Standard Daily Report Form

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 27
At a glance
Powered by AI
The documents describe daily reports from a civil construction and architectural project. They provide details on manpower, equipment, work progress and documentation with photos.

The documents describe a civil construction and architectural project for assembling work and excavation of Package 3 at a new plant site.

The main activities described include excavation work, manpower details listing positions and names, equipment used, work quantities, and documentation with photos of progress.

CONSTRUCTION DAILY REPORT

Client RPE Date 9/16/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation
1 Weather Status
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Weather 0 0 0 0 0 0 0 0 0
Legend 0 Bright = Cloudy II Drizzle Rain
2 Manpower
Working Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total Time 9 Hours

Item Pekerjaan Material Bahan


Qty (nos) Qty (nos)
No Item Pekerjaan No Material Bahan
Volume Satuan Volume Satuan
1 Perkuatan bekisting 4.28 m2 1 Balok 6x12cm 21.52 m
2 Pemasangan excavolding 7 Set 2
untuk persiapan bobok 3
3 Leveling kepala pancang 88 Titik 4
4 Leveling basement 88 Titik 5
5 Pemasangan septitank 2 unit 6
6 Urugan Septitank 2 m3 7
8
9
10
11

Direct-Manpower Indirect-Manpower
Qty (nos) Qty (nos)
No Position No Position
Yesterday Today Yesterday Today
1 Helper 17 1 Project Manager 1
2 Ass Surveyor 4 2 Site Manager 1
3 Mandor 1 3 Supervisor 2
4 QC 1
5 Safety 1
6 Logistic 1
7 Tim Suvey 2
8 Admin 1
9 SE 1
10 QS 1
11 Drafter 1

Total Manpower 22 Total Manpower 13


3 Tools and Equipment
Qty (nos) Working Time
No Description Type / Model
Yesterday Today Start Stop Duration
1 Excavator PC 200 8 08.00 17.00 8
2 Waterpass 2 8 08.00 17.00 8
4 Work Quantity 5 Note
Unit
Qty ( Nos )
Today
Target Done Remain Yesterday
Plan Actual
8 8 8 8

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT MANPOWER

Client RPE Date 9/16/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

Direct-Manpower Indirect-Manpower
No Position Name No Position Name
1 Tukang Pendi 1 Project Manager Suprapto
2 Tukang Akmal 2 Site Manager Bambang S
3 Tukang Paryono 3 Supervisor Derry & Noor
4 Tukang Sukirno 4 QC
5 Tukang Wakmad 5 Safety Agus
6 Tukang Jamari 6 Logistic Nanang & Decen
7 Tukang Jayuri 7 Tim Suvey Dedi & Erwin
8 Tukang Tamtomo 8 Admin Aziz
9 Tukang Mahmud 9 SE E van Christian
10 Tukang Sholikin 10 QS Ismail
11 Tukang Nur Rahmad 11 Drafter Tomy
12 Tukang Siswanto
13 Tukang s. Budi Utomo
14 Tukang Shofiyan
15 Tukang Suhartono
16 Tukang Tormondi
17 Tukang Jumadi Total Manpower 11
18 Mandor Ramfin
19 Ass Surveyor Jidan
20 Ass Surveyor Aceng
21 Ass Surveyor Cecep
22 Ass Surveyor Rudi

Total Manpower 22

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/16/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/16/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/16/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
Project NEW PLANT DELTAMAS - CIKAR Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
Project Coal Handling Plan Project Drawing
Area New Coal Yard Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT
Client RPE Date 9/17/2022
Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project Drawing
CIKARANG
Area PAKET 3 ASSEMBLING Work Description Excavation
1 Weather Status
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Weather 0 0 0 0 0 0 0 0
Legend 0 Bright = Cloudy II Drizzle Rain
2 Manpower
Working Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total Time 8 Hours

Item Pekerjaan Material Bahan


Qty (nos) Qty (nos)
No Item Pekerjaan No Material Bahan
Volume Satuan Volume Satuan
1 Urugan Septitank 1 m3 1
2 Pemasangan excavolding 7 Set 2
untuk persiapan bobok 3
3 Leveling kepala pancang 88 Titik 4
4 Leveling basement 88 Titik 5
5 Persipan lahan untuk 1 ls 6
pondasi genset 7
6 Bobokan Tiang Pancang 15 Titik 8
9
10
11

