrete cover depends on exposure conditions (table 3.3 of BS 8110) as well
as the aggregate size. The minimum concrete thickness should be ℎ𝑎𝑔𝑔 + 5𝑚𝑚
Loading
The following loads may be used in design:
Characteristic dead load 𝐺𝑘 i.e. the weight of the structure complete with finishes,
fixtures and partitions
Characteristic imposed load 𝑄𝑘
The design load is calculated by multiplying the dead and live loads with appropriate partial
factors of safety (table 2.1).
𝑑𝑒𝑠𝑖𝑔𝑛 𝑙𝑜𝑎𝑑 (𝑛) = 𝛾𝑓 𝐺𝑘 + 𝛾𝑓 𝑄𝑘
In most cases the 𝛾𝑓 for dead load is 1.4 while 𝛾𝑓 for live load is 1.6. However, this is subject to
confirmation from the table 2.1 of BS8110.
10
Spanning Mode and analysis
This can be calculated by finding the ratio between the longer side to the shorter one of the
𝑙𝑦
span i.e. 𝑙 . If this ratio is less than 2.0, then this implies that the load is spanning in both
𝑥
directions. If the ratio is greater than 2.0, then the slab is one way spanning. For two-way
𝑙𝑦
spanning slabs, the value of 𝑙 are used to determine coefficients used to calculate moments
𝑥
according to BS 8110 tables 3.13, 3.14 and 3.15.
For simply supported (Table 3.13)
𝑀𝑠𝑥 = 𝛼𝑠𝑥 𝑛𝑙𝑥 2
𝑀𝑠𝑦 = 𝛼𝑠𝑦 𝑛𝑙𝑥 2
For restrained slab (Table 3.14)
𝑀𝑠𝑥 = 𝛽𝑠𝑥 𝑛𝑙𝑥 2
𝑀𝑠𝑦 = 𝛽𝑠𝑦 𝑛𝑙𝑥 2
Bending
𝑀
𝐾=
𝑏𝑑 2 𝑓𝑐𝑢
𝐾 < 0.156
Note: For continuous slabs b is assumed to be 1m width of slab at the spans. However, at the
supports, b is
𝑏 = 0.15𝑙
𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑟𝑒𝑖𝑛𝑓𝑜𝑟𝑐𝑒𝑚𝑒𝑛𝑡
𝑑 = 𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏(ℎ) − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 −
2
𝐾
𝑧 = 𝑑 (0.5 + √0.25 − )
0.9
𝑀
𝐴𝑠𝑡 =
0.87𝑓𝑦 𝑧
The main steel will be in the direction of the span and the distribution steel will be in the
transverse direction. 𝑚𝑖𝑛 𝐴𝑠𝑡 can also be used to obtain the reinforcement for the distribution
steel.
11
Shear in Slabs
Design shear stress at any cross section
𝑉
𝜈=
𝑏𝑑
100𝐴𝑠
𝑏𝑑
Therefore, the concrete shear stress 𝜈𝑐 will be obtained from table 3.8. If 𝜈 > 𝜈𝑐 , shear
reinforcement is required. if 𝜈 < 𝜈𝑐 shear reinforcement is not required.
If 𝜈𝑐 < 𝜈 < (𝜈𝑐 + 0.4), area of reinforcement will be 𝐴𝑠𝑣 ≥ 0.4𝑏𝑠𝑣 ⁄0.95𝑓𝑦𝑣
If (𝜈 + 0.4) < 𝜈 < 0.8√𝑓𝑐𝑢 area of reinforcement will be 𝐴𝑠𝑣 ≥ 𝑏𝑠𝑣 (𝜈 − 𝜈𝑐 )⁄0.95𝑓𝑦𝑣
Deflection
2𝑓𝑦 𝐴𝑠 𝑟𝑒𝑞 1
𝑓𝑠 = ×
3𝐴𝑠 𝑝𝑟𝑜𝑣 𝛽
Modification factor
(477 − 𝑓𝑠 )
𝑀𝐹 = 0.55 + 𝑀 ≤ 2.0
120(0.9 + 𝑏𝑑2 )
Permissible deflection
Where the value for deflection check can be obtained from table 3.9 corresponding to the
support conditions
Actual deflection
12
𝑠𝑝𝑎𝑛
𝛿𝑎𝑐𝑡 =
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑑𝑒𝑝𝑡ℎ
Actual deflection should be less than the permissible deflection. Otherwise increase the
thickness of the slab
SLAB DESIGN
1. ONE WAY SPANNING SLAB
A one way slab is one in which the ratio of the longer length to the shorter one is greater than 2.
Effective span of the slab is taken as
a) The center to center distance between the bearings or
b) The clear distance between supports plus the effective depth of the slab
Solution:
𝑙𝑦
⁄ = 7.0⁄3.0 = 2.33
𝑙𝑥
13
Since 2.33>2.0, the slab is one way spanning as shown above.
NB: the slab spans in the shorter direction
𝑙𝑥
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2
26
Assume Φ=10mm
3000
= + 25 + 10⁄2
26
= 145.4𝑚𝑚
Therefore, use 150mm thick slab
Effective depth d
Loading
DL
Self weight of slab= ℎ × 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 0.15 × 24 = 3.6𝑘𝑁/𝑚2
Finishes and partitions = 2.0𝑘𝑁/𝑚2
Total Dead Load = 3.6 + 2.0 = 5.6𝑘𝑁/𝑚2
LL
1.0kN/m2
Design Load
𝑛 = 1.4𝐺𝑘 + 1.6𝑄𝑘
= 1.4(5.6) + 1.6(1.0)
= 9.44𝑘𝑁/𝑚2
Bending
For 1m width, slab, udl = 9.44kN/m
14
𝑤𝑙 2 9.44 × 32
𝑀= = = 10.62𝑘𝑁𝑚
8 8
𝑀 10.62 × 106
𝐾= 2 = = 0.03
𝑏𝑑 𝑓𝑐𝑢 1000 × 1202 × 25
0.03
𝑧 = 125 (0.5 + √0.25 − ) = 0.97𝑑
0.9
Deflection Check
Service stress
2 × 460 × 228
𝑓𝑠 = = 279
3 × 251
Modification Factor
(477 − 279)
𝑀𝐹 = 0.55 + = 1.56
120(0.9 + 0.7375)
Permissible deflection
𝛿𝑝𝑒𝑟𝑚 = 1.56 × 𝑑𝑒𝑓𝑙𝑒𝑐𝑡𝑖𝑜𝑛 𝑐ℎ𝑒𝑐𝑘
Table 3.9: for simply supported slab, deflection check (basic span-eff depth ratio) = 20
𝛿𝑝𝑒𝑟𝑚 = 1.56 × 20 = 31.2𝑚𝑚
Actual deflection
𝑠𝑝𝑎𝑛 3000
𝛿𝑎𝑐𝑡 = = = 25𝑚𝑚
𝑒𝑓𝑓 𝑑𝑒𝑝𝑡ℎ 120
𝛿𝑎𝑐𝑡 < 𝛿𝑝𝑒𝑟𝑚 Therefore slab is adequate in deflection
Shear
Maximum shear
15
𝑤𝑙 9.44 × 3
𝑉𝑚𝑎𝑥 = = = 14.16𝑘𝑁
2 2
Shear stress
𝑉 14.16 × 103
𝑣= = = 0.12𝑁/𝑚𝑚2
𝑏𝑑 1000 × 120
Concrete shear stress
100𝐴𝑠 100 × 251
= = 0.21
𝑏𝑑 1000 × 120
From table 3.8 𝑣𝑐 = 0.38𝑁/𝑚𝑚2
𝑣𝑐 > 𝑣 therefore slab is adequate in shear. No shear reinforcement is required
Example
For a one way spanning continuous slab
Finishes and partitions = 2.0kN/m2
Live load = 3.0kN/m2
Characteristic material strengths: 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2 and 𝑓𝑦 = 460𝑁/𝑚𝑚2
Concrete density = 24kN/m2
Mild cover condition
Thickness of slab
4500
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 25 + 10⁄2 = 155
36
Therefore use 175mm thick slab
Effective depth
𝑑 = 175 − 25 − 10⁄2 = 145𝑚𝑚
Loading
DL
16
self-weight of slab = 0.175 × 24 = 4.2𝑘𝑁/𝑚2
Finishes = 2.0𝑘𝑁/𝑚2
Total Dead Load = 4.2 + 2.0 = 6.2𝑘𝑁/𝑚2
