Part II B BMP MOP Combined 6-24-19
Part II B BMP MOP Combined 6-24-19
Part II B BMP MOP Combined 6-24-19
Additionally, the design examples apply the BMP design methodologies found in
the Virginia Stormwater Management Handbook, 2nd Edition, Draft (DCR/DEQ,
2013) to the site conditions and constraints typically encountered in linear
development projects.
1.0 in.
=
12
(1.1)
= × %!" + $
×% "+ %
× %&" (1.2)
where:
%
= Percent of site in Impervious cover (fraction)
%&
= Percent of site in Turf cover (fraction)
= Percent of site in Forested cover (fraction)
Equation 1.2 and Table 1.1 are used to calculate for the post-
development condition.
For new projects, water quality and quantity standards shall conform to Part II B
(9VAC25-870-62) of the Virginia Stormwater Management Regulations.
This design manual applies to projects that must conform to Part II B technical
criteria.
A separate design manual is provided for projects that must conform to Part II C
technical criteria.
Filter strips are used to treat runoff from areas that generate and deliver sheet
flow from adjacent impervious and managed turf areas by slowing the velocity of
runoff, which allows sediment and pollutants to be filtered by vegetation and/or
settled out of stormwater runoff. Two variations of sheet flow practices as
outlined by Virginia DCR/DEQ Stormwater Design Specification No. 2, (2013) are
Conserved Open Space and Vegetated Filter Strips. Although Conserved Open
Space is allowed in principal, it is unlikely that the right of way associated with a
VDOT project will contain the required minimum conservation space to ensure
long term viability of the practice; therefore information regarding use of
conserved open space is not included in this document.
Due to the requirement of a uniform linear edge to maintain runoff as sheet flow,
these practices are applicable to a wide array of road construction projects.
When sheet flow is proposed to either conserved open space or managed turf,
the designer must consider a number of site constraints to ensure that the
practice is applicable to the suggested use.
2.2.7 Utilities
Vegetated filter strips may be constructed over existing and proposed utilities.
Generally utilities that cross (perpendicular) a vegetated filter strip are preferred.
Long longitudinal runs of utilities (parallel to road) through a grass filter strip
should be discussed with VDOT prior to incorporating on plans due to long term
issues with maintenance on utilities affecting operation and maintenance of the
vegetated filter.
Construction Stage
Prevent soil compaction by heavy equipment
Typical Applications
Treat small areas of Impervious Cover
Compost
Optional (A soils)
Amendments
Yes (B, C, and D soils) 2
Boundary Spreader GD 3 at top of filter
PB 3 at toe of filter
1
A minimum of 1% is recommended to ensure positive drainage.
2
The plan approving authority may waive the requirement for compost amended soils for filter strips
on B soils under certain conditions
3
ELS = Engineered Level Spreader; GD = Gravel Diaphragm; PB = Permeable Berm.
2.3.2 Slopes
The allowed range for slopes through a filter is typically 1.0%-8.0% slope, in
order to maintain sheet flow throughout. In addition, upstream slopes should be
relatively flat to maintain sheet flow conditions as runoff enters the filter. If
restriction of upstream slopes is not possible, a level spreader meeting the
requirements shown in VDOT BMP Standard Detail SWM-2—Sheet Flow to
Vegetated Filter Strip may be used.
Compost shall be in accordance with the requirements set forth in VDOT Special
Provision for Soil Compost Amendments.
This section presents the design process applicable to vegetated filters serving
as water quality BMPs. The pre and post-development runoff characteristics are
intended to replicate stormwater management needs routinely encountered on
VDOT projects. The hydrologic calculations and assumptions presented in this
section serve only as input data for the detailed BMP design steps. Full
hydrologic discussion is beyond the scope of this report, and the user is referred
to Chapter 11 of the Virginia Stormwater Management Handbook, 2nd Edition,
Draft (DCR/DEQ, 2013) for details on hydrologic methodology.
