National Oil Corporation: Rev Date Description Checked Approved
National Oil Corporation: Rev Date Description Checked Approved
National Oil Corporation: Rev Date Description Checked Approved
GES L.09
INDEX
1.1 Introduction 4
1.2 Other NOC Specifications 4
1.3 Data Sheets 5
1.4 Stability Study 5
2.0 DEFINITIONS 5
2.1 Technical 5
2.2 Contractual 7
4.0 CONSTRUCTION 14
5.1 General 26
5.2 Salient Differences 26
6.0 INSPECTION 27
6.1 Procedures 27
6.2 Scope 28
6.3 Nameplates 29
7.0 TESTING 30
8.0 DOCUMENTATION 34
8.1 Introduction 34
8.2 Schedules and Reports 34
8.3 Data and Calculations 34
8.4 Drawings 35
8.5 Final Records, Documents and Manuals 35
Figures 38
1.1 Introduction
1.1.1 This specification covers the minimum requirements for the design, construction, inspection and testing of
Power Generation Units of the brushless type complete with the necessary automatic voltage regulator
(AVR).
For the purpose of this specification, Power Generation Units are defined as 3 phase medium voltage (MV),
brushless, salient pole alternators, automatic voltage regulator (AVR) and excitation system for operation
on alternating current supplies at voltages exceeding 1000 volts and ratings from 2 MVA to 41.25 MVA
inclusive.
1.1.2 This specification applies to power generation units for refineries, onshore oil & gas installations and
processing facilities, including units purchased either directly or as part of a package.
1.1.3 This specification is generally based on ANSI/NEMA standards. The Vendor/Contractor shall comply
fully with the provisions laid down in this specification. Any exception must be clearly stated and be
authorised in writing by the Owner.
1.1.4 In the event of any conflict between this specification and the Data Sheets, or with any of the applicable
codes and standards, the Vendor/Contractor shall inform the Owner in writing and receive written
clarification from the Owner before proceeding with the work.
1.1.5 This general specification will form part of the Purchase Order/Contract, together with Data Sheets,
drawings or other attachments.
The following NOC General Engineering Specifications are an integral part of this specification and any
exceptions shall be approved in advance by the Owner:
GES A.04 Noise Level Criteria and Noise Control of Mechanical Equipment
*Only the relevant specifications in the asterisked series should be forwarded, according to the selected
type of driving unit.
The technical data supplied by the Owner for the equipment is given on the Data Sheets which are included
at the end of this specification.
The Vendor/Contractor shall complete the relevant parts of the Data Sheets with the remaining information.
The Vendor/Contractor shall also to supply the necessary data to 'model' the machine in power system
stability (and load flow/fault calculation) studies.
2.0 DEFINITIONS
2.1 Technical
Statutory Tests
Statutory tests are those intended to establish compliance with selected, widely applicable requirements of
the manufacturing standard.
Critical Speed
A speed at which the amplitude of the vibration of a rotor due to shaft transverse vibration reaches a
maximum value.
Cross-current Compensation
One of two systems which permits generators in parallel, to share the reactive component of the power in
proportion to their rating while maintaining constant output voltage. See also Droop Compensation.
Droop Compensation
A system which permits generators in parallel to share the reactive component of the power in proportion to
their rating. See also Cross-current Compensation.
Dead Band
Dead band is the total magnitude of the change in steady state speed within which there is no resulting
measurable change in the position of the governor controlled valve(s). It is a measure of the speed
governing system insensitivity and is expressed in percent of rated speed.
Flexible Shaft
A shaft which is intended for operation at speeds greater than the first lateral critical speed.
In order for isochronous load sharing to be used, each turbine generator set in the system must have a
governor with the isochronous load sharing feature.
Low Voltage
Medium Voltage
A class of nominal system voltages equal to or greater than 1000 V and less than 100,000 V.
The rms "phase to phase" or "phase to neutral" voltage by which the system is designated and at (or near)
which level, the system normally operates.
Output Power
The useful electrical power measured at the output terminals after all losses are deducted; unless otherwise
stated, this is assumed to be at a lagging power factor of 0.8.
PMG
Permanent Magnet Generator; A generator in which the field excitation is supplied by permanent magnets.
Rated Power
The rating in kilowatts, which can be carried continuously without exceeding the rated temperature rise at
rated voltage and frequency.
Speed regulation, expressed as a percentage of rated speed, is the change in sustained speed when the
power output of the driving unit is gradually changed from rated power output to zero power output under
specified steady state conditions.
Stiff Shaft
A shaft which will not be operated during normal circumstances at speeds greater than the first lateral
critical speed.
Utilisation Voltage
The rms "phase to phase" voltage at the line terminals of utilisation equipment.
2.2 Contractual
Owner
The oil and gas company, an associate or subsidiary, who is the end user of the equipment.
Vendor
Contractor
Sub-Contractor
A company awarded a contract by a Contractor to do part of the work awarded to the Contractor.
Inspection Authority
The organisation representing the Owner or Vendor/Contractor that verifies that the equipment has been
designed, constructed, inspected and tested in accordance with the requirements of this specification and
the Purchase Order/Contract.
Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection Authority,
who verifies that the equipment has been designed, constructed, inspected and tested in accordance with the
requirements of this specification and the Purchase Order/Contract.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 8 of 38
Rev 0 1999
3.0 DESIGN AND PERFORMANCE
These conditions are fully detailed in GES A.06, and cover the principal conditions affecting the electrical
equipment including maximum and minimum ambient temperature, dust, humidity and altitude etc.
Internal equipment may be housed in an enclosed, air-conditioned room; full details are given in GES B.12.
Temporary excursions from these limits, e.g. during short term power failures, shall be ignored for the
purposes of equipment rating.
3.2.1 General
In general, the requirements specified herein are based on the ANSI/NEMA and other American Codes and
Standards, the most important of which are listed below.
Unless specified otherwise in the Purchase Order/Contract, the current editions of the codes and standards
at the time of order shall be used.
The Vendor/Contractor shall operate and supply certification for a Quality System complying with the
requirements of the ASQ Q9000 Series or BS EN ISO 9000, Part 1 (Design) Part 2 (Production) and Part 3
(Test and Inspection).
ANSI/IEEE 433 Large AC Rotating Machinery with High Voltage at Very Low Frequency,
Practice for Insulation Testing of,
API 670 Vibration, Axial Position and Bearing Temperature Monitoring Systems
NEMA MG-2 Safety Standard for Construction and Guide for Selection, Installation
and use of Electric Motors and Generators
NEMA MG-3 Sound Level Prediction for Installed Rotationary Electrical Machines
NEMA Standards Publication Enclosures for Electrical Equipment (1000 volts minimum)
No.250
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 9 of 38
Rev 0 1999
NEMA Standards Publication Land Based Steam Turbine Generator Sets 0 to 33,000 kW
No. SM24
When appropriate, equivalent International Standards which may be used as alternatives are listed below
and may be used with the prior approval of the Owner. Equipment and materials complying with IEC
Recommendations shall be at least equal to the requirements of this specification. The Vendor/Contractor
shall advise full details of any deviations to these requirements in his offer if IEC based documentation is
utilised.
BS 3643: Pt. 1 ISO Metric Screw Threads - Principles and Basic Data
BS 5000 Specification for Rotating Electrical Machines of particular types for particular
applications
EATS 44-5 Testing the Insulation Systems of Stator Coils for Rotating Electrical
Machines
EATS 44-5 Testing the Insulation Systems of Bars (half coils) for Rotating
Electrical Machines of Turbine Driven and Hydro Generator Types
3.3.1 Rating
Alternator rated voltage and frequency shall be as stated on the Data Sheets.
3.3.2 Operation
The alternator and ancillary equipment shall be suitable for operating under the following conditions:
(a) Continuously for 26,000 hours (3 year) periods without attention which would require the machine
to be stopped.
(b) Continuously, excepting maintenance periods, at the continuous maximum rating (CMR) for a 25
calendar year life.
(c) Connected in parallel with other machines and/or a Public Supply Authority network.
Parallel running provision is required on all machines, however the machine shall be capable of
running independently when required.
(d) The system will have large AC induction cage motors frequently switched, direct on line (DOL)
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 10 of 38
Rev 0 1999
starting.
These motors typically could be rated in excess of 1 Megawatt (whether as a single rating or a
combination of machines) and the Generator may supply starting currents of such machines to
NEMA MG1 Part 10 - Design D, kVA per horsepower = 4(BS 4999 Part 112, Design D - Column
3, Table 4).
It shall be assumed that the instant of motor switching always gives full offset current in the same
phase, with motor acceleration occupying a period of 15 seconds. The busbar voltage drop shall
not exceed 15% during load application.
(e) The Vendor/Contractor shall assume that the machines are located in an area where the
atmosphere may be corrosive and dusty and these deposits may be conductive.
Unless stated otherwise, Class "F" insulation with a Class "B" temperature rise limitation shall be
applicable to NEMA MG 1, Part 22, Clause 22.40.
The Vendor/Contractor shall supply Lightning Arresters to reduce the magnitude of induced voltages due
to lightning strikes and Surge (Capacitor) Suppressors to modify the steepness of the waveform of induced
voltages.
Both sets of devices shall be fitted on the line side of the machine and the Vendor/Contractor shall provide
full details of these devices.
3.6 Vibration
(a) For all alternators, vibration in any direction as measured on the bearing housing, shall not exceed
the limits given in Table 1 overleaf:
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 11 of 38
Rev 0 1999
Table 1: Vibration Limits
(b) The vibration limits given in Table 1 shall be measured under the following conditions:
- The alternator running uncoupled at no load, at normal voltage and frequency, and at
various speeds of its speed range.
- A half key in the shaft keyway, (or half coupling fitted, if available).