LL
Live load = 3.0𝑘𝑁/𝑚2
Analysis
Moments (BS 8110: table 3.12)
1. At Supports
Critical Moment at first interior support
𝑀 = −0.086𝐹𝑙
𝑀 = −0.086 × 60.66 × 4.5
𝑀 = −23.48𝑘𝑁𝑚
2. At Spans
Critical moment at near middle of end span
𝑀 = 0.075𝐹𝑙
𝑀 = 0.075 × 60.66 × 4.5
𝑀 = 20.47𝑘𝑁𝑚
Design
1. At Support
Bending
𝑏 = 2 × 0.15𝑙 = 0.3𝑙 = 0.3 × 4.5 = 1.35𝑚
Clause 3.4.4.4
𝑀
𝐾= 2
𝑏𝑑 𝑓𝑐𝑢
23.48 × 106
𝐾= = 0.033
1350 × 1452 × 25
𝐾
𝑧 = 𝑑 {0.5 + √(0.25 − )}
0.9
0.033
𝑧 = 𝑑 {0.5 + √0.25 − }
0.9
17
𝑧 = 0.96𝑑 > 0.95𝑑
Therefore use 𝑧 = 0.95𝑑
Area of steel required
𝑀
𝐴𝑠𝑡 =
0.87𝑓𝑦 𝑧
23.48 × 106
=
0.87 × 460 × 0.95 × 145
𝐴𝑠𝑡 = 426𝑚𝑚2
Minimum Area of steel required
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ
0.13
= × 1000 × 175
100
= 227.5𝑚𝑚2
𝐾 = 0.039
𝐾
𝑧 = 𝑑 {0.5 + √(0.25 − )}
0.9
0.039
𝑧 = 𝑑 {0.5 + √0.25 − }
0.9
𝑧 = 0.95𝑑
= 371𝑚𝑚2
18
min Ast = 227.5mm2
Therefore Try Y10-200B1 (393mm2) and Y10-250B2 (314mm2)
Deflection Check
Service Stress
2𝑓𝑦 𝐴𝑠 𝑟𝑒𝑞
𝑓𝑠 =
3𝐴𝑠 𝑝𝑟𝑜𝑣
2 × 460 × 371
𝑓𝑠 =
3 × 393
= 296
Modification Factor
(477 − 𝑓𝑠 )
𝑀𝐹 = 0.55 + 𝑀 ≤ 2.0
120(0.9 + )
𝑏𝑑 2
477 − 296
= 0.55 +
120(0.9 + 0.975)
Permissible deflection
For continuous slab, basic span-effective depth ratio according to table 3.9 is 26
𝛿𝑝𝑒𝑟𝑚 = 1.35 × 26
= 35.1𝑚𝑚
Actual deflection
𝑠𝑝𝑎𝑛 4500
𝛿𝑎𝑐𝑡 = = = 31.03𝑚𝑚
𝑒𝑓𝑓 𝑑𝑒𝑝𝑡ℎ 145
𝛿𝑎𝑐𝑡 < 𝛿𝑝𝑒𝑟𝑚 therefore slab is adequate in deflection
Shear
Maximum shear
𝑉𝑚𝑎𝑥 = 0.6𝐹 = 0.6 × 60.66 = 36.40𝑘𝑁
Shear stress
𝑉 36.40 × 103
𝑣= = = 0.25𝑁/𝑚𝑚2
𝑏𝑑 1000 × 145
Concrete shear stress
19
100𝐴𝑠 100 × 393
= = 0.27
𝑏𝑑 1000 × 145
20
Mild exposure conditions (therefore concrete cover = 25mm)
Solution
Slab sizing
Condition – simply supported
Assume bar diameters of 10mm
𝑙𝑥
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2
26
3000
= + 25 + 10⁄2 = 145.4𝑚𝑚
26
Loading
DL
Self weight of slab = 0.15 × 24 = 3.6𝑘𝑁/𝑚2
Finishes and partitions = 2.0𝑘𝑁/𝑚2
Total Dead Load = 3.6 + 2.0 = 5.6𝑘𝑁/𝑚2
LL = 3.5𝑘𝑁/𝑚2
Design Load
21
𝑛 = 1.4𝐺𝑘 + 1.6𝑄𝑘 = 1.4 × 5.6 + 1.6 × 3.5 = 13.44𝑘𝑁/𝑚2
Analysis
𝑙𝑦
⁄𝑙 = 4.5⁄3 = 1.5 < 2.0 therefore two way spanning
𝑥
For simply supported beam, use table 3.13 (also shown below) in analysis
𝑙𝑦 ⁄ 𝑙𝑥 1.0 1.1 1.2 1.3 1.4 1.5 1.75 2.0
𝛼𝑠𝑥 0.062 0.074 0.084 0.093 0.099 0.104 0.113 0.118
𝛼𝑠𝑦 0.062 0.061 0.059 0.055 0.051 0.046 0.037 0.029
Clause 3.5.3.3
22
Deflection Check
Service stress
477 − 𝑓𝑠
𝑀𝐹 = 0.55 + 𝑀
120 (0.9 + 𝑏𝑑2 )
477 − 270
= 0.55 +
120(0.9 + 0.8736)
𝑀𝐹 = 1.52 < 2.0 ∴ 𝑜𝑘
Permissible deflection
For simply supported slab, basic span-effective depth ratio according to table 3.9 is 20
𝛿𝑝𝑒𝑟𝑚 = 1.52 × 20 = 30.4𝑚𝑚
Actual deflection
𝑠𝑝𝑎𝑛 3000
𝛿𝑎𝑐𝑡 = = = 25.0𝑚𝑚
𝑒𝑓𝑓 𝑑𝑒𝑝𝑡ℎ 120
23
Example (Continuous 2 way spanning slab)
Consider the corner panel shown below. The panel has a dead load of 4kN/m 2 and a live load of
2.75kN/m2. Design the slab
Solution
Slab sizing
For a continuous slab,
𝑙𝑥 4000 10
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏 = + 𝑐𝑜𝑣𝑒𝑟 + 𝛷⁄2 = + 25 + = 141.11𝑚𝑚
36 36 2
Therefore try 150mm slab
Assume bar diameter of 12mm
𝑑 = 𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑠𝑙𝑎𝑏(ℎ) − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 − 𝛷⁄2 = 150 − 25 − 10⁄2 = 120𝑚𝑚
Loading
DL
Self weight of slab = 0.175 × 24 = 4.2𝑘𝑁/𝑚2
24
Other load = 4.0𝑘𝑁/𝑚2
Total load = 4.2 + 4.0 = 8.2𝑘𝑁/𝑚2
LL
Live load = 2.75𝑘𝑁/𝑚2
Design load
𝑛 = 1.4𝐺𝑘 + 1.6𝑄𝑘
= 1.4 × 8.2 + 1.6 × 2.75
= 15.88𝑘𝑁/𝑚2
Analysis
𝑙𝑦 4.8
= = 1.2
𝑙𝑥 4.0
1. At support
Short span
𝛽𝑠𝑥 = 0.063
𝑀𝑠𝑥 = 𝛽𝑠𝑥 𝑛𝑙𝑥 2 = 0.063 × 15.88 × 42 = 16.01𝑘𝑁𝑚
Long span
𝛽𝑠𝑦 = 0.045
𝑀𝑠𝑦 = 𝛽𝑠𝑦 𝑛𝑙𝑥 2 = 0.045 × 15.88 × 42 = 11.43𝑘𝑁𝑚
2. At span
Short span
𝛽𝑠𝑥 = 0.047
𝑀𝑠𝑥 = 𝛽𝑠𝑥 𝑛𝑙𝑥 2 = 0.047 × 15.88 × 42 = 11.94𝑘𝑁𝑚
Long span
𝛽𝑠𝑦 = 0.034
𝑀𝑠𝑦 = 𝛽𝑠𝑦 𝑛𝑙𝑥 2 = 0.034 × 15.88 × 42 = 8.64𝑘𝑁𝑚
25
Design
1. At support
Bending (clause 3.4.4.4)
𝑏 = 2 × 0.15𝑙 = 0.3 × 4.0 = 1.2𝑚
In x direction
𝑀𝑠𝑥 16.01 × 106
𝐾= 2 = = 0.037
𝑏𝑑 𝑓𝑐𝑢 1200 × 1202 × 25
𝑧 = 0.95𝑑
Area of steel required
𝑀𝑠𝑥 16.01 × 106
𝐴𝑠𝑡 = = = 351𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 120
In y direction
M=11.43kNm
𝑀𝑠𝑦 11.43 × 106
𝐾= 2 = = 0.028
𝑏𝑑 𝑓𝑐𝑢 1200 × 1202 × 25
0.13
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ = × 1000 × 150 = 195𝑚𝑚2
100
2. At span
In the x direction
11.94kNm
𝑀𝑠𝑥 11.94 × 106
𝐾= 2 = = 0.033
𝑏𝑑 𝑓𝑐𝑢 1000 × 1202 × 25
26
𝑧 = 0.96𝑑 > 0.95𝑑 therefore 𝑧 = 0.95𝑑
In the y direction
8.64kNm
𝑀𝑠𝑦 8.64 × 106
𝐾= 2 = = 0.024
𝑏𝑑 𝑓𝑐𝑢 1000 × 1202 × 25
Deflection Check
Service stress
27
Modification Factor
477 − 𝑓𝑠
𝑀𝐹 = 0.55 + 𝑀
120 (0.9 + 𝑏𝑑2 )
477 − 256
= 0.55 +
120(0.9 + 0.825)
Permissible deflection
For a continuous slab, the basic span effective depth ratio according to table 3.9 is 26
𝛿𝑝𝑒𝑟𝑚 = 1.62 × 26 = 42.12𝑚𝑚
Actual deflection
𝑠𝑝𝑎𝑛 4000
𝛿𝑎𝑐𝑡 = = = 33.33𝑚𝑚
𝑒𝑓𝑓 𝑑𝑒𝑝𝑡ℎ 120
Slab thickening is provided near the supports in order to achieve greater shear strength, and if
the slab is supported by a monolithic concrete beam the solid section acts as the flange of a T-
section. The ribs should be checked for shear at the junction with the solid slab.