Typically, vegetated filters are designed as the first step in a treatment train
approach to meeting water quality control requirements. However, due to the
applicability for treating sheet flow, there will be applications, such as shoulder
widening, that may exclusively use vegetated filters to potentially meet full
stormwater quality control requirements. In order to meet the vegetated filter
strip requirements, sufficient right-of-way must be present to meet the minimum
lengths required (see Table 2.2).
A shoulder widening project is planned along I-66 near Front Royal, Virginia.
The longitudinal slope along this section of I-66 is approximately 1.0%. The
project consists of adding a 6’ paved shoulder along the interior side (into
median) of the east bound lanes. In addition, a 50’ wide portion of the median will
be regraded for drainage improvements. The presence of HSG D soils along this
1,000’ section of the project will require compost amendments to supplement the
existing soil. The disturbed area of the project and the additional impervious
area added is minimal. Since the vegetated filter strip can also treat existing
runoff up to the road crown, it is particularly well suited for this application.
Due to a wide existing compacted gravel shoulder along the edge of the existing
pavement, the proposed widening will only add an additional 0.03 acres of
impervious area. Although the disturbed area (including median work) is 1.29
acres, the treatment area extends to the crown of the road, containing an
additional 0.29 acres of impervious cover (HSG D), and sums to 1.58 acres total
area. In the post-development condition, the time of concentration has been
calculated to be 9 minutes. Geotechnical investigations reveal compacted soil
with a high clay content. Lab tests confirm that infiltration cannot be performed at
this location. The project site does not exhibit a high or seasonally high
groundwater table.
The required site data from Table 2.3 is input into the VRRM Spreadsheet for
Redevelopment (2014) to compute load reductions for a linear project, resulting
in site data summary information shown in Table 2.4. Note that using the
redevelopment spreadsheet, the required reduction for linear projects is
computed as the sum of the Post-Redevelopment Load and the Post-
Development Load minus 80% of the Predevelopment Listed load.
It is important to note that the values in Table 2.4 are only the values for the
disturbed area of the project. Although other run-on areas (0.29 acres total) were
described in the problem statement, they are not part of the disturbed area, and
should not be entered as such in the VRRM Spreadsheet to compute required
reductions (Table 2.4).
The vegetated filter will be used to treat runoff from the disturbed area and the
run-on area (0.29 acres). Note that the VRRM Spreadsheet will warn the user
that the area (1.58 acres) exceeds the disturbed area (1.29 acres); however, it is
acceptable to treat adjacent run-on area as part of the project. Appropriate data
for post-development conditions is input into the VRRM Spreadsheet Drainage
Area tab, yielding compliance results summarized in Table 2.5.
Table 2.5 Summary of Output from VRRM Site Data Tab for Full Treatment Area
Total Impervious Cover Treated (acres) 0.32
Total Turf Area Treated (acres) 1.26
Total TP Load Reduction Achieved in D.A. A (lb/yr) 0.71
In this case, the total phosphorus reduction required is 0.20 lbs/yr. The
estimated removal is 0.71 lbs/yr; therefore, the target has been met.
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
Values for the 1-, 2-, and 10-year 24- hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 38.942421, Long -78.138086), those values are shown in Table
2.6.
Curve numbers used for computations should be those calculated as part of the
runoff reduction spreadsheet (Virginia Runoff Reduction Spreadsheet for
Redevelopment, 2013). For this site, computed adjusted curve numbers are 81,
81 and 82 for the 1-, 2- and 10-year storms, respectively (Table 2.7).
Table 2.7 Adjusted CN from Runoff Reduction Channel and Flood Protection Sheet
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.12 1.53 2.79
RVDeveloped (in) with Runoff Reduction 0.93 1.34 2.59
Adjusted CN 81 81 82
The values reported in Table 2.7 are only valid for the drainage area served
by the proposed vegetated filter drainage subarea. The remaining portion of
the site drainage area should use the appropriate curve numbers for those areas.
