TUNAY Manuscript Prefinal
TUNAY Manuscript Prefinal
TUNAY Manuscript Prefinal
2022
TABLE OF CONTENTS
Government is designed with the fully intent on creating orders in manners that will serve
the overall population democratically. Leaders are elected by the general public with the most faith
in to run an effective government, whereas the citizens expects that the government workers will
work as efficiently as possible in order for their tax money put to the best use. Alongside,
government buildings have been playing an important part of the people’s cultural and political
personality.
The design of the government building of a municipality will have varied impact on the
people in the surrounding area. As government buildings are a way to bring them together and
bind them. It is also a way of telling visitors the visual story of what makes the municipality and
the people of it as who they are. It does not necessarily mean that a government facility should be
soulless and built with the only intent of it as being purely functional, civil buildings can also be a
work of art through proper architectural expression, making it not only house a government
institution but also house its people’s dream, hopes, and goals.
When a building is well designed, we say it has character, and this character can be
communicated through various aspects of the design. And successful government buildings that
makes it a good municipality building can be shown through its implied character that deals with
the elements in design of the building that signifies the purpose of it. These elements with their
implied meanings are cultural driven in general and some of these has been in use for a great
amount of time. Another key character would be the functional character as it is more
straightforward that shows how a building is made for a specific purpose and its design that is
will cater to the needs of its users. These public buildings are built to serve its people. Functional
design dictated with a purpose and therefore is a lot easier to understand, and despite its simplicity
it is actually the most crucial part of the character of a building. Government building are not only
supposed to be seen as a solid foundation where the community can rely on, but perhaps it is also
supposed to be seen as an open place where the people can be heard and their needs are met.
What makes a good municipal building is that it is open to anyone, where people can come
from all over the place as it is identifiable, accessible, safe, and can accommodate people of
different backgrounds, goals, and reasons being there. That it has something for everybody,
whether a government transaction, a business transaction, or just simply visiting the municipal
building, as this proposal not only aims to provide a successful government service, but also as a
place that will help enrich the people’s culture and practices. A good municipal building should
also have the capability of catering and maintaining the demand of its municipality.
Whereas it will provide a framework for urbanization that will allow its surrounds for
development, while ensuring that it is still sustainable, as these places are designed for people,
taking into consideration all their human needs. Lastly, a good municipal building is capable of
nurturing a civil society. Great public spaces bring out the best in people, as they tend to act
respectful as it reflects on who they are in the public realm. These are taken care of the people who
use them, meanwhile the governments responsible for overseeing them. The Government center is
the institution or group of institutions that provides direct support to the chief executive in leading
Nabua is the mother town of Iriga City, Buhi, Bato, Balatan, Bula and Baao in
Camarines Sur. Nabua has five districts: Antacudos, Binoyoan, Caobnan, Lupa and Sabang. The
municipality is an established growth center in the southeast part of Camarines Sur Province or
the midsection of Bicol River Basin Area. southeast part of Camarines Sur Province or the
Figure 1: (Gonzalez M. (2005). Map of Camarines Sur showing the location of Nabua. Retrieved January
29 2022, from https://commons.wikimedia.org/wiki/File:Ph_locator_camarines_sur_nabua.png)
The municipality of Nabua is one land mass containing a total land area of 8,854.4193
hectares. This total land area distributed among the 42 barangays, nine of which are considered as
urban barangays. The municipality's total population accounts for 4.3% of the total provincial
population of Camarines Sur. Spread out among the 42 barangays of Nabua, there are 10,093
persons living in the urban barangays while 65,329 persons live in the rural barangays.
Among urban barangays, San Antonio Poblacion has the largest population with 2,363
persons while San Luis has the smallest with 358 persons. The Local Government Unit of Nabua
is located at Barangay San Isidro, Nabua, Camarines Sur. The Poblacion of the municipality of
Nabua is strategic area for commercial development. Presently, its commercial area can be
classified as a minor central business district which is reflective of being a tertiary urban growth
Government facilities provide services and acts as the stronghold of power within
a community, thus municipal buildings are one these several infrastructures that are need
people make transactions, process legal documents, and it’s the place where the community
For an ease of access and easier flow of transactions, these office of municipal
officials and government agencies should be in one area. Therefore, a municipal building
that are intended to cater to the demands of the people through providing services should
in one place that can also accommodate various offices of the municipal officials and
employees.
