ANCM Assignment 1
ANCM Assignment 1
Asymt 83
PROBLEMs
3.5 (A) A mass-production plant has eight machines and currently operates two 8-hr shifts per
day, 5 days per week, 50 wecks per year. The cight machines produce the same part each
at a rate of 15 pc/hr. (a) Determine the annual production capacity of this plant. (b) If the
plant were to operate three 8-hr shifts per day, 7 days per week, 52 weeks per year, deter-
mine the annual percentage increase in plant capacity.
3.6 Two million units of a certain product are to be manufactured annually on dedicated pr0-
duction machines that run 8 hr per day, 5 days per week, 50 weeks per year. (a) If the cycle
time of a machine to produce one part is 1.5 min, how many of the dedicated machines will
be
required keep
to up with demand? Assume that availability and utilization are
and that setup time can be neglected. (b) Solve part (a) except that availability = 90%.
100%
3.7 A job shop has four machines and operates 32 hr/wk. During the most recent week, ma-
chine 1 processed part A for 16 hr at a production rate of 10 pc/hr, and part B for 16 hr at a
rate of 7 pc/hr. Machine 2
processed part C for 29 hr at a rate of 14 pc/hr, and was idle 3 hr.
Machine 3 processed part D for 15 hr at a rate of 20
15 pc/hr. Machine 4
pc/hr, and part E for 17 hr at a rate of
processed part F for 15 hr at a rate of 9 pc/hr, part G for 12 hr at a rate
of 18 pc/hr, and was idle the rest of the week.
Determine (a) weekly production output of
the shop and (b)
average utilization of equipment.
3.8 A batch production plant works 40 hr/wk and has
three machines. In a
batches of parts are processed typical week, five
through these machines. Production rates (pc/hr), batch
times, and operation sequences for the parts are
(a) Determine the weekly production rate for the
given in the table below for one week.
rate equal to the
shop. (b) s this weekly production
plant capacity? If not, determine what the output would be if all three
machines could be operated up to 40
hr/wk, given the constraint that no reductions in
weekly production rates are allowed for any part. Use of a
ommended for this problem. spreadsheet calculator is rec
PeLLOTm only machine setups. These setup workers are busy the full shift. The section runs
one d-hr shift per day, 5 days per week. Scrap losses are negligible and availability= 100%.
h e production
control manager claims that the capacity of the section should be 2,00
parts per week. However, the actual output averages only 1,600 units per week. What is the
problem? Recommend a solution.
utilization of
order. Determine (a) weekly production rate, (b) workload, and (c) average
nis set ot equipment. A spreadsheet calculator is recommended for this problem.
Machine3 Machine4
Machine1 Machine 2
3 Rpd fa
Part Rp1 Rp2 Rp3
30 0.15 7.5 0.6
A 15 0.3 22.5 0.2
B 12.5 0.4 8 0.625
10 0.5
20 0.3
C 30 0.2 15 0.4
batch
parts processed through
a
3.14 The table below shows production data for five batches of
production plant. Setup times (Tsu) are given in hours. Operation cycle times ( 7 ) are given
week
fractions of time during the 40-hr
in min per cycle. Utilization fractions () are the
The parts do not proceed
that the machine is devoted to the production of these parts.
rate, (b) work-
through the machines in the same order. Determine (a) weekly productioncalculator is rec-
A spreadsheet
load, and (c) average utilization of this set of equipment.
ommended for this problem
Machine 2 Machine 3
Machine 1
f Te f
Part T f Tsu To su
su
2.25 2.01 0.140 5.00 1.56 0.190
A 2.50 1.50 0.125
0.200 1.25 2.39 0.230
B 3.00 78 0.140 2.90 1.53
0.345 2.30 .50 0.170
C 1.50 1.50 0.150 1.80 4.00
1.75 5.10 0.150 1.60 2.88 0.100
D 4.00 7.20 0.250
0.120 2.55 1.80 0.120
E 2.00 3.20 0.150 2.55 1.80
3.17 A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high
A typical part is processed sequentially through 12 machines in batch sizes of 1.
complexity.