Because the travel lane and proposed paved shoulder has a 2.08% cross slope
and the filter will extend at a 4.0% grade cross-slope from the edge of shoulder,
the required filter length (in the direction of flow) from Table 2.2 is 35’. The
designer should also confirm that the upstream length restrictions are not
Because the underlying soil type is HSG D soils, the area where the filter will be
implemented must be amended. Amendments will be according to specifications
shown in the VDOT Special Provision for Soil Compost Amendments, 2013.
Based on the requirements in that document, amendments for this project will
require incorporating 10” of compost to a minimum incorporated depth of 11.6”
(see detailed calculations in Section 4.4) using a tiller. Specific compost
requirements and incorporation requirements are discussed in that document.
Step 5 - Seeding
The grass chosen should be able to withstand both wet and dry periods. The
user is directed to the Virginia Erosion and Sediment Control Handbook (1992)
permanent seeding chapter for guidance. The selected seed mix combination
should provide low maintenance, tolerance of moisture conditions, and be
tolerant to high salt concentrations during the winter months.
Grass channels are preferable to curb and gutter or storm drains due to their
ability to treat the runoff, unlike the impervious alternatives. The Virginia
Stormwater Design Specification No. 3, Grass Channels, Draft (DCR/DEQ, 2013)
describes grass channels as particularly well suited to linear applications, such
as transportation related projects.
When a grass channel is proposed, the designer must consider a number of site
constraints to ensure that the practice is applicable to the suggested use.
3.2.8 Floodplains
Grass channels may be installed in 100 year floodplains if there is no negative
impact to flood elevation as mandated by state and federal guidelines.
1.49
' = () - 1
./0 2/.
3
, (3.1)
where:
Note that for very shallow flows the hydraulic radius (R) may be approximated by
the flow depth, D, in ft.
Channels shall be designed to convey runoff without eroding the channel for the
2 and 10-year flows. The 10-year peak flows shall be conveyed within the
channel with a minimum of 4” of freeboard.
For linear highway projects, the grass channel shall be evaluated at every
significant change in channel cross-section or slope to verify channel adequacy
for both non-erosive conveyance and verification of adequate freeboard.
The residence time for the treatment volume (1” rainfall) shall be a minimum of 9
minutes (Virginia Stormwater Design Specification No. 3, Grass Channels, Draft
(DCR/DEQ,2013)). When multiple inflow points exist, a 9 minute residence time
must be demonstrated for each point through evaluation of Equations 3.1 and
3.2 (Equations 3-1 and 3-2, Virginia Stormwater Design Specification No. 3,
Grass Channels, Draft (DCR/DEQ, 2013))
where:
4 $5 is
design treatment volume (1”) peak flow rate (cfs)
Note that the substitution of cross sectional area in Equation 3.2 with the product
of channel width and flow depth is only valid as an approximation for shallow
flows.
Combination and manipulation of Equations 3.1 and 3.2 yields solutions for
minimum channel widths and velocities as found in Equations 3.3 and 3.4.
'=4 $5 / W x D (3.4)
The velocity calculated by Equation 3.4 should be less than 1 fps. Equation
parameters, n, W, and S may be adjusted, as necessary, for site conditions to
decrease velocity, and thus, increase residence time. The minimum length of
where:
3.3.2 Geometry
Grass channels shall be either trapezoidal or parabolic in cross-section in order
to facilitate mowing and maintenance. Side slopes should be kept to a maximum
slope of 3:1 to facilitate mowing. Typically, the bottom width is between 4’ to 8’ in
width. Wider cross-sections require use of measures (typically check dams) that
prevent erosion along the channel bottom.
Check dams should be spaced (Table 3.3) to allow a minimum of 25’-40’ length
between the toe of the upstream check dam and the face of a downstream check
dam. Water impoundment on the downstream check dam shall not extend
upstream to a point where impounded stormwater touches the toe of the
upstream dam.