There are no indications neither the local residents from the municipality knows
when was the building initially built, but it was said that renovations of the existing
building started back in 2006. The local government unit of Nabua serves its people
Office spaces are too small. The existing municipal building of Nabua lacks in the
aspect of spaces, as it can no longer cater to the demands of its citizens. From the
population count of 18, 893 in the year 1903, to 86, 490 in the year 2020, it indeed
shows that the local government are having a difficult time catering to its people,
with such existing building that was meant to cater the count of people back then,
hence why the existing building is all crammed up. The existing government center
No Proper Parking Area. The Parking area of the existing government center lacks
circulation and proper parking spaces whereas even the supposedly access of
pedestrians are being obstructed by cars. And since there are not enough spaces for
the cars, the covered court beside the building are then being used as a parking area.
Insufficient Waiting Areas. Although it has been renovated, it still lacks spaces as
it is highly noticeable that there are no designated waiting areas per offices inside
doors of the offices, leaving the people no choice but to stand while waiting for
their transaction.
Figure 6: Reception area of Nabua Government Center
This area is the immediate area right after the stairs. There is only one source for
natural ventilation and lighting which is that window in the figure shown above.
And for the artificial lighting and ventilation, it is shown there is merely one fan,
that leads to the municipal mayor’s office. It is noticeably narrow for a hallway that
is mainly used by the people using the building. And as seen above, its obstructed
by chairs occupied by people. And although there are seats provided, it is also
shown that there are people left no choice but to sit in the stairs waiting for their
obstructed.
With these problems laid out, an expansion of municipal town hall is necessary.
Some of the offices shall be relocated at the proposed expansion to free up space
The purpose of this proposal is to provide a design solution on the existing building of the
Municipal Hall of Nabua with an extension for the existing building that aims to provide
architecturally and functional design approaches and space organization solution towards the
1. To provide a design solution for the existing and the proposed extension of the
building that would house more offices offering an ease of access to its people.
2. Related spatial programs that are required for designing a Government facility.
1.4.1 Goals
The main goal of the proposal is to provide an extension of the existing building in
the Municipality of Nabua, Camarines Sur through planning and designing in accordance
to the needs of the residents of the municipality of Nabua, Camarines Sur by improving the
quality of service and providing an ease of access to for its residents as well as develop a
venue for increasing quality of life enhancing the knowledge economy of the community
The proposal aims to achieve this through the following key elements:
• To assess the current existing condition of the Local Government Center Nabua,
Camarines Sur through ocular inspection and provide recording for the recreation
of the site plan and current design digitally to provide the improve dwellings and
ensure the safety of its users, and to guarantee that the proposed redevelopment of
the building and its extension would be PWD friendly and accessible for all users
in accordance to BP 344.
• To provide building plans that are in accordance with active design guidelines to
create opportunity for physical activities and exposure that would help the
This study will provide information that are needed to further understand the relationship
of architecture and government facilities through architectural solution on how architecture may
help in identifying the reliable structures and amenities to be used. The study is significant in the
improvement of designing government facilities providing ease of services to its people through
The significance this proposal gives focus on how it will benefit range of individuals,
especially the citizens within the municipality of Nabua, because of its focus on using design to
provide a facility for its citizens to have a comfortable experience. Additionally, the proposal will
The proposal will benefit the residents of Nabua, Camarines Sur since this facility
will offer services within the municipality. An improved Municipal Hall can help their
overall experience regarding their needs that will involve the said proposed facility.
Employees will be the first to experience the benefit of the expansion as it will be
easy for them to serve the people in a comfortable space where they can move without any
obstruction.
issues that brough to light by this proposal. This proposal may also serve as an example for
those who will design a government centered building proposal through the existing
1.6.4 Researchers
This research can serve as a future reference for similar proposal regarding
The proposal will be limited to studying the existing Local Government Center of Nabua,
Camarines Sur. It will describe the current state of the building and provide architectural structural,
plumbing, and electrical plans through architectural space programming and planning. Design for
the proposed building will be provided by the proponent in accordance with the design objectives
and concept.
The proponent shall provide a design solution after collecting information through ocular
observations as well as collecting feedback from the citizens and the employees of the government
center. Data will be done online and interviews will be conducted through online exchanges
because of the still limitations imposed by the IATF and De La Salle University-Dasmariñas. The
expected output of this thesis is architectural, plumbing, structural, and electrical plans of the
proponents’ design for the buildings. The proposed expansion shall be built within the municipality
The conceptual framework of the study is built upon the understanding of the current
context of Government Centers to determines the ideal design for the Local Government Center
of Nabua for its users. The study of Semiology Approach in designing capitol buildings by Nory
Narvaez-Pernes, N. L., and Santos, M. I. P. will be used as the basis for the process of the study.
