Bates and Hunter Project Report
Bates and Hunter Project Report
Bates and Hunter Project Report
8952 – 216 A Street, Langley, B.C. V1M 4C7 Tel: (604) 513 - 3134
E-Mail: [email protected] Fax: (604) 513 - 3730
Technical Report
on the
Bates Hunter Project
Permits for operations at the Bates Hunter Mine and water treatment plant were
reviewed by the author and by permitting consultant Frank Filas, P.E. The mine permit
status was investigated at the Colorado Division of Reclamation Mining and Safety in
Denver, which issued Permit M-90-041 for the Bates Hunter Mine. The permit is
currently active. Exploration activities at the Bates Hunter Mine were approved by
Central City in a Special Exception Use Permit dated April 14, 1986. It is important to
note that the Central City permit does not allow for full-scale mine production or disposal
of waste rock and debris on the surface. The Water Discharge Permit was investigated
at the Colorado Department of Public Health in Denver; Permit #0043168 is in good
standing and allows the Bates Hunter to discharge up to a 30-day average of 300 gpm.
The State of Colorado Division of Reclamation, Mining, and Safety have approved
Notice of Intent Mineral Prospect Permit numbers P-2006-018 and P-2006-033,
authorizing surface exploration drilling on the Bates Hunter Project.
The Bates Vein was close to the center of early mining activity in the area. Production
records indicate that the Bates Hunter Mine produced approximately 154,000 ounces of
gold. Although the Bates Vein was one of the richest and most productive in the early
history of the area, it was never consolidated and mined to any great depth. Large-scale
mine development of the Bates Hunter Project has been greatly inhibited by the
fragmented nature of land ownership created by many small 1860’s era lode claims.
The Bates Hunter shaft is reported to extend to a depth of 745 feet and has been
dewatered and rehabilitated to about 420 feet from the collar. The shaft is equipped with
a 2-compartment 85-foot-tall steel head frame and a single-drum 5-foot hoist suitable for
exploration and/or small-scale production at a rate of 200 tons per day or less. Other
mine-site facilities include compressors, hydro and minimal support infrastructure such
as a small office, a mine dry, toilet facilities with showers, and a small shop. A water
treatment plant has been constructed adjacent to the mine head frame. Its practical
throughput has been approximately 100 gpm which is approximately equal to the mine
water inflow. It may be possible to upgrade this facility to handle substantially more
discharge and accelerate dewatering and rehabilitation activities. Fred Jones, Colorado
Commissioner of Mines from 1943-1950, was probably one of the last men to see the
lower levels of the Bates Hunter Mine. Jones described ore shoots occurring on the
300, 700 and 800 (745??) foot levels. On the 300 foot level, samples taken over a 40
feet strike length ranged from 0.34 to 1.8 opt Au. On the 700-foot level, he states that
the “ore stopes 4 feet wide” and that 50 feet of the ore is exposed near the shaft that
assayed from 0.4 to 4.60 opt Au.
The Buell mine on the Leavitt vein was one of the major producers in the Central City
District and is included in the Hunter Gold mineral claims. Fosset (1876) described the
Buell “The ore body was generally four to ten feet wide, but at a depth of 400 feet
widened to 16 feet. Great pockets and seams of smelting ore were found”.
The Central City mining district lies within a terrain of Precambrian rocks that comprise
the core of the Front Range portion of the Rocky Mountains in Colorado. Initial
greenschist metamorphism and deformation produced mostly upright, tight isoclinal
folds with a penetrative fabric and associated bodies of pegmatite. Intrusion of the Silver
Plume biotite-muscovite granite was accompanied by thermal metamorphism, minor
deformation, and intrusion of pegmatites. Uplift and erosion of the Precambrian rocks
resulted in a beveled surface upon which terrestrial and marine sediments were
deposited. Tertiary-aged igneous activity and related mineralization occurred throughout
the Front Range region. After a lull in plutonism and volcanism, tectonism was
dominated by basaltic magmatism related to the development of the Rio Grande Rift.
Extensive erosion has exposed the mineralization and caused supergene enrichment of
gold, silver, and copper near the surface. The Precambrain rocks in the Central City
district are an inter-layered and generally conformable sequence of gneiss, migmatite,
and intrusive igneous rocks. Tertiary through Oligocene-aged igneous rocks of the
Central City district consists of leucocratic granodiorite porphyry, quartz monzonite
porphyry, bostonite porphyry and quartz-bostonite porphyry. Precious and base-metal
deposits in the Central City area are mesothermal vein-type deposits formed at 220° to
380° C in the early Tertiary under 2,600 to 4,600 feet of cover possibly above an
alkaline porphyry molybdenum system. Vein textures suggest passive infilling of
fractures. Veins range in thickness from hairline to 8 feet, and are surrounded by wall-
rock alteration envelopes as thick as 80 feet. Grades of vein mineralization detected
during the exploration program range up to 5.9 opt Au. Four distinct stages of
mineralization have been identified in the Central City district based on crosscutting
relations among intrusions and various vein types. The veins grade into one another but
can be classified according to the distinctive mineralogy and geochemistry of each
stage of mineralization. Vein structure and orientation is a separate issue from the
temporal paragenesis of mineralization: veins of different stages do not necessarily
have unique orientations and may share the same orientation as other mineralization
stages. Mineralization at Central City has been dated in Laramide times of the late
Cretaceous and early Tertiary.