Direct-Manpower Indirect-Manpower
Qty (nos) Qty (nos)
No Position No Position
Yesterday Today Yesterday Today
1 Helper 17 1 Project Manager 1
2 Ass Surveyor 4 2 Site Manager 1
3 Mandor 1 3 Supervisor 2
4 QC 1
5 Safety 1
6 Logistic 1
7 Tim Suvey 2
8 Admin 1
9 SE 1
10 QS 1
11 Drafter 1

Total Manpower 22 Total Manpower 13


3 Tools and Equipment
Qty (nos) Working Time
No Description Type / Model
Yesterday Today Start Stop Duration
1 Waterpass 2 8 08.00 17.00 8
2
4 Work Quantity 5 Note
Unit
Qty ( Nos )
Today
Target Done Remain Yesterday
Plan Actual
8 8 8 8

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT MANPOWER

Client RPE Date 9/17/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project Drawing
CIKARANG
Area PAKET 3 ASSEMBLING Work Description Excavation

Direct-Manpower Indirect-Manpower
No Position Name No Position Name
1 Tukang Pendi 1 Project Manager Suprapto
2 Tukang Akmal 2 Site Manager Bambang S
3 Tukang Paryono 3 Supervisor Derry & Noor
4 Tukang Sukirno 4 QC
5 Tukang Wakmad 5 Safety Agus
6 Tukang Jamari 6 Logistic Nanang & Decen
7 Tukang Jayuri 7 Tim Suvey Dedi & Erwin
8 Tukang Tamtomo 8 Admin Aziz
9 Tukang Mahmud 9 SE E van Christian
10 Tukang Sholikin 10 QS Ismail
11 Tukang Nur Rahmad 11 Drafter Tomy
12 Tukang Siswanto
13 Tukang s. Budi Utomo
14 Tukang Shofiyan
15 Tukang Suhartono
16 Tukang Tormondi
17 Tukang Jumadi Total Manpower 11
18 Mandor Ramfin
19 Ass Surveyor Jidan
20 Ass Surveyor Aceng
21 Ass Surveyor Cecep
22 Ass Surveyor Rudi

Total Manpower 22

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/17/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/17/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/17/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
Project NEW PLANT DELTAMAS - CIKAR Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT
Client RPE Date 9/18/2022
Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project Drawing
CIKARANG
Area PAKET 3 ASSEMBLING Work Description Excavation
1 Weather Status
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Weather 0 0 0 0 0 0 0 0
Legend 0 Bright = Cloudy II Drizzle Rain
2 Manpower
Working Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total Time 8 Hours

Item Pekerjaan Material Bahan


Qty (nos) Qty (nos)
No Item Pekerjaan No Material Bahan
Volume Satuan Volume Satuan
1 Pengambilan data 336 Titik 1
kemiringan pancang 2
3
4
5
6
7
8
9
10
11

Direct-Manpower Indirect-Manpower
Qty (nos) Qty (nos)
No Position No Position
Yesterday Today Yesterday Today
1 Ass Surveyor 4 1 Project Manager 1
2 2 Site Manager 1
3 3 Supervisor 2
4 QC 1
5 Safety 1
6 Logistic 1
7 Tim Suvey 2
8 Admin 1
9 SE 1
10 QS 1
11 Drafter 1

Total Manpower 4 Total Manpower 13


3 Tools and Equipment
Qty (nos) Working Time
No Description Type / Model
Yesterday Today Start Stop Duration
1 Total Station 8 08.00 17.00 8
2
4 Work Quantity 5 Note
Unit
Qty ( Nos )
Today
Target Done Remain Yesterday
Plan Actual
8 8 8 8

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT MANPOWER

Client RPE Date 9/18/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project Drawing
CIKARANG
Area PAKET 3 ASSEMBLING Work Description Excavation