- For alternators having provisions for vibration monitoring systems, vibration shall also be
measured on the shaft adjacent to each bearing housing or through the bearing or
coupling housing. Vibration as measured shall not exceed the limits given in Table 1
above:
Reference shall be made to MG 1, Part 22, Clause 22.54 and Part 20, Clause 20.54.
(a) Standard ratings shall be in accordance with Table 20.10, Part 20 of NEMA MG 1, or if steam
turbine driven, to Table 2.1 of NEMA Standard SM24.
At rated speed, the alternator shall have sufficient capacity to continuously match the full rated
output of the prime mover under both summer and winter extremes of ambient conditions
specified, without exceeding the Insulation Class F total temperature limit (limited to Class B
temperature rise).
(b) A Service Factor of 1.0 shall be assumed for the alternator rating and characteristics which shall
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 12 of 38
Rev 0 1999
comply with the requirement of the latest editions of NEMA MG1, Part 22 (BS 2757, 4999 and
5000) except where modified by this specification. The complete alternator output characteristic
curves shall be provided with the Tender.
(c) The alternator rated voltage shall be nominal (as on the Data Sheets) ± 6%. Maximum ground
fault current shall be limited to 25% of the machine's nominal full load current by a high
impedance neutral grounding transformer or resistor as agreed with the Owner. The
Vendor/Contractor shall quote the net alternator output after subtracting all power absorbed by the
generator, exciter and main shaft driven auxiliaries as well as auxiliaries fed directly from the
machine or exciter. Sustained rated outputs shall also be possible within the stated voltage
variations at rated power factor, in accordance with the requirements of NEMA MG1 (BS 5000
Part 99).
(d) The prospective three-phase fault current infeed from the system to the alternator shall be taken as
equivalent to 25 kA rms symmetrical.
(e) Continuous operation over a frequency range of nominal, -6% + 2.5% shall be possible at rated
stator current. Below -6% nominal frequency the output voltage may be reduced pro rata with
frequency.
(f) The alternator shall have a short circuit ratio of 0.45 unless stated otherwise on the Data Sheets.
The ratio shall be based on the per unit no-load excitation current at rated alternator voltage and
the per unit short-circuit excitation current at rated alternator current.
(g) The tolerance on the stated values of transient and sub-transient reactances shall be ± 0.15 per unit
of the stated value.
(h) The Vendor/Contractor shall provide with the tender a statistical survey of his test results for
machines of the same or similar frame and output showing the distribution of the deviation from
the predicted value. Great importance is attached to the reactance values. The switchgear making
duty often also imposes a constraint on the minimum confirmation and agreement. The dynamic
stability of the system with the potentially low stored energy constants often also imposes
limitations on the maximum transient reactance.
(i) The maximum prospective 3 phase rating fault making current of the MV switchgear shall be at
least equivalent to 25 kA rms symmetrical, and shall be assumed to be of this value for
consideration of winding/termination stressing unless stated otherwise on the Data Sheets.
(j) The constraints imposed by switchgear fault and fault clearing times incur potential dynamic
stability problems which focus attention on the overall machine inertia constants. Subject to
confirmation and agreement, the inertia constant for both turbine and generator shall be advised in
MJ/MVA.
(k) The design shall take into account the non-natural reactance which may be required (should the
frame size be increased) to maintain the fault current contribution to the switchgear making duty
within the permissible value.
(l) The machine shall be capable of a momentary overload of 150% normal current for 1 minute with
the field set for normal load excitation.
(m) Excitation shall be of the brushless type with a Permanent Magnet Generator (PMG) Voltage
Control Unit, Exciter and rotating diodes as shown in the diagram in Section 10.0.
The PMG shall have a high excitation field forcing capability to provide good motor starting
characteristics and, for fault clearance, a sustained short circuit capability of three times the
normal full load current for 10 seconds.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 13 of 38
Rev 0 1999
(n) The characteristics of the complete alternator including the excitation system shall maintain a
steady state voltage of ± 2.5%, between no load and rated load.
(o) The alternator shall be capable of withstanding Negative Phase Sequence Current (I2) up to 10%
of rated stator current (See NEMA MG1 Part 22, Clause 22.46).
3.7.2 Waveform
The output waveform of the alternator shall be sinusoidal; the allowable degree of distortion shall be
limited to a TIF as detailed in Clause 16.43 of NEMA MG1 Part 16, or if steam turbine driven, to the
values given in Clause 2.13.3 of NEMA Standard SM24.
The voltage regulation as measured at the alternator terminals shall either be as stated in Section
16.4.8.2.4, Part 16 of NEMA MG1 or shall be a minimum of Grade 3.11 (VR3) to BS 4999 Part
140 which requires restoration to ± 1% of voltage in not more than 10 seconds after a transient
disturbance, whichever is the more onerous.
The transient performance shall be better than that stated in Part 16, Clause 16.48.2.3 & 4 of
NEMA MG1 (VR 2.13 of Table 1 'Voltage Regulation Grades' of BS4999 part 140) and shall be at
least as follows:
35% Rated Current (at rated voltage) Load Application & 100% Rated Current Load Removal
Maximum recovery time 0.5 seconds to 97% of rated voltage. Overvoltage not more than 38%
with rated kVA at 0.8 pf thrown off, with maximum recovery time to 103% rated voltage not more
than 1 second.
With 35% rated current applied at a power factor between 0.4 and zero lagging, the initial voltage
drop shall be limited to 15% of rated voltage with recovery to 97% of rated voltage in less than 0.5
seconds.
Note:
A Design 'D' induction motor as defined in NEMA MG1 Part 10, (or combination of motors) rated
at 1400 kW shall also be capable of starting without exceeding the maximum voltage drop of 15%
of rated voltage with recovery to 97% of rated voltage in less than 0.5 seconds and restoration to ±
1% of the steady state voltage within 10 seconds.
3.8 Noise
(a) The noise level criteria for the plant shall be as specified in GES A.04.
(b) Unless stated otherwise on the Data Sheets for individual machines, the sound pressure level shall
not exceed 81 dB(A) measured at not less than 1.1 yards (1 metre) from the equipment surface.
However, certain machines may have an overcritical (flexible shaft) rotor-bearing system. The first critical
speed shall be lower than 80% of the synchronous speed but should not be lower than 60% of the
synchronous speed. The second critical speed shall not be lower than 125% of the synchronous speed.
The enclosures shall be adequately braced so that the critical speeds do not transmit excessive vibration into
the enclosure and components.
3.10 Overspeed
The machine shall be so constructed that in emergency they will withstand without mechanical injury,
overspeeds above the rated synchronous speed of 125% synchronous speed for 2 minutes.
Alternators driven by machines which require a variable torque during each revolution, e.g. Diesel Engines,
shall have sufficient inertia to limit the deviation factor in the open circuit line to line terminal voltage to a
value not exceeding 0.1 as specified in NEMA MG1, Part 22, Clause 22.42.
The additional inertia necessary to comply with the current variation and speed irregularity requirements,
should be added to the rotating mass of the alternator.
If this requirement cannot be met, approval shall be obtained from the Owner regarding an alternative
design.
(a) The alternator shall be suitable for satisfactory parallel (droop or isochronous) operation with
other machines and systems, however, it shall be suitable for running independently if required.
(b) The speed governor will be provided by the Driving Machine supplier. For the purpose of
Electrical System Design and Operation, it is assumed that it will be a fast acting Electronic
Governor with a maximum speed regulation of 4% droop (Class C to NEMA Standard SM24,
Table 3.1).
4.0 CONSTRUCTION
4.1.1 The alternator(s) shall be salient pole rotor type with either Air to Air or Air to Water cooling as detailed
later in Section 4.7.
Open type machines with filter ventilation (pulse filters or other types) are not considered in this
specification.
4.1.2 Class "F" Insulation materials complying with the requirements of NEMA MG1 Part 1/IEEE Std.1 (BS
2757 and BS 4999 Part 144), shall be used as extensively as possible for the alternator and excitation
equipment. The use of other than Class "F" material as a main insulation shall be stated in the Tender.
Details of the insulation shall accompany the tender and shall be supported by evidence of satisfactory
experience of a number of years continuous operation.
4.1.3 The direction of rotation shall be as required by the prime mover and indicated on the Data Sheets.
4.1.4 The main terminals shall be distinctly and permanently marked and identified to NEMA MG1 Part 2 (BS
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 15 of 38
Rev 0 1999
4999 Part 108).
4.2 Stator
4.2.1 The casing of the stator shall be of fabricated steel construction and the enclosure shall be a minimum of
IP54 to NEMA MG1 Part 5 (BS 4999, Part 5) totally enclosed.
4.2.2 All fixings and fastenings on the stator, components, windings and enclosures shall be positively locked to
withstand any vibratory and starting duties imposed on them.
4.2.3 The stator core shall be made up of high permeability, low loss silicon steel laminations suitably braced and
located to ensure true concentricity of the core and to reduce magnetic noise and vibration to a minimum.
No bolts or clamps shall pass through the core and permanently located and robust radial support fingers
shall be provided for the slot teeth.
4.2.4 The stator frame shall be of pressed and welded construction with the core clamped between endplates and
located by keybars. The baseplate shall be of the welded steel box girder type, stress relieved, where
necessary. The completed structure shall be proven to be free from excessive vibration including vibration
from critical speeds.
4.2.5 The ends of the stator frame shall be enclosed by rigid metallic end covers/bells. Rigid baffles shall be
provided to protect the stator end wirings and to control the distribution of the cooling air. Where these
baffles are subject to magnetic fields, they shall be of non-magnetic material. GRP baffles shall be braced
to prevent aerodynamic buffeting. The design shall prevent excessive 100 Hz/120 Hz vibration being
transmitted to the machine foundations, pipes or associated equipment.