Stage 3 composite base-metal sulfide mineralization consists of gray, dark gray, and
black quartz veins 0.1 to 6 feet wide with variable amounts of coarse-grained
chalcopyrite and pyrite, fine-grained tennantite, coarse-grained enargite, fine-grained
marcasite, and a very fine-grained black mineral with lesser bornite, chalcocite,
sphalerite, galena, and possibly goldfieldite(?) or sylvanite. Gold content is highly
variable within the composite base-metal sulfide veins. Typically, the higher gold grades
are found within irregular streaks and lenses of the more chalcopyrite-rich portions of
coarse sulfide veins.
Three orientations of veins have been identified in the area of the Bates Hunter project.
The highly productive northeast-trending veins (azimuth ~055º) contain abundant
coarse sulfides and have complex geochemistry; they contain high gold, silver, copper,
base metals, trace elements, and uranium. The veins and minor stockworks of Central
City are best described as undulatory veins. Undulatory veins are faults (and to a lesser
extent joints) that propagated as curviplanar surfaces and commonly exhibit undulating
or corrugated shapes.
Through surface geologic mapping, compilation of old mine maps, drilling, and three-
dimensional computer modeling, the complex nature of the undulatory veins
characteristic of the Bates Hunter Mine is becoming clearer. The most productive veins
are not a single vein but a complex network of branching undulatory vein segments
between major parallel vein branches spatially located 30 to 60 feet apart. Ore shoots
coincide with undulations in both strike and dip of master veins. Ore shoots generally
have well-defined visual boundaries, high-grade gold and silver concentrations
coinciding with the readily visible base-metal sulfides. Ore shoots in pyrite veins without
the presence of base metals, are less readily visible.
Management has been conducting exploration of the Bates Vein and adjacent veins
since 2004. The company is currently engaged in a Phase II surface drilling program,
planned for 6,000 feet in three holes to test the depth potential of vein intersections
beneath the historic Bates Hunter Mine workings. Management geologist
During the author’s recent site visit to the property (July 2nd to 3rd, 2008), independent
chip samples were taken by the author from the underground workings and select
sections of drill core were quartered under the author’s supervision. All samples were in
the author’s personal possession until they were delivered to ACME Labs in Vancouver
for analysis. The author’s independent sampling confirms the presence of high grade
gold. The reproducibility of the silver assays is good while gold assays were quite
variable. Given that the quantity of sample obtained by quartering very short core
intervals was only about 150 grams per sample, it is not unreasonable to see significant
differences between the author’s and Management’s assay results for gold and silver
over the same interval.
No modern mineral processing or metallurgical testing has been done on the Bates
Hunter Project. Based on historical methods of processing, it is expected that the
mineralization would be amenable to recovery by sulfide flotation followed by smelting
of the flotation concentrates to remove gold. The presence of sporadic but appreciable
amounts of copper in the veins (in the 0.50% Cu range) precludes using cyanide
leaching as a recovery technique since copper is a voracious cyanide consumer that
The author has reviewed Management’s sampling methods and approach, sample
preparation, analysis, data verification and security procedures, carried out by
Management, during its exploration program and is of the opinion that they are sufficient
and that the data produced is valid for the mineralization being explored.
There are currently no mineral reserves or resources of any category on the Bates
Hunter claim group. However, historical data leaves no doubt that a significant amount
of high-grade gold still remains on the claim group. Information gleaned from historical
Bates Hunter reports indicate that there were several known and defined ore shoots in
the mine prior to closure. Samples taken during the recent dewatering efforts to the 163
foot depth in the shaft range from trace to 6.0 opt Au.
It is the author’s opinion that from 20% to 80% of the known vein systems could result in
exploration success. The Bates vein produced 154,000 ounces to an average depth of
476 feet or 323 ounces per vertical foot. A rule of thumb for underground mining is that
one can mine comfortably at a rate of approximately 50% to 65% of the reserves
tonnage (or ounces) per vertical foot. Based on this, historical data suggests that the
Bates Vein alone could produce between 160 and 210 ounces of gold daily (55,000 to
75,000 ounces annually). Based on historic records, it is roughly estimated that the
Bates vein alone represents an exploration target that could host approximately 500,000
ounces of gold to a depth of 2,000 feet. The 16,100 feet strike lengths of all the veins
covered by the project claims could increase this potential substantially. Acquisition of
other contiguous properties could again multiply this potential. If one extrapolates the
historical production data to 2,000 feet depth, the Bates Hunter Project could host 1.8
million ounces of gold. Given that historical records are very fragmented, incomplete
and not NI 43-101 compliant, it is the author’s opinion that the project may eventually
discover 1 to 3 million ounces of gold on the property. Based on the historical 1,702
ounces of gold per vertical foot, gold production at a rate of 850 to 1,100 ounces daily
(300,000 to 400,000 ounces annually) is theoretically possible. Based on historical data
and recent “remnant” and muck sampling underground, it is expected that “mineable”
The Bates Hunter Project represents a real exploration target that could yield significant
gold production. A staged systematic approach should be used to establish mineable
reserves prior to attempting to develop the property through to commercial production.
