Job Safety Analisys: Project Name Job Activity

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

JSA Security Level: CONFIDENTIAL

JOB SAFETY ANALISYS QHSE

Project Name : Site location :


Date: 17 June 2013

Job activity : Customer : Rev: 00

TASK HAZARD RISK WHO IS EXPOSED? RISK ASSESS ADDITIONAL CONTROLS RISK ASSESS
HE P RV Risk Level Action required HE P RV Risk Level Action required
~ Make sure the area is barricaded
and nobody is working beneath.
~ Appropriate PPE must be warn
such as hard hat, gloves, safety
boots and safety harness.
falling objects, lifting fatality / Injury / Property EXTREMELY ~ If ladder is in use should not be
Antenna Installation Employees / Public 4 4 16 detailed SOP required 2 4 8 HIGH RISK Control Plan Required
objects, dropping objects Damage HIGH RISK damaged and no self built.
~ No alone working.
~ No night time working.

~ Exclusion zone to be confirmed


by VF,
~ All amployees should be trained
MODERATE
RF Exposure Non-ionising radiation injury employees/public 2 2 4 Controlplan required about RF hazards, 1 2 2 LOW RISK Review at next opportunity
RISK
~ RF signage will be in place,
~ Process for planned outage to
be agreed with VF where work is
~ All power tools should be in
good condition.
~ Grinding and cutting machines
should have guard.
~ Flammable materials should be
segregated and stored at safe
distance.
~ Appropriate PPE should be used
MODERATE such as glasses, welding masks,
Using power tools Electrocution fatality, Fire, Injury Employees 2 3 6 Control Plan Required 1 3 3 LOW RISK Review at next opportunity
RISK safety shoes, hard hats and
gloves.
~ Employees should be competent
to use power tools.
~ Damage tools not to be used.
Visual inspection should be done
prior to each use.
~ Power tools should be secured if
in use at height.
~ Pre-task assessment ( load
baring, capability, surface
conditions, pipes, vents, edge
protection) should be done.
~ Make sure there is anchorage
points on the roof if there is no
edge protection in place.
EXTREMELY Immediate Action Required Before ~ Safety harness should be used MODERATE
Roof top working Falling , dropping objects fatality, Injury Employees / Public 4 4 16 2 4 8 Control Plan Required
HIGH RISK Proceeding wherever necessary. RISK
~ No alone working. Make sure
sufficient lighting provided.
~ No night time working on top of
the roofs.
~ All employees should have
working at height training
certificate.

3/21/2019 - Telecom Installation HUAWEI Confidential Page1of2


JSA Security Level: CONFIDENTIAL

TASK HAZARD RISK WHO IS EXPOSED? RISK ASSESS ADDITIONAL CONTROLS RISK ASSESS
HE P RV Risk Level Action required HE P RV Risk Level Action required
~ Approprate PPE such as gloves,
glasses, hard harts and safety
MODERATE
Cabling tripping, falling injury employees 2 3 6 Control Plan Required boots should be used, 1 3 3 LOW RISK Review at next opportunity
RISK
~ All cable restraints fixings to be
free of sharp edges.
~ Approprate PPE such as gloves,
glasses, hard harts and safety
boots should be used.
~ Provide sufficient lighting during
poor visibility,
~ Cranes and trucks should have
reversing alarms,
Cranes tipping, loads ~ Operators should have valid
Lifting equipment to roof Fatality, Injury, property EXTREMELY Control Plan / Further Risk Reduction MEDERATE
falling, struck by moving Employees / Public 4 3 12 certificate, 2 3 6 Control Plan Required
top damage HIGH RISK Mesures Required if practicable RISK
parts, ~ All cranes should have periodical
inspection records,
~ Slings and other lifting devices
should be in good condition and
SWL should be indicated.
~ All lifting operations should be
done by competent people,
~ Determine the possible reaction
areas for complaints before move.
~ Clear and early communication
with landlords, tenants, closed
neighbours to notify nature of
MODERATE
Execution public reaction injury Employees / Public 2 4 8 HIGH RISK Control Plan Required work. 1 4 4 Review at next opportunity
RISK
~ Considering the people in terms
of noise, waste, sensitivitıes and
visibility of themselves.

3/21/2019 - Telecom Installation HUAWEI Confidential Page2of2