Lesson 7 Resourcing Projects
Lesson 7 Resourcing Projects
Lesson 7
After completing this chapter…
⚫ Create a HR Management plan
⚫ Describe methods of resolving
resource overloads
⚫ Compress a project schedule using
crashing and fast tracking
2
Technical Abilities Needed
when Resourcing Projects
Create a
staffing
management
plan
Assign Schedule a
Compress project with
person(s) a project
to each limited
schedule resources
activity
3
Behavioral Abilities Needed
when Resourcing Projects
⚫ Select the right people
⚫ Schedule overtime
4
Behavioral Abilities Needed
when Resourcing Projects
⚫ Estimate amount of work per activity
⚫ Deal
with people from diverse
backgrounds
Behavioral
Technical
6
Key Resourcing Considerations
Project
Personnel tradeoffs and
skill precedence's
development
Resource
People cost limitations
Project cost
7
Estimate Resource Needs
⚫ How many resources of each type and skill
or knowledge level are needed.
⚫ Consider support needs such as
information systems and human resources
⚫ Consider constraints placed upon how
people are hired, scheduled, and released
8
Plan Human Resource
Management
Plan Human Resource Management – “the process of
identifying and documenting project roles, responsibilities,
required skills, reporting relationships, and creating a staffing
management plan. PMBOK® Guide
⚫ Identify
potential resources
⚫ Determine resource availability
⚫ Decide timing issues
Staffing management plan – “a component of the human
resource plan that describes when and how project team
members will be acquired and how long they will be needed.”
PMBOK® Guide
9
Identify Potential Resources
Work functions job titles and range of
⚫ responsibilities
degrees and professional
Professional discipline
certifications
experience and
Skill level
performance ratings
Specific Available
skill gaps vs.
needed
Opportunity
options
13
Decide Timing Issues when
Resourcing Projects
⚫ When to bring people on board
⚫ Get the team functioning effectively
⚫ Plan for keeping the team motivated
and on schedule
⚫ When to reward and recognize the
project team
⚫ When and how to release project
participants
14
Staffing Management Plan
Issues
15
Project Team Composition
Issues
Outsourcing
Cross-functional
16
Assign a Resource to each
Activity
⚫ Show resource responsibilities on
RACI chart
⚫ Show resource assignments on Gantt
Chart
17
Show Resource Responsibilities
on RACI Chart
Responsibility assignment matrix (RAM) – “a grid that shows
the project resources assigned to each work package.”
PMBOK® Guide
19
Show Resource Assignments
on Gantt Chart Person responsible for
each activity is listed
next to the activity in
the Gantt Chart
Schedule
20
Methods of Resolving Resource
Overloads
⚫ Reorder the activities
⚫ Acquire or borrow additional
resources
⚫ Reduce project scope or extend
project schedule
⚫ Inform the sponsor of severe
overloads
⚫ Resource level the overloaded
person’s schedule
21
Resource Leveling
⚫ Delay activities so the person doesn’t
perform as many activities at the same
time (most common)
⚫ Delay noncritical activities by an
amount no more than their slack
⚫ Allow the project to slip
Resource Leveling – “a technique in which start and finish
dates are adjusted based upon resource constraints with the
goal of balancing demand for resources with the available
Supply.” PMBOK® Guide
22
Resource Leveling
⚫ Ifnon-critical activities must be
completed at the rate of effort in the
original schedule, reassign activities to
another worker
23
Compress the Project
Schedule
⚫Actions to reduce the critical path
⚫Crashing
⚫Fast tracking
24
Actions to Reduce the Critical
Path
⚫ Reduce the project ⚫ Schedule activities at the
scope and/or quality. same time.
Which critical
path activity
costs the least
Which
on a per day
activities are
basis to speed
on the critical
up?
path?
27
Crashing
Example
Set Up
28
Crashing Example – After
Round 1
29
Crashing Example – After
Round 2
30
Crashing Example – in “All-
Crash” Mode
31
Crashing Consideration
Questions How fast can
the project be
completed? To crash the
project one day,
what activity
would be crashed
To crash the and what would it
project two days, cost?
what activities
would be crashed
If there is a bonus If there is a bonus
and what would it
of $125 per day of $225 per day
cost in total?
for finishing early, for finishing early,
what would I what would I
crash and how crash and how
fast would I get fast would I get
done? done?
32
Fast tracking
Activities normally performed in series
are performed at the same time
33
Summary
⚫ PM needs to look at the listed activities and
estimate the resources needed to perform each.
⚫ RACI charts depict work activities on a vertical
scale
⚫ Use resource leveling to reduce peak demands by
postponing non-critical activities
⚫ Look for methods of accelerating (or compressing)
the project schedule.
◦ Crashing provides a decision to pay extra
money to speed up certain activities on the
critical path
◦ Fast tracking allows activities that are normally
conducted in sequence to be overlapped, or
performed in parallel
34