Management should continue to dewater and rehabilitate the shaft and explore the
property with both surface and underground drilling to confirm the existence of
mineralization near the abandoned workings and undertake metallurgical test work.
Priority should be given to dewatering activities.
The assay results from BH 08-10 indicate that low cost underground bulk tonnage
mining may be conceivable and heretofore neither contemplated nor investigated. It is
recommended that Management assay a number of 100 foot intervals of drill core
straddling the Bates Vein to determine if there is potential for bulk mining.
A Phase II Budget of $2 million (in progress) encompassing a 6,000 foot drilling
program of three or more deep holes along with continuation of dewatering activities is
recommended. The Phase II Budget includes a recommended expenditure allowance of
$500,000 to undertake upgrading of the water treatment plant to increase its throughput
and accelerate dewatering activities. Contingent upon successful completion of Phase II
In 1984, George Otten purchased the Bates Hunter Mine and surrounding claims, and
added several contiguous claims over the next few years. Otten installed the present
mine headframe and hoist, built the hoist house, and rehabilitated the mine shaft to a
depth of 217 feet. In 1993 he commissioned the construction of the present water
treatment plant. On September 20, 2006, Management entered into an agreement with
George Otten, and a group of companies either owned or controlled by him, to purchase
the physical assets, mineral claims and land tenure parcels held by
Tertiary through Oligocene-aged igneous rocks of the Central City district consist of
leucocratic granodiorite porphyry, quartz monzonite porphyry, bostonite porphyry and
quartz-bostonite porphyry (Sims, Drake and Tooker, 1963). The older intrusions tend to
form small irregular stocks and the younger ones form long thin dikes that trend
northwest, northeast, and due east. Field relations clearly indicate that the quartz
bostonite porphyry and bostonite porphyry are the oldest Tertiary intrusive rock, and
these early bostonites show a close spatial association with uranium mineralization that
dates at 58±1 Ma (Phair, 1979). The Laramide intrusive rocks of the region are among
the most radioactive igneous rocks in the world (Larsen and Phair, 1954); the quartz
bostonite porphyry, for example, is about 15 times as radioactive as the average granitic
rock (Sims, 1982).
6.4 Mineralization
The discussion of mineralization below is the work of project geologists Brian Alers, a
“qualified person” and John Shallow, a consulting geologist. The author has not
personally corroborated all of the evidence presented, but it is consistent with his
observations and knowledge of the project’s geology.
Four distinct stages of mineralization have been identified in the Central City district
based on crosscutting relations among intrusions and various vein types (Tables 3 and
4; Sims, Drake and Tooker, 1963). The veins grade into one another but can be
classified according to the distinctive mineralogy and geochemistry of each stage of
mineralization. They are referred to below as Stages 1 through 4. Further refinement of
the vein paragenesis was achieved by identifying specific structural relationships and
The veins and minor stockworks of Central City are best described as undulatory veins,
as discussed by Wise (2005). Undulatory veins are faults (and to a lesser extent joints)
that propagated as curviplanar surfaces and commonly exhibit undulating or corrugated
shapes. They result from local stress field variations related to the interaction of
Figure 10 illustrates that vein sampling by Alers from un-mined remnants of the
historical workings confirms the presence of high grade but variable gold content in the
veins. Alers’ limited sampling, of the upper 163 feet of the mine, generally corroborate
historical sampling data for these levels and add credibility to the potential for defining
“mineable” high grade shoots on the lower levels indicated by historic documentation
and assays as shown on Figure 10. Neither the recent sampling by Alers nor the
historical sampling and anecdotal information are adequate to support that an economic
mine can be established. However, the indicated high grade nature and vein widths up
to 24 inches or more, imply that further exploration is warranted.
7.4 Mine Dewatering and Rehabilitation
The Bates Hunter mine workings, which extend to a depth of about 745 feet, are
currently flooded to a depth of about 420 feet. Management has been dewatering the
workings in order to provide access for further underground mapping and sampling, and
ultimately underground drilling. At the time of the author’s visit on July 3rd, 2008
dewatering had reached and exposed the floor of the 424-foot level shown on Figure
10. This level is open in both directions from the shaft and may provide Management
with their first opportunity to acquire substantial underground sampling data. The
company has been rehabilitating the Bates shaft as the water level lowers, adding
timbers, ladders, lighting, ventilation, communication, safety features, and other
improvements as necessary.
