SAMPLE Project Analysis Introduction

The Parlynet 2002 project to upgrade Victorian Parliament's software was unsuccessful due to poor project management. Key issues included a lack of project integration and planning, an unclear project scope, poor financial management that led to budget overruns, failure to account for an election during the project timeline, inadequate testing resulting in quality problems, insufficient training of staff and users, poor communication, and a lack of risk management strategies. The project was rolled out late and the upgraded software system performed poorly.

Uploaded by

Firehun Alemu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views8 pages

SAMPLE Project Analysis Introduction

The Parlynet 2002 project to upgrade Victorian Parliament's software was unsuccessful due to poor project management. Key issues included a lack of project integration and planning, an unclear project scope, poor financial management that led to budget overruns, failure to account for an election during the project timeline, inadequate testing resulting in quality problems, insufficient training of staff and users, poor communication, and a lack of risk management strategies. The project was rolled out late and the upgraded software system performed poorly.

Uploaded by

Firehun Alemu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Project Analysis Introduction

Parlynet is the information technology software which is used throughout the state and links the
entire major functional elements of the Victorian Parliament. In June 2002 it was decided to
upgrade the software, the project was known as Parlynet 2002 Project. It was rolled out in
November 2002, few months after the implementation, the complaints regarding the speed and
the performance of the Parlynet. Therefore, the audit was done to check the fault in the system.

Identification and Analysis of Issues

The Parlynet 2002 Project was not successful due to the shortfalls in the project management.
Therefore the identifications have been made on the parts of the projects which have either
been neglected or poorly managed. The identified areas are project integration, scope of the
project, cost involved in the project, time, quality of the project, human resource of the project,
communication in the project and also the project’s risk management. Below is the detailed
analysis of the project and also how the situations have been saved.

Analysis of Project Integration

Project integration is the process which involves the coordination with all the knowledge areas.
It is very important to have good project integration in order to have a success in the project
however the project integration was missing in the Parlynet Project. The project was just started
without any planning and project integration is the important part of the planning. The project
integration involves project charter, project management plan, project execution, monitor and
control, perform change control and last close the project. (Tesch, Debbie, Timothy
Kloppenbourg and John Stemmer. 2003) Except project execution, none of the other tasks were
performed. The project charter is important as it involves the project background and
justification of the project. It also outlines the roles and responsibilities of the project manager
and project sponsor, which were missing. The IT manager along with the steering committee
should have planned a project charter before the start of the project as it would have helped
them in gaining the direction of the project and also understanding the outcome of the project.
Analysis of Scope of the Project

Scope of the project is the work involved in creating the products of the project and also the
processes for the same. ( Armstrong, Dan. 2004). In Parlynet Project the scope was not defined
clearly. The project scope includes what all to be involved and what not to be involved however
the Steering Committee did not restricted the scope and had lot of segments involved in the
project because of which the project became very large. The project was started without the
clear understanding of the requirements in the project and also the involvement. A good project
Scope management will involve project charter, requirement documentation and policies and
procedures related to the scope. However, as mentioned earlier, all these points were missing. In
fact the project scope statement was not made at the planning stage. The scope statement
should have been made which would have included realistic scope which would have been
completed successfully or the bigger task should have been broken into smaller projects
(Nicholas, J M. 1989) and involve the users in the project team to help the project team make
realistic and achievable goals. Also the meeting which was just conducted once should have
been done more frequently so that the better understanding the scope statement was made
more specific and clear.

Analysis of Financial management

Appropriate financial management was another concern of the shortfalls happened to the
project. This is due to the negligence from the Steering Committee side, as they did not track
the funds and their proper usages during the project. Though the budget was allocated to the
project yet the project crossed the budget and was short of 1.664 million dollars, which was then
given by the parliament under exceeding pressure. The problem was the weak policies and
procedures made for the parliamentary usage. There was not one person to authorise the deals
and procurement of materials required. Also, the deals were made without referring the funding
budgets. As per the report; deals have been signed and approved by unknown people and also
not from the steering committee. Also the deal was signed with the contractor without going
through the process of tender. This would have been avoided if the clear responsibilities were
allocated to the steering committee, project sponsor and also the project manager (Posner, B . Z.
1987). The detailed financial report should have been made monthly, to check the fund available
and how to manage them. (Burke, R. (1998). All the project deals and requirements should have
gone through the process of tender so that the best available rates have been made to the
project.

Analysis of Time

The completion date for the project was November 2002 however it was completed and rolled
out by the end of January 2003. This happened because of the elections which coincided with
the project in November 2002. The decision to start the project just before the election was the
wrong decision as it created disturbances to the work in the electorate office and also in the
parliamentary departments which adversely affected the delay in implementation of the project.
Since the Steering committee knew the forthcoming elections, they should have waited for the
elections to go over and then would have started with the process of up gradation of Parlynet.
This happened because of the poor project planning by the committee and the sponsor and
also the project manager.