The architecture of the structure, client security, and local area building are covered in the
conceptual framework. This will help in deciding the significant components to be considered in
the venture proposition. Alongside adhering to building laws and principles, the proponent can
then convert this data into schemes and space programs which will then, at that point, be converted
into plans.
Figure 9: The Semiological approach used in the study synthesizing different approaches from various
sources.
The following terms are characterized as per the proponent’s utilization of it in this proposal:
combination.
• Indoor Ecological Quality. A term used to access to views, comfortable temperatures,
something.
• Sustainable. Refers to the practice that maintains a condition without harming the
In the study conducted by Marc Edelbert Villanueva, Maria Liezel Caroche, Angelo
Ani, and Micah Ramirez of University of Philippines Los Baños, it takces the
satisfaction of employees in the work places that are influenced by many factors such
as the compensation, career growth and development, interaction to peers and office
design. The study determined the impact of office design on the satisfaction of the
This paper aims to review the literature that claims to link the layout of the office
environment to the productivity of its occupants. The office layout discussion will
include the open-plan office vs cellular office debate, and also the matching of the office
connected to consistency. It is clear that while terms such as open-plan and cellular
offices are used frequently, there does not appear to be universally accepted definitions
of these terms. Similarly, the term productivity is used, although the definition and the
Figuera (1993)
The study proposes the Reconstruction of the Cabatuan Municipal Hall as the authors
of the project were mainly concerned about the possibility of the failure of the old
structure and presented an ultimate solution for the problem, The study shows that the
existing building also lacks offices that are causing the inconvenience and delays of
transactions its people. The study found that the proposal would greatly benefit its
A house bill that was introduced by the Honorable Juan Pablo P. Bondoc, fourth
Nograles, representative from the first district of Davao City Philippines. The house
bill states in its explanatory note that this bill requires all the government building be
practices for the purpose of reducing the building impacts on environment and human
health.
The proponent of this proposal has explained the situation of the existing building,
affecting large factor in lack of spaces, consumption, air and atmosphere. Thus, this act
counters the policy on sustainable development and the right of people to have balanced
In the Chapter 9 of the book “Sustainable Philippine Cities 2030”, the building
design and management was discussed. The introduction of the book noted that impacts
of residual use of buildings and how much percent of energy consumption from the
operation of government buildings and how much percent of energy consumption from
the operation of government buildings. It also discussed the need for the sustainable
structure or also known as the green building and how it is already making its way
through government facilities. The green building can be more efficient if there is an
The aim of the chapter is to provide more information to the LGU‟s about
terms of resources throughout its lifetime. A long span plan by the government to lessen
the effects in the future and serves as the implementation to attain the vision of
An article published by Rappler enumerated some of the usual complaints when people
transacting in their respective city or municipal hall. A survey was conducted to 463
people, where 253 were complaints while the rest are up for the good services.
2.2.1 Proposed Expansion and Design of Two Additional Floors for New
This project study proposes for the expansion and additional two floors for the New
Philippines. The proposed expansion, 1184.3 square meters in area including the
laboratories, restrooms, study areas and roof deck. The electrical, plumbing and water
supply layout are also included. The construction of the project will have a duration of
The proposed project was about the replacement of the old Municipal Hall of
Igbaras that will provide a safer structure and a more suitable environment for both
employees and transacting publics. The project has a total area of 1440 square meters
and will house additional offices. The estimated cost for the two storey structure will
be Php 20,302,405.68.
The study was useful and could serve as basis for the design of a municipal hall.
Concepts and computation for its structural design and estimates can serve as a guide
According to the article that was written by Chito Chavez for Manila Bulletin, the
city government of Quezon City opened a One-Stop-Shop (OSS) for building and
The said project was in accordance to Mayor Bautista‟s Executive order 11-2017
mandating the city‟s Architectural Department to provide space for one-stop-shop for the
officials in each department. The project aims to eliminate illegal activities like red tape
This methodology is used for this proposal to gather all the necessary information and data
that are needed in order to fulfill the objectives of the study and meet the criteria of designing a
government facility in order to achieve the desired output for the proposal entitled, TUGDOK: A
The proponent shall conduct online surveys and interviews, research from books that are found
online, as well from articles and papers. The information gathered shall help in the formation of
schemes, and design solutions that will meet the objectives of the study which is to provide a plan
for the expansion of the Municipal Hall that will provide ease of service to the citizens of the
Building Laws such as PD 1096 and BP 344 are consulted as the government
facility standards to create a safe, functional and aesthetically pleasing government facility
proposal.