BH-06-01 Gregory 50623 49556 8353 292 -52 9/8/06 9/23/06 405 Twisted off drill string at 405
BH-06-02 Gregory 50648 49557 8353 292 -52 9/26/06 11/24/06 2025
BH-06-02A Gregory -- -- -- Abandoned part of BH-06-
02 Created by wedge at 520
BH-06-03 Gregory N 50626 49621 8356 280 -62 11/25/06 11/27/06 50 Down-hole survey off target;
called hole at 50
BH-06-04 Gregory N 50626 49621 8356 280 -62 11/28/06 12/11/06 291 Wedge set wrong; called
hole, moved to E. Mammoth
BH-07-05 Mammoth E 50338 48755 8613 305 -60 2/11/07 2/14/07 51 Down-hole survey off target;
called hole at 51
BH-07-06 Mammoth E 50338 48755 8613 305 -60 2/15/07 2/23/07 184 Down-hole survey off target;
called hole at 184
BH-07-07 Mammoth E 50338 48755 8613 302 -58 2/23/07 9/1/07 1945 Twisted off drill string at
1945
BH-07-08 Mammoth E 50338 48755 8613 302 -58 9/28/07 12/20/07 2265 Wedged off BH-07-07 at
823
feet
Phase II
BH-08-09 Packard 49742 49060 8427 6 -62 2/27/08 5/20/08 2353 Completed
Gulch
BH-08-10 Packard 49755 49044 8427 295 -59 5/24/08 7/3/08 1936 Completed
Gulch
Note: E/N coordinates are in feet relative to the Bates Hunter Mine shaft collar at E50,000/N50,000.
Surface drilling results to date indicate good potential for developing a resource on the
Bates Hunter Project. These results show anomalous gold in the Branch, Hartford
German, Foot & Simmons, Groundhogg, Gregory, Dump, Leavitt and Mosell veins
(Figures 12 - 15). It is characteristic of the deposits at Central City and vein deposits in
general, to be variable in grade and width. Although not all these intercepts are of “ore
grade” or mineable widths, they do indicate that these veins are mineralized at the
locations drilled and that they may have potential ore grades elsewhere, warranting
more exploration of these veins.
Table 7 shows that many potential “ore grade” intercepts were identified in the Phase I
and II drilling programs. These results confirm that the high-grade historical samples at
the bottom of the Bates Hunter workings (Figure 10) may extend to depth below the
workings and that mineralization on all veins appears to extend to depth as well.
Although other vein intercepts were below ore grade, this is not unexpected given the
variable nature of the Central City veins.
Shaft 163' SW
02 Wall Stringers BH 5067 grab 0.01 0.13 448
04 BH 07-07 1844.1 1844.6 0.5 0.07 0.73 5,854 0.24 1.06 7,100
05 BH 06-04 145.0 146.0 1.0 0.25 0.44 1,246 0.94 0.62 6,400
06 BH 06-04 146.0 146.5 0.5 1.27 1.14 6,499 1.78 1.08 10,900
07 BH 06-04 146.5 147.5 1.0 0.44 0.76 7,110 1.17 1.11 10,100
08 BH 06-04 147.5 148.5 1.0 0.61 1.66 3,370 0.20 1.90 11,900
09 BH 06-04 148.5 149.0 0.5 2.39 5.16 >10,000 0.07 6.51 22,700
10 BH 07-08 2146.4 2147.0 0.6 9.21 7.44 >10,000 3.43 5.37 44,800
The gold production cited on Table 9 represents only the RECOVERED and
REPORTED production subsequent to initiation of smelting activities in 1868.
Production data from 1859 to 1968 representing early production from non-sulfide ores
was never recorded. In addition, the above gold production ounces only represent what
the author has been able to glean from historical literature and is incomplete. Figure 16
shows that the Bates Hunter Project includes 11 additional veins that were mined to
varying extents for which production data has NOT been found.
Historical and current exploration data suggests that there is exploration potential for
high-grade gold on the claim group. Information gleaned from historical Bates Hunter
reports indicate that there were several known and defined ore shoots in the mine prior
to closure. The Bates Hunter mine was last opened in the late 1930’s. Fred Jones, M.E.,
who later became the Colorado Commissioner of Mines, worked at the Bates Hunter in
1936. He stated in a letter dated 1939 that “there were three shoots of ore opened on
the 300, 700 and 800 (745??) levels. One shoot on the lower level was continuous for a
length of 440 feet with the west breast still in ore averaging 0.58 oz. Au over a 4 foot
width.” Samples taken during the recent dewatering efforts to the 163 foot depth in the
shaft range from trace to 6.0 opt Au (Figure 10). Sampling by Fred Jones and the author
is shown on Figure 10 as well, showing comparable grades. His notation of a zone
about 60 feet long indicates that it consists of parallel veins averaging about 10 feet
wide and assaying between 0.80 to 8.6 opt Au.
The long-term potential of the Bates-Hunter Project is the depth and strike continuation
of known veins and others that may be discovered from underground exploration
activities. If the known veins continue to the 2,400 foot level as they did on the adjacent
Fifty Mines Property which produced over 1 million ounces, the Bates Hunter Project
could produce in the order of 1 to 3 million ounces of gold to that depth as well.
