Project Management and Contract Administration
Project Management and Contract Administration
Unit-1
Introduction to Projects
Learning
objectives
After completion of this unit, students will be able to:
Understand the phases of the life cycle of projects and their significance.
Defining a Project they start one day and finish one day, contrary
to mass manufacture where the operations
Consider the following activities: are perpetual.
• A flyover is built in a city.
All these activities described above fall in the
• Metro rail is constructed in New Delhi.
category of projects.
• A ship is built for the navy.
• A new residential building is constructed.
A project can be defined as a temporary
Do you see anything common in all these endeavor to achieve a specific, well-defined
activities? objective.
Now consider some more activities:
1
Hence, project method comprises three as already discussed, are temporary
major entities endeavors. While the projects are in
progress, they pass through well-defined
stages of life cycle.
Parent Project Team Customer
Organisation • Each project produces a unique product:
The projects are not repetitive
manufacturing activities. The product of a
project is unique. Future projects will never
Figure 1.1: Projects in contemporary organizations create the same specifications of a product.
The parent organization selects the team • Interdependence: Each project is comprised
leader and the team members from its of a number of tasks. All the tasks involved
different divisions as per requirement of skills in a project are unique independent entities,
and qualifications for the project. The project but they depend upon each other for their
team is responsible for interacting with the performance. For example, a specific task
customer and ensure that the outcome of the may not be able to start unless some of the
project meets the requirements of the precedingtasksare completed.
customer.
• The projects have a life cycle: The projects, Figure 1.2: Stages in the life cycle of a project
2
Conception: Scheduling:
During this stage, the management of the The project time schedules are developed
parent organization, comes across various during this phase. The project is broken into
ideas of projects, each project having its own smaller tasks and work packages, and the time
necessity, and significance. The project ideas required for individual tasksis assessed. The
are generally the outcome of brainstorming or breaking of the project into smaller tasks and
other means of idea generation. The ideas work packages is called Work Breakdown
thus generated are subjected to screeningon Structure (WBS). The interdependence of the
the basis of management’s priorities, tasksis also established during this phase. The
organizational needs, and importance of the time required for completion of the project is
project to achieve organizational goals. then assessed using the compiled information
of tasks interdependence and task time
Selection: requirements. Various techniques used for
The scarcity of resources may prohibit the scheduling are PERT, CPM, Gantt chart, and
management to launch all screened projects Milestone analysis.
simultaneously. The management then selects
various projects to be undertaken considering Monitoring and control:
various criteria like management priorities, Once the project is in process, it is necessary
competitive necessity, significance of project, to ensure that the various activities are
etc. For example, the management may completed at the scheduled time and within
considera project for new product decided budget. Exceeding time or cost will
development more significant than the lead to schedule overrun or cost overrun.
construction of a new warehouse. A number Also, since the projects are also characterized
of numeric and non-numeric techniques are by scarcity of resources and the simultaneous
used by management for the purpose of demand for resources by different tasks and
project selection. The numeric techniques work packages, it becomes essential to apply
include the financial assessment of projects techniques for rational and optimum
and also the comparative scoring. utilization, and allocation of the resources in
such a manner that the impact on project
Planning: objectives is minimum. The process
The selection phase is followed by planning ofcomparing the project progress with plans
the project. During this phase, various aspects refers to monitoring. Control refers to
relating to the projectare planned which identifying deviations and taking action to
include scope definition, resource minimize the impact of deviations. This phase
requirement planning, skills required for the also monitors the assessed risks and in the
project, manpower requirement, event of a risk becoming a reality, responds to
procurement requirement, financial planning, risk, mitigating its impact and changes are
and specification definition. The outcome of made to the plan if necessary due to the
this process is a project plan which remains to occurrence of the risk.
be a roadmap to the project. The project plan
is also used as a tool for project control. Evaluation:
Another important aspect of this phase is Evaluation refers to analyzing the project
identifying the risks involved during the project performance to ensure that the project
life and planning to counter these risks in the objectives are met. Evaluation involves
event of them becoming a reality. schedule performance, cost performance,
3
specifications achievement, actions taken to a lot of confusion and conflict regarding the
respond to risks, resource use and allocation, authority and reporting hierarchy.
and management of outsourcing and
contracting. The evaluation is carried out at Quick Momentum:
the end of the project and during different As the aspects relating to project become
stages of project progress. The during project clear, and direction is established, the project
progress evaluation provides the basis for gains speed. This is the phase of quick
taking corrective actions if needed and the momentum. The speed increases fast and
end of project evaluation is carried out to reaches a peak. This is the phase when
learn from the completed project so as to monitoring and control of the projectare in
perform the future projectsmore efficiently existence.
and effectively. The technique generally used
for evaluation is called project audit.
Project completion
Termination:
The project comes to the finishing part at this
stage. This phase identifies the need for
terminating a project. Please note that
termination does not always mean successful
completion of the project. Termination of
project may be a result of project failure or
changed management priorities or lack of
funds and resources. Final accounting of
project is carried out in this phase, and the Slow beginning Quick Momentum Slow finish
4
The planned measures of the three criteria Performance
make the target for the project.
Performance:
The product of a project must perform what Target
it was intended for. The specifications of
project output must meet the planned and Time Cost
agreed specifications. Performance is generally
one of the aspects leading to conflict between
client and project team leader. It is essential to
Figure 1.4: Project success criteria
clearly define the project objectives in the
planning phase leaving no scope for dispute.
Performance is the most important criteria for
the success of a project.
5
Cost: cause intangible losses like loss of reputation,
No project can be provided with unlimited loss of trust, and customer dissatisfaction but
resources. Each project is associated with a also leads to cost overrun. Many times the
budget in totality and a budget for each part of schedule overruns lead to financial
the project. For a project to be termed as compensations to the customer apart from
successful, it is essential that the project is additional expense in resources. A project for
completed within defined budget. The reasons being termed as successful needs to be
causing cost overrun need to be identified at completed in scheduled time.
the planning stage and controls need to be
applied to avoid such circumstances to arise. A project is successful if it can achieve its
performance objectives within scheduled
Time: time and allotted budget or cost.
Finishing in scheduled time is an important
aspect of projects. Schedule overruns not only
Review Questions
6
Project Management & Contract Administration
Unit-2
Overview of
Project Management
Learning
objectives
After studying this unit, the student will be able to:
Identify tools and techniques of project management at different stages of project progress.
1
activities (time by which activities can be
delayed without delaying the project),
monitoring of progress with respect to time
and corrective actions if needed.
Cost Management:
The budget is one of the constrained
resources for projects. Lack of financial
resources may cause a project to shut down
before completion. So it is necessary to
estimate the cost involved in the project and
also the cost involved in individual tasks of the
project. Cost management is about analyzing Risk Management:
and anticipating the cost involved in a project Risk is involved in the project at every stage of
and its continuous monitoring to avoid cost its life cycle. The risk, ifbecomes a reality may
overrun. It involves planning, budgeting, result in cost overrun and schedule overrun or
allocating and controlling the project cost. even project failure. Risk management is about
anticipating the risks for the complete
Human resource management: project,assessing the gravity of risks, planning
People involved in a project are important to for responding to risks and actually responding
its success. Forming the right and competent to risk if it materializes. Risk management also
project team is necessary for any project. involves management of changes in project
Also, since the personnel in the team are from plans if needed as a result of a riskactually
different functional groups, it is necessary to happening.
define responsibilities unambiguously and
avoid any conflicts. Human resource Procurement management:
management is about selection of personnel Outsourcing is an integral part of projects.
for the project, team development, managing Organizations outsource part of projects
conflicts, and motivating and leading the team. either because of lack of in-house
competence or because outsourcing may be
economical as compared to doing it in-house.
The outsourced part is not in direct control of
Cost Time the project leader, so it is essential to install
Management Management controls to ensure the quality of work
outsourced. Procurement management is
about selecting vendors, contracting and
Scope Project Human contract management.
Management Management Resource
Management
2
• WBS
• Budgeting
• Work element
costing
• Risk
Level of effort
identification
• Risk
assessment • CPM
• Risk response • PERT
development • Slack • Project audit
• Gantt chart • Project audit
• Resource life cycle • Extinction
leveling • Audit report • Addition
• Resource • Integration
allocation • Starvation
Time
3
work breakdown structure, work element impact of the occurred risk.
costing, and budgeting.
The occurrence of the risk and the action
Tools used for planning risk include risk taken to counter the risk may sometimes lead
identification, risk assessment, and risk to the requirement of reducing total time for
response development. finishing the project, and the technique of
project crashing is used to evaluate the extent
The technique used for planning resource to which a project can be crashed and the cost
requirements is work breakdown analysis. involved for crashing the project.