The structure's specific location through Google Earth shall provide the necessary
information and data that will help in creating the site analysis of the site. The location,
topography, and its immediate surrounding shall be determined for the effective use of light
and passive cooling and shall serve as an access point to and from the building which then
will towards the proper approach to the proposal’s effective design and possible layout.
3.2.3 Review or Related Literatures and Projects
The proponent gathered research papers, case studies, information, and data related
to designing a government facility, and shall use these to help in creating design objectives
and criteria for the proposal for it to be an effective proposal that shall provide an ease of
service towards its users. These works of literature are then studied in order to help in
Local projects are studied in order to know the facilities that should be provided for
this proposal. These will help the proponent come up with schemes that soon shall be
translated into design concept and space programming that are relevant to the proposal and
Once all the necessary information and data are gathered, it will be analyzed in
order to determine what information shall be synthesized into the final output. Concepts
and ideas shall be formed as these are important in coming up with design solutions for the
The proponent shall use the World Wide Web for collecting other relevant
information and data. This is to access public websites such as new articles in order to
access information related to Government Centers which will help the proponent to
Site Inventory – It’s a form of contextual inventory and is the first step in the
design process that leads to a thorough understanding of the project site and context which
Space programming is the proponent's primary task during the schematic design
terms of the sizes of the spaces that are taken into consideration, the location of each room,
the facilities and buildings, the total number of its users as well as the furniture including
It’s a process that shows the initial concepts of the development of the proposed
project in the phase of planning. The proponent shall use this presentation method for the
issues and other factors of the site and analyze how would these factors affect the
surroundings.
A. Conceptual Diagrams
identify, rationalize, and contextualize the key structures of the proposal through
interrelationships.
B. Graphic Method
shall present the formulation of the zoning and the circulation that includes the
circulation diagram allowing the proponent to present the flow of the proposal.
C. Issue-Rejoinder Analysis
The proponent used this table presentation shows the categorized spaces
that are required for the proposed project and deliberates both the issues and the
The proponent shall use this method as a way to integrate the concepts and ideas
that are collected to articulate the building form and function in relation to the aspects of
the proposal. Defining the appropriate and ideal system for the design purpose form the
It is the method where all the gathered data for the proposal such as the building
innovative complex.
3.4 Methods of Data Presentation
formulation and theories of design and is considered as the final result of the study of the
proposal.
Digital architectural drawings that present the shape, function, and circulation
The existing Local Government Unit of Nabua is located within the municipality of Nabua,
Camarines Sur. It is found along the Pan-Philippine Highway. On the site stands the exiting
Camarines Sur. The municipality has a total land area of 8,854.4193 hectares. This
total land area distributed among the 42 barangays, nine of which are considered as
urban barangays. The municipality of Nabua given its land mass is entirely
soil types classified as clay loam or san loam having a silty texture. These soil types
The total land area is divided which are the urban or built-up area, the
agricultural areas, easement, open grasslands, water bodies. Most of these built-up
areas, roads, cemetery and dumpsite. The largest concentration of built-up areas is
found in San Isidro where the site is located and is considered as the Poblacion of
the Municipality.
Poblacion area is considered the Central Business District with the larger
public market, a church, and the seat of local government. This area is a modern
iteration of the Law of indies wherein the seat of local government is surrounded
These map shows the nearest facilities related to safety and security of its users.
Marked with a star pin is the Municipal Hall of Nabua, and the red marks are the
a. Fire Stations – There are 2 Fire stations within the Municipality of Nabua.
The Nabua fire station is located within the 3-kilometer radius of the site.
Nabua. There is one station that is situated within the 3-kilometer radius of
the Site.
c. Barangay Halls – Nearest to the site is the San Luis Barangay Hall.
It’s the Don Henrico Hospital which is located within the 3-kilometer radius
of the Site.
within the 3-kilometer radius of the site within the Municipality of Nabua.