Direct-Manpower Indirect-Manpower
No Position Name No Position Name
1 Ass Surveyor Jidan 1 Project Manager Suprapto
2 Ass Surveyor Aceng 2 Site Manager Bambang S
3 Ass Surveyor Cecep 3 Supervisor Derry & Noor
4 Ass Surveyor Rudi 4 QC
5 5 Safety Agus
6 6 Logistic Nanang & Decen
7 7 Tim Suvey Dedi & Erwin
8 8 Admin Aziz
9 9 SE E van Christian
10 10 QS Ismail
11 11 Drafter Tomy
12
13
14
15
16
17 Total Manpower 11
18
19
20
21
22

Total Manpower 22

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/18/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/18/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT
Client RPE Date 9/19/2022
Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation
1 Weather Status
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Weather 0 0 0 0 0 0 0 0 0
Legend 0 Bright = Cloudy II Drizzle Rain
2 Manpower
Working Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Total Time 9 Hours

Item Pekerjaan Material Bahan


Qty (nos) Qty (nos)
No Item Pekerjaan No Material Bahan
Volume Satuan Volume Satuan
1 Urugan Septitank 0.5 m3 1
2 Pemasangan excavolding 4 set 2
untuk persiapan bobok 3
3 Leveling kepala pancang 80 Titik 4
4 Leveling basement 80 Titik 5
5 Trial Mix Dynamix Plan 1 ls 6
7
8
9
10
11

Direct-Manpower Indirect-Manpower
Qty (nos) Qty (nos)
No Position No Position
Yesterday Today Yesterday Today
1 Helper 17 1 Project Manager 1
2 Ass Surveyor 4 2 Site Manager 1
3 Mandor 1 3 Supervisor 2
4 QC 1
5 Safety 1
6 Logistic 1
7 Tim Suvey 2
8 Admin 1
9 SE 1
10 QS 1
11 Drafter 1

Total Manpower 22 Total Manpower 13


3 Tools and Equipment
Qty (nos) Working Time
No Description Type / Model
Yesterday Today Start Stop Duration
1 Waterpass 2 8 08.00 17.00 9
4 Work Quantity 5 Note
Unit
Qty ( Nos )
Today
Target Done Remain Yesterday
Plan Actual
9 9 9 9

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT MANPOWER

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing
Area PAKET 3 ASSEMBLING Work Description Excavation

Direct-Manpower Indirect-Manpower
No Position Name No Position Name
1 Tukang Pendi 1 Project Manager Suprapto
2 Tukang Akmal 2 Site Manager Bambang S
3 Tukang Paryono 3 Supervisor Derry & Noor
4 Tukang Sukirno 4 QC
5 Tukang Wakmad 5 Safety Agus
6 Tukang Jamari 6 Logistic Nanang & Decen
7 Tukang Jayuri 7 Tim Suvey Dedi & Erwin
8 Tukang Tamtomo 8 Admin Aziz
9 Tukang Mahmud 9 SE E van Christian
10 Tukang Sholikin 10 QS Ismail
11 Tukang Nur Rahmad 11 Drafter Tomy
12 Tukang Siswanto
13 Tukang s. Budi Utomo
14 Tukang Shofiyan
15 Tukang Suhartono
16 Tukang Tormondi
17 Tukang Jumadi Total Manpower 11
18 Mandor Ramfin
19 Ass Surveyor Jidan
20 Ass Surveyor Aceng
21 Ass Surveyor Cecep
22 Ass Surveyor Rudi

Total Manpower 22

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing

Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing

Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing

Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing

Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION

Client RPE Date 9/19/2022


Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
NEW PLANT DELTAMAS -
Project CIKARANG Drawing

Area PAKET 3 ASSEMBLING Work Description Excavation

PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager
CONSTRUCTION DAILY REPORT DOCUMENTATION
Client RPE Date
Discipline & Job Des Civil Const. & Architectural Contractor PT. Total Solusi Konstruksi
Project Coal Handling Plan Project Drawing
Area New Coal Yard Work Description Excavation
PICTURE

Prepared Checked Approved

( ) ( ) ( )
Supervisor Site Engineer / Site Manager Project Manager