Hand Over Note

The site engineer was handing over responsibilities to the site supervisor. Key tasks included: [1] Demolishing concrete covers to inspect rebar and structures, [2] Coating rebar with epoxy, [3] Pouring new concrete after formwork and mix approval, and [4] Smoothing and plastering concrete surfaces. The site engineer supervised workers and ensured all tasks were completed per specifications.

Uploaded by

Yousab Jacob
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views5 pages

Hand Over Note

The site engineer was handing over responsibilities to the site supervisor. Key tasks included: [1] Demolishing concrete covers to inspect rebar and structures, [2] Coating rebar with epoxy, [3] Pouring new concrete after formwork and mix approval, and [4] Smoothing and plastering concrete surfaces. The site engineer supervised workers and ensured all tasks were completed per specifications.

Uploaded by

Yousab Jacob
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

HAND OVER NOTE

Name Of Out goining person : Mr Achraf Ben Salah Designation: Site Engineer

Name Of Person Taking Over Charge: Mr Abdessalem Abidi Designation: Site Supervisor

GTS 07-18
Item Task Discription of Task
Demolition of concrete cover around pedastles and structures related to valves & founded
damaged until appearence of steels rebars
1 Concrete Demolition

Coating with Sika Dur Epoxy product , rebars of demolished concrete structures

2 Rebars Inspection & repair

4 Pouring concrete Setting up formworks , Adding Sikalatex ,Mix design aproval , Manual concrete pouring ,

5 Concrete smoothing and plastering Concrete surface smoothing and plastering activities

Bituminous coating ( if needed )


6 Painting with bituminous coating if needed

7 Reinstatement Reinstatement & housekeeping of the area


ER NOTE
Station :

neer Date of leaving :

visor Department: Technical Department

Details of Task
The Site engineer identify with the presence of company inspector all damaged structures in Zliten cement station and mentionned
cracks , give instruction to workers and supervise concrete cover demolition activities as per company specifications and Safety rules

After having been appearing steel rebars behind of demolished concrete cover , Company inspector with Contractor site engineer
proceed to the repair using Sika Dur product as approved epoxy , Contractor workers have got instruction from site engineer to finalise
this activity as per company specifications

The site engineer supervise when Formworks are set up in place , take posistion , fixed and prioir to pour concrete , Sikatatex product is
ejected on the surface to be filled with new concrete to ensure the adhesion , The mix design of concrete contain the sika grout product
with very high caracteristic for concrete adhesion and against crush

Formworks is removed and concrete surface is smoothed by contractor workers if any founded holes or non conformity , plastering
works are perfomed to finalise the surface of the structure and protect the concrete cover against humidity

To finalise , structure of valve may be coated with Bituminous product to protect the surface against selt and humidity , In fact it is up to
client inspector if the area air is over detrimental

Contractor workers clean the area and remove all waste maerials / unwanted materials from the site following site engineer instructions
to perform the housekeeping in the work area
Dated Signature of Person Handing Over charge
Dated Signatures of Person Taking Over charge
Dated Signatures of the Supervisors