Scheduling Evaluation
This phase of project management plans the It is important to evaluate the performance of
time schedules for various tasks involved in project at various stages of its progress to
the project and also for the project in totality. identify any hidden or probable problems so
The start and finish time of varioustasksis that corrective actions can be taken before
determined along with slack of the tasks. The the problems cause major adverse impact on
critical activities of the project are identified project objectives. The tool used for
which if delayed, will cause the project to be evaluation is project audit, which involves an
delayed. The interdependence of various in-depth examination of the project
tasksis also established during this phase. The performance on various performance criteria.
techniques used during this phase involve The result of audit is an audit report which
Critical path method (CPM), project forms the basis of taking corrective measures
evaluation and review technique (PERT), for the project and preventive measures for
Gantt chart and milestone analysis. The the future project.
optimal utilization of resources is also planned
during this phase which uses techniques like Termination
resource allocation and resource leveling. This phase recognizes the need for
terminating a project with or without
Monitoring and control successful completion. The conditions leading
While the project is in progress, it is important to project termination include extinction,
to ensure that progress is in line with the plans. addition, integration, and starvation.
The monitoring and control is on the basis of
comparing and evaluating the work completed
at a specific time with the planned schedule
and planned budget for various tasks of the
project. Analytical techniques like cost
performance index (CPI), schedule
performance index (SPI), critical ratio (CR),
milestone analysis and tracking signal are used
during this phase. Gantt chart is also used to
compare performance with plans.
4
Review Questions
5
Project Management & Contract Administration
Unit-3
Project Selection
Non-numeric Models
Learning Project Selection
Non-numeric Models
objectives roject Selection
Non-numeric Models
After studying this unit, the student will be
able to : Can you identify the project proposals in the
above scenario?
Understand the importance of project
selection Consider a top management meeting of ABC
Corporation in progress.
Identify and apply appropriate
non-numeric selection model for project Managing Director:
selection Gentlemen, we have called for this meeting to
discuss the recently observed fall in our sales.
There seems to be a serious quality issue
which we need to resolve.
Marketing Manager:
Sir, we need to launch a customer survey
project to get direct information about
customer satisfaction and complaints. The
sales have recently dropped and the customer
loyalty seems to be shifting to a new
competitor.
Product Manager:
I understand the competitors have provided
many innovative features in their product.
Why don’t we go for redesign and
development of additional features in our
existing product or develop a new product
model itself? That may help in building
customer trust and loyalty.
Marketing Manager:
I think we can go ahead with product design
part after the customer needs are understood
through a survey.
Production Manager:
We have been using our existing technology
to the full potential. I was just thinking of
placing a request for new technology
procurement and installation. I feel that the
new technology will be able to raise the
maybe a good number and it becomes
quality standards of the existing product to
necessary to select project proposals for
the extent that may again attract the buyers to
implementation. It requires prioritization of
us. These days we are just producing and
the available project ideas.
stocking, sales not being able to push products
in the market.
Project selection is the process of evaluating
and analyzing the available project proposals
Materials Manager:
to identify and prioritize the projects on the
That reminds me, we need to build a new
criteria of their significance to organizational
warehouse to stock our raw materials and
goals and the budget constraints.
products. The current space is not adequate
to store all we have. We are sometimes
forced to keep our material in the open. Process of Project
Recently there was a theft also at night. I really Selection
don’t know what our security is doing.
The project selection process involves the
Security in charge: following:
We are managing this large premise with just a
handful of security guards. If the company is Gathering of project ideas:
not willing to employ more staff, at least the The ideas are gathered for projects from
boundary wall may be raised by another three different channels like employee suggestions,
feet with wire fencing and halogen light. operative or competitive necessity, and
customer requests.
The various project proposals that crop up
can be: Screening:
• A customer satisfaction survey The gathered ideas are subjected to screening
• New product development which evaluates ideas on the basis of their
• Existing product redesign and modification significance to the organization and financial
• New technology purchase and installation viability. The ideas not significant for
• Construction of a new warehouse organizational objectives or not financially
• Raising and fencing of boundary wall with viable are rejected, and the ones which are
halogen lighting viable and significant are subjected to the next
step.
2
Employee Customer
suggestions requests
Management
priorities
Operational Competitive
needs needs
Project ideas
Screening
Significant Reject
and viable?
Determine
selection criteria
Choose a project
selection model
Compare projects
using model Meets
criteria?
Select
3
basis of their relative significance and financial the projects. The models in this category
analysis results. include:
• Payback period
Selection: • Present value
The projects are selected for implementation • Net present value
on the basis of their relative priority. • Benefit-cost ratio
• Rate of return
Project
selection
Numeric Non-Numeric
4
Sacred Cow Model of generator becomes necessary. If
government policy restricts the operation of
This model selects the project on the basis of industry that causes water pollution,
wish and enthusiasm of some senior and installation of water treatment plant may be
powerful manager in the organization. Being necessary to avoid plant shut down.
the dream of senior officer, it is accepted by
the junior managers although they may not be All the situations mentioned above are in the
fully convinced of the idea. The junior category of operating necessity because if
managers in such situation are unable to those projects are not initiated, the
express their disagreement even though they organization shall not remain operative.
may have all the doubts in the success of the
project. Often formal evaluation and financial viability
is skipped in such situations and project is
Many times in organizations we find senior started immediately.
officers saying in a meeting:
Competitive Necessity
“Why don’t we develop an IT system that
merges all our operations and also A project may be selected because it becomes
connects us to the customer” essential to maintain competitive status in the
“I think we should try to design software market.
for” Consider the following situations
“Can’t we initiate a project for”
• The competitor has introduced new
features in the product with reduced
Such suggestions of the officer are taken as an price threatening the loss of market share
instruction by the junior officers and project is to the organization.
initiated. • The competitor has developed software
which makes it possible for customers to
The model is sacred in the sense that the contact and order online and the product
project remains in existence until it is can be delivered at the doorstep,
successfully finished or the senior officer threatening shift of customer loyalty
himself realizes that the idea will not work and because of ease.
terminates the project midway.
What action does the management of the
organization is expected to take to counter
Operating Necessity the threat and retain its market share?
The project may be selected for The first situation would call for a redesign of
implementation because it is necessary for the the product that will enhance product
plant to remain in operation. specification and can be produced at lower
cost. In the second situation, it may be
If heavy rains are expected, and a lot of necessary for the organization to develop a
material is stocked in the open, it may be system that allows better reach to the
necessary to construct a covered warehouse customers.
immediately. If a power cut is expected for a
long duration in next few months, installation Both the situations described above make it
5
necessary for the organization to initiate a are subjected to careful financial and
project for product design and development subjective analysis. The project is initiated if it
or customer contact system development. is found to be financially viable and meets
Projects are necessary because the market organization’s objectives. The payback period
share and loyalty of customers to the of the new FMCG product may be too large
organization are threatened. These are the or return on investment may be too low. The
examples of project selection on the basis of cost of establishing and operating a testing
competitive necessity model. house may not be economical and also the
skills needed may not be available with the
Like operating necessity, the model of organization. The distribution channels for
competitive necessity also bypasses formal thread and cloth may be different with
evaluation and financial analysis. different market segments.
The objective of any project is the growth of Comparative benefit model compares many
the organization. A project may be selected projects in consideration at a time. The
because it is in alignment with the existing projects under consideration are evaluated on
product line of business or it fills a gap in the their relative merit and are prioritized.
existing operating system leads to the vertical
integration of the organization. The technique used for comparative benefit
model is Q-Sort.
An FMCG company may initiate a project for Q-Sort adopts the following process:
installation of the facility for an additional • The relative merits of the projects are
FMCG product because it is in alignment with assessed.
existing distribution channels and existing • The projects are divided into Good, Fair
customer segment. (Project in alignment with and Poor categories on the basis of their
existing product line) relative merits.
• If the number of projects in any category
A manufacturing company initiates a project exceeds eight, it is further subdivided into
for establishing a testing laboratory, so the + and –, for example, good+ and Good–,
product testing can be carried out inhouse in fair+ and fair–, poor+ and poor–.
place of being outsourced. (Project fills a gap • The process is repeated until all groups
in the existing system) have 8 or less members.
• On the basis of relative merits of projects,
A textile factory manufacturing thread initiates all projects within the group are arranged
a project for establishing a facility for cloth in order from best to worst.
manufacturing. (Vertical Integration) • The priority of the project is determined
on the basis of the group they belong to
However the projects, before being initiated, and their position within the group.