Figure 17 shows the LCC Mall which is located right in front of the existing
site. Figure 18 shows the Public Market located within the 3-kilometer
a. These maps show the access within the municipality and towards its
of Nabua to its closest neighboring city which is the City of Iriga. Figure
20 shows the distance from the Municipality of Nabua to Naga which is the
In the following figures, the existing layout of the Municipal Hall, Covered Court, and
LGU offices are shown. Since the Local Office could not retrieve the plans or any paperwork
regarding the buildings, except for the main building these drawings are derived from the
proponent’s ocular inspection and measurements, as well as images from Google Earth. The plans
Departments with its growing number of employees and additional department. Provision for
appropriate emergency facilities such as fire exits, adjustments of hallway sizes that are in
accordance to RA NO. 9514 to ensure the safety of its users through proper zoning and circulation
red line shows the trunk road or the main access towards the site. The orange line
indicates as a primary road, it is also the access road towards its neighboring city
which is the city of Iriga. The yellow lines are indicated as the secondary road
within the municipality. The beige lines indicate as minor road and access within
the municipality, meanwhile the white lines are primarily used for residential
access.
Sun path is from East to East, according to the wind rose is from Northeast
to Southwest with the stronger winds coming from the northeast portion.
Wind Path
Sun Path
https://www.worldweatheronline.com/nabua-weather-averages/camarines-sur/ph.aspx
Figure 32: Monthly Average Rainfall
https://www.worldweatheronline.com/nabua-weather-averages/camarines-sur/ph.aspx
Traffic Points
▪ Vegetation
All the green patches on the map represents the greenery and vegetation.
SWOT ANALYSIS
STRENGTH WEAKNESSES OPPORTUNITY THREAT
• The site is
situated within • The existing • The current
existing site experiences structure on the
features such as noise pollution site is in dire
parks, church, need of repair
schools, and • There is no and
malls. • The noises
landscape construction,
coming directly
within the allowing for
from the road
• The site offers existing site. new
because the site
scenic view developments
is situated
with Mount and building
along a trunk
Iriga at sight. construction.
road
• The general • The structure
neighborhood can create new
is near a fire and better
station, police facilities.
station and
hospital.
• Residents
communicated
their pride in
locally sourced
food and
agriculture.
Figure 31 shows the buildings nearby and which area the site is located, as well as what
facilities are available within the vicinity. The proposed site is labeled as number 1 and
3 1
4 5
6
4.1.2.8 Table 1: Summary of Site Evaluation
Accessibility
There must be a sure access to • The site of the project
the site and must be clear of is along a trunk road,
obstruction and it must be which gives it a direct
easy to access. access towards the
site.
Neighborhood
Context
The existing buildings of the • The existing building
site is important to record to lacks in the aspect of
ensure a cohesive design having a cohesive
proposal. This also affects the design despite its
light and wind the building renovations.
receives. • The existing building
do not have adequate
lighting, both natural
and artificial.
• The existing building
lacks adequate
ventilation, both
natural and artificial.
Site Capacity The site size and its potential • There is a limited
uses. Since this is an space within the
improvement of an old existing site.
facility,
the site cannot be changed
and
must be maximized.
Natural Features
Views available to the site, its • There is one tree
natural vegetation, its climate within the site.
and how much sun it receives • The site is relatively
is important to consider in its flat.
design. • The site receives
direct sunlight.
Site Security
The safety and security of the • The site has nearby
building is important police outposts.
especially since these house
students at the university.
• Circulation
• Spatial Planning
• Natural Ventilation
• Natural Lighting
• Fire Exit
Currently, users would have to cross the Pan Philippine Highway to access
the site. There are not much green spaces within the area around the existing
building. The lack of seats in the supposedly waiting areas are highly noticeable.
▪ Before Proposal LEGEND
PUBLIC
PRIVATE
OFFICES
UTILITY
PARKING LOBBY
STAIRS OFFICES
LEGEND
PUBLIC
OFFICES
PRIVATE
• Foyer
• Lobby
PUBLIC • Visitors • Offices
• Restroom
• Garden
• Foyer
• Lobby
• Government Officials
• Offices
PRIVATE • Government
• Server Room
Employees
• Restroom
• Garden
• Utility Room
SERVICE • Personnel • Control Room
• Storage Room
4.1.3.4 Behavioral Analysis
• Public – Visitors/Citizens
o Visitors are what makes up the public users for this building.
• Service – Personnel
daily routine.
LEGEND
PUBLIC
OFFICES
PRIVATE
UTILITY CONFERENCE
ROOM
CONTROL
STORAGE
In the new normal setting, one of the new protocols is allowing only a
be a great deal of a wait, and outdoor lounges would be a feasible solution for the
lack of seats in the existing building’s waiting area, and it is in adherence to the
protocol of the new normal setting, not only that but to also utilize outdoor space.