2004 $70,380
2005 $415,775
2006 $1,236,965
2007 $1,943,012
2008 $1,064,055
Total $4,666,887
Assume that Management is able to define 1 million ounces of reserves and resources
as described in previous sections of this report and also assume that Management is
able to place the property into production at a rate of 300 to 500 tons per day. Assuming
that the “ore” grades 0.50 oz Au/ton or better, the author estimates that the operating
costs at this rate would be in the order of about $200 to $250 per ounce. At present
gold prices, the gross value of “operating profit” over the life of the operation could be in
the range of $500 to $700 million spread out over a 10 to 20 year mine life (assuming
favourable metallurgical recoveries, etc).
Assume that Management is able to sell the project to a willing buyer based on the
POTENTIAL in-ground gold content. In today's market, a willing buyer will pay anywhere
from $50 to $100 per ounce of POTENTIAL Reserves and Resources. On this basis, a
willing buyer would pay somewhere from $50 to $100 Million for the project.
Based on the above, it is the author’s opinion that the Bates Hunter Project has a
value of $50 to $100 million in today’s market based on the resource POTENTIAL.
Assuming successful completion of dewatering and underground resource
definition whereupon a feasibility study could be completed, this value could
increase substantially.
Bastin, E.S., and Hill, J.M., 1917, Economic geology of Gilpin County and adjacent parts of Clear Creek
and Boulder Counties, Colorado: U.S. Geological Survey Professional Paper 94, 379 p.
Billings, R.S., 1912, Report on the Mines and Mills of the U.P.R. Milling and Mines Company of Gilpin
County, Colorado. (Private Co. Report)
Caine, J.S., Nelson, E.P., Beach, S.T., and Layer, P.W., 2006, Structural fabrics, mineralization, and
laramide kinematics of the Idaho Springs-Ralston Shear Zone, Colorado Mineral Belt and Central Front
Range Uplift: The Mountain Geologist, Special Issue on the Structural Geology of the Colorado Front
Range, v. 43, no. 1, p. 1-24.
Callbreath, J.F., Jr., 1899, The mineral resources of Clear Creek County, Colorado: Mining Reporter, v.
40, Denver, Colo.
Chapin, C.E. and Cather, S.M., 1981, Eocene tectonic and sedimentation in the Colorado Plateau Tocy
Mountain area: in Dickenson, W.R., and Payne, W.D., eds., Relations of tectonics to ore deposits in the
southern Cordillera: Arizona Geological Society Digest v. 14, p. 173-198.
Collins, G.E., 1904, The relative distribution of gold and silver values in the ores of Gilpin County,
Colorado: Transactions of the Institute Mining and Metallurgy Vv. 12, p. 480-495.
Endlich, F.M., 1874, Preliminary report upon the mining districts of Colorado, in Hayden, F.V., Annual
Report of the United States Geological and Geographical Survey of the Territories, embracing Colorado,
being a report of progress of the exploration for the Year 1873: Washington, U.S. Government Printing
Office, p. 276-301.
Filas, F., 2006, Preliminary Environmental Permitting Assessment, Bates Hunter Project, Central City,
Colorado: September 22.
Fossett, F., 1876, Colorado, its gold and silver mines, farms and stock ranges and health and pleasure
st
resorts: 1 ed., Crawford, N.Y.
James, L.P., 1986, Dregs 1986 Spring Field Guide Book: Denver Region Exploration Geologists Society,
86 p.
Jones, F., 1937, Letter to Mr. Harry M. Williamson
Jones, F., 1939, Report on the Bates-Hunter Group of Mines: March 20, 1961.
Larson, E.S., Jr. and Phair, G., 1954, The distribution of uranium and thorium in igneous rocks, in Faul,
H., ed., Nuclear Geology: New York, John Wiley and Sons, p. 75-88.
Lipman, P.W. 1982, Tectonic setting of the mid to late Tertiary in the Rocky Mountain Region—A Review,
in Proceedings of the Denver Region Exploration Geologists Society Symposium, The Genesis of Rocky
Mountain Ore Deposits: Changes with Time and Tectonics: Denver Region Exploration Geologists
Society, Denver, Colorado, p. 125-131.
Lovering, T.S., and Goddard, E.N., 1950, Geology and ore deposits of Front Range, Colorado: U.S.
Geological Survey Professional Paper 223, 319 p.
May, David L., (May 1996) Bates Hunter Mine and Golden Gilpin Mill, Geologic Report for Hunter Gold
Mining Corp.
Minsearch Inc. 1989, The Bates Hunter Mining Property, Central City Mining District, Colorado, (Private
Company Report for Central City Consolidated Mining)
Moench, R.H., and Drake, A.A., Jr., 1966, Economic geology of the Idaho Springs district, Clear Creek
and Gilpin counties, Colorado: U.S. Geological Survey Bulletin 1208, 91 p.
O’Gorman, Glenn R., April 15, 2007, Independent Engineers Report for the Bates Hunter Project
Phair, 1979, Interpretation of lead-uranium ages of pitchblende deposits in the central Front Range,
Colorado: Geol. Soc. America Bull., v. 90, p. 858-870.
Pierce, R., 1890, The association of gold with other metals in the West: Am. Inst. Min. Eng. Trans., v. 18,
p. 449.
Rice, C.M., Lux, D.R., and Macintyre, R.M., 1982, Timing of mineralization and related intrusive activity
near Central City, Colorado: Economic Geology, v. 77, p. 1655-1666.