Hollow blocks should be soaked in water before placing concrete in order to avoid cracking of
the top concrete flange due to shrinkage
28
Example
A ribbed floor continuous over several equal spans of 5.0m is constructed with permanent
fiberglass moulds. The characteristic material strengths are 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2 and 𝑓𝑦 =
250𝑁/𝑚𝑚2. Characteristic dead load = 4.5kN/m2. Characteristic live load = 2.5kN/m2
Solution
Loading
𝑢𝑙𝑡𝑖𝑚𝑎𝑡𝑒 𝑙𝑜𝑎𝑑𝑖𝑛𝑔 = 0.4(1.4𝐺𝑘 + 1.6𝑄𝑘 )
= 0.4(1.4 × 4.5 + 1.6 × 2.5)
= 4.12𝑘𝑁/𝑚
Ultimate load on span F
𝐹 = 4.12 × 5.0 = 20.6𝑘𝑁
Bending
1. At mid span: design as T-section
𝑀 = 0.063𝐹𝑙
𝑀 = 0.063 × 20.6 × 5.0
= 6.49𝑘𝑁𝑚
𝑀 6.49 × 106
𝐾= =
𝑏𝑓 𝑑 2 𝑓𝑐𝑢 400 × 1702 × 25
= 0.022
𝑧 = 0.95𝑑
𝑀 6.49 × 106
𝐴𝑠𝑡 = =
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 170
= 100𝑚𝑚2
Therefore provide 2Y8B in the ribs (101mm2)
= 108𝑚𝑚2
Therefore provide 2Y10B in the ribs (157mm2) in each 0.4m width of slab
3. At the section where the ribs terminate: this occurs 0.6m from the centre line of the
support and the moment may be hogging so that the 100mm ribs must provide the
concrete area required to develop the design moment. The maximum moment of
resistance of the concrete ribs is
𝑀 = 0.156𝑓𝑐𝑢 𝑏𝑑 2
𝑀 = 0.156 × 25 × 100 × 1702
= 11.27𝑘𝑁𝑚
Which must be greater than the moment at this section, therefore compression steel is
not required.
Deflection Check
At mid span
100𝐴𝑠 100 × 101
=
𝑏𝑑 400 × 170
= 0.15
Table 3.11 Modification factor = 1.05 for 460N/mm2. Therefore, for 250N/mm2, MF=1.93
𝑏𝑤 100
= = 0.25 < 0.3 ∴ basic span − eff depth ratio = 20.8
𝑏 400
Permissible deflection
𝛿𝑝𝑒𝑟𝑚 = 1.93 × 20.8
= 40.14𝑚𝑚
Actual deflection
𝑠𝑝𝑎𝑛 5000
𝛿𝑎𝑐𝑡 = =
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑑𝑒𝑝𝑡ℎ 170
𝛿𝑎𝑐𝑡 = 29.4𝑚𝑚
30
Actual deflection is less than the permissible deflection. Therefore, the rib is adequate in
deflection.
Shear
With 0.6m of slab provided at the support, maximum shear in the rib 0.6m from the support
centre line will be
= 0.5𝐹 − 0.6 × 4.12
= 0.5 × 20.6 − 2.5
= 7.83𝑘𝑁
Shear stress
𝑉
𝜈=
𝑏𝑑
7.83 × 103
=
100 × 170
= 0.46𝑁/𝑚𝑚2
100𝐴𝑠 100 × 101
= = 0.59
𝑏𝑑 100 × 170
Therefore, concrete shear stress will be 𝜈𝑐 = 0.65𝑁/𝑚𝑚2
Therefore, the section is adequate in shear
Topping reinforcement
Clause 3.6.6.2
Consider 1m width of slab
0.12
= × 50 × 1000 = 60𝑚𝑚2 /𝑚
100
Therefore provide A65-BRC mesh topping.
31
Table 3.17 (BS 8110-1997)
Type of slab Minimum thickness of topping (mm)
Slabs with permanent blocks
a) Clear distance between ribs not more
than 500mm jointed in cement: sand
mortar not weaker than 1:3 or
11N/mm2 25
b) Clear distance between ribs not more
than 500mm, not jointed in cement:
sand mortar 30
c) All other slabs with permanent blocks 40 or one-tenth of clear distance between
ribs, whichever is greater
All slabs without permanent blocks 50 or one-tenth of clear distance between
For slabs without permanent blocks ribs, whichever is greater
The drop panels are effective in reducing the shearing stresses where the column is liable to
punch through the slab, and they also provide an increased moment of resistance where the
negative moments are greatest.
The simplified formwork and the reduced storey heights make it more economical
Windows can extend up to the underside of the slab
There are no beams to obstruct the light and the circulation of air
The absence of sharp corners gives greater fire resistance as there is less danger of
concrete spalling and exposing the reinforcement
32
(b)
(c)
(a) Slab without drop panel or column head; (b) floor with column head but no drop panel; (c)
Floor with drop panel and column head
33
6. The panel thickness is generally controlled by deflection. The thickness should not be
less than 125 mm
METHODS OF ANALYSIS
Analysis of the slab may be done by dividing the slab into frames or by empirical analysis.
34
(c) Simplified method
Moments and shears may be taken from Table 3.19 of the code for structures where lateral
stability does not depend on slab-column connections. The following provisions apply:
1. Design is based on the single load case
2. The structure has at least three rows of panels of approximately equal span in the direction
considered.
The design moments and shears for internal panels are obtained from Table 3.19 of the code
35
𝑙ℎ0 = 870𝑚𝑚
4 × 8702
ℎ𝑐 = √ = 982𝑚𝑚 ≯ 0.25 × 6000 = 1500𝑚𝑚
𝜋
36
The effective span is
982
𝑙 = 6000 − 2 × = 5345𝑚𝑚
3
Design load
The design calculations for the reinforcement in the column and middle strip are made using
b=3000mm
37
From the table above, M/bd2<1.27
Therefore
𝑀 146.8 × 106
𝐴𝑠𝑡 = = = 3534𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 201
Provide 19bars 16mm in diameter to give an area of 3819mm2. Two thirds of the bars i.e.
13bars are placed in the centre half of the columns strip at a spacing of 125mm. a further four
bars are placed in each of the outer strips at a spacing of 190mm. this gives 21 bars in total
38
Column strip positive reinforcement
𝑀 121.3 × 106
= = 1.77
𝑏𝑑2 3000 × 1512
From the diagram above, M/bd2>1.27 Therefore
100𝐴𝑠
= 0.92
𝑏𝑑
151
𝐴𝑠 = 0.92 × 3000 × = 4167.6𝑚𝑚2
100
Provide 21 16mm bars spaced at 150mm (4221mm2)
Shear
Shear
𝑉 = 1.15 × 16.13(36 − 0.872 ) = 653.7𝑘𝑁
Shear stress (clause 3.7.7.2)
𝑉 653.7 × 103
𝜈= = = 0.93𝑁/𝑚𝑚2 < 0.8√𝑓𝑐𝑢
𝑢0 𝑑 4 × 870 × 201
39
Shear stress
𝑉 627.5 × 103
𝜈= = = 0.53𝑁/𝑚𝑚2
𝑢𝑑 5892 × 201
In the centre half of the column strip 16mm diameter bars are spaced at 125mm (1608mm2)
1⁄
30 3
From table 3.8, 𝑣𝑐 = 0.67 × ( ) = 0.71𝑁/𝑚𝑚2
25
𝑣𝑐 > 𝑣 ∴ no shear reinforcement is required
Deflection Check
Service stress
𝑠𝑝𝑎𝑛 6000
𝛿𝑎𝑐𝑡 = = = 39.7𝑚𝑚
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑑𝑒𝑝𝑡ℎ 151
The slab is therefore ok in deflection
Cracking
According to Clause 3.12.11.2.7 maximum spacing between bars should be the lesser of 750mm
of 3 times the effective depth.
For drop panel 3𝑑 = 3 × 201 = 603𝑚𝑚
40
Arrangement of bars
Arrangement of bars is as shown below
41
SUMMARY ON SLAB DESIGN
1. Dimensional Considerations
The two principal dimensional considerations for a one way spanning slab are its width and
effective span.
2. Reinforcement areas
Sufficient reinforcement must be provided in order to control cracking. Minimum area of
reinforcement should be
0.24% of total concrete area when fy=250N/mm2
0.13% of total concrete area when fy=460N/mm2
The minimum area of distribution steel is the same as for the minimum main reinforcement
area. The size of bars for the slab should not be less than 10mm diameter. They should also
not exceed 20mm.
42
BEAMS
Beams are flexural horizontal members. The 2 common types of reinforced concrete beam
section are
1. Rectangular section
2. Flanged sections of either – L and T
This is generally rounded off to 0.45fcu. The strain is 0.0035 as shown in the figure above
Referring to table 2.2for high yield bars, the steel stress is
𝑓𝑦
⁄
1.15 = 0.87𝑓𝑦
From the stress diagram above, the internal forces are
C =force in the concrete in compression
43
= 0.447𝑓𝑐𝑢 × 0.9𝑏 × 0.5𝑑
= 0.201𝑓𝑐𝑢 𝑏𝑑
𝑀
𝐾=
𝑏𝑑2 𝑓𝑐𝑢
= 0.87𝑓𝑦 𝐴𝑠 × 𝑧
𝑀
𝐴𝑠 =
0.87𝑓𝑦 𝑧
2. Flanged beams
There are two types of flanged beams namely
L-beam – mostly found at edges
T-beam
44
T and L beams form part of a concrete beam and slab floor. When the beams are resisting
sagging moments, part of the slab acts as a compression flange and the members may be
designed as L or T-beams.