A landscaping plan will assist connect the structure to its surroundings and
will help make the entrance area look more attractive. A barrier to the building face,
that has been made previously. To stay cohesive with the current style, the
proposed building will have the same features such as the arches and its
functions must be carefully taken into account. Routes through the building
never have wide access through the main hall or other public places, and
they should always have direct access from the locations they serve. The
exterior form of the existing building will remain as is, but there would be
Each are considered to create a plan that will maximize functionality that
visitors.
The concept for the floor plan combines an open office plan with a
cellular office plan, whereas the workstations in the open office plan are
different-sized work zones. While the cellular office concept divides the
entire office into separate rooms (or cubicles) set up such that each
requirements of not only the building code but also the health and safety
regulation.
assets.
4.2.1.4 Design Objectives
o To design a structure that meets the needs of the people who will use it
integrated system
performance attributes.
o To design a resilient building that has the ability to survive and maintain
o BP 344
columns were used to support the upper floor of the building. Louvres are added
for the natural lighting and ventilation purposes. Skylight are added in the waiting
areas to allow light through. Arches are also featured in order to adhere to the
serve the public; the idea is to let it be neutral. On its frontage, arches are
The building will have a simple modern design that allows an environment
where the users are not strained by a strict motif or theme. The existing
shape of the building is a rectangle, a shape that maximizes the space in the
site and its functionality. This shape represents stability and solidity. It will
use an open plan to accommodate the future plans of changing the layout
since it is typical for offices to change layout to adhere to the needs of its
users.
4.2.5 Semantics of Form and Material Expressions
• The main materials that will be used in the project proposal will be concrete
as the building’s main shell, and masonry walls as the partitions for the
• The main roofing material that will be used will be G.I sheet as it is the best
choice in terms of durability and weather resistance. This will be used in the
• The proposed ground floor will use ceramic tiles to stay consistent with the
existing main building, as ceramic tiles are in best option to choose in terms
where there would be a lot of foot traffic. Meanwhile the second floor will
use wood flooring such as engineered wood planks and to stay consistent
The spaces are derived from the observation of the existing floor plan of the main
building and its current conditions. Employees and residents who frequent the building were
interviewed (10 Respondents) not only base on their experience in the existing building, but their
Experience in the working environment of the environment, meanwhile some are unsatisfied
Air and Lighting Quality circulation of air and dust. Some responses are
building.
ones.
Unorganized Work Stations The arrangement of the Provision for an organized
• Functional Zoning
• Foyer
• Lobby
PUBLIC • Visitors • Offices
• Restroom
• Garden
• Foyer
• Lobby
• Government Officials
• Offices
PRIVATE • Government
• Server Room
Employees
• Restroom
• Garden
• Utility Room
SERVICE • Personnel • Control Room
• Storage Room
• Matrix Diagram
FOYER PRIMARY
SECONDARY
LOBBY UNDESIRED
OFFICES
RESTROOM
GARDEN
UTILITY ROOM
CONTROL ROOM
STORAGE ROOM
• Interrelationship Program
FOYER
GARDEN
CONFERENCE
ROOM
OFFICE
SUPPLY
TOILET
OFFICES
UTILITY
INFO
WAITING
STORAGE
AREA
CONTROL
LOBBY
EVENT
HALL
FOYER
GARDEN
PARKING
The plan of the buildings in the scheme 1 follows a similar floor plan
as the old one, while integrating features such as fire exits, and
comfort rooms, and waiting areas within the building which the
The plan of buildings in Scheme 2 are larger and is suit for the
open floor plan style. Public comfort rooms placed within the
buildings, waiting areas, and fire escape routes are also placed.
4.4.1 Identification and Analysis of Passive and Active Approaches in Lights and
Ventilation
The structures frontage faces the west and faces the Pan-Philippine
Highway. It is observed from the site analysis that the site experiences heavy
rainfall in the months of January to March and strong winds from the Southwest
(Refer to Figure 27 and 28). Several approaches are considered for the cooling of
the buildings such as use of light-colored paint for its exteriors, window openings
for the cross ventilation. The proposed structures are aimed for natural light and
ventilation.
The aim is to lessen the usage of mechanical cooling through the use of passive
cooling system to facilitate the air circulation within the building. The ventilation
for the offices will be facilitated through louvre windows as well as ceiling fans to
reduce the need of using air-conditioned units. Louvre windows has efficient
keeping the interior cool and comfortable for its users. These types of windows can
be installed at any given height, allowing more air to pass through. These types of
windows are also not easily affected by the direction of wind and can be opened
designed to block the entry of the hot summer sun and restrict the view of the
The best position to provide thermal mass and solar gains are inside the building.