Simms, P.K., 1982, Geology of the Central City area, Colorado—A Laramide mining district, in
Proceedings of the Denver Region Exploration Geologists Society Symposium, The Genesis of Rocky
Mountain Ore Deposits; Changes with Time and Tectonics: Denver Region Exploration Geologists
Society, Denver, Colorado, p. 95-100.
Simms, P.K., Drake, A.A., and Tooker, E.W., 1963, Economic geology of the Central City district, Gilpin
County, Colorado: U.S. Geological Survey Professional Paper 359.
Simms, P.K., and Gable, D.J., 1964, Geology of Precambrian rocks of the Central City district, Colorado:
U.S. Geological Survey Professional Paper 474-C.
Stewart Environmental Consultants, 1994, Report of a Phase I environmental site assessment performed
at the proposed Mammoth Hill mixed use development, Central City, Colorado: Fort Collins, Colorado, 49
p.
Tedesco, S. A., 1997, Geological report on the Bates Hunter Mine and Golden Gilpin Mill: prepared for
Hunter Gold Mining Corp., 28 p.
Tweto, O., 1975, Laramide (late Cretaceous-early Tertiary) orogeny in the southern Rocky Mountains, in
Curtis, B. F., ed., Cenezoic history of the southern Rocky Mountains: Geological Society of America
Memoir 144, p. 1-44.
Tweto, O., and Sims, P.K., 1963, Precambrian ancestry of the Colorado mineral belt: Geological Society
of America Bulletin, v. 74, p. 991-1014.
Williams, Harry, 1934?, Stope, sample, and section map of the Bates Hunter Mine: unpublished map,
scale 1 inch = 30 feet.
Williamson Mine Correspondence, March 20, 1961
Wise, J.M., 2005, Undulatory silver-rich polymetallic veins of the Castrovirreyna District, Central Peru:
fault growth and mineralization in a perturbed local stress field: Economic Geology, v. 100, p. 680-795.
Various unpublished private companies maps and data.
Various Unpublished Maps and Data located in the Archives of The Colorado School of Mines
Certificate of Qualifications
Glenn R. O’Gorman, B. Sc., P. Eng., FCIM
I, Glenn R. O’Gorman, President of OREM Inc., do hereby certify that:
1. I am an Independent Consulting Professional Mining Engineer and a “qualified person” as defined
in Canadian Securities Administrators National Instrument 43 – 101 (NI 43 - 101), residing at
8952 - 216A Street, Langley, B.C., Canada V1M 4C7.
2. I am a graduate of Queen’s University of Kingston, Ontario, 1974, with the degree of Bachelor of
Applied Science in Mining Engineering.
3. I have been practicing mining engineering and have worked as a miner, Mine Operator,
Consulting Engineer and Corporate Executive over a span of 35 years since 1974. I have been a
Registered Member in good standing of the British Columbia Association of Professional
Engineers and Geoscientists since 1995, (Member #18191), a member of the Association of
Professional Engineers of Ontario since 1974, (Member #34599506) and a Member of the Order
of Engineers of the Province of Quebec since 1979 (Member #34442). I have been a member of
both the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) (Member #96091) and the
Society of Mining Engineers of the American Institute of Mining Engineers (Member #2406590)
for over 30 years and am a Fellow of the CIM.
4. This report is based on a number of field visits made to the Bates-Hunter Gold Project from
December 2003 to July 2008, and on reports, maps, and other documents examined or acquired
while examining the Bates-Hunter operations and in various state and county archives in the
State of Colorado.
5. This report has been prepared as an Independent Engineers Report of the Bates-Hunter Project.
6. No limitation has been imposed upon my access to the property or to persons, information, data
or documents relevant to the subject matter of this report.
7. As of the date of this certificate, I have disclosed all relevant material of a technical nature which
to the best of my knowledge might have a bearing on the viability of the project or the
recommendations contained within this report. I am not aware of any material fact or material
change not reflected in this report, the omission to disclose which makes this report misleading.
8. I neither have any interest or securities, directly or indirectly, nor do I expect to receive any direct
or indirect interest or securities in Hunter Gold Mining Inc. or any affiliate thereof that is the
subject of this report.
9. I am responsible for all sections of this report entitled “Technical Report on the Bates Hunter
Project” dated July 15, 2008. Geological interpretations, geological mapping, core logs, assaying
and underground sampling data and information have been provided by Brian Alers, Project
Geologist for the Bates Hunter Project, a “qualified person” as defined in Canadian Securities
Administrators National Instrument 43 – 101 (NI 43 - 101). Mr. Alers interpretations and data were
reviewed by an independent geological consultant (Mr. Dave Smith, M. Sc., P. Eng., P. Geo.),
Project Manager of the Bates Hunter Project. Mr. Smith’s views, opinions and recommendations
were relied upon for planning the work program contained in this report. All maps and figures
have been provided by Management or third parties and have been verified for accuracy and the
sources are duly noted on them.
10. I consent to the filing of this Report with any stock exchange or other regulatory authority and any
publication by Management including electronic publication in publicly accessible company files
or websites.