4.2.6 The Owner's Inspector may require to check the truth of the stator bore at four positions around the
clockface at either end and in the centre of the stator 'pack'. Tolerances to be not more than ± 20 mil (0.5
mm) on nominal size.
The core slots shall be of the open type and wedges shall not be magnetic such as glass fibre.
4.3.1 The stator winding shall be of diamond involute, rectangular strip, form wound type coils, with short
pitched (chorded) turns. The output voltage waveshape shall be sinusoidal with particular emphasis on
minimising the harmonic components of current generally (And 5th and 7th components in particular) plus
the 3rd and 9th components which can flow when the alternator neutral is effectively connected to earth
and the machine is operating in parallel with other machines or the industrial power system.
4.3.2 The conductors shall consist of a number of parallel insulated strips of copper of substantial cross section
transposed as necessary to minimise losses. The general construction of the stator and the bracing of the
winding overhang shall provide adequate cooling and avoid hot spots.
4.3.3 The winding shall be discharge free on a voltage falling to 'nominal' + 6%.
The preferred series of tests on the coils and completed stator is detailed in ANSI/IEEE 95 and 433
(BS 4999 Part 144).
The Vendor/Contractor shall detail in the tender which tests are included. He shall quote an extra price for
each test not included but which he is able to perform.
4.3.4 Anti-corona graphitised tape protection with end grading shall be applied to the slot portion of the insulated
coils with a semi-conducting stress grading tape applied to the end of the corona shield. The insulation
shall be void free and homogeneous.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 16 of 38
Rev 0 1999
4.3.5 The stator winding overhang shall be supported from the frame keybars and adequately braced to prevent
movement under the specified system conditions for motor starting. The bracing shall withstand without
movement the full voltage fault currents associated with a sudden short circuit across the main terminals
with full automatic voltage regulator action when the alternator is connected to the prospect fault level
detailed on the Data Sheets.
4.3.6 One completed machine of any series shall undergo 100% rated terminal voltage sudden short circuit
testing, (preferably) with "point on wave" of switching selected to give at least one shot with full offset in
one phase. High speed photography of the end winding is also preferred to demonstrate the soundness of
the bracing, although physical inspection and a HV pressure test (after the short circuit) is acceptable, as is
random switching if "point on wave" is not possible.
4.3.7 The windings shall be arranged for star connection with all six ends brought out to Elastimold (or equal)
fully fault tested terminals and clearly permanently identified with phase and sequence. The terminals (bus
bars) shall be suitable for receiving the number and type of cables or bus bars per phase specified on the
Data Sheets, with their appropriate termination.
4.3.8 Contact between adjacent coils between coils and other conductors and between the six winding end tails
shall be avoided by adequate spacing, bracing and support. Suitable insulating spacers are not
precluded. Great care is taken on the industrial system to preclude phase to phase MV faults, by
using the appropriate cabling etc. Similar care is expected of the Vendor/Contractor in the
arrangements of the alternator and connections and full details shall be given in the tender.
4.3.9 The six ends of the winding (Line and Neutral) shall be brought out onto the same side (left hand side
viewing from non drive end) of the machine (on the opposite side to the cooler and lubricating oil
pipework) into a Fabricated sheet steel integral Line/Neutral cubicle.
Adequate space shall be provided by the Vendor/Contractor for the mounting of:
(a) 1-3 Phase double secondary VT, 110v Synchronising, 110v Instruments (100 VA, Class 1)
complete with Primary and Secondary Fuses;
(c) 6-Class 'X' 'Ring' CTs for Differential Protection (3 in Line and 3 in Neutral end);
(d) 3-Class 5P20 12VA, General Protection 'Ring' CTs (Neutral end);
(f) If relevant, any Differential ring CTs required for Generator Transformer Differential Protection
(Line end);
(j) Rogowski Coils (Line end) for non invasive monitoring of the Stator Winding condition.
Notes:
1. The CT and VT connections shall be brought out to a separate external terminal box to allow
access without opening the main connection chamber.
2. The copperwork shall be adequately sized for the full load current of the machine and be braced
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 17 of 38
Rev 0 1999
for a 25 kA fault level (or as indicated on the Data Sheets).
3. The tender shall include full details of the proposed method of winding/terminations, which shall
be to the Owner's approval.
4.3.10 Nine off Simplex 3 wire resistance temperature detectors (RTDs) (6 in use and 3 spare) with platinum
elements having a resistance of 100 ohms at 0°C, shall be equally distributed between the 3 phases,
complete with surge protection against overvoltages induced from the stator winding.
Each element shall be located about the middle of the core and alongside the insulating separator between
the top and bottom coil in the slot. The connections shall be brought out by screened leads (if necessary to
reduce pick up) to a terminal box safely accessible from outside the stator with the machine in service. The
heat run of the completed machine will identify the highest reading elements in each phase and these shall
be marked for use on site for service monitoring of the stator temperature.
Bearings may be either the 'end frame bracket' type or 'pedestal' type according to the Vendor/Contractor's
recommendation.
4.4.1 All bearings on the main shaft system shall be of white metal sleeve type with forced oil lubricated from the
turbine oil system. The bearing pedestals (if utilised) shall be mounted on the common rigid steel box bed
frame of the machine; bearings must be free from instability due to oil whirl.
4.4.2 The bearings shall be insulated to prevent the circulation of shaft currents which would damage the
bearings. A removable copper earthing strap shall be fitted in a readily visible place on the bearing housing
to earth the shaft and allow periodic measurement of the shaft system insulation from earth.
4.4.3 The oil and lubrication system shall in other respects follow the specification for that of the driving
machine.
4.4.4 Embedded Duplex (PT100) resistance temperature detector for use with a remote indicator with Temp
Alarm/Trip facilities shall be fitted to each bearing. Single bearing machines may be utilised if it is
financially advantageous and if agreed and co-ordinated with the Driving Equipment/Gearbox
Vendor/Contractor.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 18 of 38
Rev 0 1999
4.5 Rotor
4.5.1 The salient pole rotor body shall be of forged steel, preferably comprising one solid forging. The forging
shall be manufactured by an approved forgemaster and shall be subjected to stringent quality control
throughout manufacture.
The Vendor/Contractor shall submit with this offer, full details of the proposed schedule of tests and quality
control together with details of the material and heat treatment to be applied to the forging. The rotor body
shall be thermally stable under all service conditions.
4.5.2 The salient pole rotor shall be machined from a single steel forging.
After rough machining the forging shall be subjected to 100% ultrasonic witnessed examination;
equipment, probes, calibration and sensitivity shall be to the approval of Owner.
4.5.3 The design of the rotor shall give an adequate margin (say 0.2 pu, 20%) between rotor critical speeds and
the normal running speed and shall exceed the overspeed test speed. The critical speeds shall be declared
with the tender and the Vendor/Contractor shall demonstrate that full account has been taken of oil film and
bearing flexibilities.
4.5.4 The maximum permissible error in air gap shall be declared in the tender. These shall be taken into account
when plotting unbalance magnetic forces against stiffness of rotor and stator. The overspeed test on the
completed rotor shall be in accordance with NEMA MG1 (BS 4999 Part 143) but shall not be less than
125% of the normal synchronous speed. The balance shall be checked both before and after the overspeed
test to prove that nothing has been displaced by the test. The Vendor/Contractor shall declare the balancing
procedure used during factory tests and that procedure required on site subject to any maintenance
operations.
4.5.5 The vibration level for the complete rotor (with the half coupling fitted), measured at the bearing housings,
vertically, axially and transversely shall be to NEMA MG1 or better i.e less than one half of the maximum
values quoted in NEMA MG1 (BS 4675 Class IIIB), i.e a limit of 2.25 mm/s RMS total velocity when
tested at the Vendor/Contractor's works. This test to be performed with the rotor in both unexcited and
excited conditions. As far as possible, all balance weights shall be fitted into the body of the rotor.
4.5.6 All bolts or other fastenings on the rotor shall be positively locked.
4.5.7 The space required for rotor withdrawal shall be shown on the tender drawings. The proposed method
shall be stated with the instruction manual and any necessary special tools and handling devices shall be
included in the tender.
4.6.1 Deformation of the rotor winding due to "copper-shortening" or phase or earth faults developing either in
the machine or on the connected system shall be avoided by suitable choice of material and rotor design.
The rotor-cooling system shall be entirely suitable to ensure that no hot spots develop and details of the
cooling method shall be included in the tender.
4.6.2 The rotor winding shall be high conductivity copper strip. All joints between coils shall be adequately
brazed. The winding insulation shall be Class "F" (limited to Class 'B' rise) as detailed in NEMA MG1 Part
16, with the specified cooling air or cooling water temperature.
4.6.3 The field coils are to be of strip on edge construction with interturn insulation cured under heat and
pressure to give fully consolidated units. The coils are to be insulated with spools top and bottom and
additional insulation as necessary. The insulated coils are to be assembled on the poles and held in place
with bolted on pole shoes and 'V' blocks between the coils where necessary.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 19 of 38
Rev 0 1999
4.6.4 The clamping blocks used in the rotor winding shall be approved material and suitable for the high
temperature and mechanical forces which exist in the rotor.
4.6.5 Particular attention shall be given to the insulating and securing of coils to avoid vibration and the possible
failure or slackening of either the connector or its insulation under any condition of service.
4.6.6 The Vendor/Contractor shall supply curves showing permissible single and unbalanced phase loading
against time.
4.7.1 The cooling system shall be either Totally Enclosed Water-Air cooled (Part 1 of NEMA MG1 CLause
1.26.8,) or Totally Enclosed Air to Air cooled (Part 1 of NEMA MG1 1.26.9,) as indicated on the Data
Sheets.
4.7.2 The ventilation shall have combined axial and radial flow. Care shall be taken in selecting the combination
of radial ducts to avoid pure tone noise generation. The cooling air flow shall be distributed to cause a
uniform temperature throughout the windings and iron.
