Chapter 09 Project Risk Management (PMF)
Chapter 09 Project Risk Management (PMF)
Chapter 09 Project Risk Management (PMF)
Management
Overview of Project Risk Management
Plan Risk Management Process
Identify Risks Process
Plan Risk
Management Project Risk
Management
Identify Risks
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Control Risks
Plan Risk Management Process
Identify Risks Process
Risk Management Plan
Risk Breakdown Structure
Project
Technology
Regulatory Planning
Resources
Complexity Market
and Interfaces Controlling
Funding
Customer
Performances
and Reliability Weather Prioritization Communication
Quality
Based on the PMBOK Guide, Fourth Edition
Risk Management Plan
Risk Categories
The following may be sources or categories of risk:
Organizational risks
External risks
Internal risks
Unforeseeable risks
Outputs
Risk Register
Use the risk register to document risks and their impact.
Risk Management Matrix (Risk Register)
Project Project #
Project manager Sponsor
Project artifacts Updated
Trigger
Event/ Date
ID Risk Description Category Indicator Contingency Plan Fallback Plan Owner Status Entered Date to Review
1
2
3
4
5
6
7
8
9
Perform Qualitative Risk Analysis
Process
Tools and Techniques
Probability and Impact Matrix
0.90 0.09 0.27 0.45 0.63 0.81 0.81 0.63 0.45 0.27 0.09
0.70 0.07 0.21 0.35 0.49 0.63 0.63 0.49 0.35 0.21 0.07
0.50 0.05 0.15 0.25 0.35 0.45 0.45 0.35 0.25 0.15 0.05
0.30 0.03 0.09 0.15 0.21 0.27 0.27 0.21 0.15 0.09 0.03
0.10 0.01 0.03 0.05 0.07 0.09 0.09 0.07 0.05 0.03 0.01
Impact 0.1 0.3 0.5 0.7 0.9 0.9 0.7 0.5 0.3 0.1
Gray zone threat requires both contingency and fall back plans. Gray zone opportunity should be pursued.
Purple zone threat requires contingency plans. Purple zone opportunity requires at least an
enhancement plan.
Blue zone threat may be acceptable. Blue zone opportunity may be acceptable.
Perform Quantitative Risk Analysis
Process
Data Gathering and Representation Techniques
Probability Distributions
Beta Distribution Triangular Distribution
P 0.1 P 0.1
r r
o o
b b
a a
b b
i i
l l
i i
t 0.0 0.0
t
y y
Time Time
Quantitative Risk Analysis and Modeling Techniques
EMV Analysis
Fallback plan
Developed when the selected risk
strategy is not fully effective or if risk has
a high impact
Outputs
Risk Register Updates
The updated (completed) risk register might include:
Identified risks and descriptions
Triggers (symptoms and warning signs)
Risk owners and assigned responsibilities
Outputs of qualitative and quantitative analysis
Response strategies
Specific actions taken if risk occurs
Results from qualitative and quantitative risk analysis
Primary and secondary responses for each risk
Residual and secondary risks
Risk budget
Contingency and fallback plans
Contingency reserves for time and cost
Control Risks Process
Tools and Techniques
Workarounds