12. In my professional opinion, the Bates Hunter Project is a property of merit that warrants
undertaking the exploration program recommended in this report.
13. I have read Canadian Securities Administrators National Instrument 43-101 “Standards of
Disclosure for Mineral Projects” and have prepared this report in compliance with NI 43-101 with
NI form 43 – 101 F1. This report may be used as a “Property of Merit Report” to qualify the Bates
Hunter Project for meeting stock exchange listing requirements.
th
Signed at Vancouver B.C. this 15 day of July, 2008.
Letter of Authorization
Glenn R. O’Gorman, B. Sc., P. Eng., FCIM
Management has the Author’s consent to the filing of this NI 43-101 compliant Technical Report on the
Bates Hunter Project dated July 15, 2008 with any stock exchange or other regulatory authority and any
publication by Management including electronic publication in publicly accessible company files or
websites. This report may be used in a Statement of Material Facts or similar document, but may not be
abbreviated or excerpted without my written consent.
th
Signed at Vancouver, B.C., this 15 day of July, 2008.
I
MINERAL RIGHTS I I
500 FEET
D HUNTER GOLD
I 100 METERS
D MAMMOTH
HILL LLC
I
I
Figure 3. Mineral Rights of the Bates-Hunter Project (most claims are approximately located).
topography from
USG$ 7.5' Quads
Black Hawk
Central City
I
,...,_.,
I
SURFACE RIGHTS I I
500 FEET
HUNTER
I 100 METERS
rt
contour interval = 40 feet
MAMMOTH I
topography from
HILL LLC
I USG$ 7.5' Quads
Black Hawk
Central City
Figure 4. Surface Rights of the Bates-Hunter Project, (some claims are approximately located).
----30feet
Figure 5. General Facilities Map, Bates Hunter Mine.
8600
8500 ft
NE
8400 ft
BATES - HUNTER
0.75 opt Au MINE
8300 ft
ft
8200 ft
' 8100
"-..
Q)Q)> ' '-
,-==::::=:;;::::::::::::::::=;:::::m-
c:::::::::==::::::== =
•
STOPE S
BOBTAlL
TUNNEL
LEVEL
=====."-. 0.46 to 1.16
STOP
8000 ft -
co
Q)
, r opt Au / 0.5' - 300 ft
(/) II 11
7900 ft cA-LLI-STE-RM-INE- - - \
- 400 ft
.0
7800 ft
-
co
Q)
0
1:8] through tunnel
[III] out of section tunnel
\
\ - 500 ft
7700 ft C:
IZI into section tunnel - 600 ft
collapse
7600 ft m D stopes from Schumann Section - 700 ft
stope 727 ft level
7500 ft
5.78 opt Au 0.76 opt Au/ 0.75' - 800 ft
o---- 0.74 opt Au/ 0.5'
7400 ft
0.16 to 3.8 opt Au
BH08-10 -o BH06-02 - 900 ft
Golden Mile drill hole GOLD ASSAYS
7300 ft 0.215 opt Au / 0.6'
(approximate)o
7200 ft
0.48 opt
Au/ 10'
0 0.1 - 0.5 oz/ton -
.c
c..
Q)
-1000 ft
t
r;;:::;7 Boulder Creek granodiorite - Contact
(1.7ga) - Fault
Hornblende diorite to
quartz diorite Synform: axial trace
Antiform: axial trace
- Amphibolite NORTH Antiform, Overturned: axial trace
Synform, Overturned: axial trace
0 Feldspar-rich gneiss
Plunge of fold element
redrawn from:
Feldspar-rich gneiss & homblede gneiss USGS MAP 1-2605
(interlayered) ---1kilometer
43
---A.._
Figure 7, Regional Geology of the Bates-Hunter Mine Project, Central City, Colorado.
Contact
Quaternary alluvium Fault
0 Tertiary intrusive
XX:'.'::,._ foliation with lineation
0
Q Pegmatite
j Synform: axial trace
granodiorite (1.7 ga) Antiform: axial trace
Antiform, Overturned: axial trace
Synform, Overturned: axial trace
Plunge of fold element
MINOR FOLDS
Felsic gneiss -=+ Zfold
}-- symmetric fold
...s=-+ Sfold
Biotite gneiss
fold axis
-E-+ open synform
- Amphibolite ++ open antiform
100 METERS
redrawn from:
Sims and Gable, 1964
USGS PP-474-C, Plate 1
Figure 8, Generalized Geologic Map of the Bates-Hunter Project Area. From Sims and Gable, 1964.
Model based upon mine mapping and sampling,
by Brian Alers, 2005-2006.
Levels 93' and 119'
0 ft
GOLD ASSAYS (oz/ton)
D 6 0 0.5- 1.0 oz/ton
?