According to clause 3.4.1.5, the effective widths 𝑏𝑓 of flanged beams are:
𝑙
a) For T-beams: web width + 𝑧⁄5 or actual flange width if less
𝑙
b) For L-beams: web width + 𝑧⁄10or actual flange width if less
Where 𝑙𝑧 is the distance between points of zero moment (which for a continuous
beam may be taken as 0.7times the effective span)
𝑀
𝐾=
𝑏𝑓 𝑑 2 𝑓𝑐𝑢
𝑀
𝐴𝑠𝑡 =
0.87𝑓𝑦 𝑧
𝑉
𝜈=
𝑏𝑤 𝑑
100𝐴𝑠
𝑏𝑤 𝑑
Example
45
A concrete section of 𝑏𝑤 = 250𝑚𝑚and 𝑏𝑓 = 600𝑚𝑚, slab thickness = 150mm and beam
depth = 530mm, 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2and 𝑓𝑦 = 425𝑁/𝑚𝑚2 . Design moment at the ultimate limit
state is 160kNm, causing sagging.
𝑀 160 × 106
𝐾= = = 0.038
𝑏𝑓 𝑑2 𝑓𝑐𝑢 600 × 5302 × 25
𝑧 = 0.95𝑑 = 0.95 × 530 = 503𝑚𝑚
𝑑 − 𝑧 (530 − 503)
𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑛𝑒𝑢𝑡𝑟𝑎𝑙 𝑎𝑥𝑖𝑠 𝑥 = =
0.45 0.45
𝑀 160 × 106
𝐴𝑠𝑡 = = = 861𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 425 × 0.95 × 530
Therefore provide 2Y25 bars area=982mm2
Transverse steel in the flange
𝑡𝑟𝑎𝑛𝑠𝑣𝑒𝑟𝑠𝑒 𝑠𝑡𝑒𝑒𝑙 𝑖𝑛 𝑡ℎ𝑒 𝑓𝑙𝑎𝑛𝑔𝑒 = 3ℎ𝑓 = 3 × 150
= 450𝑚𝑚2 /𝑚
46
Sufficient reinforcement must be provided in order to control cracking. Minimum area
of reinforcement should be
0.24% of total concrete area when fy=250N/mm2
0.13% of total concrete area when fy=460N/mm2
e) Minimum spacing of reinforcement
Minimum spacing of reinforcement should be = ℎ𝑎𝑔𝑔 + 5𝑚𝑚
f) Maximum spacing of reinforcement
When the limitation of crack widths to 0.3mm is acceptable and the cover to
reinforcement does not exceed 50mm, the maximum clear distance between adjacent
bars will be:
300mm when fy=250N/mm2
160mm when fy=460N/mm2
The main structural design requirements to examine in concrete beams are:
a) Bending ULS
b) Cracking SLS
c) Deflection SLS
d) Shear ULS
(c) Analysis
47
The design loads are calculated using appropriate partial factors of safety fromBS8110: Part 1,
Table 2.1. The reactions, shears and moments are determined and theshear force and bending
moment diagrams are drawn.
(d) Design of moment reinforcement
The reinforcement is designed at the point of maximum moment, usually the centre ofthe
beam. Refer to BS8110: Part 1, section 3.4.4.
(e) Curtailment and end anchorage
A sketch of the beam in elevation is made and the cut-off point for part of the
tensionreinforcement is determined. The end anchorage for bars continuing to the end of
thebeam is set out to comply with code requirements.
(f) Design for shear
Shear stresses are checked and shear reinforcement is designed using the proceduresset out in
BS8110: Part 1, section 3.4.5. Notethat except for minor beams such as lintels all beams must
be provided with links asshear reinforcement. Small diameter bars are required in the top of
the beam to carryand anchor the links.
(g) Deflection
Deflection is checked using the rules from BS8110: Part 1, section 3.4.6.9
(h) Cracking
The maximum clear distance between bars on the tension face is checked against thelimits
given in BS8110: Part 1, clause 3.12.11.
(i) Design sketch
Design sketches of the beam with elevation and sections are completed to show all
information.
Solution
𝑑 = ℎ − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 − 𝛷⁄2
Assume 𝛷 = 20𝑚𝑚
𝑑 = 450 − 25 − 20⁄2 = 415𝑚𝑚
1. Loading
DL
Self weight= 0.45 × 0.20 × 24 = 2.16𝑘𝑁/𝑚
Other = 12𝑘𝑁/𝑚
Total = 14.16𝑘𝑁/𝑚
LL
48
Live load = 15𝑘𝑁/𝑚
Design Load
𝑛 = 1.4𝐺𝑘 + 1.6𝑄𝑘
= 43.84𝑘𝑁/𝑚
Maximum moment
𝑤𝑙 2
𝑀=
8
43.84 × 42
𝑀=
8
= 87.68𝑘𝑁𝑚
Maximum shear
𝑤𝑙
𝑉=
2
43.84 × 4
𝑉=
2
𝑉 = 87.68𝑘𝑁
2. Design
Bending
𝑀
𝐾=
𝑏𝑑 2 𝑓𝑐𝑢
87.68 × 106
=
200 × 4152 × 25
= 0.101
𝑧 = 0.87𝑑
Area of steel required
𝑀
𝐴𝑠𝑡 =
0.87𝑓𝑦 𝑧
87.68 × 106
=
0.87 × 460 × 0.87 × 415
49
= 607𝑚𝑚2
Minimum area of steel required
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ
0.13
= × 450 × 200
100
= 117𝑚𝑚2
Therefore try 2Y20 bars (628mm2)
Shear reinforcement
𝑉𝑚𝑎𝑥 = 87.68𝑘𝑁
Shear stress
𝑉 87.68 × 103
𝜈= =
𝑏𝑑 200 × 415
= 1.06𝑁/𝑚𝑚2
0.8√𝑓𝑐𝑢 = 0.8√25 = 4.0𝑁/𝑚𝑚2
Concrete shear stress
100𝐴𝑠 100 × 628
=
𝑏𝑑 200 × 415
= 0.76
Table 3.8 (BS 8110)
𝜈𝑐 = 0.572𝑁/𝑚𝑚2
𝜈 > 𝜈𝑐 therefore shear reinforcement is required
𝜈𝑐 + 0.4 < 𝜈 < 0.8√𝑓𝑐𝑢 therefore use the formula: 𝐴𝑠𝑣 ≥ 𝑏𝑣 𝑠𝑣 (𝜈 − 𝜈𝑐 )/0.95𝑓𝑦𝑣
Therefore,
0.95𝑓𝑦𝑣 𝐴𝑠𝑣
𝑠𝑣 ≤
𝑏𝑣 (𝜈 − 𝜈𝑐 )
Assume 2 legs Y8 links 𝐴𝑠𝑡 = 101𝑚𝑚2, 𝑓𝑦𝑣 = 250𝑁/𝑚𝑚2
50
0.95 × 250 × 101
𝑠𝑣 ≤
200(1.06 − 0.572)
𝑠𝑣 ≤ 246𝑚𝑚
Deflection Check
Service stress
2𝑓𝑦 𝐴𝑠 𝑟𝑒𝑞 2 × 460 × 607
𝑓𝑠 = = = 296
3𝐴𝑠 𝑝𝑟𝑜𝑣 3 × 628
Modification factor
477 − 𝑓𝑠
𝑀𝐹 = 0.55 + 𝑀
120 (0.9 + 𝑏𝑑2 )
477 − 296
= 0.55 +
120(0.9 + 2.525)
4000
=
415
= 9.64𝑚𝑚
51
For uniformly loaded continuous beams with approximately equal spans, table 3.5 (also shown
below) can be used in analysis to find moments and shear at the supports. Other conditions for
such a beam are (clause 3.4.3):
a) Characteristic imposed load should not exceed characteristic dead load
b) Loads should be substantially uniformly distributed over three or more spans
c) Variations in span length should not exceed 15% of longest
Example
A continuous rectangular beam of 450x200mm has a dead load of 18kN/m and live load of
12kN/m. characteristic strengths 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2 and 𝑓𝑦 = 460𝑁/𝑚𝑚2
Solution
𝑑 = ℎ − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 − 𝑙𝑖𝑛𝑘𝑠 − 𝛷⁄2
Assume Y8 links and 𝛷 = 20𝑚𝑚
𝑑 = 450 − 25 − 8 − 20⁄2 = 407𝑚𝑚
1. Loading
DL
Self weight of beam = 0.45 × 0.2 × 24 = 2.16𝑘𝑁/𝑚
Other = 18.00𝑘𝑁/𝑚
Total= 2.16 + 18.00 = 20.16𝑘𝑁/𝑚
LL
Live load = 12.00𝑘𝑁/𝑚
52
Critical shear = 0.6𝐹
𝑉 = 0.6 × 47.42
= 28.45𝑘𝑁
b) At spans
Critical moment = 0.09𝐹𝑙
𝑀 = 0.09 × 47.42 × 4.0
= 17.07𝑘𝑁𝑚
3. Design
Bending
a) At support
𝑀 20.86 × 106
𝐾= 2 =
𝑏𝑑 𝑓𝑐𝑢 200 × 4072 × 25
= 0.025
𝑧 = 0.97𝑑 > 0.95𝑑therefore use 𝑧 = 0.95𝑑
b) At span
𝑀 17.07 × 106
𝐾= = = 0.021
𝑏𝑑 2 𝑓𝑐𝑢 200 × 4072 × 25
𝑧 = 0.98𝑑 > 0.95𝑑therefore use 𝑧 = 0.95𝑑
53
0.13 × 200 × 450
𝑚𝑖𝑛𝑎𝑠𝑡 = 0.13%𝑏ℎ = = 227.5𝑚𝑚2
100
Deflection
Service stress
Modification factor
Permissible deflection
54
𝑠𝑝𝑎𝑛 4000
𝛿𝑎𝑐𝑡 = = = 9.83𝑚𝑚
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑑𝑒𝑝𝑡ℎ 407