6
Identify all Projects
Determine relative
priority position of the
projects
7
Project Management & Contract Administration
Unit-4
Project Selection
Numeric Models
Learning Present Value
F
PV =
(1+r)n
Example
If a project is expected to generate ` 1000 at
the end of 1 year and ` 5000 at the end of 2
years, calculate the present value of both the
transactions if the rate of interest is 12%.
Solution:
F
PV =
(1+r)n
For the first transaction
1000 interest is 10%, calculate the present value of
PV =
(1+ 0.12)1 the revenue.
1000
= = 892.9 7000
(1.12)1 PV =
(1+ 0.10)5
For the second transaction Solution
Instead of calculating we will use the present
5000
PV = value table
(1+ 0.12)2
As the number of years increases, the So present value of ` 7000, received after five
calculation becomes more cumbersome. years
Present value tables may be used for finding
the present value. = 0.0.62092 × 7000 = ` 4346.44
2
Year Investment ( ) Revenue ( )
(Initial investment) 50,000
1 20,000
2
3 10,000
4 35,000
5 5,000
6 25,000
7
8 40,000 5,000
9
10 12,000
Salvage value 2,000
Solution
Let us identify the factors for all transactions
from the PV Table and calculate the individual
present values.
3
NPV = ∑ (Total present value of all revenues) NPV = ∑ (Total present value of all revenues)
− ∑ (Total present values of all investments). − ∑ (Total present values of all investments).
= 1,33,373.25 − 1,13,723.70
C= 56833.56 − 95303.35 = −38469.79 = ` 19,649.55
Use of Annuity
Example
A project involves an investment of ` 30,000
at the end of each year for five years. The
returns are ` 25000 at the end of each year for
eight years. Calculate the NPV. The rate of
interest is 10%.
Solution
The factor for an annuity for five years at 10%
rate of interest is 3.79079.
4
Project A Project B
Year
2 20,000 25,000
5 20,000 25,000
Solution
Project A
Year
Investment Return Annuity Present
PV of
Investment PV Factor Return Factor for Value of
Investment
5 Years Annuity
Initial
investment 40,000 1.0 40,000
2 20,000
4 20,000
5 20,000
Total 69,105.05
5
Project A
Initial
investment 60,000 1.0 60,000
2 25,000
5 25,000
Total 90,928.40
6
For recovering, ` 1,00,000, another ` 55,000 is
required. However, in the third year, the
revenue is ` 60,000. We will use interpolation
to determine payback period.
Example
A project is expected to generate revenue of
` 5000 annually for five years. If investment in
the project is ` 15,000, determine the internal
rate of return. If management expects a rate
7
of return 10%, is the project viable?
Solution
Present value of investment = ` 19,000
For an annuity of ` 5,000 for five years:
(1 + r)n r = 1.099 PV
Total PV 19000
8
Project Management & Contract Administration
Unit-5
Case Study 1
New Delhi Laboratories
Private Limited (NDL)
1
profits have not been up to expectation, but
that was because we ventured into a project
for the first time and we could not anticipate
expenses accurately.” Divyansh replied.
2
Project Management & Contract Administration
Unit-6
Project Selection
Scoring Models
Learning
objectives
After studying this unit, the student will be able to:
Identify and apply appropriate scoring selection model for project selection
• Training requirements Should not take more than one year to complete
• Safety
Should be compliant with government
• Consistent with current operations safety regulations
• Availability of raw materials Should not require the hiring of additional
man power
• Potential market
• Government policies In-house competence should be available
• Impact on brand value and image of the Raw material should be available easily,
organization and its prices should be stable
Should be complementary to existing business
This model evaluates the project on various All projects in consideration are evaluated on
subjective criteria and indicates whether a each of the deciding factors, and the project
project qualifies for specific criterion or not. must qualify on an adequate number of
The project is selected if the total number of factors to be selected.
1
Project 1 Project 2
Factors
Does not Does not
Qualifies qualify Qualifies qualify
Should not take more than
one year to complete
Should be complementary
to existing business
ACTIVITY
A company manufacturing automobile spare parts is
planning to initiate a project for development and
installation of an IT system for integrating its
marketing, operations, design, stores, and quality
control sections. List the factors that you would
consider as criteria for evaluating the project.
2
Project XYZ
Factors
1 2 3 4 5
Should be complementary
to existing business
Project XYZ
Factors Weight
1 2 3 4 5
In-house competence 1
should be available
Should be complementary 5
to existing business
3
relative importance and significance of the Rating = (∑weight × rating)
factors affecting project selection decision are = 5 × 4 + 2 × 3 + 10 × 2 + 1 × 4 + 3 × 3 + 5
established. ×1+4×3
= 20 + 6 + 20 + 4 + 9 + 5 + 12 = 76
Initial
Periods in years investment 1 2 3 Salvage 5. Calculate the payback period for the
Cash
inflow 2,00,0001,50,000 80,000 10,000 following data of a project.
Project X
Cash
outflow 50,000 30,000 30,000 30,000 30,000 Initial investment ` 50,000
Cash 2,25,0001,10,000 90,000 15,000 Returns
inflow
Project Y
Cash 70,000 28,000 28,000 28,000 28,000
outflow
Year 1 2 3 4
The rate of interest is 10% Return 20,000 15,000 18,000 5,000
4
Project Management & Contract Administration
Unit-7
Project Planning
Learning
objectives
After studying this unit, the student will be able to:
Disintegrate the project into smaller tasks and work packages and create the WBS
1
conflict during the project life. ensured that it has a proper mix of authority
also.
Types of Responsibilities
Allocating Responsibility
Primary responsibility:
Primary responsibility refers to overall Identify all tasks involved in the project.
responsibility for the task assigned including
managing people involved in task and ensuring Develop the work breakdown structure.
time, cost and quality of the work.
Allocate primary responsibility for level 1
Secondary responsibility: tasks.
It refers to the responsibility assigned to a
person for ensuring better fulfillment of Allocate responsibility for level 2 tasks in
primary responsibility. consultation with the person responsible
for level 1 tasks.
Supportive responsibility:
The responsibility assigned for providing Allocate responsibilities in this fashion up
technical or managerial support to the to the last level of work packages.
persons with primary or secondary
responsibility. Generally, the supportive Identify the need for secondary
responsibility is assigned to a person, responsibility and supportive
considered as an expert in the area of work. responsibility for all the tasks.
Supportive responsibility may be given to any
member of the organization, whether in the Allocate the secondary and supportive
project team or not. responsibilities accordingly.
2
Responsibility Primary Secondary
Development of
1 1.1 survey questionnaire
2 1.1.2 Preparation of
questionnaire
2 1.1.3 Approval of
questionnaire
Filter consumer
data base and select
2 1.2.1 consumers who
purchased company’s
TV in last 3 years
Develop requirement
2 1.3.2 document and
seek quotations
3
Responsibility Primary Secondary
Transfer of survey
2 1.5.1 data on computer
The time estimates of the project activities are It provides information about the impact
determined on the basis of: of various activities on project
completion.
• Estimates from records of past projects
• Experience of the project team members
It forms a basis for planning the
• Critical study of work involved in the task
resources.
Generally, three types of time estimates are
determined for all tasks and work packages:
4
Time EstimatE MATRIX
5
Summary Review Questions
6
Project Management & Contract Administration
Unit-8
Work Breakdown Structure
Learning Planning Work
Scope—Work Breakdown
objectives Structure
After studying this unit, the student will be Work breakdown structure is a technique of
able to: exploding the project into smaller work
packages with an objective of creating clarity
Identify project as a system of work about the work to be done for accomplishing
packages the project.