he shop contains a total of ten conventional machine tools and operates 40 hr/wk of pro-
auction time. Average time values on each part per machine are: machining time = 0.6 hr,
work handling time = 0.4 hr, tool change time = 0.3 hr, setup time = 4 hr, and nonop
eration time = 10 hr. A new programmable machine is being considered that can pertorm
all 10 operations in a single setup. The programming of the machine for this part will require
1 hr, however, the programming can be done off-line, without tying up the machine. Setup
time will be just 3 hr because simpler fixtures will be used. Total machining
time will be
reduced to 75% of its previous value due to advanced tool control algorithms; work han-
will be reduced
ding time will be the same as for one machine; and total tool change time
control. For the one
by 30% because tools will be changed automatically under program
each conventional machine.
machine, nonoperation time is expected to be 10 hr, same as for
conventional machines and for thee
new
(a) Determine the manufacturing lead time for the
the following alternatives: (1)a
programmable machine. (b) Compute the plant capacity for
containing two of the
job shop containing the ten traditional machines, and (i) job shop
a
are represented by
the data given
new programmable machines. Assume the typical jobs
alternatives in part
above. (c) Determine the average level of work-in-process
for the two
(b), if the alternative shops operate at full capacity.
consists of three opera-
3.18 A factory produces cardboard boxes. The production sequence
are three machines in
the factory,
tions: (1) cutting, (2) indenting, and (3) printing. There
when op-
one for each operation. The machines are
100% reliable and operate as follows
rolls of cardboard are fed into the cutting
erating at 100% utilization: (1) In cutting, large material for 4,000 blanks.
machine and cut into blanks. Each large roll contains enough
but it takes 35 min to
Production cycle time =
0.03 min per blank during a production run,
indentation lines are pressed into the blanks
change rolls between runs. (2) In indenting,
to allow the blanks to later be bent into boxes. The blanks from the previous cutting op-
eration are divided and consolidated into batches whose starting quantity
2,000 blanks.
=
blanks per min. Between batches, changeover of the printing plates is required, which
takes 20 min. In-process inventory is allowed to build up between machines 1 and 2, and
between machines 2 and 3, so that the machines can operate independently as much as pos-
sible. Determine the maximum possible output of this factory during a 40-hr week, in com-
pleted blanks per week (completed blanks have been cut, indented, and printed)? Assume
steady-state operation, not startup.
Manufacturing Costs
319 (A) The break-even point is to be determined for two production methods, one manual and
the other automated. The manual method requires two workers at $16.50/hr each.
Together,
their production rate is 30 units per hour. The automated method has an initial cost of
$125,000, a 4-year service life, no salvage value, and annual maintenance costs= $3,000.
No labor (except for maintenance) is
required for the machine, but the power to operate
it is 50 kW (when running). Cost of electric
power is $0.05 per kWh. The production rate
for the automated machine is 5 units hour.
per (a) Determine the break-even point for
the two methods, using a rate of return =
25%. (5) How many hours of
would be required for each method to reach the operation per year
break-even point?
Economics
Metrics and
Chap. 3 / Manufacturing
tain
3.20 Theoretically, any given production plant has an optimum output levl nally related
production plant has annual fixed costs = $2,000,000. Variable cost is [unco O
50.
t
be described by the function Cy=
T dI
TO annual output Q in a manner that can
Total annual cost is given by TC = C+ C.0. The unit sales price for oneprou
where UC7
minimizes unit cost UC,
dLS0. (a) Determine the value of O that (b) Determine
carned by the plant at this quantity.
nd compute the annual profit earned by the plant;
and compute the
annua
e that maximizes the annual profit
Ot
duc
profit earned by the plant at this quantity.
company for
the most yeal recent
return =
15%; salvage 8-hr shifts, 250 days per
40%. The work center
will be operated two workload
on the machine (b) If the
=
in machine $250,000,
=
cell will
the 30%. The work =
starting
presents time and cost data for
the six operations: 7su setuptime, 7, =
part han-
dling time, 7, = operation processing time, 7, = tool handling time where applicable,
T = nonoperation time, C, = operating cost ot the work center, and C, = tool costs