If the conditions in clause 3.4.3 are not fulfilled, then the beam can be analyzed by method of
distribution of moments
Example
A continuous flange beam of 450x200mm has 3 spans. The end spans have a dead load of
15kN/m and live load of 12kN/m. The middle span has a dead load of 20kN/m and live load of
16kN/m. characteristic strengths 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2 and 𝑓𝑦 = 460𝑁/𝑚𝑚2
Solution
𝑑 = ℎ − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 − 𝑙𝑖𝑛𝑘𝑠 − 𝛷⁄2
Assume Y8 links and 𝛷 = 20𝑚𝑚
𝑑 = 450 − 25 − 8 − 20⁄2 = 407𝑚𝑚
a) Loading
End spans
DL
Self weight of beam = 0.45 × 0.2 × 24 = 2.16𝑘𝑁/𝑚
Other = 15.00𝑘𝑁/𝑚
Total= 2.16 + 15.00 = 17.16𝑘𝑁/𝑚
LL
Live load = 12.00𝑘𝑁/𝑚
Middle span
55
DL
Self weight of beam = 0.45 × 0.2 × 24 = 2.16𝑘𝑁/𝑚
Other = 20.00𝑘𝑁/𝑚
Total= 2.16 + 20.00 = 22.16𝑘𝑁/𝑚
LL
Live load = 16.00𝑘𝑁/𝑚
56
Analysis
Taking moments about 2
43.22 × 2.52
2.5𝑉1 + 59.64 − =0
2
𝑉1 = 30.17𝑘𝑁
Taking moments about 1
43.22 × 2.52
+ 59.64 − 2.5𝑉1−2 = 0
2
𝑉1−2 = 77.88𝑘𝑁
Taking moments about 3
56.62 × 42
4𝑉2−3 − 59.64 + 59.64 − =0
2
𝑉2−3 = 113.24𝑘𝑁
Taking moments about 2
56.62 × 42
+ 59.64 − 59.64 − 4𝑉3−2 = 0
2
𝑉3−2 = 113.24𝑘𝑁
Taking moments about 4
43.22 × 2.52
2.5𝑉4−5 − − 59.64 = 0
2
𝑉4−5 = 77.88𝑘𝑁
Taking moments about 3
43.22 × 2.52
− 59.64 − 2.5𝑉5 = 0
2
𝑉5 = 30.17𝑘𝑁
57
Moments
77.88 2.5 − 𝑥
=
30.17 𝑥
𝑥 = 0.6981𝑚
Also
113.24 4 − 𝑦
=
113.24 𝑦
𝑦 = 2𝑚
Moment at end span
1
𝑀= × 30.17 × 0.6981
2
= 10.53𝑘𝑁𝑚
58
b) Design
1. At support
Critical moment = 59.64kNm
b = 200mm
Bending
𝑀 59.64 × 106
𝐾= = = 0.072
𝑏𝑑 2 𝑓𝑐𝑢 200 × 4072 × 25
𝑧 = 0.91𝑑
Area of steel required
𝑀 59.64 × 106
𝐴𝑠𝑡 = = = 402𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.91 × 407
Minimum Area of steel required
0.13
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ = × 200 × 450 = 117𝑚𝑚2
100
Therefore provide 2Y16B (402mm2), 1Y12B (113mm2)
2. At span
Critical moment = 53.6kNm
0.7 × 4000
𝑏𝑓 = 200 + = 760𝑚𝑚
5
Bending
𝑀 53.6 × 106
𝐾= = = 0.017
𝑏𝑓 𝑑 2 𝑓𝑐𝑢 760 × 4072 × 25
𝑧 = 0.98𝑑 > 0.95𝑑therefore, 𝑧 = 0.95𝑑
𝑀 53.6 × 106
𝐴𝑠𝑡 = = = 346.4𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 407
Shear
𝑉𝑚𝑎𝑥 = 113.24𝑘𝑁
59
Shear stress
𝑉 113.24 × 103
𝜈= = = 1.39𝑁/𝑚𝑚2
𝑏𝑑 200 × 407
Deflection Check
Service stress
477 − 𝑓𝑠
𝑀𝐹 = 0.55 + 𝑀
120 (0.9 + 𝑏𝑑2 )
477 − 264
= 0.55 +
120(0.9 + 0.4258)
𝑀𝐹 = 1.89
Permissible deflection
𝑠𝑝𝑎𝑛 4000
𝛿𝑎𝑐𝑡 = = = 9.83𝑚𝑚
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑑𝑒𝑝𝑡ℎ 407
Redoing the example above but assuming that the beams are flanged:
60
Example
A continuous flange beam of 450x200mm has a dead load of 18kN/m and live load of 12kN/m.
characteristic strengths 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2 and 𝑓𝑦 = 460𝑁/𝑚𝑚2
Solution
𝑑 = ℎ − 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑐𝑜𝑣𝑒𝑟 − 𝑙𝑖𝑛𝑘𝑠 − 𝛷⁄2
Assume Y8 links and 𝛷 = 20𝑚𝑚
𝑑 = 450 − 25 − 8 − 20⁄2 = 407𝑚𝑚
4. Loading
DL
Self weight of beam = 0.45 × 0.2 × 24 = 2.16𝑘𝑁/𝑚
Other = 18.00𝑘𝑁/𝑚
Total= 2.16 + 18.00 = 20.16𝑘𝑁/𝑚
LL
Live load = 12.00𝑘𝑁/𝑚
d) At spans
Critical moment = 0.09𝐹𝑙
𝑀 = 0.09 × 47.42 × 4.0
= 17.07𝑘𝑁𝑚
61
6. Design
Bending
a) At support
𝑀 20.86 × 106
𝐾= =
𝑏𝑑 2 𝑓𝑐𝑢 200 × 4072 × 25
= 0.025
𝑧 = 0.97𝑑 > 0.95𝑑therefore use 𝑧 = 0.95𝑑
b) At span
0.7𝑙𝑥⁄ 0.7 × 4000
𝑏𝑓 = 𝑏𝑤 + 5 = 200 + = 760𝑚𝑚
5
𝑀 17.07 × 106
𝐾= = = 0.005
𝑏𝑓 𝑑 2 𝑓𝑐𝑢 760 × 4072 × 25
𝑧 = 0.99𝑑 > 0.95𝑑therefore use 𝑧 = 0.95𝑑
62
𝑉 28.45 × 103
𝜈= = = 0.35𝑁/𝑚𝑚2
𝑏𝑑 200 × 407
Deflection
Service stress
Modification factor
Permissible deflection
Actual deflection
𝑠𝑝𝑎𝑛 4000
𝛿𝑎𝑐𝑡 = = = 9.83𝑚𝑚
𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑑𝑒𝑝𝑡ℎ 407
63
SUMMARY ON DESIGN OF BEAMS
a) Calculate the ultimate loads, shear force and bending moment acting on the beam
b) Check the bending ULS. This will determine an adequate depth for the beam and the
area of tension reinforcement required
c) Check deflection SLS by using relevant span effective depth ratios
d) Check shear ULS and provide the relevant link reinforcement
64
COLUMNS
Columns are structures that carry loads from the beams and the slabs down to the foundations.
They are therefore primarily compression members although they may also have to resist
bending forces due to the continuity of the structure.
Classification of columns
Reinforced concrete columns are classified as either braced or unbraced, depending on how
lateral stability is provided to the structure as a whole. A concrete framed building may be
designed to resist lateral loading, e.g. wind action in two distinct ways
a) The beam and column may be designed to act together as a rigid frame in transmitting
the lateral forces down to the foundations. In such an instance the columns are said to
be unbraced and must be designed to carry both the vertical (compressive) and lateral
(bending) loads.
b) Lateral loading may be transferred via the roof and floors to a system of bracing or shear
walls designed to transmit resulting forces down to the foundations. The columns are
then said to be braced and consequently carry only vertical loads.
Columns may further be classified as short or slender. Braced columns may therefore either be
short or slender. For a short braced column
𝑙𝑒𝑥
< 15
ℎ
And
𝑙𝑒𝑦
< 15
𝑏
Where
𝑙𝑒𝑥 effective height in respect of column major axis
𝑙𝑒𝑦 effective height in respect of column minor axis
ℎdepth in respect of major axis
𝑏width in respect of minor axis
Clause 3.8.1.6 – 𝑙𝑒𝑥 and 𝑙𝑒𝑦 are influenced by the degree of fixity at each end of the column
𝑙𝑒𝑥 or 𝑙𝑒𝑦 = 𝛽𝑙0
65
c) Condition 3. The end of the column is connected to members which, while not
specifically designed to provide restraint to rotation of the column will, nevertheless,
provide some nominal restraint.
d) Condition 4. The end of the column is unrestrained against both lateral movement and
rotation (e.g. the free end of a cantilever column in an unbraced structure).
66
a) Column cross-section
The greater cross-sectional dimension should not exceed four times the smaller one.
Otherwise it should be treated as a wall.