4.7.3 A pair of shaft mounted fans shall draw the cool air from the heat exchanger outlets. One fan shall be
mounted at each end of the shaft. Each fan shall be of substantial design with individual blades bolted to
the shaft by two bolts with locking washers. The fan shall be shrouded to prevent unwanted air
recirculation and designed to work at its best efficiency point in conjunction with the cooling system. The
materials of construction shall not be subject to stress corrosion cracking. The fan maximum stress at
overspeed shall not exceed 30% of the elastic limit. The fan design and natural frequencies of vibration
shall be determined theoretically and practically to avoid resonances and evidence of this shall be produced
before manufacture commences.
4.7.4 The arrangement of the shaft seal shall preclude bearing lubrication oil mist from being induced into the
cooling air circuit by the suction of the alternator cooling fans.
4.7.5 Provision shall be made for ready access into all temperature chambers for inspection and cleaning.
4.7.6 Provision shall be made for measuring the air temperature at the exit from and entry to the heat exchangers
by the provision of 3 Duplex RTDs externally mounted and also 1 Duplex RTD in Exciter Hot Air Circuit.
The arrangement shall allow safe replacement of the RTD's whilst the machine is on line.
Duplicate 50% Banks of Top Mounted water cooled heat exchangers shall be provided. One exchanger
shall be in each path of the divided flow main ventilation system.
Provision shall be made for easy removal of the two heat exchanger bundles. The space for handling
coolers shall be declared on the machine drawing.
The heat exchangers shall be 2 off 50% Bundles each of high integrity design and construction, with
individual leak detector features for each 'Bundle'. The side sheets and tube plates shall be cross braced to
withstand handling without risk of leakage.
A shut off valve and short elbow pipe (with flange) shall be provided for each of the two Bundles (Total of
4 valves).
Where the exchangers are not double tube/tube plate type, the heat exchanger construction shall be as
follows:
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 20 of 38
Rev 0 1999
The water side tube plate shall be:
(a) Carbon steel with minimum thickness of 1.5" (30 mm) including a corrosion allowance of ¼"
(6 mm). The tubes shall be expanded into this tube plate with an expansion length of 1" (25 mm)
from the air side of the plate. The water side shall be protected by two full coats of epoxy
bitumastic paint applied to the prepared surface.
(b) The elements shall be single wall aluminium Finned Tubes of high grade (90/10) cupro-nickel
(equivalent to BS 2871 grade CN 102) with a minimum thickness of 20 SWG. The tubes shall be
expanded to eliminate any gap between the tube and tube plate.
(c) Baffle spacing or lacing shall be provided to prevent tube vibration and fatigue failure. For this
the Vendor/Contractor shall supply detailed drawings and flow data for the air circuit. The water
boxes shall be of cast or fabricated carbon steel and have a corrosion allowance of 120 mil
(3 mm). The construction shall be robust to avoid distortion or damage during handling. Internal
surfaces exposed to water shall be protected by a process of surface preparation followed by two
complete coats of bitumastic paint.
(d) All steel surfaces shall be prepared and adequately painted to prevent corrosion.
(e) A spray baffle in the return air circuit shall be fitted after each element to prevent water ingress to
the alternator in the event of leakage, and a catchment tray and leakage detector shall be fitted for
each of the `bundles'.
The tender shall declare the method of construction proposed. The fouling margin shall be stated, together
with information on required quantities, predicted exit temperature, total heat rejection, exchanger rating
etc. as required on the data schedule.
(a) The unit shall be top mounted and of carbon steel with an adequate corrosion allowance for a 25
year life.
(b) All steel surfaces shall be prepared and adequately painted to GES X.06 to prevent corrosion.
4.9 Excitation
4.9.1 The method of excitation shall be subject to detailed agreement by the Owner, a high speed of response is
required to assist dynamic and system stability, and generally complying with the relevant part of MG1 (BS
5000).
The excitation system shall be Brushless including a close coupled permanent magnet generator (PMG).
In the interests of fast response and reliability, no part of the excitation system (compounding CT) shall be
used for another purpose. this excludes the VT which should, however, have double secondaries with a
110 V for the AVR and 110 V for Synchronisation and metering.
4.9.2 The excitation system shall have quick acting field suppression (as well as Field Forcing) and be complete
with:
1- thyristor type automatic voltage regulator suitable for controlling the output voltage of the
brushless A.C. generator specified, to within ± 0.5% of its nominal rated value when running
singly at rated power factor.
1- Excitation limits module with current limit CT, PF potentiometer, meter relay and power factor
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 21 of 38
Rev 0 1999
relay.
1- Hand control module with Auto follow-up and Null Balance allowing automatic changeover
(without disturbance) from 'AUTO' to 'HAND' Control upon failure of the AVR or field failure as
well as manual transfer from 'HAND' to 'AUTO'.
1- Hand/Auto contactor.
1- Excitation contactor.
4.9.3 The system offered must have been in service satisfactorily and proven for several years continuous
operation. The tender shall include an application list of relevant machines of similar frame, together with
full technical details of the proposed system.
4.9.4 All rotating excitation machines shall be integral driven from the main shaft.
4.9.5 The cooling air for shaft driven excitation equipment shall be taken from the main machine air circuit.
4.9.6 A system of monitoring and alarm shall be provided which indicates when a critical number of diodes have
failed, such as one arm of a bridge, which require the set to be shut down. It is not acceptable to allow the
machines to run until a cascade failure of semi-conductors leads to pole slipping.
4.9.7 All connections between main exciter, any rectifiers and the alternator rotor shall be designed to avoid the
possibility of short circuits and earth faults.
4.9.8 The insulation levels, thermal and voltage ratings of all components in the regulation and excitation system
shall be adequate, and shall also survive pole slipping following system faults or loss of excitation.
4.9.9 Where the main excitation circuit rated voltage does not exceed 500 volts, the rectifiers where fitted and the
main exciter and circuit shall be insulated for a test voltage of 1500 volts. Where the excitation circuit
rated voltage exceeds 500 volts, the insulation level voltage shall be suitable for 4000 V plus twice rated
field voltage. The exciter main circuit and any rectifier assembly shall withstand an insulation test
appropriate to the insulation level voltage, according to the relevant National Standard.
4.9.10 The excitation circuit of the main exciter, including any pilot exciters shall be designed for a working
voltage of 220 volts minimum. The insulation test voltage shall be 1500 volts minimum.
4.9.11 Each bridge arm shall have two fully rated diodes in series and be protected by the Diode Failure Detector.
The peak voltage rating of each semi-conductor arm shall be not less than 10 times the rated DC output
voltage (130 V) of the rectifier circuit.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 22 of 38
Rev 0 1999
The current rating of each arm shall be at least 50% greater than the normal rated current of the Semi-
conductor arm.
4.10.1 The automatic voltage regulator shall be high speed, continuously acting without deadband and
compounded for parallel operation. It shall exhibit long term stability and freedom from drift.
4.10.2 The adjustment range for the voltage setting shall allow the machine to operate on open circuit at the rated
voltage, and to allow the alternator full reactive lagging capability at 0.8 pf to be reached at the system
nominal voltage. The adjuster shall be power operated and arranged for remote electrical control.
4.10.3 The regulator shall incorporate automatic high speed overvoltage protection reducing the excitation when
the alternator terminal voltage reaches 120% of rated value. The protection shall reduce the terminal
voltage to the rated value.
4.10.4 Preference shall be given to the static amplifier system which is well proven. A regulator sensitive ± .005
pu is desired.
4.10.5 The required minimum overall performance is stipulated in Section 3.7.2 of this specification.
The regulator shall be suitable for operating from a 110 volt, 50 Hz/60 Hz (or as specified on the Data
Sheets) voltage transformer output.
4.10.6 The maximum distance between the machine excitation regulator panel and the switchgear that could affect
the accuracy and operation shall be stated. Vendor/Contractor should incorporate a voltage transformer in
the machine, if this is necessary. Details of the design to clarify this point should be included in the
Tender.
Provision shall be made for remote manual control of excitation with the automatic regulator out of service
for maintenance and full details shall be included in the Tender. This should include means of safe
isolation of the automatic voltage regulator for maintenance. The range of manual control shall be at least
that given by the automatic system. Automatic follow up of the manual control system shall be provided,
together with automatic means of smooth changeover from automatic regulation to manual control of
excitation (null balance meter etc).
4.10.7 The arrangements of any rheostats or adjustable resistances shall be such that loss of sliding contact does
not interrupt the exciter field circuit. They shall be located in the top of cubicles with adequate ventilation
to avoid overheating and heat retention in the cubicles.
Automatic means shall be provided for suppressing the main exciter and rotor field rapidly on internal
alternator fault and render all modes of operation inoperative. Suppression will be initiated by a signal
from the alternator balance protection on the generator switchgear control/relay panel provided by others.
Where the suppression is not directly on the main field winding, the Vendor/Contractor shall declare the
forcing means provided to obtain rapid suppression.
The exciter fields shall not be damaged by over-voltages during field suppression.
The excitation system and AVR shall include the following features:
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 23 of 38
Rev 0 1999
- Single running feature
- Parallel running with automatic load sharing
- Over and under excitation limiter
- Rotating diode failure indication
- Hand voltage adjustment feature (± 5%)
4.12 Indication
4.12.1 The requirements for initiating measurement, indication and alarm are as follows:
c) Alarms schedule:
(d) Water Cooler Leakage Detection - one per Bank (if water cooling utilised)
Note:
Four off isolating valves plus necessary pipework with flange (local elbow) to be fitted on the inlet and
discharge points of the water cooler banks (if utilised).
Local alarms and indications may be included in this contract mounted on the local supervisory panel in
agreed positions.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 24 of 38
Rev 0 1999
Remote alarms and indications will be supplied under another contract but the responsibility for the
initiating devices, as specified above and for installing them and connecting them to terminals suitable for
the receipt of the outgoing multicore cable connections is included in this contract.