Interior louvres are more accessible that allows mobility, maintenance, and requires
less structures and cost. A louvre as a daylighting system has been proved to
achieve optimal daylight performance, especially under a highly luminous sky with
sun.
daylighting to its occupants of office building and other dee-plan building spaces,
The electrical system will be designed so that each building has its own set
of circuit breakers, making it simple for users to find and use. Circuits will be
assembled based on their intended function (lighting, power, and other electronics
with high voltage usage). The wirings will be of the proper thickness, and the circuit
breakers will be enclosed in the proper materials. It is necessary for the circuit
switch to trip or automatically turn off when there is damage or an overload. The
The plumbing system for office buildings is varies but mainly consists of
lines of lavatories and toilet rooms, both public and private. The continuous vent
principle will be applied to the lines of fixtures in the proposed building to the
benefit of the plumbing system. Each building would house a centralized utility
system to ensure that the potable and non-potable water demands are continually
met which includes domestic plumbing, mechanical, and electrical that will utilize
services in the users of the building, often times with various needs and demands.
Offices have different power requirements depending on size and the way in
which each employee can go about their daily tasks. To ensure the most effective
generally need at least two sockets for the most basic set up of a phone
uninterrupted supply to the building to ensure that there will be no disruption to the
productive operating of the various services operating in the building, avoiding and
delays to their services. Residual current circuit breakers should be specified for
The offices will be provided with their own air-conditioning units and
electric fans to facilitate the mechanical ventilation in each office. Common areas
such as waiting area, information, will be ventilated through fans and natural
ventilation. These areas receive the most foot traffic and passive cooling will be
window is important to have more efficient cross flow ventilation within the
It is common in offices that layouts and partitions often change where the
airflow assumed at system installation may not be as effective for its current
situation. Uneven temperatures and air stagnation can easily occur in variety of
places. A reliable and effective way of changing the air in a building can be
achieved through the use of ventilation equipment together with opening windows
and entrance doors. To create an air passage for efficient ventilation for offices, it
is better to open two windows instead of one, and two diagonal windows to each
https://www.daikinindia.com/ventilation-methods-offices-and-stores
Ventilation openings especially in the walls between offices will also be used, as it
is more efficient to have internal windows than just having external louvre windows
alone. Clerestory louvre windows will be used for this ventilation to allows the hot
For refrigeration, these windows must be able to seal the air in when closed for
when the users of the buildings decided to use the air conditioning unit to lower the
The proposed structure will have two levels, and the proposed conveying
system must be effective and will maximize the space given. The stairs shall follow
the standard set by the national building code and must be safe to use. Specific
efficiency and for the building and safety for those using the space. Installation of
motion sensor lights in the stairways can contribute to reduce the energy costs of
the building as well as the increase of its energy efficiency. To maximize the area,
provided throughout the structure. The routers and wiring should be hidden for
enhance the productivity, and personnel working within the framework of the
The main concerns of the existing building are the lack of fire detection,
alarm, and security. To ensure the safety of its users, CCTV’s will be placed in the
public spaces such as the foyer, lobby, waiting areas and hallways. This is for the
safety and to keep track of the people who goes in the building, considering it’s a
A wet pipe sprinkler system with a pendent sprinkler head will be placed
along with automatic fire alarm system and manual fire alarm will be placed.
Smoke alarms and mounted hazard fire extinguishers will also be places. Visual
cues such as fire exit signs and directional arrows will be placed in the areas where
it is visibly and easily seen. Each office, room, and areas will have a fire exit map
outer shell, which will keep it upright. Additionally, the structure must be supported
The structural system must be cost effective and secure. The structural
structure must be resilient to different vibrations and the passage of time. The
system must be able to support the building through strong winds and rain, as well
as earthquakes that may occur. It must be fire resistant and permit enough floor to
ceiling height without having an excessively tall construction. Since the building
utilizes windows and various wall apertures, structural components like columns
block off these openings. These components are most likely to be centered and
A steel framework would be too costly and impractical for this two-story
be adopted, built with posts and lintels. These posts and lintels create a framework
within which stone walls or infill can be installed. This building's stability is
members include the slab, which supports the vertical loads, the columns, the
beams, and the foundation, which is typically situated below the natural grade line.
and the steel. As it makes the best use of both materials, it provides a dependable
maintenance.