67
c) Minimum Spacing of Reinforcement
BS 8110 recommends minimum bar spacing of 5mm more than the size of aggregate
d) Maximum Spacing of Reinforcement
There is no limit of maximum spacing of reinforcement. However, for practical reasons,
maximum spacing of main bars should not exceed 250mm
e) Links
Linksbe provided in columns in order to prevent lateral buckling of the longitudinal main
bars due to action of compressive loading
f) Compressive ULS
This may be divided into 3 categories
i) Short braced axially loaded columns
ii) Short braced columns supporting an approximately symmetrical arrangement of
beams
iii) Short braced columns supporting vertical loads and subjected to either uniaxial or
biaxial bending
68
𝑁 = 0.35𝑓𝑐𝑢 𝐴𝑐 + 0.67𝐴𝑠𝑐 𝑓𝑦
Or
𝑁 = 0.35𝑓𝑐𝑢 (𝐴𝑔 − 𝐴𝑠𝑐 ) + 0.67𝐴𝑠𝑐 𝑓𝑦
c) Short braced columns supporting vertical loads and subjected to either uniaxial or
biaxial bending
Columns supporting beams on adjacent side whose spans vary by more than 15%
will be subjected to uniaxial bending
Columns at the corners of buildings on the other hand are subjected to biaxial
bending. In such an instance, the column should be designed to resist bending
about both axes.
For such, design carried out for an increased moment about one axis only.
If
𝑀𝑥 𝑀𝑦
≥
ℎ′ 𝑏′
The increased moment about the x-x axis is
ℎ′
𝑀′𝑥 = 𝑀𝑥 + 𝛽 𝑀
𝑏′ 𝑦
If
𝑀𝑥 𝑀𝑦
<
ℎ′ 𝑏′
69
𝑏′
𝑀′𝑦 = 𝑀𝑦 + 𝛽 𝑀
ℎ′ 𝑥
Where
𝑏overall section dimension perpendicular to y-y axis
𝑏′effective depth perpendicular to y-y axis
ℎoverall section dimension perpendicular to x-x axis
ℎ′effective depth perpendicular to x-x axis
𝑀𝑥 bending moment about x-x axis
𝑀𝑦 bending about y-y axis
𝛽coefficient obtained from BS 8110 table 3.22
The area of reinforcement can then be found from the appropriate design chart in BS 8110
Part 3 using N/bh and M/bh2
g) Shear ULS
Axially loaded columns are not subjected to shear and therefore no check is necessary.
h) Cracking SLS
Since cracks are produced by flexure of the concrete, short columns that support axial loads
alone do not require checking for cracking. However, all other columns subject to bending
should be considered as beams for the purpose of examining the cracking SLS.
i) Lateral Deflection
Deflection check for short braced columns is not necessary
Examples
Example 1
A short braced column in a situation of mild exposure supports an ultimate axial load of
1000kN, the size of the column being 250mm x 250mm. Using grade 30 concrete with mild
reinforcement, calculate the size of all reinforcement required and the maximum effective
height for the column if it is to be considered as a short column.
Solution
𝑁 = 0.4𝑓𝑐𝑢 (𝐴𝑔 − 𝐴𝑠𝑐 ) + 0.75𝐴𝑠𝑐 𝑓𝑦
𝐴𝑠𝑐 = 1424.5𝑚𝑚2
Try 4 Y25 (1966mm2)
70
Links
Diameter required:
The diameter required is the greater of
a. One quarter of the diameter of the largest main bar i.e. 25/4=6.25mm
b. 6mm
The spacing is the lesser of 12 times the diameter of the smallest main bar i.e. 12x25=300mm
or the smallest cross-sectional dimension of the column i.e. 250mm
Therefore provide Y8 links at 250mm spacing
Example 2
A short braced reinforced concrete column supports an approximately symmetrical
arrangement of beams which result in a total vertical load of 1500kN being applied to the
column. Assuming the percentage of steel to be 1 %, choose suitable dimensions for the column
and the diameter of the main bars. Use HY reinforcement in a square column
𝑁 = 0.35𝑓𝑐𝑢 (𝐴𝑔 − 𝐴𝑠𝑐 ) + 0.67𝐴𝑠𝑐 𝑓𝑦
𝐴𝑠𝑐 = 0.01𝐴𝑔
1500 × 103 = 0.35 × 35(𝐴𝑔 − 0.01𝐴𝑔 ) + 0.67 × 0.01𝐴𝑔 × 460
1500 × 103 = 12.25𝐴𝑔 − 0.1225𝐴𝑔 + 3.082𝐴𝑔
1500 × 1000
𝐴𝑔 = = 98619.33𝑚𝑚2
15.21
71
Example 3
A short braced column supporting a vertical load and subjected to biaxial bending is shown
below. If the column is formed from grade 40 concrete, determine the size of HY main
reinforcement required.
𝑀𝑥 60
′
= = 0.23
ℎ 260
𝑀𝑦 35
= = 0.17
𝑏′ 210
𝑀𝑥 𝑀𝑦
>
ℎ′ 𝑏′
Hence use equation 40 of BS 8110
ℎ′
𝑀′𝑥 = 𝑀𝑥 + 𝛽 𝑀
𝑏′ 𝑦
𝑁 600 × 103
= = 0.2
𝑏ℎ𝑓𝑐𝑢 250 × 300 × 40
72
From Table 3.22, 𝛽 = 0.77
260
𝑀′𝑥 = 60 + 0.77 × × 35 = 93.37𝑘𝑁𝑚
210
𝑑 260
= = 0.87 ≈ 0.85
ℎ 300
𝑁 600 × 103
= =8
𝑏ℎ 250 × 300
𝑀 93.37 × 106
= = 4.15
𝑏ℎ2 250 × 3002
100𝐴𝑠𝑐
From chart, = 1.6
𝑏ℎ
1.6𝑏ℎ 1.6 × 250 × 300
𝐴𝑠𝑐 = = = 1200𝑚𝑚2
100 100
73
NB:
BS 6399: Section 6: reduction in total imposed load
Clause 6.1 of BS 6399 stipulates that the following loads do not qualify for reduction in total imposed
floor loads
a) Loads that have been specifically determined from knowledge of the proposed use of the
structure;
b) Loads due to plant or machinery;
c) Loads due to storage.
Number of floors with loads qualifying for Reduction in total distributed imposed load on all
reduction carried by member under consideration floors carried by the member under consideration (%)
1 0
2 10
3 20
4 30
5 to 10 40
Over 10 50 max
The table below can be used to calculate the load total load at any particular floor:
For buildings with more than 5 storeys, it is important to consider factors of safety for
earthquake.
74
FOUNDATIONS
Foundation is the part of a superstructure that transfers and spreads loads from the structure’s
columns and walls into the ground.
Types of footing
Pad footing
Combined footing
Strap footing
Strip footing
In the design of foundations, the areas of the bases in contact with the ground should be such
that the safe bearing pressures will not be exceeded. Design loadings to be to be considered
when calculating the base areas should be those that apply to serviceability limit state and they
are:
Dead plus imposed load = 1.0𝐺𝑘 + 1.0𝑄𝑘
Dead plus wind load = 1.0𝐺𝑘 + 1.0𝑊𝑘
Dead plus imposed plus wind load= 1.0𝐺𝑘 + 0.8𝑄𝑘 + 0.8𝑊𝑘
When the foundation is subjected to both vertical and horizontal loads, the following rule
should apply:
𝑉 𝐻
+ < 1.0
𝑃𝑣 𝑃ℎ
Where
𝑉 = the yield vertical load
𝐻 = the horizontal load
𝑃𝑣 = the allowable vertical load
𝑃ℎ = the allowable horizontal load
The calculations to determine the structural strength of the foundations, that is the thickness of
the bases and the areas of reinforcement, should be based on the loadings and the resultant
ground pressures corresponding to the ultimate limit state
Pad footing
The principal steps in the design calculations are as follows:
1. Calculate the plan size of the footing using the permissible bearing pressure and the critical
loading arrangement for the serviceability limit state
2. Calculate the bearing pressures associated with the critical loading arrangement at the
ultimate limit state
3. Determine the minimum thickness h of the base
4. Check the thickness h for punching shear, assuming a probable value for the ultimate shear
stress
75
5. Determine the reinforcement required to resist bending
6. Make a final check of the punching shear having established the ultimate shear stress
precisely
7. Check the shear stress at the critical sections
8. Where applicable, the foundation and structure should be checked for over-all stability at
the ultimate limit state
Example
Design a pad footing to resist characteristic axial loads of 1000kN dead and 350kN imposed
from a 400mm square column with 16mm dowels. The safe bearing pressure on the soil is
200kN/m2 and the characteristic material strengths are 𝑓𝑐𝑢 = 25𝑁/𝑚𝑚2and 𝑓𝑦 = 425𝑁/𝑚𝑚2
Solution
Loading
Assume footing self weight of 150kN.
76
𝑁
𝑣=
𝑐𝑜𝑙𝑢𝑚𝑛 𝑝𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟 × 𝑑
1500 × 103
= = 1.80𝑁/𝑚𝑚2
400 × 4 × 520
The ultimate shear stress is not excessive, therefore h=600mm will be suitable
d) Bending reinforcement
At the column face which is the critical section
2.8 − 0.4
= 1.2𝑚
2
1.2
𝑀 = (257 × 2.8 × 1.2) × = 518𝑘𝑁𝑚
2
For concrete
𝑀 = 0.156𝑓𝑐𝑢 𝑏𝑑 2
77
= 0.156 × 25 × 2800 × 5202 × 10−6
= 2839𝑘𝑁𝑚
𝑀
𝐴𝑠𝑡 =
0.87𝑓𝑦 𝑧
518 × 106
=
0.87 × 425 × 0.95 × 520
= 2836𝑚𝑚2
= 0.22
From BS 8110, table 3.8, the ultimate shear stress 𝑣𝑐 = 0.39𝑁/𝑚𝑚2 this is greater than
punching shear stress which is 𝑣 = 0.25𝑁/𝑚𝑚2 therefore a base of 600mm deep is
adequate
Critical section for shear is 1.5d from the column face as shown above
Shear
𝑉 = 257 × 2.8 × 0.42 = 302.2𝑘𝑁
78
Shear stress
𝑉 302.2 × 103
𝑣= = = 0.21𝑁/𝑚𝑚2 < 0.39𝑁/𝑚𝑚2
𝑏𝑑 2800 × 520
Combined footings
In a case whereby two columns are very close to each other such that the two pad
footings designed overlap, a combined footing is necessary. A combined footing is a
base that supports two or more columns. These may either be rectangular or
trapezoidal.