Analysis of the Project Quality

The whole problem in the project has aroused because the project that was completed was not
up to the mark. The users faced troubles because of the speed of the system, reliability on the
system and also the functionality of the system. This was known due to the survey done among
the users of the systems. Other issues with the system were the long log in times, security of the
system and delay in access to the electronic files. The contractor of the project had planned the
testing for Parlynet 2002 project; however the testing was not done due to the pressure to roll
out the project. It is imperative for any project to go through the process of pre roll out testing
so that in case of any performance issues they can be changed or rectified. The failure of testing
the system is the main cause of systems not performing as per the standards. The project team
should have made sure that the testing happens on the system (Gobeli, D., & Larson, E. (1987).
Also the project team should have users of the system, who would have told about the shortfall
of the systems before the roll out of the project.
Analysis of Human resource Management

The poor role of the human resource was sighted in the project. Firstly, the key responsibilities
were not divided among the project team handling the Parlynet 2002 project. They were not
told about the duties and also the team made was not up to the mark. Secondly, there was no
systematic reporting to the hierarchy therefore all followed their own ways. Thirdly, the IT
manager resigned in June and the HR department did not recruit anyone and his absence
project sponsor acted as the IT manager and all the pertinent decisions he took alone. These
decisions should have been taken in the consultation with the new IT manager as he would have
been knowledgeable and experienced in the field. Fourthly, since the IT staffs were not skilled
enough to handle the vast change and the implementation, the department should have hired
the new experienced team before the roll out of the project. The team would have been in the
position to train the users on the new applications. Lastly, the people who were supposed to use
the system were not trained adequately due to which half of the problems raised. It was
informed by the contractor that the new application would require in depth training and also
skilled people to train however this point was not take seriously by the project team. The human
resource department along with the project team should have forecasted the need and
requirement of the skilled staff and also the training.

Analysis of the Communication Process

It is vital for any project to be successful to have a proper communication at all levels. However,
this was quite evident from the study that the communication did not played important role in
the Parlynet 2002 project. The lack of communication between the project team and the
contractor, lack of communication between the users and the project team and also the lack of
communication among the project team itself resulted in the failure of the project. The
contractor was left with all the communication management with the users and the
stakeholders. The passing of duties was not corresponded adequately among the team
members. Team members did not follow the hierarchy. Half of the decisions were taken by the
people who were not from the project team. This all would have been avoided if the proper
written document would have been made about the responsibilities, reporting and
accountability. The communication process should have been channelized (Wateridge, J 1998)
which would have given transparency in the project as well.

Analysis of the Risk and Procurement Management

Another reason for the failure of the project was the lack of risk management strategies. The
project team did not design any strategies for the potential risks and the framework for the
same was missing. The risks that would have been managed were:
 The risk of project delivery not meeting the deadline
 The risk of delay of the roll out of the project
 The risk of not meeting the requirement of the users
 The risk of system not performing
 The risk of exceeding the budget for the project
 The risk due to decentralisation of IT system.

In case the project team had foreseen these risks, the project would have been successful. It is
very important for any project team to do the risk analysis as the success and failure depends on
the same. The project team should have made the management committee for risk analysis, who
would have audited the risks at the time of initiation, execution and the post implementation.
( Baccarini, D 1999). The proper risk management plan should have been made by the team; this
would have helped them to face the problems adequately and efficiently.

Analysis of Five Process Group

The project management is divided into the five processes (Globerson, S & Zwikael, O 2002) :

1. Project initiation Process


2. Project Planning Process
3. Project Execution Process
4. Project Monitoring and Controlling Process
5. Project Closing Process

It is vital for any organisation or for any project to follow them for the success of the project.
However, it was found that the Parlynet 2002 project has not undergone this approach. As
discussed earlier the project planning was missing, apart from this the team did not carried out
the project initiation process also. The team straight started with the execution of the project,
since the first two processes were missing, the execution did not resulted well. This was mainly
due to the lack of knowledge and distribution of responsibilities to the project manager. The PM
was not actively involved in the execution process. Apart from this the monitoring of the project
at different level was not done and neither there was any control on the project in terms of the
finances. The closing process was not carried out, where the testing of the new upgraded system
should have been done and the approval should be taken from the immediate users. (Chuad, K.
B., Tummula, V. M. R., & Nkasu, M. M. (1995). If the project team had focussed on all the
processes, the Parlynet 2002 project would have been a success story.

Recommendations and Justifications

Parlynet 2002 Project is the project management failure as the team did not followed the
process cycle, which in turn brought lot of difficulties as well as the issues. It left the users
frustrated as they were unable to use the system efficiently. The recommendations are made
keeping in mind the finances of the project, human resource and the operations of the project.
Following are the recommendations along with the justification that I have listed for getting the
project on track:

Once the implementation of the project is done, I will make sure that the users are well trained
on the system and also on the new applications. It is important for them to undergo the training
as it will hone the skills to operate the system more efficiently. Also, they will know how to
operate the system and open the electronic files efficiently. Training will help the users to clear
the doubts as well in case they have any.