Construction
Project of building
2
SURVEY FOR ASSESSING CONSUMER NEEDS
Level 1 tasks
1.1 Development of survey questionnaire
1.2 Deciding the sample customer group
1.3 Hiring a consultant for conducting survey
1.4 Conducting survey
1.5 Analysis of survey results and report preparation
Hiring a Analysis of
Development Deciding consultant for Conducting survey results
of survey the sample conducting survey and report
questionnaire customer group survey preparation
1.2.3 Collect data of sales in different zones and 1.5.2 Generation of reports
identify zones with dropped sales 1.5.3 Analysis and study of reports
1.5.4 Compilation of analysis results with
recommendations
Level 2 tasks
1.3 Hiring consultant
1.3.1 Identify consultants
1.3.2 Develop requirement document and seek
quotations
1.3.3 Personal meeting with consultants
1.3.4 Negotiation and finalization
3
Development of Survey questionnaire
Filter consumer data base Select 200 customers at Collect data of sales in
and select consumers random and develop different zones and
who purchased details of product and identify zones with
company’s TV in last 3 customers dropped sales
Compilation of
Transfer of survey Generation Analysis analysis
data on computer of reports and study of results with
reports recommendations
Conducting survey
Submission of
Analysis of results survey
Pilot survey by and modification Main survey by reports by
consultant in questionnaire consultant consultant
after sertiny
Hiring consultant
Develop
Identify requirement Personal meeting Negotiation and
consultants document and see with consultants finalisation
quotations
Since all level 2 tasks seem to be clearly need be, the level 2 tasks can be broken into
defined with respect to work specifications, smaller work elements at level 3.
further breakup is not necessary. However, if
4
ACTIVITY
A company manufacturing machine tools is planning
to initiate a project for procurement and installation
of a latest CNC machine to enhance capacity and
quality of its products. Identify various activities
involved, and prepare a work breakdown structure.
5
Project Management & Contract Administration
Unit-9
Developing Project Network
Learning Project Monitoring and
Control
objectives
The project time plan as referred to in the
After studying this unit, the student will be previous section provides the generic time
able to: estimates for different work packages or
activities of a project. It is now required to
Develop network schedule for a project estimate the completion time of the project in
and estimate time for completion totality. It is important to note here that the
project completion time is not the sum of the
Determine activity slack time taken by all work components
individually. It is because some of the activities
Estimate probability of project may be parallel while others might be
completion in a specific time sequential. So, the total time taken by the
project shall be less than the sum of the time
Determine the extent to which project taken by its individual activities.
can be crashed
In this section, we shall understand the
Develop Gantt chart for the project concepts behind the scheduling of the
activities of a project, i.e., establishing start
time and finish time of the various activities of
a project. We shall broadly understand two
techniques of project scheduling viz. Network
analysis and Gantt chart.
Network Analysis
C A
2
Activities B and C can start after activity A is
complete.
ACTIVITY
However, activity D can start only after both Consider a project for construction of a building.
activities B and C are complete. It is not Identify various activities involved and establish their
possible to draw an arrow from both the precedence relationship. Draw a network for the
activities B and C, as one activity can be identified activities. How many burst, merge,
represented by one arrow only. We make use hybrid, and simple events are contained in the
of a dummy activity in such cases. A dummy network?
activity is one which is not real, does not
consume time, used only for the continuation
of network and generally represented by a
dotted arrow.
OR
Activity Predecessor
A -
B A
B A F B,C
C A
Let us try to draw the network for above
D B situation.
E B,C
For the first five steps, we can use the
F D,E
situations discussed above.
3
Since activity F can start only after both
activities B and C are complete, we will have
to use two dummy activities to depict it.
Example 9.1
Following is the information related to a
software development project.
1 Specification development A -
2 Process mapping B -
4 Testing of software D C
6 Procurement of hardware F E
9 Pilot test I H
10 Training of users J I
4
Solution
Example 9.2
Following is the information related to a
construction project.
1 Design development A -
2 Design approval B A
3 Vendor identification C A
5 Laying foundation E D
6 Raising pillars F E
7 Structure development G F
8 Finishing H G
9 Electrical work I G
10 Inspection J I
5
Project Management & Contract Administration
Unit-10
CPM
Critical Path Method CPM involves the following steps:
(CPM) • Draw the project network
After the development of the network, the • Identify the paths leading from start to
interrelation of the various activities involved finish
in the project is established. The next process
is establishing a time for the activities. The • Calculate the total time along each path
time estimation has already been discussed in
previous sections. The establishment of time • The path with longest total time is the
taken by activities becomes the basis of critical path
further analysis which involves the
determination of project completion time and • The activities on the critical path are
slack of activities. critical activities
1
Activity Activity Activity time
A - 3
B - 5
C - 7
D C 3
E A, B 7
F E, D 3
G D 2
H F, G 2
A3
B5 E7 F3
H2
C7
D3 G2
Figure 10.1
We can identify four paths along this network. The longest path on the network is the
Critical Path.
A–E–F–H
B–E–F–H BEFH with a time requirement of 17 days is
C–D–G–H the longest path and is the critical path.
C–D–F–H
Project completion time is equal to the time
Calculate the time taken by each path by required by critical path and is equal to 17 days
adding the activity time on the path. for this project.
2
However, the method requires physically time is 3, 5, and 7 respectively, so the early
identifying all paths and calculating time finish for these activities is 3, 5, and 7.
required by each path. If the number of
activities is more, the network gets Activity D can start after activity C is
complicated, and it becomes almost completed, so that activity D cannot start
impractical to identify each path by before 7, i.e., ES of activity D is 7 and its
observation. So, a more scientific technique is activity time being 3, its early finish is
required to identify the critical path on the 7 + 3 = 10.
network.
Activity ES EF LS LF
The technique involves identifying four values A 0 3
for each activity: B 0 5
C 0 7
Early start: D 7 10
The earliest start time for the activity. It E 5 12
depends upon earliest completion time of all F 12 15
predecessor activities. G 10 12
H 15 17
Early finish:
The earliest time for the finish of the activity is
obtained by adding the activity time to the Activity E can start after both activities A and
earliest start. For example, if the earliest start B are completed. So, activity E can start
of the activity is 32, and time required by the earliest at 5 and its activity time being 7, its EF
activity is 4, the early finish will be 32 + 4 = 36. is 5 + 7 = 12.
Activities A, B, and C have no predecessor, so Since we would like to finish the project at the
that they can start at time zero. The activity earliest, the late finish of the last activity is
3
equal to its early finish. So LF for activity H is non-critical activities can be delayed to some
17. Since activity H has to finish at 17, it must extent without affecting the completion time
start at 17 − 2 = 15 (LS). of the project but delay in any critical activities
leads to project delay.
Activities F and G must be completed before
activity H starts, so both activities F and G
must finish at 15. The late start of succeeding
activity is equal to late finish of all preceding
activities. The late start of activities F and G is
therefore 12 and 13 respectively.
Activity ES EF LS LF
A 0 3 2 5
B 0 5 0 5
C 0 7 2 9
D 7 10 9 12
E 5 12 5 12
F 12 15 12 15
G 10 12 13 15
H 15 17 15 17
4
Example 10.2
The time required for completion of activities
for example 9.1 is as follows:
1 Specification development A - 20
2 Process mapping B - 15
4 Testing of software D C 5
6 Procurement of hardware F E 25
9 Pilot test I H 10
10 Training of users J I 30
Solution
Let us start with developing the project
network.
C 90
D5
A 20
G 30
J 30
B 15 I 10
H 10
E5 F 25
5
S. No. Task code ES EF LS LF
1 A 0 20 0 20
2 B 0 15 5 20
3 C 20 110 20 110
5 E 15 20 110 115
6 F 20 45 115 140
6
Project Management & Contract Administration
Unit-11
Case Study 2
Alpha solutions private clients from visiting site and they may
limited – Should we really offer business to competitors. they may
go for this project? offer business to competitors.
“Sir, I had been discussing this new building • Our work requires late sitting many
project with Anuj. He has many valid reasons times, which may not be possible due to
for continuing at the present premises rather inconvenient location. due to
than constructing a new building” Anil said inconvenient location.
looking at Mehra.
• Is the internet connectivity good there?
“Is it so? I always thought owning our own
office building was a great idea. Why don’t • Support services may not be nearby.
you call Anuj and we can discuss this issue?”
Mehra said. • Is it really financially worth? We are
paying a rent of just e are paying a rent
After half an hour, Anil and Anuj were sitting in of just ` 35000/ - per month. - per
chairs in Mehra’s cabin. month.
“Yes Anuj, what you have to say? I understand • Being on a single floor here, our
you have some disagreement with this interpersonal relations are excellent.
project.” Being on a single floor here, our
interpersonal relations are excellent.
“Sir, with due regards to your decision for We are all working like a team. A large
shifting to a new building, I have some building may lead to
reservations on this issue.” compartmentalization and will impact
organization culture.
“I do not deny the positive aspects of shifting, compartmentalization and will impact
but we cannot ignore some factors.” organization culture.
“Can you tell me about your concerns?” • Is it really our priority today?
Mehra said.
1
Mehra looked at the list carefully for some
time. “Anil, what you have to say about it?”