Two external ground terminals shall be provided on the frame in a visible position. The terminals shall be
rated to carry the full load current of the alternator for 0.4 seconds without exceeding 412°F (200°C)
temperature.
4.14 Heaters
Adequately rated anti-condensation heaters shall be fitted to prevent condensation when the machine is shut
down. The rating need not be adequate to dry out the alternator prior to commissioning but shall maintain
the insulation resistance during any prolonged shut down periods.
Heaters shall be metal sheathed type wound for the relevant voltage and frequency indicated on the Data
Sheets, with magnesium oxide (powder) insulation. They shall be arranged so that all live leads and
connections inside the case are fully insulated with heat resisting insulation and all joints shall be brazed.
The leads shall terminate in a separate terminal box readily accessible when the machine is in service. The
box cover shall be labelled "Danger - Isolate Elsewhere".
The rating of heaters (alternator and exciter) shall be declared on the tender.
The Vendor/Contractor shall include all ancillary equipment required for the efficient running of the
alternator mentioned in this specification.
Where any ancillary rotating equipment incorporating AC rotating machines, such as barring gear, or other
drive motors, is provided, they shall comply with the relevant Owner specification.
The recommended spares list shall provide for components included in the ancillary equipment.
4.16 Noise
Subject to the requirements of GES A.04, the noise level generated by the equipment under normal
operating conditions when measured shall not exceed an ISO NR 85 curve when expressed as sound
pressure level relative to 2 x 10 N/M2. This noise level shall be measured at 3 feet (1 m) from the periphery
of each item of the equipment. Directivity effects shall be measured.
The sound power levels shall be calculated and declared if they are likely to be in excess of 100 dBWatt on
the A scale.
The terminal boxes, panels and doors giving access to live terminals shall be suitably labelled to warn of
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 25 of 38
Rev 0 1999
the danger.
Ancillary equipment wiring shall be ferruled completely and every component identified with a reference
keyed to the schematic diagram.
4.19 Cabling
Block wiring diagrams to show the number of cores for each external cable shall be provided within 60
days from the date of the order.
Final wiring diagrams shall be provided in ample time to enable the Electrical Cabling Installer to
programme and proceed with the installation and connection of the cables.
4.20 Vibration
Vibration limits shall be in accordance with Section 3.5 and the method of measurement shall be in
accordance with either NEMA MG1 and NEMA MG3 or BS 4999 Part 142, as relevant.
Non contact detectors shall be provided as specified by Owner to match the Driver Vibration Detector
Control Module.
(a) the half coupling shall be supplied "rough bored" by the driven equipment Vendor/Contractor for
finish machining and balancing by the alternator Vendor/Contractor.
(b) the coupling design shall be based on the maximum transient torques which can be expected at the
coupling in the case of a two or three phase short circuit.
4.22 Painting
This shall be effected to GES X.06 but as a minimum, the equipment is to be thoroughly cleaned free of
scale, sand, rust and grease and despatched in a fully finished condition.
4.23 Responsibility
The Vendor/Contractor must accept responsibility for checking all electrical and pneumatic signal
connections, and for the correct functioning of the equipment supplied. All instruments shall be tested and
approved and except where agreed to the contrary, they shall also be checked at Site after erection to ensure
that they give accurate indication of the conditions which they are intended to measure.
Torsional Analysis
The alternator Vendor/Contractor shall supply the information needed for the Driven Equipment
Vendor/Contractor to effect a shaft torsional analysis of the complete installation.
5.1 General
This specification is primarily written for machines manufactured in accordance with the American
(NEMA) Standards.
This section does not attempt to list every difference between American (NEMA) standards and IEC
standards, but covers only those salient differences that could affect the final installation if not properly
addressed during the Design phase of a contract.
The NEMA Standards in many cases utilise imperial units (horsepower, feet, pounds, degrees fahrenheit,
foot candles, etc), whilst the IEC Standards utilise SI units (metres, grammes, degrees celsius etc).
Note
For electrical equipment, the (American) Institute of Electrical and Electronic Engineers (IEEE) have
recommended that the use of the imperial (British-American) units in use be reduced as rapidly as possible
in favour of the SI units, with certain implementations such as the use of horsepower being phased out first.
Where practicable, both systems have been shown in this standard and on the Electrical data Sheets since
the transition will take some time to fully implement.
The standard frame sizes in MG-1 will be different to those in IEC 72, however, in either case, the final
frame sizes are normally assigned by the vendor against the required duty.
The IEC Code precisely defines the ingress protection offered to the machine by its enclosure against solid
bodies and moisture. The NEMA Code, MG-1-Part 5, is now similar, and for most refinery installations,
an enclosure of "IP54" (as defined in both codes) should be adequate for most installations.
Full details of the comparison of IEC and American practices are detailed in NOC Specification GES L.35
and are not reiterated here.
If it is intended to purchase a machine to IEC Standards, reference shall be made to the contract hazardous
area drawing produced from the principles stated in GES L35 to establish the enclosure type needed.
Note: The National Electrical Code NFPA 70, Article 500 and API.RP500 cover the American approach
to hazardous (Classified) areas in some detail.
5.2.5 Cooling
The concepts are similar i.e. air or water cooled etc., only the method of identifying them is different.
Provided the requirement is clearly stated in words, it should not be a problem.
Generally, for continuously rated machines, the IEC standards recognise only a continuous maximum
rating (CMR) which relates to a service factor of "1.0".
The principal methods of testing machines and evaluation of performance are covered in the IEC standards
by the parts of IEC-34 detailed above.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 27 of 38
Rev 0 1999
The American machines are tested against ANSI/IEEE standards and all differ slightly.
This should not be a problem as the requirements are judged against guarantee figures given at the pre-
order stage by the Vendor and if agreed beforehand, either standard would be acceptable for the test
procedures and tolerances to cover the tests required and specified in NOC standard specifications.
NEMA MG-1, (1993) part 2, gives terminal major markings with a "T" prefix, whereas the IEC code
utilises U, V, W for phases.
5.2.9 Grounding
Concerned with the nature and location of an intentional electrical interconnection between the Electrical
System Conductors and Ground.
In British Practice, the terms "Grounding" and "Ground" are replaced by "Earthing" and "Earth".
6.0 INSPECTION
6.1 Procedures
The inspection requirements are covered by the document "General Conditions of Purchase" which forms
part of the Purchase Order/Contract. Additional requirements are given below.
(a) The Vendor/Contractor shall allow the Inspector free access to all areas of manufacture,
fabrication, assembly and testing.
(b) The Vendor/Contractor always has the responsibility to provide adequate quality control and
inspection of equipment and materials as defined in ASQ Q9000 or ISO 9000. Any inspection by
Owner or his Inspector shall not relieve the Vendor/Contractor of these responsibilities or those
under his guarantees.
(c) Any defects noticed in the course of fabrication shall be brought to the attention of the Owner's
Inspector, who shall decide if the faulty material or workmanship should be repaired or rejected.
(d) If inspection is waived, the required data shall be forwarded to the Owner. If submission of data is
not requested, all data shall be retained by the Vendor/Contractor for issue to the Owner on
demand, for at least five years.
(e) The Vendor/Contractor shall provide a safe working environment for the Inspector and alert the
Inspector of potential hazards.
6.2 Scope
Inspector shall inspect the alternators to ensure that they comply with the requirements of the latest revision
of this specification and Data Sheets, drawings or other attachments to the material requisition, and the
latest revision of the Vendor/Contractor's documentation and data relating to the specific material
requisition.
All shopwork and testing of the alternator set shall be carried out to the complete satisfaction of the Owner,
but his approval shall not relieve the Vendor/Contractor of the responsibility for the guarantees covered in
the Purchase Order/Contract.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 28 of 38
Rev 0 1999
In particular, at least the following shall be checked:
(a) physical check of general appearance and finish. Mechanical assembly including good welding,
full nuts on bolted parts, undamaged condition and general worthiness,
(b) proper mechanical and electrical operation of all functional parts including auxiliaries, meters,
indicators and relays etc.,
(c) dimensions check, particularly overall length, breadth, height and fixing centres and stator bore
against the Vendor/Contractor's certified drawings,
(d) check of cable termination locations, direction, type and terminals against specification and
Vendor/Contractor's certified drawings,
(e) works and Site tests as detailed in Sections 7.1 and 7.2 of this specification,
(i) terminals,
(l) accessories,
(m) bearings,
(n) lubrication,
Inspector shall ensure that any shortcomings in the Vendor/Contractor's documentation or data are rectified
before any equipment or material is accepted for shipment.
6.3 Nameplates
(b) the machine manufacturer's or the bearing manufacturer's identification of all bearings,
(c) for machines with sight feed oilers, information on the setting of the oiler bottle height adjustment
above some convenient reference plane to maintain the proper level of oil in each bearing
reservoir,
(d) for machines with unidirectional fans, a separate data plate with rotational arrow,
Alternator nameplate and data plate material shall be stainless steel and shall be attached by stainless steel
fastenings.
A permanently marked 'direction of rotation' arrow shall be included in the alternator end shield.
7.0 TESTING
(a) Statutory tests are, in general, those detailed in those National Standards which pertain to the
equipment being tested.
(b) Type tests are to prove the general design of the equipment and the Vendor/Contractor may submit
test certificates of tests which have been carried out on identical equipment. Notwithstanding any
provision in a National Standard, the Owner shall have the right to accept such certificates in lieu
of the specified type tests or to reject them. Any type tests necessary shall be carried out at the
Vendor/Contractor's cost in all cases where such certificates are not available, or are rejected.