I will assign responsibilities to people in order to resolve the system problems adequately and
efficiently. Since the same was not done before, due to which all the problems have arouse. It is
important to delegate the work and have people accountable for the work as then only work is
efficiently done. Once the people are responsible and accountable for the work then only they
perform the task efficiently.

I will develop the training needs that are required by the IT staff so that they are well aware
upon the usage of the new upgraded system and can also help the users in learning the new
system and can also be helpful in the performance issues of the system. It is important to train
the staff adequately so that they can manage to check for the problem.

I will also recruit new IT staff that would have experience in handling the similar kind of systems
and applications as they would be able to resolve the problem quickly and will also be the
extended help to the IT department.

The parliament should clearly describe the roles and responsibilities at all levels so that decision
making can be done more efficiently at all levels. It is vital to follow the hierarchy in terms of
roles and responsibilities.

The risk should be identified in the project so that they are effectively managed when required.
It is very important to identify the risks so that the teams are prepared for the consequences
before they happen.

I will recommend that the Steering committee along with the project sponsor and the project
manager should have meetings at regular intervals to check the performance and the execution
of the project and also make minutes of the meeting and also note the approvals made.

The financial report should be made and review should be done at the regular intervals and also
all the procurements should be made by the tender process. This way the cost incurred can be
controlled.

All the financial decisions should be made and approved by the people responsible and
accountable for the same. This ways, the unknown people’s involvement can be mitigated.

The project team should develop a plan regarding the IT requirements and prioritize and time
lines in order to solve the problems. At this moment solving the system issue are the most
important part therefore the adequate plan should be made on solving the issues an d also the
priority and deadlines should be set.

I will make the Joint service department and the IT unit work together in order to set priorities
for solving the problems so that the maximum problems are solved within time limit.

I will develop an action plan, where I will keep the users informed about the actions been taken
to upgrade the programme and also keep them updated about the actions been taken on
solving the system’s problem. It is important to keep the users informed so that they are aware
about the time it is going to take to solve the problem as they need the computers and laptops
for their day to day work.

I will engage the experienced and skilled personnel to et up the software in order to solve the
problems, follow the timelines by monitoring them and also monitor the work flow of the
project.

I will also do the analysis of Parlynet for the network volume and the operating environment in
order to check for the reasons for the bad performance of the software and also how to improve
the same.

In order to make sure that such problems do not occur again, I will ask the parliament to review
their IT strategies so that in case required changes can be made in the same. Also, will make
sure that the policies and procedures are developed in order to guide the IT department.

I will also establish the benchmark for the system’s performance assessment. This would make
the process easy for the information technology department. The benchmark will include the
system’s performance and its availability, the networks performance, the ability of the help desk
to resolve the issue and also issues related to the security of the system.

Conclusion
The Parlynet 2002 Project was the failure due to the poor project management. If the project
management would have been done, the Parlynet was the success. Many aspects of financial
management, human resource management and risk management was also not followed
however the analysis and the recommendations along with the justification have been
mentioned in the project which would be helpful in resolving the issues and will also act as the
guidelines for the next project.

References
Armstrong, Dan. 2004. “Six Degrees of Project Management.” Baseline.
Baccarini, D 1999, 'The Logical Framework Method for Defining Project Success', Project
Management Journal, vol. 30, no. 4, pp. 25-32.
Burke, R. (1998). Project Management Planning and Control. New Jersey: Wiley Meredith, J., &
Mantel, S. (2002). Project Management a Managerial Approach. New York: John Wiley & Sons.
Chuad, K. B., Tummula, V. M. R., & Nkasu, M. M. (1995). Project management structures in Hong
Kong industries. International Journal of Project Management 13(4), 253-257.
Gobeli, D., & Larson, E. (1987).Relative effectiveness of different project structures. Project
Management Journal 18(2), 81-85.
Globerson, S & Zwikael, O 2002, 'The Impact of the Project Manager on Project Management
Planning Processes', Project Management Journal, vol. 33, no. 3, pp. 58-64.
Nicholas, J M. 1989. 'Successful project management: a force-field analysis‘ J System
Management 24-30
Posner, B Z. 1987 'What it takes to be a good project manager' Project Management Journal 28
(1) 51-54
Tesch, Debbie, Timothy Kloppenbourg and John Stemmer. 2003. “Project Management Learning:
What Literature Has to Say.” Project Management Journal.
Wateridge, J 1998, 'How can IS/IT projects be measured for success', International Journal of
Project Management, vol. 16, no. 1, pp. 59-63