REVIEW QUESTIONS
2
Project Management & Contract Administration
Unit-12
PERT
Learning
objectives
After studying this unit, the student will be able to:
1
are as follows:
1 A - 1 3 5
2 B - 1 3 11
3 C A, B 2 5 8
4 D C 3 4 11
5 E C 4 7 16
6 F D 1 2 3
7 G E 4 6 14
8 H F, G 1 1 1
Solution:
4 1 1
1 A 1 3 5 3 =
6 3 9
10 5 25
2 B 1 3 11 4 =
6 3 9
6
3 C 2 5 8 5 = 1 1
6
8 4 16
4 D 3 4 11 5 =
6 3 9
12
5 E 4 7 16 8 = 2 4
6
2 1 1
6 F 1 2 3 2 =
6 3 9
10 5 25
7 G 4 14 14 7 =
6 3 9
0
8 H 1 1 1 1 = 0 0
6
2
The expected time estimates can now be used • Draw project network.
to estimate the expected completion time of • Identify critical activities.
the project along the same lines as in case of • Determine variance of all critical
CPM. The standard deviation of the project activities.
completion time can also be estimated. The • Calculate the sum of variances of all
standard deviation of the project completion critical activities (This is the variance of
will depend upon the standard deviation of project completion time).
critical activities. • Calculate the standard deviation of the
project completion time by taking the
To estimate project completion standard square root of the variance.
deviation:
Example 12.2
Determine the expected project completion
time and project completion time’s standard
deviation for example 10.5.
Solution:
Standard Variance
ET Deviation
S. Task Immediate 2
No. Code Predecessors PT+4MLT+OT PT - OT PT - OT
6 6 6
4 1 1
1 A - 3 =
6 3 9
10 5 25
2 B - 4 =
6 3 9
6
3 C A, B 5 = 1 1
6
8 4 16
4 D C 5 =
6 3 9
12
5 E C 8 = 2 4
6
2 1 1
6 F D 2 =
6 3 9
10 5 25
7 G E 7 =
6 3 9
0
8 H F, G 1 = 0 0
6
3
Let us draw the network for the project. The
time indicated against each activity is the
expected time for the activity.
A3
D5 F2
B4 C5 H1
E8 G7
Figure 12.1
The paths from start to finish in the network The extent of variation depends upon the
and the time required on each path can be standard deviation. The larger the standard
identified as: deviation of the project time, larger can be the
• A – C – D – F – H (3 + 5 + 5 + 2 + 1 = 16) variation in the actual project completion
• A – C – E – G – H (3 + 5 + 8 + 2 + 1 = 19) time.
• B – C – D – F – H (4 + 5 + 5 + 2 + 1 = 17)
• B – C – E – G – H (4 + 5 + 8 + 2 + 1 = 20) We will now understand how the probability
of project completion in a specific time can be
determined. The variation in the project
BCEGH being the longest path is the critical completion time is expected to follow a
path and activities on this path are critical normal distribution. For determining
activities. The expected time of project probability of project completion in a specific
completion is equal to the time required by time T, calculate standard normal variate Z.
longest path, i.e., 20 days.
T-Te
Z=
σ
Sum of variances of the critical activities:
Where T is the time period
25 25
= +1+4+ +0
9 9 Te is the expected time of project
95 completion
= = 10.56
9
Standard deviation of the project completion σ is the standard deviation of the
time is equal to the square root of the project completion time
variance of project completion time
Determine the area under the curve for the
= 10.56 = 3.25 relevant part as indicated in the graph below.
4
Example 12.4
What is the probability of completing the
Probability
of project project in 17 days in example 5.5?
Completion
in time T
Solution:
Probability of project
Te T completion in 17 days
Figure 12.2
Example 12.3
What is the probability of completing the
project in 24 days in the example 10.5?
T Te
Solution: Figure 12.3
Te = 20 days Te = 20 days
T = 24 days T = 17 days
Standard deviation = 3.25 days Standard deviation = 3.25 days
T-Te T-Te
Z= Z=
σ σ
24-20 17-20
Z= = 1.23 Z= = 0.92
3.25 3.25
The value of the area under the curve for Z = The value of the area under the curve for Z =
1.23 (From normal distribution table) is 0.92 (From normal distribution table) is
0.3907. This is the area between Te and T. The 0.3212. This is the area between Te and T. The
area on the left side of Te is 0.5 (The normal area on the left side of Te is 0.5 (The normal
curve being symmetrical and total area under curve being symmetrical and total area under
the curve is 1.0). the curve is 1.0).
So the total shaded area = 0.5 + 0.3907 = So, the total shaded area = 0.5 − 0.3907 =
0.8907 0.1093
The probability of the project being The probability of the project being
completed in 24 days is thus 0.8907. completed in 17 days is thus 0.1093.
5
Example 12.5
What is the probability of completing the
project in 19 to 22 days in example 10.5?
Solution:
Probability of
project completion
between times
T1 and T2
T1 Te T2
Figure 12.4
Te = 20 days
T1 = 19 days
T2 = 22 days
Standard deviation = 3.25 days
T-Te
Z=
σ
22-20
Z= = 0.62
3.25
19-20
Z= = 0.31
3.25
6
Project Management & Contract Administration
Unit-13
Slack
Learning
objectives
After completion of this unit, students will be able to:
1
Activity time
ES ES ES
EF EF EF
LS LS Total Slack LS
LF LF LF
Figure 13.3
A - 6
B A 3
C - 10
C 10
B3
A6
Figure 13.4
Total Slack
Activity Predecessor Time ES EF LS LF
TS=LS-ES
A - 6 0 6 1 7 1
B - 3 6 9 7 10 1
C B 10 0 10 0 10 0
2
So, both activities A and B have a slack of one
day. However, note that if slack of one day is
consumed by activity A, then activity A
finishes in 7 days. To finish in 10 days, activity B
has to start immediately without an
opportunity to utilize its total slack. However,
if slack was not consumed by activity A, it was
possible for activity B to start one day late. So,
if total slack is consumed by an activity, it
impacts the slack available to the subsequent
activities.
Example 13.1
Calculate total slack for each of the activities
for following data of a project.
A - 3
B - 5
C - 7
D C 3
E A, B 7
F E, D 3
G D 2
H F, G 2
Solution:
Let us start with the development of a
network for this project and determine ES, EF,
LS, and LF for all activities.
A3
B5 E7
F3
H2
C7
D3 G2
Figure 13.5
3
Total Slack
Activity ES EF LS LF
TS = LS - ES
A 0 3 2 5 2-0=2
B 0 5 0 5 0-0=0
C 0 7 2 9 2-0=2
D 7 10 9 12 9-7=2
E 5 12 5 12 5-5=0
F 12 15 12 15 12 - 12 = 0
G 10 12 13 15 13 - 10 = 3
H 15 17 15 17 15 - 15 = 0
Free slack:
Free slack refers to the time by which an
activity can be delayed without affecting the
early start of its succeedingactivities.
ES ES ES
EF EF EF
LS LS LS
LF LF LF
Figure 13.6
4
Example 13.2
Calculate free slack for each of the activities
for the data from example 9.1.
A - 3
B - 5
C - 7
D C 3
E A, B 7
F E, D 3
G D 2
H F, G 2
Solution:
Let us start with the development of a
network for this project and determine ES, EF,
LS, and LF for all activities.
A3
B5 E7
F3
H2
C7
D3 G2
Figure 13.7
5
Total Slack
Activity ES EF LS LF
TS = LS - ES
A 0 3 2 5 5-3=2
B 0 5 0 5 5-5=0
C 0 7 2 9 7-7=0
D 7 10 9 12 10 - 10 = 0
E 5 12 5 12 12 - 12 = 0
F 12 15 12 15 15 - 15 = 0
G 10 12 13 15 15 - 12 = 3
H 15 17 15 17 17 - 17 = 0
Independent slack:
Independent slack refers to the time by which
an activity can be delayed if the preceding
activity finishes late and succeeding activity
starts early. This slack is independent because
its consumption by the activity does not
impact the slack of other succeeding activities.
6
The slack if not consumed is lost and is not
transferred to succeeding activities, in contrast
to total slack. Independent slack can be
calculated as:
IS = ESs – LFp – t
ES ES ES
EF
EF EF
LS
LS LS
Slack
LF LF LF
Activity Time
Figure 13.8
Example 13.3
Calculate free slack for each of the activities
for the data from example 11.1.
A - 3
B - 5
C - 7
D C 3
E A, B 7
F E, D 3
G D 2
H F, G 2
Solution:
Let us start with the development of a
network for this project and determine ES, EF,
LS, and LF for all activities.