The proportions of the footing
Should not be too long as this will cause larger longitudinal moments on the lengths
projecting beyond the columns
Should not be too short as this would cause the span moments in between the
columns to be greater hence making the transverse moments to be larger
Thickness should be such that would ensure that shear stresses are not excessive
Process of design
The principal steps in the design calculations are as follows:
1. Calculate the plan size of the footing using the total load of both columns (for
serviceability limit state) and the permissible bearing pressure
2. Calculate the centroid of base
3. Calculate the bearing pressures associated with the critical loading arrangement at
the ultimate limit state
4. Assume the thickness h of the footing
5. Check the thickness h for punching shear
6. Determine the reinforcement required to resist bending
7. Make a final check of the punching shear having established the ultimate shear
stress precisely
8. Check the shear stress at the critical sections
Example
A combined footing supports two columns 300mm square and 400mm square with
characteristic dead and imposed loads as shown below. The safe bearing pressure is
300kN/m2 and the characteristic material strengths are 𝑓𝑐𝑢 = 30𝑁/𝑚𝑚2and 𝑓𝑦 =
460𝑁/𝑚𝑚2
79
Assume footing self weight = 250kN
a) For Serviceability Limit State
𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 = 250 + 1000 + 200 + 1400 + 300 = 3150𝑘𝑁
Area of base required
𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 3150
𝐴= = = 10.5𝑚2
𝑠𝑎𝑓𝑒 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 300
Try 4.6m x 2.3m base
𝑎𝑐𝑡𝑢𝑎𝑙 𝑎𝑟𝑒𝑎 = 4.6 × 2.3 = 10.58𝑚2
b) Centroid of footing
Load on 300mm column = 1200kN
Load on 400mm column = 1700kN
Total load = 1200 + 1700 = 2900kN
The resultant load will act somewhere in between the columns. Therefore,
taking moments about the centerline of 400mm column
3 × 1200 = (1700 + 1200) × 𝑥̅
3 × 1200
𝑥̅ = = 1.24𝑚
(1700 + 1200)
80
d) Moment and Shear Force
𝑢𝑑𝑙 = 400 × 2.3 = 920𝑘𝑁/𝑚
Point loads
1. 𝑊1 = 1.4 × 1000 + 1.6 × 200 = 1720𝑘𝑁
2. 𝑊2 = 1.4 × 1400 + 1.6 × 300 = 2440𝑘𝑁
The loading, shear force and bending moment diagram are as shown below
81
e) Shear
Punching shear cannot be checked since the critical perimeter 1.5h from the column
face lies outside the base area. Because the footing is a thick slab with bending in two
directions, the critical section for shear is taken as 1.5d from the column face
f) Bending reinforcement
Longitudinal reinforcement
Mid-span of the columns
𝑀 = 717𝑘𝑁𝑚
𝑀 717 × 106
𝐴𝑠𝑡 = = = 2549𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 740
𝑀 340 × 106
𝐴𝑠𝑡 = = = 1208𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 740
0.13
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ = × 2300 × 800 = 2392𝑚𝑚2
100
Transverse bending
1.152
𝑀 = 400 × = 265𝑘𝑁𝑚
2
82
Area of steel required
𝑀 265 × 106
𝐴𝑠𝑡 = = = 942𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 740
Strip Footing
Strip footings are provided to bear the loads transmitted by walls in the case of load bearing
walls or where a series of columns are close together.Strip footings are analyzed and designed
as inverted continuous beamssubjected to ground bearing pressure. With a thick rigid footing
and a firm soil, a linear distribution of bearing pressure is considered. If the columns are equally
spaced and equally loaded the pressure is uniformly distributed but if the loading is not
symmetrical then the base is subjected to eccentric load and the bearing pressure varies as
shown below:
The bearing pressure will not be linear when the footing is not very rigid and the soil is soft and
compressible. In these cases the bending moment diagram would be quite unlike that for a
continuous beam with firmly held supports and the moments could be quite large, particularly
if the loading is unsymmetrical.
Reinforcement is required in the bottom of the base to resist transverse bending moments in
addition to the reinforcement required for the longitudinal bending. Footings which support
heavily loaded columns often require stirrups and bent up bars to resist shearing forces.
83
Example
Design a strip footing to carry 400mm square columns equally spaced at 3.5m centres. The
columns require 16mm dowels and the characteristic loads are 1000kN dead and 350kN
imposed. The safe bearing pressure is 200kN/m2 and the characteristic material strengths are
fcu=25N/mm2 and fy=460N/mm2.
Solution
Try footing depthof 700mm. Assume self weight of footing = 40kN/m
For Serviceability limit state
𝑄 1000 + 350 + (40 × 3.5)
𝑤𝑖𝑑𝑡ℎ 𝑜𝑓 𝑓𝑜𝑜𝑡𝑖𝑛𝑔 = = = 2.13𝑚
𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 200 × 3.5
Provide a strip of 2.2m wide
𝑀 693 × 106
𝐴𝑠𝑡 = = = 2976𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 612.5
Minimum area of steel required
0.13
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ = × 2200 × 700 = 2002𝑚𝑚2
100
84
Area of steel required
𝑀 495 × 106
𝐴𝑠𝑡 = = = 2126𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 612.5
Therefore provide Y20 top bars at 125mm centres (2513mm2)
Transverse Reinforcement
1.12
𝑀 = 257 × = 156𝑘𝑁𝑚
2
Area of steel required
𝑀 156 × 106
𝐴𝑠𝑡 = = = 670𝑚𝑚2
0.87𝑓𝑦 𝑧 0.87 × 460 × 0.95 × 612.5
Minimum area of steel required
0.13
min 𝐴𝑠𝑡 = 0.13%𝑏ℎ = × 1000 × 700 = 910𝑚𝑚2
100
Therefore provide Y16 – 200 (1005mm2) bottom steel
Shear
1.5d from the column face
𝑉 = 257 × 2.2 × (3.5 × 0.55 − 1.5 × 0.6125 − 0.2) = 456𝑘𝑁
Shear stress
𝑉 456 × 103
𝑣= = = 0.34𝑁/𝑚𝑚2 < 0.35𝑁/𝑚𝑚2
𝑏𝑑 2200 × 612.5
Therefore no shear reinforcement required
Raft Foundation
A raft foundation is a combined footing which covers the entire area beneath a structure and
supports all the walls and columns. This type of foundation is most appropriate and suitable
when soil pressure is low or loading is heavy, and the spread footings would cover more than
one half of the planned area. This way the raft is able to transmit the load over a wide area.
The simplest type of raft is a flat slab of uniform thickness supporting the columns. Where the
punching shears are large the columns may be provided with a pedestal at their base. The
pedestal serves a similar function to the drop panel in a flat slab floor.Other more heavily
loaded rafts require the foundation to be strengthened by beams to forma ribbed construction.
The beams may be either downstanding or upstanding.
Raft foundations normally rest on soil or rock, or if hard stratum is not available or is deep, it
may rest on piles
85
Piled Foundations
Piles are used where the soil conditions are poor and it is uneconomical to use spread footings.
There are two types of piles
1. Bearing piles – this is a pile that extends through poor stratum and its tip penetrates a
small distance into hard stratum. The load on the pile is supported by the hard stratum
2. Friction piles–this is a pile which extends through poor stratum and so bears its load
bearing capacity in the friction acting on the sides of the piles
Concrete piles may be precast and driven into the ground, or they may be the cast in situ type
which is bored or excavated.
A soil survey has to be carried out in order to determinedepth to firm soil as well as the
properties of the soil. This will help find the length of piles required.
Group piles can also be used. With these, the minimum spacing of piles should not be less than
1. The pile perimeter – for friction piles
2. Twice the least width of the pile – for end bearing piles.
Bored piles are sometimes enlarged at their base so that they have a larger bearing area
86
b) Area of horizontal reinforcement
The area of horizontal reinforcement in walls where the vertical reinforcement resists
compression and does not exceed 2% is given in cl.3.12.7.4 as
𝑓𝑦 = 250𝑁/𝑚𝑚2 0.3% of concrete area
2
𝑓𝑦 = 460𝑁/𝑚𝑚 0.25% of concrete area
c) Links
If compression reinforcement exceeds 2%, links must be provided through the wall
thickness (clause 3.12.7.5). Minimum links – 6mm or one-quarter of the largest
compression bar
d) Walls with axial forces and significant transverse and in-plane moments
The effects should be assessed in three stages as follows.
i) In-plane. Considering only axial forces and in-plane moments, the distribution of
force along the wallis calculated by elastic analysis, assuming no tension in the
concrete (see 3.9.3.4).
ii) Transverse. The transverse moments are calculated (see 3.9.3.3).
iii) Combined. At various points along the wall, effects a) and b) are combined and
checked using theassumptions of 3.4.4.1.