D 6 0 1 - 5.0 oz/ton
• .A. e > 5.0 oz/ton - 100 ft
SQUARES = O'GORMAN ASSAYS
TRIANGLES= MANAGEMENT
ASSAYS CIRCLES= HISTORIC
ASSAYS
= = = =163][1evfil::
- 200 ft
202 ft level
278 ft level
[] fill
tsZI decline shaft towards viewer 430 ft level
D tunnel or shaft 424 ft level
cutout 0.17
D stope FW 3" 0.12
IZI through tunnel HW 18" 0.96
C
am tunnel away from viewer
0
:.::;
IZI tunnel towards viewer
ro -cribbing 498 ft level
>
Q) caved
iii
l
Synform: axial trace
Antiform: axial trace
ENE sulfide veins Antiform, Overturned: axial trace
Synform, Overturned: axial trace
(types 1 & 2)
Plunge of fold element
MINOR FOLDS
3 E-W veins z fold
(types 3 & 4) }--.
•
symmetric fold
fold axis
Diamond drill holes ---s=-+ s fold
I
open synform
++ open antiform
25
'f BH07-
g . OOJ-
fgn
----- /
,
13
50 METERS
80
8200 ft
CP -1 00 ft
1400'
7200 ft
G)
m 0 1000 FT LEVEL
(/)
zmr= -1 00 ft
7100 ft
-1 00 ft
C
7000 ft
6900 ft 06-0 -1 00 ft
-1 0 ft
6800 ft
Figure 12. Cross-section of Bates Hunter Project 2006 diamond drill holes.
8600 ft
NW Plane of section: 304/90
view towards 034 N MAMMOTH
8500 ft Packard Gulch DRILL SITE
8400 ft
.8
C/)
1e
0 ft
a.
8200 ft
ine - 100 ft
nnel Le I Bobtail tunnel
8100 ft
?
s:
0
- 200 ft
en
8000 ft
rm ? - 300 ft
r
7900 ft
- 400 ft
u, 0.39 Ag / 1.0'
7800 ft
u, 1.36 Ag / 1.2'
- 500 ft
u, 1.11 A / 1 .6'
,-..;
7700ft co
0 - 600 ft
.c
..._o_
7600 ft
iE - 700 ft
0
75001 I
I
7 4;0 0 ft 0.0
0.
1
- 800 ft
0.012 - 900 ft
hooft 0.119 A ,
0.235 Au, 1 E-W TRENDING VEINS
-1000 ft
0.018 Au, .
7200 ft NE TRENDING VEINS
-1100 ft
ALL VEINS INFERED FROM
7100 ft SURFACE AND DRILL DATA.
-1200 ft
ASSAY DATA REPORTED IN
7000 ft
u, 5.37 A / 0.6' OUNCES PER TON (opt)
U , 1 .40 Ag / 0.5' -1300 ft
250 feet
6900 ft s/o?-oa
-1400 ft
Figure 13. Cross-section of Bates Hunter Project 2007 diamond drill holes.
8600 ft SECTION PLANE= 006/90
s VIEW TO 276° (WEST)
N
PACKARD GULCH DRILL SITE
GREGORY GULCH
8300 ft
0
8200 ft
- 100 ft
8100 ft
I - 200 ft
8000 ft
0.017 Au, 0.8 Ag / 0. POSSIBLE - 300 ft
0.749 Au, 0. 8 Ag/ 2. BUELL MIN
q 0.552 Au, 0. 2 Ag / 1 '
7900 ft ffi 0.033 Au, 0 0 Ag/ 1.
STOPES
- 400 ft
p
7800 ft
- 500 ft
7700 ft
- 600 ft
7600 ft
- 700 ft
0 BH07-08
7500 ft 1265'
- 800 ft
7400 ft
- 900 ft
7300 ft
-1000 ft
7200 ft
-1100ft
7100 ft
-1200 ft
7000 ft
-1300 ft
6900 ft
-1400 ft
6800 ft
600 ft
6700 ft
X-W TRENDING VEINS
6500 ft
NE TRENDING VEINS
6200 ft
250 feet
8400 ft
8300 ft
_J 0 ft
_J
8200 ft
w
(/)
100 ft
Z O c:::::J
<(
8100 ft BOBTAIL TUNNE
200 ft
w I 1.2'
8000 ft (!)
300 ft
7900 ft C'·
() - 400 ft
;:=
7800 ft z
? 5
f
- 500 ft
7700 ft <(
- 600 ft
BH08- 0
(!)
7600 ft (!)
- 700 ft
0
7500 ft r
Cl - 800 ft
z
:::>
7400 ft C'· 0 d- , - 0.037 Au, .50 Ag 0.5'
- 900 ft
w 0.158 Au, .30 Ag 0.7'
-z
(!)
7300 ft 0.215 Au, .30 Ag 0.6'
-1000 ft
.,_ _ 0.053 Au, 0.39 I 1.0'
7200 ft 0.256 Au, 0.00 I 0.5'
0.338 Au, 0.00 g I 0.5' -1100 ft
7100 ft
0.286 Au, 0.00 g / 1.0'
0.112 Au, 0.00 g I 0.5'
0.168 Au, 0.00 g I 0.5' -1200 ft
6900 ft
E-W TRENDING VEINS -1400 ft
I
I
17. WHITESIDE:
MINERAL RIGHTS II
D HUNTER GOLD
21 ACRES
I I
500 FEET
100 METERS
---
Central City