7
A3
B5 E7
F3
H2
C7
D3 G2
Figure 13.9
Independent Slack
Activity ES EF LS LF
IS = ESS - LFP - t
A 0 3 2 5 5-0-3=2
B 0 5 0 5 5-0- 5=0
C 0 7 2 9 7-0-7=0
D 7 10 9 12 10 - 9 - 10 = -2
E 5 12 5 12 12 - 5 - 7 = 0
F 12 15 12 15 15 - 12 - 3 = 0
G 10 12 13 15 15 - 12 - 2 = 1
H 15 17 15 17 17 - 15 - 2 = 0
8
Independent slack for G = ESH – LFD – tG or
15 – 12 – 2 = 1
Example 13.4
The time required for completion of activities
in example 5.1 is as follows:
1 Specification development A - 20
2 Process mapping B - 15
4 Testing of software D C 5
6 Procurement of hardware F E 25
9 Pilot test I H 10
10 Training of users J I 30
9
Determine total slack, free slack, and
independent slack for all activities.
Solution:
Let us start with developing the project
network.
C 90
D5
A 20
G 30
J 30
B 15 I 10
H 10
E5 F 25
Figure 13.10
Independent
S. Task Total Slack Free Slack Slack
ES EF LS LF FS = ESS - EF IS =
No. Code TS = LS - ES
ESS = LFP - t
1 A 0 20 0 20 0-0=0 20 - 20 = 0 20 - 0 - 20 = 0
2 B 0 15 5 20 5-0=5 15 - 15 = 0 15 - 0 - 15 = 0
4 D 110 115 165 170 165 - 110 = 55 170 - 115 = 55 170 - 110 - 5
= 55
7 G 110 140 110 140 110 - 110 = 0 140 - 140 = 0 140 - 110 - 30
=0
8 H 140 150 140 150 140 - 140 = 0 150 - 150 = 0 150 - 140 - 10
=0
9 I 150 160 150 160 150 - 150 = 0 160 - 160 = 0 160 - 150 - 10
=0
10 J 160 170 160 170 160 - 160 = 0 170 - 170 = 0 170 - 160 - 30
= -30
10
Knowledge of activity slack is important for
project managers. Slack provides an
understanding of the time by which activities
can be delayed and as such help in focusing
attention on activities with lower slack to
ensure project completion in time. Slack also
helps in resource planning. If the requirement
of resources varies widely over different
periods, slack is used to shift the start time of
activities in a manner that resource
requirement over different periods becomes
uniform without affecting project completion
time. In case of limited resources, slack
provides the basis for deciding priorities for
resource allocation to competing activities.
11
Project Management & Contract Administration
Unit-13
Slack
Project Management & Contract Administration
Unit-14
Project Crashing
Learning Project Crashing
Normal Solution:
cost Let us first draw the network of the project
and identify the project completion time.
Crash time Normal time
Time
D6
A8
Figure 14.1 C 12
Crash time: The minimum time Find the paths leading to finish from the start
required for completion of an activity. of the network and their time requirement.
• C 12
Normal cost: The cost of completing
• A – D 14
an activity under normal circumstances
• B – E 11
with planned resources.
A – D is the critical path, being the longest
Crash cost: The cost required to route, and A and D are critical activities.
complete an activity in minimum possible
time. Note that if we want to reduce project
completion time, activity on the critical path
As can be observed from the graph, as we has to be slashed. Reduction in time of a
move from normal time toward crash time, non-critical activity will not result in project
the cost increases, i.e., the crash cost is higher time reduction. Let us now find out the crash
than the normal cost of the activity. This cost per day for each activity.
additional cost is due to additional resources Crash cost - Normal cost
Creash cost per day =
employed for completing the activity in Normal time - Crash time
shorter period.
2
Activity Normal Crash Normal Crash Crash Cost
Time Time Cost Cost per Day
Project Crashed
Activities
Critical Activity Cost of project
completion Paths that can
Path crashed crashing completion
time be crashed time
C 12
14 AD 14 A-D A, D A 500 13
BE 11
C 12
13 AD 13 A-D A, D A 500 12
BE 11
C 12
A-D D D 750
12 AD 12 500 11
C C C
BE 11
C 11 A-D None
Further crashing is not possible because on
11 AD 11 C C one of the critical path, no activity can be
further crashed.
BE 11 B-E B-E
So the project can be crashed by three days, Cost of crashing by 2 days 500 + 500 =
completing it in eleven periods in the place of 1000
fourteen and cost of crashing is as below: Cost of crashing by 3 days 500 + 500 +
Cost of crashing by 1 day 500 750 + 500 = 2250
3
Example 14.2
Consider the following project
A - 12 8 4000 5600
B A 6 4 2500 3500
C A 3 2 600 900
D A 5 4 1600 1950
E C, D 4 2 3400 3800
F B, E 8 5 1000 2800
G D 4 2 1200 2800
H F, G 7 5 1800 4000
F8
B6
E4
A 12 C3 H7
D5
G4
Figure 14.3
4
Normal Crash Normal Crash Crash cost
Activity time time cost cost per day
5
Crashed
Project Activities
Critical Activity Cost of project
completion Paths that can be
Path crashed crashing completion
time crashed time
ABFH 33
ACEFH 34
36 ADEFH A, D, E, F, H E 200 35
ADEFH 36
ADGH 28
ABFH 33
ACEFH 33
35 ADEFH A, D, E, F, H E 200 34
ADEFH 35
ADGH 28
ABFH 33
ACEFH 32
34 ADEFH A, D, E, F, H D 350 33
ADEFH 34
ADGH 28
ABFH 33
ACEFH 32 ADEFH A, F, H
33 A 400 32
ADEFH 33 ABFH A, B, F, H
ADGH 27
ABFH 32
ACEFH 31 ADEFH F, H
32 F 600 31
ADEFH 32 ABFH B, F, H
ADGH 26
ABFH 31
ACEFH 30 ADEFH H
31 ABFH H 1100 30
ADEFH 31 B, H
ADGH 26
ABFH 30
ACEFH 29 ADEFH H
30 H 1100 29
ADEFH 30 ABFH B, H
ADGH 25
ABFH 29
ACEFH 28 ADEFH Further crashing is not possible because on
None one of the critical path, no activity can be
29 ABFH B
ADEFH 29 further crashed.
ADGH 24
6
Project Management & Contract Administration
Unit-15
Developing Gantt Chart
Learning Gantt Chart
Scheduling:
Gantt chart is a simple tool to depict the
sequence of activities in a project and can be
used to estimate the scheduled finish of the
project. The Gantt chart created to show the
planned start and finish of activities is called
the Baseline Gantt chart.
Resource allocation:
Often the projects deal with limited resources,
and it becomes important to allocate
resources to the activities in a manner that has
least impact on project completion schedule.
Also, a project manager is always interested in
the allocation of resources in such a manner
that the demand for resources is uniform to
the extent possible during the project life.
Gantt chart forms the basis for identifying
resource requirements at different periods
during the project and helps the manager to
allocate resources in most efficient manner. differentiating between planned progress and
actual progress.
Controlling:
The baseline Gantt chart becomes the basis of The structure of the Gantt chart looks as
control. Apart from the scheduled activities, below, ABCD and E being the activities
the current state of the project can also be involved in the project.
depicted on the Gantt chart which provides
basis for comparing planned versus actual A
progress and taking actions as necessary. B
Time Scale
C
D
Structure of Gantt Chart
E
As discussed earlier, Gantt chart is a graph
with x-axis indicating time scale and Y-axis Time Scale
shows various activities involved in the Figure 15.1
project. Horizontal bars along x-axis indicate
the activities, their length being proportional Example 15.1
to the time required by the activities. Colors, Develop a Gantt chart for a project with
shades or outlines can be used in the bars for following data
2
Activity Predecessor Time
A - 3
B - 5
C - 7
D C 3
E A,B 7
F E,D 3
G D 2
H F,G 2
Solution:
H
12
34
36
78
10
11
12
13
14
15
16
17
18
9
Figure 15.2
Example 15.2
Create a baseline Gantt chart for the following
project.
Activity A B C D E F G H
Time 12 6 3 5 4 8 4 3
3
Solution:
A
B
C
D
E
F
G
H
12
34
56
78
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
9
Figure 15.3
Example 15.3
Following is the data pertaining to plan and
actual progress on day 17 for the project in
example 15.2. Show the plan and progress on
a Gantt chart.
Activity A B C D E F G H
Time 12 6 3 5 4 8 4 3
Progress on
100% 75% 100% 60% - - - -
day 17
Solution:
H
12
34
56
78
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
9
Figure 15.4
4
Example 15.4
Develop the Gantt chart for the following
network.
