Day 1 - 0930 To 1015 NDT High and Low
Day 1 - 0930 To 1015 NDT High and Low
Day 1 - 0930 To 1015 NDT High and Low
of Deep Foundations
High Strain
-&-
Low Strain
Testing
For Foundation to Be Adequate
• Must have adequate soil
support (capacity)
Can be determined by:
• Static Load Tests
• Dynamic Load Tests
• Dynamic Analysis (Wave
equation or Formula)
• Static Analysis (caution:
be very conservative)
For Foundation to Be Adequate
• Must have adequate
structural strength:
• Sufficient cross section
• Sufficient material
strength
• Integrity - Lack of major
defects
• how to assess?
Why Test?
• Duty of Care to the public to build safe
structures.
• An ounce of prevention is worth a pound of
cure. We spend lots of money. Testing is
cheap compared to remediation.
• Uncertainty in foundation
Increases Risk
• Testing answers unknowns
Reduces Risk
Why Test?
Defects aren’t uncommon for pile construction
Why Test?
Prof. Mike O’Neill indicated 20% of shafts
have defects, and “since these flaws
are identifiable by NDE, they are, by
definition, not ‘minor’ ”
Beginning of Impact
(Pile Top)
High Strain Integrity Testing
Impedance Loss
(Pile Toe)
High Strain Integrity Testing
• “Wave Up” reflection is affected by:
• Change in Pile Impedance
• Change in Soil Resistance
High Strain Integrity Testing
• “Wave Up” reflection is affected by:
• Change in Pile Impedance
• Change in Soil Resistance
• Pile Impedance is defined by the
function:
• Z = EA/c
• Sudden changes in impedance
indicate a change in pile cross-
sectional area.
High Strain Integrity Testing
• Expect the pile toe to appear at time
2L/c after impact.
• Twice the distance of the pile,
enough time for the stresswave to
go down and come back.
2L/c
High Strain Integrity Testing
Generally Increasing Wave Up:
No Integrity
Issues
Detected
Limitations / Disadvantages
• Best use: uniform Driven Piles
• Driven pile integrity usually not of concern
• Relatively high cost
Low Strain Integrity Testing
• Pile Integrity Test (time domain)
• Sonic Integrity Test
• Impact Echo
• Pulse Echo
(defect)
Pile Preparation
Remove fractured or
contaminated concrete
Grind a flat spot to
attach accelerometer
PIT – Basic Interpretation
Good Pile
Bad Pile
8#
2#
900 mm dia.
SLT failed at L=25m
less than half 6m rock socket
required
Good pile with local bulge
at about 25 ft and clear toe
Major defect
near top
10 10
15 15
20
20
25
25
30
30
Relative Vol.: 0.96
35 Construct. Vol. 1.00
35 Max Profile: 1.08 at 14.53 ft
40 Min Profile 0.79 at 30.08 ft
40.00 ft (12700 ft/s)
40
x2
45
45
50
50
55
55
60
60
Magn V 0.076 in/s (0.080) ft diam
Low Strain Integrity Testing
Advantages
• Cost Effective
• Apply to any or even all concrete pile/shaft
• Minimal pile preparation
• Finds MAJOR defects
• Sometimes can test piles in structure
Limitations / Disadvantages
• Best use: CFA/ACIP or drilled shafts
• Solid section of concrete needed
• Limited to 30 to 50 L/D
• Difficult interpretation for highly non-uniform
• Cannot locate defect quadrant
Conclusions
• Significant portion of drilled foundations have
defects
• Testing & remediation reduces risk of foundation
failures
• High strain testing evaluates integrity with large
driving hammer or drop hammer. May be used
with any slender foundation (Steel, concrete,
timber, etc).
• Low strain testing evaluates with a hand-held
hammer, only applicable for concrete
foundations.
– Sometimes applicable for foundations in service