(c) Tests at Vendor/Contractor's works shall comprise Statutory Tests, Type Tests (if needed) and
Routine Tests. All plant and equipment whether specifically noted or not shall be subjected to
tests in accordance with the applicable National Standard, and Codes accepted by the Owner and
the requirements of the attached Data Sheets.
7.2.1 The power generation units shall be subjected to the following Works Routine Tests witnessed on all
machines of a series covered by the same Purchase Order/Contract, except as indicated:
(d) The excitation equipment shall be subjected to the following Works tests (effected with main
machine):
Note:
During the factory vibration tests, the readings on the machines' vibration probes shall be noted for
comparison with the Vendor/Contractor's vibration test equipment results.7.2.
Each completed part of the heat exchanger shall be fully tested at room temperature at the
Vendor/Contractor's works.
'In service' cooling, water temperature at the inlet to the heat exchangers to be assumed at the temperature
indicated on the Data Sheets. However, for test purposes, the coolers can be tested at the fortuitous
temperature available. The working pressure will be nominally 75 psig (5.3 bar) and the water side test
pressure shall be 1.5 x Working Pressure 120 psig (8 bar).
7.2.3 Noise
(a) The following noise test procedure shall be followed unless agreement to the contrary is made in
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 31 of 38
Rev 0 1999
writing, i.e. fully loaded (during zero power factor test), unless otherwise specified, octave band
sound pressure level measurements are to be made as detailed in NEMA, MG1, MG3, &
ANSI/IEEE Publication No. 85 (BS 4999 Part 109).
(b) Zero P.F. load run accepted, but account must be taken of background noise level by the method
described below.
(c) The set of decibel readings for each active band is to be tabulated and shall not exceed the levels
for Noise Rating 85dB(A).
(d) The running tests on one set of each rating are to be carried out in the presence of the Purchaser's
Inspecting Engineer, who will be responsible for approving the testing arrangements, the location
of the sound measuring equipment and for checking the accuracy of the recorded noise level.
A pure tone is present in a noise when a component in a given octave band is within 10 dB of the
total level in the chosen octave band. Such a pure tone would be detected normally by ear but
special instrumentation is necessary if a quantitative analysis of the tone is required.
The background noise levels when the machine is not on test should be determined using the same
filters and at the same points as for the test. The readings at each point with the machine on test
ought to exceed those due to the background noise alone by at least 10 dB.
7.2.4 Notes:
1. If vibration probes are specified and are then fitted by the alternator Vendor, measurements of
alternator vibration during tests shall be made with those probes installed.
2. Full load heat run, including a minimum running time of four hours at final running temperature.
Temperature rise shall be determined by resistance and by RTD (for alternators so equipped). The
Vendor shall keep a continuous test log during the entire heat run, making entries of data intervals
not exceeding one half hour. Data shall include temperature reading of each RTD.
The Vendor/Contractor shall keep a continuous test log during the entire heat run, making entries
of data intervals not exceeding one half hour. Data shall include temperature reading of each
RTD.
If alternator Vendor/Contractor's test facilities are not capable of making a conventional full load
heat run, the Vendor shall submit to the Ownerfor approval, complete details of an alternative test
that will permit measurement or determination of the machine heating at full load. This test shall
permit measurements of alternator vibration throughout the test for a minimum period of 4 hours
with the machine operating at rated speed, and with its rotor at full load temperature.
3. Observation of bearings and mechanical operation of the machine during the full load heat run.
Measurements of vibration shall be made on each bearing housing throughout the entire period of
the heat run. For machines having provisions for vibration monitoring systems, vibration
measurements shall also be made on the alternator shaft at each bearing. Vibration on bearing
housings and shaft shall not exceed limits specified. Heat run test log data shall include amplitude
and unfiltered frequency of vibration at each bearing, and for machines having forced feed
lubrication, oil pressures and inlet and outlet oil temperature at each bearing.
7.2.5 The following tests will be subjected to Owner's inspection during manufacture:
7.3.1 In all cases the Vendor/Contractor shall submit his test procedures in writing to the Owner for approval
prior to the start of the testing programme.
The Vendor/Contractor shall submit a schedule of Site Acceptance Tests that are to be undertaken to ensure
that the equipment is satisfactory.
The test schedules shall be approved by the Owner. There shall be a separate set of acceptance tests for
each item of equipment.
(d) Full load run until temperatures are stabilised, followed by a one hour run.
(e) Functional testing required to prove the operations of the associated equipment (turbine, gearbox,
cooling equipment protection, control and excitation cubicles).
(f) Excitation and AVR follow up including alternator response and stability tests. This will include
application and removal of full load.
(i) Load throw with figures in Section 3.7.3 (using UV Recorder) to prove Governor and AVR
response.
Note: Oscillograms
Oscillograms are to be taken during the tests in the works for S/C and at site to prove voltage, current and
response times and steady state parameters during the tests.
The initial acceptance tests shall be performed by the Vendor/Contractor when all relevant equipment has
been installed.
Fourteen days after the systems have been put into service, or fourteen days after the initial acceptance
tests, whichever is the earliest, the Final Acceptance Tests shall be effected by the Vendor/Contractor, and
be witnessed by the Inspector.
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 33 of 38
Rev 0 1999
7.5 Test Certificates
Final acceptance of the system will be given following satisfactory Final Acceptance Tests.
All copies of test certificates shall be furnished with final drawings as called for in documentation section.
The Final Acceptance Tests shall be witnessed by the Inspector who shall retain one copy of the certified
tests.
7.6.1 Supply
7.7.1 The Vendor/Contractor shall provide with the Tender, copies of all Type Test Certificates applicable to the
alternator(s) and ancillary equipment being provided; in the absence of such certificates, the Owner
reserves the right to require the tests to be performed at the Vendor/Contractor's expense.
8.0 DOCUMENTATION
8.1 Introduction
8.1.1 This section covers the documentation required for the design, selection, fabrication, inspection and testing
for all the equipment, components and services to be provided against this specification.
8.1.2 The detailed list of documents that are required is included with the Purchase Order/Contract, however as a
minimum the following listed documents will be provided by the Vendor/Contractor:
. General Arrangement,
. Foundation Layout,
. Single Line Diagram,
. Schematic and block wiring diagrams.
8.1.3 The documents as listed may be considered as a minimum requirement; all details to confirm compliance
with the relevant specifications, and to allow a full and continued appraisal to be made of the
Vendor/Contractor's proposals and interpretations of the ordered equipment, should be submitted in
accordance with the schedule specified in the Purchase Order/Contract.
8.1.4 Any production or procurement undertaken by the Vendor/Contractor which is prior to the relevant
documentation being submitted and reviewed by the Owner is at the Vendor/Contractors risk.
8.1.5 On all documentation the Owner Order number, equipment title, tag number and project name shall be
quoted.
8.1.6 All documentation shall be checked and signed by the checker before submission.
8.2.1 The Vendor/Contractor shall submit with his tender a preliminary quality control plan and proposals for
Factory acceptance and site acceptance tests.
8.2.2 The Vendor/Contractor shall include with his tender documentation a statement of proposed Sub-
Vendors/Sub-Contractors, a document submission schedule for all documents based on a review cycle of
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 34 of 38
Rev 0 1999
three weeks and outline programme for procurement and production activities.
8.2.3 The Vendor/Contractor shall incorporate any revisions agreed with the Owner during the enquiry review
stage and submit revised tender documentation for approval.
8.2.4 Monthly reports shall be submitted by the Vendor/Contractor detailing design, procurement, production
and documentation activities. The format of which shall be agreed with the Owner.
8.3.1 The Vendor/Contractor shall supply with his tender completed Data Sheets containing all the relevant
information necessary for appraisal of the design by the Owner.
8.3.2 Project specific instructions will be issued to the Vendor/Contractor with the Purchase Order/Contract,
which describes the data and calculations to be submitted, and the methods of submission.
8.3.3 The Vendor/Contractor shall be responsible for obtaining approvals from the Inspection Authority.
8.3.4 All calculations shall be carried out in clear and logical manner. Where conditions involve the use of
formulae or methods not specified in the Design Code, the source of these formulae or methods shall be
clearly referenced.
8.3.5 Computer calculations will only be acceptable if all input is shown, together with calculated values of
intermediate terms and factors and options chosen, as well as final calculated dimensions, stresses or other
values and the computer program has been validated to the satisfaction of the Owner.
8.3.6 Calculations and drawings that are interdependent, i.e. foundation loading and equipment footprint, shall be
presented for appraisal together.
8.4 Drawings
8.4.1 The drawings listed with the Purchase Order/Contract shall be sent by the Vendor/Contractor to the Owner
and/or the Inspection Authority for review and approval.
8.4.2 The components and process to produce the ordered equipment shall be shown in sufficient detail to be
fully appraised e.g. outline drawings, components list and schematic.
8.4.3 General arrangement drawings shall be to scale and show the relative location and main dimensions of all
components including elevations.
8.4.4 Detail drawings which may be included on the general arrangement shall include thicknesses and
dimensions of all components.
8.4.5 As-built drawings may be the general arrangement drawings marked-up with the actual as-built dimensions.
8.5.1 Two copies of the Data Dossier shall be supplied, and shall be a record of the manufacturing process.
Where stated in the Purchase Order/Contract, it shall contain the following:
8.5.2 Six sets of the Installation, Operations and Maintenance Manual (IOM) shall be specifically compiled for
the equipment supplied. A compendium of manufacturer's data for a range of like products is not
acceptable. The IOM shall contain the following:
The IOMs shall be presented in A4 format, and be securely bound in heavy duty 4 ring binders.
8.5.3 The Vendor/Contractor shall produce as built documents revised to indicate field changes.
8.5.4 The Vendor/Contractor shall supply one set of mylar original drawings.
All documentation (drawings, calculations and Data Sheets etc.) shall be produced by the
Vendor/Contractor in electronic format.