Design Procedure
Design may be done by
a) Using an interaction chart
b) Assuming a uniform elastic stress distribution
c) Assuming that end zones resist moment
88
Interaction chart
89
Example: Wall subjected to axial load and in-plane moments using design chart
The plan and elevation for a braced concrete structure is shown below. The total dead load of
the roof and floors is 6kN/m2. The roof imposed load is 1.5kN/m2 and that for each floor is
3.0kN/m2. The wind speed is 45m/s and the building is located in a city centre. Design the
transverse shear walls as straight walls without taking account of the columns at the ends. The
wall is 160mm thick. The materials are grade 30 concrete and grade 460 reinforcement
90
Therefore 𝑙𝑒 = 0.75𝑙 = 0.75 × 3150 = 2362.5𝑚𝑚
𝑙𝑒 2362.5
= = 14.8
ℎ 160
Dead and imposed loads on shear wall
Dead Load
Roof + floor slabs = 10 × 6 × (6 × 8) = 2880𝑘𝑁
Wall self weight = 0.2 × 24 × 6 × 35 = 1008𝑘𝑁
Total load at base = 3888𝑘𝑁
Imposed load
Table 2 of BS 6399 allows 50% imposed load reduction
Therefore
𝑖𝑚𝑝𝑜𝑠𝑒𝑑 𝑙𝑜𝑎𝑑 = (0.5 × 1.5 × 6 × 8) + (0.5 × 3 × 9 × 6 × 8) = 684𝑘𝑁
Dead and imposed loads on the ends of the walls from the transverse beams
Roof + floor slab = 10 × 6 × 4 × 8 = 1920𝑘𝑁
Column swt (400x400mm) = 0.4 × 0.4 × 35 × 24 = 134𝑘𝑁
4
Imposed load = 684 × 6 = 456𝑘𝑁
Wind load
Refer to CP3: Chapter V part 2
Condition: ground roughness factor – category 4
Building size – class B
𝑉𝑠 = 𝑉𝑠1 𝑠2 𝑠3
𝑞 = 0.613𝑉𝑠 2
Wind load values as analyzed from CP3 Chapter V pt.2 are as shown in the table below
H (m) 𝑠1 𝑠2 (𝑡𝑎𝑏𝑙𝑒 3) 𝑠3 𝑉𝑠 𝑞
Roof to floor 6 35 1.0 0.89 1.0 40.1 0.99
Floor 6 to 3 21 1.0 0.76 1.0 34.2 0.72
Floor 3 to base 10.5 1.0 0.63 1.0 28.4 0.48
𝑙⁄ = 40⁄ = 1.8
𝑤 22
ℎ⁄ = 35⁄ = 1.6
𝑏 22
𝑏⁄ = 40⁄ = 1.8
𝑑 22
From table 10, 𝐶𝑓 = 1.06
91
The wind loads are resisted by the 4 shear walls. The wind loads and moments at the base are
as follows:
𝐹 = 𝐶𝑓 𝑞𝐴𝑒
Roof to floor 6 load = 1.06 × 0.99 × 10 × 14 = 146.9𝑘𝑁
10.5
Moment = 146.9 × = 4113.2𝑘𝑁𝑚
2
Floor 6 to 3 = 1.06 × 0.72 × 10 × 10.5 = 80.2𝑘𝑁
10.5
Moment = 80.2 × (10.5 + ) = 1263.2𝑘𝑁𝑚
2
Floor to base = 1.06 × 0.48 × 10 × 10.5 = 53.4𝑘𝑁
14
Moment = 53.4 × (10.5 + 10.5 + ) = 280𝑘𝑁𝑚
2
Load Combination
a) Case 1
𝑁 = 1.2(𝐷𝐿 + 𝑖𝑚𝑝𝑜𝑠𝑒𝑑 + 𝑊𝑖𝑛𝑑)
= 1.2{3888 + 684 + 2(1920 + 134 + 456)} = 11510.4𝑘𝑁
moment = 1.2 × 5656.8 = 6788.2𝑘𝑁𝑚
b) Case 2
𝑁 = 1.4(𝐷𝐿 + 𝑊𝑖𝑛𝑑)
= 1.4{3888 + 2(1920 + 134)} = 11194.4𝑘𝑁
moment = 1.4 × 5656.8 = 7919.5𝑘𝑁𝑚
c) Case 3
𝑁 = 1.0 × 𝐷𝐿 + 1.4 × 𝑊𝑖𝑛𝑑 𝐿𝑜𝑎𝑑 = 3888 + 2(1920 + 134) = 7996𝑘𝑁
moment = 1.4 × 5656.8 = 7919.5𝑘𝑁𝑚
100𝐴𝑠𝑐⁄
𝑏ℎ = 0.6
92
Consider 1m of wall. The steel area in each of the two rows is
0.6 × 1000 × 160
𝐴𝑠𝑐 = = 480𝑚𝑚2 /𝑚
2 × 100
Therefore provide two rows of 12mm diameter bars at 200mm centres (565mm 2/m)
N = 4300kN
My=2100kNm
Mx=224kNm
Design the reinforcement for the heaviest loaded end zone 500mm long. The materials are
grade 30 and grade 460 reinforcement
Solution
Stresses
Elastic analysis
𝐴 = 150 × 4000 = 6.0 × 105 𝑚𝑚2
𝑏𝑑 3 150 × 40003
𝐼= = = 8.0 × 1011
12 12
Maximum stress
𝑁 𝑀
𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑠𝑡𝑟𝑒𝑠𝑠 = +
𝐴 𝑧
But
𝑏𝑑 2 150 × 40002
𝑧= = = 4 × 108
6 6
Therefore
4300 × 103 2100 × 106
𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑠𝑡𝑟𝑒𝑠𝑠 = + = 7.17 + 5.25 = 12.42𝑁/𝑚𝑚2
150 × 4000 4 × 108
93
1750
𝑠𝑡𝑟𝑒𝑠𝑠 = 7.17 + 5.25 × = 11.76𝑁/𝑚𝑚2
2000
500 1
At end zone, the portion of portion of moment Mxwill be 4000 = 8 𝑀𝑥
224
𝑀= = 28𝑘𝑁𝑚
8
𝑁
= 11.76
𝑏ℎ
𝑀 28 × 106
= = 2.5
𝑏ℎ2 500 × 1502
From interaction chart
100𝐴𝑠𝑐
= 1.5
𝑏𝑑
1.5𝑏𝑑 1.5 × 150 × 500
𝐴𝑠𝑐 = = = 1125𝑚𝑚2
100 100
PRESTRESSED CONCRETE
Prestressing refers to the purposeful and controlled creation of permanent stresses in a
structural member, before the full dead and live loads are applied so that they counteract all or
part of these loads. It serves 2 main purposes:
To improve resistance of a member to dead and live loads
To modify behavior of a member or structure in such a way as to make it more suitable
for its intended purpose
Prestressing in concrete is done with the aid of tensioned steel wires or strands referred to as
tendons. These are anchored against concrete
94
sum of the compression and bending stresses if it is assumed that the concrete will act
elastically
Eccentric prestress
By applying the force eccentrically on the concrete cross section, the effect will be as shown
below. The effects offer further advantage when attempting to produce working stresses within
required limits
95
Advantages of prestressed concrete
Permanent cracks can be avoided
Much less steel is required since the weight of the high strength prestressing steel is only a
fraction of the weight of reinforcement which it replaces
The cross-section of the member can be smaller, since the whole of the concrete is put to
structural use
Not only is the concrete fully utilized, but the need for tension reinforcement is also
removed
The resistance of beams to shearing and flexural cracks is considerably increased making it
possible to provide longer and spans or cantilevers using comparatively shallow and slender
sections
By controlling the amount of prestress, a structure can be made to be either rigid or flexible
without affecting its ultimate resistance. A flexible structure is more resilient and will
absorb considerable energy before failure due to impact and thus show improved
performance under seismic and dynamic conditions
Prestressed structures, especially liquid retaining structures, have improved durability
Disadvantages
The fact that most, if not all, of the concrete cross section is in compression under all load
combinations means that any inherent problems due to long term creep movements are
increased.
From the point of view of construction, a high level of quality control is required, both for
material production and for locating the tendons within the structure.
The technology required for prestressing concrete may not be available in many developing
countries and so may prove to be uneconomical
96
Advantages of pre tensioning over other methods of prestressing
Excellent and reliable bond can be obtained between the concrete and tensioned
steel over its entire length
Since production is done in a factory, it is easier to ensure that there is satisfactory
supervision than on site
Disadvantages
Tendons must be straight which may cause difficulty when trying to produce the
acceptable final stress level throughout the entire length of the member. It may
therefore be necessary to reduce either the prestress force or eccentricity at the
ends in which case tendons must either be debonded or deflected
2. Post tensioning
In this case, prestress force is applied by jacking steel tendons against an already cast concrete
member. The tendons are threaded through ducts cast into the concrete, or in some cases pass
outside the concrete section. Once the tendons have been tensioned to their full force, the
jacking force is transferred to concrete through special anchorages.
The prestress force in post tensioned members is usually provided by many individual wires or
strands grouped into large tendons and fixed to the same anchorage. The concentrated force
applied through the anchorage sets up a complex state of stress within the surrounding
concrete and reinforcement is required around the anchorage to prevent concrete from
splitting.
After stressing, the remaining space in the ducts may be left empty (unbonded construction) or
it may be filled with grout under high pressure(bonded construction). Grout helps in
transmitting of forces between steel and concrete under live load thereby increasing the
ultimate strength of the member. Unlike pre tensioning, it is possible to incorporate curved
tendons. The flexible sheaths can be held to a curved shape while the concrete is poured
around them.
Advantages of post tensioning over pre tensioning
Tensioning can be carried out in stages, for all tendons in a member, or for some of
them. This can be useful where the load is applied in well defined stages.
97