A3
F2
D5
B4 H1
C5
E8 G7
Figure 15.5
Solution:
B
C
F
G
H
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
Figure 15.6
5
Project Management & Contract Administration
Unit-16
Case Study 3
Alpha solutions private limited was established The schedule of the project was
in 2012. The company started undertaking as follows:
projects for developing internet security
A 10 B 12 D 30 F5
software from corporates. By the year 2016,
the company was already doing business with
more than 30 corporates and had developed
the reputation of its expertise in the field. The C 15
E 10
company was headed by Mr. Mehra as the
Managing Director, and Anil assisted him as
chief project manager. Anil was responsible
Anil received a call from CEO of Mohit
for allotting the new projects to one of eight
industries before the start of the project,
project managers working for the company.
requesting him to see if the project instead
could be delivered five days earlier. Anil
Anuj was the project manager for a project
promised to reply by the end of the day. Anil
with Mohit Industries, one of the most
had a discussion with Anuj and Mr. Mehra.
important clients of Alpha Solutions. The
While Anuj was reluctant to accept the
project started on January 1, 2016 and was
change, Mr. Mehra did not want to antagonize
scheduled to be handed over to the client in
an important client. He asked Anil to handle
60 days.
the situation. While Anil talked to the client
again, telling him that completing the project
1
earlier would involve additional resources and
will not remain viable for the organization, the
client offered to cover additional expenses up
to Rs. one lakh. Anil again had a meeting with
Mr. Mehra and appraised him of the discussion
with client. Mr. Mehra asked Anil to analyze
the cost involved and also whether the project
can be shortened by five days at all.
A 10 8 12000
B 12 12 -
C 15 12 20000
D 30 25 18000
E 10 10 -
F 5 5 -
Questions
2
Project Management & Contract Administration
Unit-17
Developing Baseline
Cost Curve
1
Learning
objectives
After completion of this unit, students will be able to:
Project X
A B C D
A 5 - C
B
B 2 -
D
C 4 B
D 6 B
1
0 1 2 3 4 5 6 7 8 9 10
Cost
A 100
B 70
C 200
D 150
A 100 30 20 20 20 10
B 70 20 50
C 200 70 30 40 60
D 150 40 20 30 30 20 10
2
1 2 3 4 5 6 7 8
Figure 17.1
C Wiring roughed in A 1 3
E Siding on D 2 5
Windows, insulation, walks,
F plaster and garage E 8 17
G Furnace B 1 9
3
Activities
C 0.90
D 0.90 0.90
E 0.75 0.75
G 2.70
H 0.60 0.60
L 1.20
M 0.60 0.60
Week 1.80 1.80 1.80 1.80 1.80 1.80 0.80 3.60 0.90 1.35 1.35 1.09 1.09 1.09 1.09 1.84 0.64 0.64 0.64 0.50 0.50 0.50 0.50 0.50 0.50 0.60 0.60
cost
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Time
(weeks)
4
35
30
25
20
15
10
1 4 7 10 13 16 19 22 25
Figure 17.2
5
Project Management & Contract Administration
Unit-18
Project Budgeting
and Activity Costing
Learning A budget is a plan for resource allocation.
Also, it acts as a control mechanism.
objectives
Allocation on the basis of forecast of
After studying this unit, the student will be
resources, quantities needed, and when it
able to:
is needed.
Understand the process involved in
Uncertainties are involved.
project budgeting
2
Top Down Budgeting
Bottom Up Budgeting
Considers
Overheads
Allowances
General and administrative costs
3
Project Management & Contract Administration
Unit-19
Project Monitoring
with Gantt Chart
Learning Project Monitoring and
Control
objectives
While it is important to plan a project
After studying this unit, the student will be adequately, it is equally important to ensure
able to: that the plans are implemented in a manner
that project objectives are achieved. It
Understand the basic process of project involves two aspects:
monitoring and control
• Continual and periodic verification of the
project progress.
Use tracking Gantt chart for monitoring
• Identifying deviation from plans and taking
of projects
actions if required.
Project monitoring is the process of verifying
the project performance on the basis of data
collected from the project and project control
refers to comparing the actual performance
with targets or plans, identifying deviations if
any and taking the required actions. Deviation
can be defined as the differences between
“What is and what should be.” The various
aspects of the project that need to be
controlled are:
• Schedules
• Cost
• Specifications or quality
Process of Project
Monitoring and Control
Apply action
Verify effectiveness of
action taken
Figure 19.1
Define project objectives: Identify deviation:
The project objectives include the information The difference between the actual progress
about the desired time of project completion, and desired progress indicates a deviation.
the budget for completion of the project and
the quality specification of the project output. Various tools used for the monitoring and
control of the projects are
2
Example 19.1
Develop the Gantt chart for the following
network.
A3
D5 F2
B4 C5 H1
E8 G7
Figure 19.2
Activity A B C D E F G H
% complete
100% 100% 100% 80% 60% 0 - -
on day 14
Solution:
H
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
Figure 19.3
3
Following is the tracking Gantt chart:
H
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
Figure 19.4
The chart indicates that activity D is lagging will get delayed unless activity D is
behind on day 14. As a result, activity F has controlled at this point and is completed in
not yet started, where it should have started another one day. However, activity E seems
by this time. The indication is that project to be faster than scheduled.
4
Project Management & Contract Administration
Unit-20
Project Monitoring
(Earned Value Analysis)
Learning
objectives
After studying this unit, the student will be able to:
1
Determine BCWP for each activity and the
project in totality.
E 0 1000 0% of 1000 = 0
2
Example:
Consider the following information about a
project during its implementation.
A 100 2000
B 100 3500
C 100 1500
D 60 3000
E 40 1000
3
index compares the planned cost with actual
cost incurred.
BCWP
CPI =
ACWP
CV = BCWP − ACWP
Example:
Determine CPI and CV for all activities and
the project in totality.
4
Activity % Completion Budgeted cost ACWP
D 60 3000 1500
E 40 1000 500
% Budgeted BCWP CV =
Activity Completion ACWP BCWP CPI =
cost ACWP BCWP - ACWP
5
Schedule variance (SV):
Schedule variance determines the actual
difference in BCWP and BCWP and is
calculated as
SV = BCWP – BSWS
Example:
% Scheduled
Activity Budgeted cost % Actual Completion
Completion
B 100 3500 90
C 100 1500 90
D 60 3000 35
E 40 1000 0
&
% Actual BCWP
Activity Scheduled Budgeted SV =
Comple BCWP BCWS SPI =
Completion cost BCWS BCWP - ACWP
-tion
6
Total BCWP = 7550 The value of CR is considered acceptable in
Total BCWS = 9200 the range of 1.05 to 0.9. It is a general practice
7550 by project managers to plot the value of CR
SPI =
9200 on a control chart and take action when it
Cost variance = 7550 – 9200 = –1650 crosses the acceptable limits.
The work done is lagging behind the schedule
by work worth 1650.
1.05
Critical ratio
1.0
Critical Ratio (CR)
0.9
SPI and CPI individually evaluate the
performance of the project with respect to
Figure 20.1
schedule and cost respectively. However, as
we have seen, these two aspects are not
independent. Impact of the variance in one
parameter affects the performance of another
parameter.
CR = CPI × SPI
7
% % Actual
Budgeted
Activity Scheduled Actual Cost
cost
Completion Completion Incurred
D 60 3000 35 1500
E 40 1000 0 500
Example:
For the above data collected during a
milestone of the project, calculate the critical
ratio.
Solution:
% % Actual
Budgeted
Activity Scheduled Actual Cost BCWP BCWS
cost
Completion Completion Incurred
8
Milestone 1 2 3 4 5
Solution:
Milestone 1 2 3 4 5
9
Project Management & Contract Administration
Unit-21
Case Study 4
Alpha Solutions Private “Please plan for the requirement of cash also
Limited – Planning for a with the timeline so we can arrange it when
New Office Building required.”
“Anil, you can consider the budget as “I will do that sir” Anil responded.
approved. Schedule a meeting with Mr. Arya
and prepare the complete plan for In a detailed meeting with Mr. Arya, three days
construction” Mehra told Anil while crossing later, Anil and Anuj arrived at the time
his cabin. “You can involve Anuj with you if estimates of the project activities. They also
you want.” established the interrelationship of the
activities.
“Yes sir, I would like Anuj with me. Recently he
has been showing his analytical capabilities. I The details were presented to Mehra in a
plan to raise him to senior project assistant meeting a few days later.
shortly.” Anil said.