The format shall be compatible with that used by the Owner and shall be agreed at the commencement of
the contract.
In addition to the 'hard copies' required under the contract, copies of the electronic records shall be issued
to the Owner for all approved documentation, this forming part of the Vendor/Contractor's contractual
obligations.
All bare surfaces which are exposed during transit or storage shall be given a coat of temporary rust
inhibiting material.
Surface preparation, painting and painting materials shall be in accordance with GES X.06.
9.2 Spares
The Vendor/Contractor shall submit with his proposal, a priced list of recommended spares for start-up and
two years operation for review by the Owner. This list shall include, but not be limited to:
GENERAL ENGINEERING SPECIFICATION GES L.09
POWER GENERATION UNITS (INCLUDING AVR) Page 36 of 38
Rev 0 1999
- special tools (including rotor 'threading' equipment), if required,
- insulating material,
- gaskets,
- fittings and hardware,
- 1 set bearing liners (drive end),
- 1 set bearing liners (non drive end),
- 1 set of diodes (and fuses if fitted),
- 1 set of surge suppressors (field resistors),
- 5 litres 'touch up' paint.
This section describes the minimum requirements for the preservation and protection of generators during
the sea and land transportation and storage prior to installation.
The probable storage period will be specified in the order/enquiry and will extend from the time of
despatch to the time of unpacking at site. If the storage period is not stated, a minimum period of 24
months shall be assumed. Packing to be suitable for sea freight.
(a) After mechanical completion at the works, the equipment shall be left in a clean dry condition.
(b) The Vendor/Contractor shall be responsible for loading and anchoring the item(s) to prevent
damage during shipment.
The Vendor/Contractor shall submit his procedures for packing and preservation for review by the Owner.
9.4 Shipping
The equipment shall not leave the Vendor/Contractor's works for shipment until the release has been
approved by the Owner's Inspector.
9.5 Warranty
The Vendor/Contractor shall warrant all material and services supplied against any defect for a period of
twelve (12) months after commissioning, or twenty-four (24) months from the date of delivery to site,
whichever is the shorter period, or for the period stipulated in the Purchase Order/Contract.
Should any item be found defective, the Vendor/Contractor shall be responsible for all costs associated
with restoring the equipment to the standard specified by the Purchase Order/Contract.
1 VENDOR/CONTRACTOR
2 GENERATOR OUTPUT kVA at PF lag
3 RATED VOLTAGE volts
4 RATED FREQUENCY Hz
5 SPEED RPM
6 SUBTRANSIENT REACTANCE % Minimum
7 NEUTRAL GROUNDING METHOD DIRECT /UNGROUNDED / RESISTOR/
8 DUTY CONT. BASE / EMERGENCY / BLACKSTART /
9 TYPE OF EXCITATION STATIC / BRUSHLESS / PMG PILOT /
10 SERVICE LIFE YEARS
11 VOLTAGE RANGE volts TO volts
12 VOLTAGE REGULATION STEADY STATE & TRANSIENT
13 WAVEFORM
14 FREQUENCY VARIATION DURING OPERATION ± Hz
15 LOCATION INDOOR / OUTDOOR
16 DESIGN AMBIENT TEMPERATURE °F(°C)
17 AMBIENT TEMPERATURE MIN/MAX/AVERAGE °F(°C) °F(°C) °F(°C)
18 HUMIDITY %
19 ALTITUDE ft. (m)
20 TROPICALISATION YES/NO
21 COOLING MEDIUM AIR / FRESH WATER / SEAWATER
22 COOLING MEDIUM DATA:
23 NORMAL TEMPERATURE °F(°C)
24 MINMUM / MAXIMUM TEMPERATURE °F(°C)
25 SUPPLY PRESSURE NORMAL / MAXIMUM psig(kPag)
26 SYSTEM DESIGN PRESSURE psig(kPag)
27 ENCLOSURE COOLING TYPE: CACA / CACW / TEFC
28 DEGREE OF PROTECTION IP54 /
29
30 INSULATION CLASS:
31 STATOR
32 ROTOR
33 EXCITER
34
35 TEMPERATURE RISE:
36 STATOR °F(°C) °F(°C)
37 ROTOR °F(°C)
38 EXCITER °F(°C)
39
40 ANTICONDENSATION HEATER REQUIRED ? YES/NO volts
41 SEPARATE TERMINAL BOX YES/NO
42
43 TERMINAL BOX DATA:
44 MAIN - CONSTRUCTION EXCITER - CONSTRUCTION
45 MAIN - LOCATION EXCITER - LOCATION
46 NEUTRAL - LOCATION
47 AUXILIARY - LOCATION
48 CURRENT TRANSFORMERS QTY. / LOCATION /
49
50 FRAME GROUND INTERNAL / EXTERNAL
Revision No./Date 0
Prepared by/ Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\l-series\l-09\dl0901r0.xls
DATA SHEET NO.
POWER GENERATION UNITS
(INCLUDING AVR) P.O./CONTRACT NO.
CLIENT
1 VENDOR/CONTRACTOR
2 CABLE DETAILS CORES SIZES in(mm²) TYPE GLAND in(mm)
3 MAIN
4 NEUTRAL
5 AUXILIARY
6 ANTI-CONDENSATION HEATER
7 EXCITER
8 DIRECTION OF CABLE ENTRIES
9 SPECIAL ENTRIES
10 SPECIAL TERMINATIONS
11 STRESS RELIEVING
12 BEARINGS - DRIVE END Standard / Ball / Ball & Roller / Sleeve
13 BEARINGS - NON DRIVE END Standard / Ball / Ball & Roller / Sleeve
14 STATOR WINDING TEMPERATURE DETECTION
15 AIR CIRCUIT TEMPERATURE DETECTION
16 BEARING TEMPERATURE DETECTION
17 WATER LEAKAGE DETECTION
18 VIBRATION DETECTION
19
20 PARALLEL OPERATION REQUIRED yes / no
21 DETAILS OF PARALLEL SOURCES:
22 VOLTAGE / FREQUENCY / SPEED V Hz RPM
23 SUBTRANSIENT REACTANCE
24 RATING
25 OTHER DATA ON PARALLEL SOURCES
26
27 DRILLING RIG LOADS (IF APPLICABLE)
28 CALCULATED MAXIMUM VALUE FOR HARMONIC CONTENT % Minimum
29 IT IS ASSUMED THAT ALL SCR EQUIPMENT WILL BE ................. kVA
30 TYPE AT THIS STAGE. Harmonic No. % of Drilling Load
31 5
32 7
33 11
34 17
35 19
36 UNBALANCED LOADS:
37 NEGATIVE PHASE SEQUENCE MAGNITUDE
38 THIRD HARMONIC MAGNITUDE
39
40 FINISH
41 COLOUR
42 LIFE EXPECTANCY Years
43 AREA CLASSIFICATION OF LOCATION Class Div Group Temp Class
44 EQUIPMENT CERTIFICATION REQUIRED
45 MAXIMUM NOISE LEVEL OFF LOAD @ 3 FT (1M) 85 dB(A)MAX.
46 POLARISATION INDEX YES/NO
47 SURGE CAPACITORS/ARRESTORS/AMMETER CT BY VENDOR/CONTRACTOR/OWNER
48
49
50
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\l-series\l-09\dl0901r0.xls
DATA SHEET NO.
POWER GENERATION UNITS
(INCLUDING AVR) P.O./CONTRACT NO.
CLIENT
1 VENDOR/CONTRACTOR
2 MANUFACTURER
3 EQUIPMENT TYPE / FRAME SIZE /
4 RATED VOLTAGE volts
5 RATED CURRENT amps
6 RATED OUTPUT kW @ PF
7 RATED FREQUENCY Hz
8 SYNCHRONOUS SPEED RPM
9 RATED EXCITATION volts amps
10 REACTANCES:
11 SUB TRANSIENT X"d % ±
12 TRANSIENT X'd % ±
13 NEGATIVE X2 % ±
14 SYNCHRONOUS Xd % ±
15 GENERATOR EFFICIENCIES:
16 AT 100% RATED OUTPUT %
17 AT 75% RATED OUTPUT %
18 AT 50% RATED OUTPUT % °F (°C)
19 ANTI-CONDENSATION HEATER - GENERATOR W V Hz Ph
20 ANTI-CONDENSATION HEATER - EXCITER W V Hz Ph
21 EXCITER TYPE ROTARY / AC /DC /STATIC
22 MANUFACTURER
23 MODEL NO. / FRAME SIZE
24 OUTPUT kW
25 RATED VOLTAGE / CURRENT V A
26 INPUT VOLTAGE / CURRENT V A
27 AVR MANUFACTURER
28 MODEL NO. / FRAME SIZE
29 OUTPUT kW
30 RATED VOLTAGE / CURRENT V A
31 INPUT VOLTAGE / CURRENT V A
32
33 PM PILOT GENERATOR MANUFACTURER
34 MODEL NO. / FRAME SIZE
35 OUTPUT kW
36 RATED VOLTAGE / CURRENT
37 INPUT VOLTAGE / CURRENT
38
39 MOMENT OF INERTIA (J) lb.ft² (kgm²)
40
41 CACW COOLING WATER:
42 DESIGN TEMPERATURE °F (°C)
43 INLET / OUTLET TEMPERATURE / °F (°C)
44 WORKING PRESSURE - NORMAL psig(kPag)
45 WORKING PRESSURE - MAXIMUM ALLOWED psig(kPag)
46 CW FLOW - NORMAL usgpm (l/sec)
47 CW FLOW - MINIMUM ALLOWED usgpm (l/sec)
48
49
50
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\l-series\l-09\dl0901r0.xls
DATA SHEET NO.
POWER GENERATION UNITS
(INCLUDING AVR) P.O./CONTRACT NO.