Since reinforced concrete is both robust and fire resistant, it makes for a good
structural system in this building, which emphasizes safety. Concrete hollow blocks
with vertical bars will also be used to construct the exterior and interior walls.
Admin, & Admin. (n.d.). "The bunker": A project to promote ease of doing business in Bataan.
bunker-a-project-to-promote-ease-of-doing-business-in-bataan.
Bataan Government Center and Business Hub. Invest in Bataan. (n.d.). Retrieved December 7,
and-business-hub.
By. (2012, February 12). What everybody ought to know about identifying existing site
http://www.cselandscapearchitect.com/2012/02/06/what-everybody-ought-to-know-about-
identifying-existing-site-conditions/.
Camarines Sur. Orgullo Kan Bikol (OKB). (2012, July 11). Retrieved December 7, 2021, from
https://okbikol.wordpress.com/bicol-region/camarines-sur.
Gashi, Kujtim & Krasniqi, Ibrahim. (2019). The One-Stop Shop Approach: New Public
10.19044/esj.2019.v15n1p185.
brief-history.
Holeywell, R. (n.d.). What makes a great city? great public spaces. and these 6 rules. The
https://kinder.rice.edu/2016/10/03/what-makes-a-great-city-great-public-spaces.
Home. One-Stop Shops for Citizens and Business | OECD iLibrary. (n.d.). Retrieved December
en/index.html?itemId=%2Fcontent%2Fpublication%2Fb0b0924e-en.
Howard, C. (2017, August 3). Putting one-stop-shops into practice: A systematic review of the
from https://www.exeley.com/evidence_base/doi/10.21307/eb-2017-002.
Inquirer, P. D. (2018, July 8). Duterte Oks Palayan City Hub as it Park. INQUIRER.net.
palayan-city-hub-park.
Nicolas and De Vega Law Offices. (2020, August 19). Improving efficiency in the Philippine
government – the anti-red tape law - law firm in Metro Manila, Philippines: Corporate,
family, IP Law, and Litigation Lawyers. Law Firm in Metro Manila, Philippines |
Corporate, Family, IP law, and Litigation Lawyers. Retrieved December 7, 2021, from
https://ndvlaw.com/improving-efficiency-in-the-philippine-government-the-anti-red-tape-
law.
Vashakidze, G. (2016, January 12). One-stop-shop access in the delivery of public services; its
https://www.academia.edu/20184320/One_Stop_Shop_Access_in_the_Delivery_of_Public
_Services_Its_Impact_on_Service_Effectiveness_and_Efficient_Governance.
Villanueva, Marc & Caroche, Maria Liezel & Ani, Angelo & Ramirez, Micah. (2019).
Haynes, Barry. (2008). The impact of office layout on productivity. Journal of Facilities
Uniting the movement. Sport England. (n.d.). Retrieved June 28, 2022, from
https://www.sportengland.org/
Plumbing & mechanical for office, Hospitality & Retail Buildings. Metropolitan Industries |.
mechanical-systems-office-hospitality-retail-buildings/
for Passive Lighting | MIT Technology Licensing Office. (n.d.). Retrieved July 4, 2022, from
https://tlo.mit.edu/technologies/daylighting-energy-efficient-window-louver-system-
passive-lighting
Jerome, N. (1970, January 1). [PDF] application of the maslow ' s hierarchy of need theory ;
impacts and implications on organizational culture , human resource and employee ' s
performance DR .: Semantic scholar. [PDF] Application of the Maslow ' s hierarchy of need
theory ; impacts and implications on organizational culture , human resource and employee
https://www.semanticscholar.org/paper/Application-of-the-Maslow-%E2%80%99-s-
hierarchy-of-need-%3B-%2C-Jerome/b0bcc8ca45193eaf700350a8ac2ddfc09a093be8
Gutiérrez, R. U., Du, J., Ferreira, N., Ferrero, A., & Sharples, S. (2019, January 23). Daylight
Control and performance in office buildings using a novel ceramic Louvre System. Building
https://www.sciencedirect.com/science/article/pii/S0360132319300368
Plumbing & mechanical for office, Hospitality & Retail Buildings. Metropolitan Industries |.
mechanical-systems-office-hospitality-retail-buildings/
Plumbing for office buildings. (n.d.). Retrieved July 1, 2022, from https://chestofbooks.com/home-
improvement/construction/plumbing/Plumbing-Illustrated/Plumbing-For-Office-
Buildings.html