1
Budgeted Time estimate (in weeks)
Activity Activity Code
number cost
(in lakhs) Optimistic Most likely Pessimistic
Advertisement
A P11A 1.75 3 3 3
for architect
Selection of
B P11B 0.75 2 4 7
architect
Design by
C P12A 2.25 5 9 15
for architect
Advertisement
E P22A 1.50 3 3 3
for contractor
Selection of
F P22B 0.50 2 5 8
Contractor
Specification
G P23A 1.25 4 9 14
development
Order placement
H P23B 0.55 2 3 6
Building
I P23C1 65.45 30 42 48
construction
Wood work
J P23C2-1 32.50 6 9 14
Furnishing
K P23C2-2 20.50 3 7 12
Upholstery
L P23C2-2 5.50 3 5 9
2
Activity Predecessor
Activity Activity
number activities
K Furnishing P23C2-2 I
L Upholstery P23C2-3 J, K
QUESTIONS
1. Prepare a weekly cash requirement for
the project. (Consider that the cost of
activities is uniformly spread over its
duration)
3
Project Management & Contract Administration
Unit-22
Project Monitoring
with S Curve
Learning
objectives
After studying this unit, the student will be able to:
Time
Figure 22.1
1
However, the cost curves for ACWP and
BCWP may not follow the same pattern. The
variation in patterns of ACWP and BCWP as
compared with the BCWS curve provides vital
information about project performance.
1 Specification development A - 20
2 Process mapping B - 15
4 Testing of software D C 5
6 Procurement of hardware F E 25
9 Pilot test I H 10
10 Training of users J I 30
C
A D
B J
I
H
E F
2
15 20 45 110 115 140 150 160 190
Figure 22.2
A 100 200
1 20 B 100 500 1000 1000
E 100 300
3
Figure 22.3
Cost
Variance
BCWP
Schedule
slipage
Figure 22.4
The above graph shows three curves namely been completed and so BCWP is 100%, same
ACWP, BCWP, and BCWS. You can observe as BCWS. The SPI, therefore, will be 1. So, at
that the ACWP curve finishes after the BCWS project finish, SPI will be equal to 1. Note that
curve on x-axis and higher on y-axis. The SPI and schedule slip are not same. Schedule
difference between planned finish time and slip refers to the period by which project has
actual finish time is termed as schedule slip. been delayed whereas SPI is the ratio of
Observe that BCWP curve finishes after BCWP to BCWS.
BCWS on time scale but finishes at the same
point as BCWS on cost scale. It is due to the
fact that at completion, 100% of work has
4
The following can be interpreted from the ACWP at project finish = 52000
graph: Scheduled finish = 200 days
Actual finish = 210 days
Schedule slip:
Difference between the actual finish and
planned finish
Schedule variance:
Difference along cost curve between BCWP
and BCWS
Cost variance:
Difference along cost curve between BCWP
and ACWP
SPI:
Ratio of the value of BCWP to BCWS along
cost axis
CPI:
Ratio of the value of BCWP to ACWP along
cost axis
Cost overrun:
Difference between BCWP and ACWP along
cost axis at project finish
Example:
Interpret the following graph.
52000
50000
ACWP BCWS
BCWP
200 210
Figure 22.5
5
Example:
Consider the following curves developed
during the project. Prepare a project
performance report based on weeks 20, 35,
60, and 75.
90
80
70
60
BCWS
50
ACWP
40
BCWP
30
20
10
10 15 20 25 30 35 40 45 50 55 60 65 70 75
Figure 22.6
Week 20 35 60 75
BCWP 11 28 65 71
BCWS 16 40 68 71
ACWP 30 56 72 77
CV -19 -28 -7 -6
SV -5 -12 -3 0
6
Project Management & Contract Administration
Unit-23
Resource Planning
Learning
objectives
After studying this unit, the student will be able to:
Resource Planning and In this unit, we will try to answer the above
Allocation questions faced by project managers.
Cost and schedule are two major objectives The resources can be
of projects. However, both these objectives • Human resource
are influenced by the availability of resources • Machinery
at the right time and right place. One of the • Equipment
concerns of the project manager is to ensure • Materials
effective utilization of the resources in order • Skills
to achieve the project objectives.
Resources maybe available in-house or maybe
The project manager is faced with questions outsourced. The uncertainty about resource
like availability is higher if it is outsourced.
1
identifying the cost implications of resources
required for various work packages.
Specification Prototype
development development
(A) (B)
Development of
Designing the Casting Moulding
engineering drawing
assembly (A2) (B1) (B2)
(A1)
Inspection
Prototype testing (B5)
(A)
Figure 23.1
The resource requirements are identified for responsible for the work packages. The
individual work package by the managers resource matrix may be in the below shape.
2
Resource Requirement for work packages
Code Work package
Manpower Machinery Equipment Material
Development of
CAD-1
A1 engineering Draughtsman-2
Digitizer-1
drawing
Design engineer-1
Designing Hydraulic CAD-1
A2 Civil engineer-1
assembly crane Digitizer-1
Draughtsman-1
Systems
engineer-1 Simulation
A3 Simulation
Design software
engineer-1
Mechanical
engineer-1 Casting Cast iron
B1 Casting
Casting Machine -3KG
operator-2
Mechanical
engineer-1 Moulding
B2 Moulding Machine
Moulding
operator-2
Mechanical
Heat treatment engineer-1 Heat treatment
B3
Heat treatment chamber
operator-1
Design engineer
Hydraulic
C1 Prototype trial Hydraulic crane
crane
operator
The resource requirements for various work Similarly, the addition of requirements for
packages can be converted to the resource level 1 activity provides the resource
requirement for level 1 activity. requirements for the project.
3
Resource Requirement for Level 1 Activities
Draughtsman-2 CAD-1
Specification Design engineer-1 Digitizer-1
A Hydraulic crane
development Civil engineer-1 Simulation
System engineer-1 software
Mechanical
engineer-1
Casting operator-2 Casting machine Finishing
Prototype Moulding operator-2 Moulding machine equipment Cast iron
B development Heat treatment
Heat treatment Mould test -3KG
operator-1 chamber equipment
Cast die mechanic
Inspection engineer
Project
4
When are the Resources
Required?
However, the above table does not show the
duration for which the resources are required
or the period when they are required. To
assess it, information needs to be compiled for
the time taken by activities and the start and
finish of the activities.
A2 Designing assembly 25 -
A3 Simulation 3 A1, A2
B1 Casting 2 A2
B2 Moulding 4 B1
B3 Heat treatment 2 B2
5
Project Management & Contract Administration
Unit-24
Resource Loading
and Leveling
Learning Types of Resource
Constraints
objectives
• People
After studying this unit, the student will be • Materials
able to: • Equipment
• Working Capital
Identify the resources required for the
project Projects may be
Time-constrained projects
Resource Loading
A 2 - 2
B 3 - 2
C 5 - 4
A (2)
C (5)
Project network
B (3)
B
Gantt Chart
C
Figure 24.1
Day 1 2 3 4
A 2 2 - -
B 2 2 2 -
C 4 4 4 4
Resource requirement 8 8 6 4
5
C
4
B
3
A
2
Figure 24.2
2
Resource Leveling
Day 1 2 3 4 4
A 2 2 - - -
B 2 2 2 - -
C 4 4 4 4 4
Resource 8 8 6 4 4
requirement
10
C
4
B
A
2
A (2)
C (5)
Project network
B (3)
3
A
B
Gantt Chart
C
Figure 24.3
Day 1 2 3 4 5
A 2 2 - - -
B 2 2 2 2 2
C 4 4 4 4 4
Resource requirement 8 8 6 6 6
5
C
4
B
3
A
2
Figure 24.4
4
Project Management & Contract Administration
Unit-25
Project Termination
Learning
objectives
After studying this unit, the student will be able to:
1
The Termination Process
Step 1: Decision
• Based on the degree to which the project
meets goals and objectives set for it.
• Factor scoring or weighted factor scoring
or Delphi or a combination may be used
for making a decision.
Delphi
database Scoring
model
Termination
rule set
Yes
Terminate
project
Figure 25.1
2
Project Management & Contract Administration
Unit-26
Case Study 5
Alpha Solutions Private
Limited – Planning Under
Time and Resource
Constraint
D G
E
A B
F
C
Figure 26.1
1
required the same specialist, and he could
work on only two activities at a time. There
are periods when three activities are working
together, and that means some activities will
have to wait. The project will take 17 weeks in
place of 15, and the customer will be lost
forever.
QUESTIONS
1. Prepare a resource load table of the
project on the basis of given information.