CLIENT
1 VENDOR/CONTRACTOR
2 CACW - AIR
3 DESIGN TEMPERATURE °F (°C)
4 INLET TEMPERATURE °F (°C)
5 OUTLET TEMPERATURE °F (°C)
6
7 AIR REQUIREMENTS scfm (m³/hr)
8
9 AIR COOLER TEST PRESSURE psig(barg)
10
11 BEARING TYPE - DRIVE END
12 BEARING TYPE - NON DRIVE END
13 LUBE OIL QUANTITY gal (litres)
14
15 SPECIAL RUNDOWN REQUIREMENTS NONE /
16
17 LUBE OIL FOR DRIVER & GENERATOR
18
19 WEIGHTS:
20 STATOR PACK lb(kg)
21 MANUFACTURER BASE FRAME lb(kg)
22 PEDESTAL BEARING lb(kg)
23 ROTOR INCLUDING EXCITER lb(kg)
24 EXCITER STATOR lb(kg)
25 PMG PILOT GENERATOR STATOR lb(kg)
26 COOLERS lb(kg)
27 OTHER ITEMS lb(kg)
28
29 TOTAL WEIGHT - lb(kg)
30
31 COOLER MANUFACTURER :
32 COOLING WATER FLOW RATE usgpm (l/sec)
33 COOLING WATER TEMP RISE °F (°C)
34 COOLING WATER PRESSURE DROP psi (bar)
35
36 FILTER DETAILS
37 PRESSURE DROP NORMAL in. wg (Pa)
38 PRESSURE DROP MAX in. wg (Pa)
39 AIR FLOW scfm (m³/sec)
40
41 TEMPERATURE SETTINGS :
42 AIR TEMP ALARM °F (°C)
43 AIR TEMP. TRIP °F (°C)
44 WINDING TEMP ALARM °F (°C)
45 WINDING TEMP TRIP °F (°C)
46 BEARING TEMP ALARM °F (°C)
47 BEARING TEMP TRIP °F (°C)
48
49
50
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\l-series\l-09\dl0901r0.xls
DATA SHEET No.
GENERATOR STUDY
P.O. / CONTRACT No.
CLIENT
PLANT LOCATION SHEET 1 of 5
SERVICE ITEM No. No. of UNITS
INFORMATION FROM VENDOR / CONTRACTOR
VENDOR/CONTRACTOR
1 NOTES 1. Unless otherwise stated all Data items to be in PU values to generator base.
2 1.0 GENERATOR DATA
3 UNITS VALUE TOL ± %
4 1.1 Rating MVA
5 1.2 Inertia (GD²) - Alternator only - GD²
6 1.3 Stator resistance (Ra), hot PU
7 1.4 Stator resistance (Ra), cold PU
8 1.5 Direct axis sub-transient reactance (x"d) PU
9 1.6 Direct axis transient reactance (x'd) PU
10 1.7 Direct axis synchronous reactance (xd) PU
11
12 1.8 Quadrature axis sub-transient reactance (x"q) PU
13 1.9 Quadrature axis transient axis reactance (x'q) PU
14 1.10 Quadrature axis synchronous reactance (xq) PU
15
16 1.11 Direct axis O/C transient time constant (T'd)
17 1.12 Direct axis O/C sub-transient time constant T"d)
18 1.13 Quadrature axis O/C transient time constant (T'qo)
19 1.14 Quadrature axis O/C sub-transient time constant (T"qo)
20
21 1.15 Potier reactance (xp) PU
22 1.16 Saturation factor (Sf) PU
23 1.17 Saturation index (Si) PU
24 1.18 Damping factor (Da) PU/PU
25 speed
26 1.19 Zero sequence resistance (Ro) PU
27 1.20 Zero sequence reactance (Xa) PU
28 1.21 Negative sequence resistance (R2) PU
29 1.21 Negative sequence reactance (X2) PU
30
31
32 2.0 SATURATION FACTOR
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47 Unsaturated (rated current) values should be entered for xd,xq,x2 & x0.
48 Saturated (rated voltage) values should be entered for x'd,x"d,x'q,x"q.
49 Saturation index is used in equation If = V + kV Si
50
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\l-series\l-09\dl0902r0.xls Sheet1
DATA SHEET No.
GENERATOR STUDY
P.O. / CONTRACT No.
CLIENT
PLANT LOCATION SHEET 2 of 5
SERVICE ITEM No. No. of UNITS
INFORMATION FROM VENDOR / CONTRACTOR
VENDOR/CONTRACTOR
1 3.0 AVR DATA UNITS VALUE
2 3.1 Forward gain (Ka)
3 3.2 Feedback gain (Kfb)
4 3.3 Forward time constant (Ta)
5 3.4 Feedback or second forward lead time constant (Tfb)
6
7 3.5 Input filter constant (Tr)
8 3.6 Maximum amplifier output (V max)
9 3.7 Minimum amplifier output (V min)
10
11 3.8 Maximum rate of exchange of amplifier output (D max)
12 3.9 Amplifier control range (rnge)
13
14 3.10 Amplifier lead time constant (Tb)
15 3.11 Second feedback or forward lag time constant (Tfbb)
16 3.12 Exciter gain (Ke)
17
18 3.13 Exciter time constant (Te)
19 3.14 Maximum exciter output (E max)
20 3.15 Minimum exciter output (E min)
21 3.16 Exciter saturation constant (S1)
22 3.17 Exciter saturation constant (S2)
23
24 3.18 Compounding constant (Kp)
25 3.19 Compounding constant (Kq)
26 3.20 Compounding constant (exciter) (Ks)
27 3.21 Compounding CT saturation (CTs)
28
29 3.22 Manufacturer of AVR
30 3.23 Reference number of AVR
31 3.24 Type of AVR
32 3.25 Type of excitation system
33
34 NOTE 1 Exciter saturation constants are equal to S = (A - B) / B
35 Where A = pu exciter input signal (VOUT')
36 B = pu exciter output signal (EFD')
37 S1 = value at 75% Emax
38 S2 = value at 100% Emax (S2>S1)
39
40 NOTE 2 It is assumed that excitation is the brushless type unless other wise stated, and that the
41 AVR performance is correctly represented by the block diagram for an IEEE Type 2 model.
42 If an alternative block diagram represents the system offered, then the Vendor is requested
43 to represent the system by the appropriate block diagram bearing the AVR terms and
44 the appropriate parameters.
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\l-series\l-09\dl0902r0.xls Sheet2
DATA SHEET No.
GENERATOR STUDY
P.O. / CONTRACT No.
CLIENT
PLANT LOCATION SHEET 3 of 5
SERVICE ITEM No. No. of UNITS
INFORMATION FROM VENDOR / CONTRACTOR
VENDOR/CONTRACTOR
1 4.0
2 The exciter characteristics shall be defined by the provision of pairs of
3 voltage / current points which describe the saturation curve on the load
4 characteristic.
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38 Definitions
39
40 (a) 1 pu generator voltage is defined as the rated voltage of the generator.
41
42 (b) 1 pu exciter output is that voltage required to produce rated generator
43 voltage on the generator air gap line.
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\l-series\l-09\dl0902r0.xls Sheet3
DATA SHEET No.
GENERATOR STUDY
P.O. / CONTRACT No.
CLIENT
PLANT LOCATION SHEET 4 of 5
SERVICE ITEM No. No. of UNITS
INFORMATION FROM VENDOR / CONTRACTOR
VENDOR/CONTRACTOR
1 5.0 GENERAL PURPOSE SPEED GOVERNOR DATA UNITS VALUE
2 5.1 Speed droop pu or %
3 5.2 Control valve time constant (T1) sec
4 5.3 Driver time constant (T5) sec
5
6 Control valve limit rates
7 5.4 Increasing output (rinc) pu / sec
8 5.5 Decreasing output (rdec) pu / sec
9
10 Speed sensor
11 5.6 Gain (Gbs)
12 5.7 Time constant (Tbs) sec
13
14 Control valve second block
15 5.8 Lag time constant (T3) sec
16 5.9 Lead time constant sec
17
18 5.10 Driver lead time constant (T4) sec
19 5.11 Make of governor :
20 5.12 Maker type number :
21 5.13 Type of governor :
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37 SS - Generator Shaft Speed SO - Synchronous speed
38
39 K - 1 / Droop Pm - Mechanical power output to generator.
40
41
42 Note: Alternative data sheet is required for electronic governors of the Woodward type.
43
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\l-series\l-09\dl0902r0.xls Sheet4
DATA SHEET No.
GENERATOR STUDY
P.O. / CONTRACT No.
CLIENT
PLANT LOCATION SHEET 5 of 5
SERVICE ITEM No. No. of UNITS
INFORMATION FROM VENDOR / CONTRACTOR
VENDOR/CONTRACTOR
1 6.0 DRIVER PERFORMANCE CURVE DATA (required if governor has variable limits)
2 UNITS VALUE
3 Increasing output
4 6.1 Time from 0.0 pu to 0.2 pu sec
5 6.2 Time from 0.0 pu to 0.4 pu sec
6 6.3 Time from 0.0 pu to 0.6 pu sec
7 6.4 Time from 0.0 pu to 0.8 pu sec
8 6.5 Time from 0.0 pu to 1.0 pu sec
9
10
11 Decreasing Output
12 6.6 Time from 1.0 pu to 0.8 pu sec
13 6.7 Time from 1.0 pu to 0.6 pu sec
14 6.8 Time from 1.0 pu to 0.4 pu sec
15 6.9 Time from 1.0 pu to 0.2 pu sec
16 6.10 Time from 1.0 pu to 0.0 pu sec
17
18
19 7.0 DRIVER DATA
20
21 7.1 Inertia of driver at alternator (include coupling)
22 (GD² in kgm² or inertia constant in MJ/MVA)
23
24 7.2 Maximum engine output power MW
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\l-series\l-09\dl0902r0.xls Sheet5