• Check Dam Forebay: These cells (Figures 3.1 and 3.2) act as forebays
to allow sediment to settle out of stormwater runoff prior to entering the
grass channel. In addition, it is used as an energy dissipater to reduce the
velocity of incoming stormwater runoff and prevent erosive damage within
the main channel.
• Grass Filter Strips: Runoff entering a grass channel as sheet flow may
be treated by a grass filter strip. The purpose of the grass buffer
strip/energy dissipation area is to reduce the erosive capabilities of runoff
prior to its entrance into the main channel. The recommended minimum
length of the grass filter strip should not be less than 10’ when using the
maximum side slope of 5:1. An alternative design may be used that
integrates road shoulders, requiring a 5’ minimum grass filter strip at 20:1
(5%), that is combined with 3:1 (or flatter) side slopes of the swale to
provide pre-treatment. See VDOT BMP Standard SWM-PT: Pre-
treatment (Pretreatment Forebay).
This section presents the design process applicable to grass channels serving as
water quality BMPs. The pre- and post-development runoff characteristics are
intended to replicate stormwater management needs routinely encountered on
VDOT projects. The hydrologic calculations and assumptions presented in this
section serve only as input data for the detailed BMP design steps. Full
hydrologic discussion is beyond the scope of this report, and the user is referred
to Chapter 11 of the Virginia Stormwater Management Handbook, 2nd Ed., Draft
(DCR/DEQ, 2013) for details on hydrologic methodology.
The proposed widening will add an additional 0.10 acres of impervious area (0.45
acres, total land disturbance), and reduce the turf area post-development to 0.65
Geotechnical investigations reveal a sandy loam soil that is well drained. Lab
tests confirm that infiltration is possible at this location with Ksat ranging between
0.57 and 1.98 in/hr. The project site does not exhibit a high or seasonally high
groundwater table.
Initially, the designer should use the Virginia Runoff Reduction Method (VRRM)
spreadsheet (Virginia Runoff Reduction Spreadsheet for Redevelopment, 2014)
to calculate removal for a linear project and ensure that the required water quality
load reduction is met by using the proposed grass channel for treatment. Note
that using the redevelopment spreadsheet, the required reduction for linear
projects is computed as the sum of the Post-Redevelopment Load and the Post-
Development Load minus 80% of the Predevelopment Listed load. In this case,
the total phosphorus reduction required is 0.39 lbs/yr (Table 3.6). The estimated
removal is 0.41 lbs/yr; therefore, the target has been met (Table 3.7).
Table 3.6 Site Data Summary Table from VRRM showing Required Phosphorus
Removal
Site Rv 0.51
Post-development Treatment Volume (ft3) 2,024
Post-development TP Load (lb/yr) 1.27
Total TP Load Reduction Required (lb/yr) 0.39
Table 3.7 Drainage Area Summary Table from VRRM showing Achieved
Phosphorus Removal by Grass Channel A/B soils
Total Impervious Cover Treated (acres) 0.45
Total Turf Area Treated (acres) 0.65
Total TP Load Reduction Achieved in D.A. A (lb/yr) 0.41
Values for the 1, 2, and 10-year 24-hour rainfall depth should be determined from
the National Oceanographic and Atmospheric Administration (NOAA) Atlas 14
and entered into the channel and flood protection tab of the VRRM spreadsheet.
For this site (Lat 38.37167, Long -77.49431), those values are shown in Table
3.8. Curve numbers used for computations are the adjusted curve number
calculated as part of the runoff reduction spreadsheet. For this drainage area,
results from the channel protection tab of the runoff reduction spreadsheet are
shown in Table 3.9, and result in adjusted curve numbers of 74, 74 and 75 for
Input data (rainfall depths from Table 3.8, drainage area, time of concentration,
and CN from Table 3.9) is used in the Natural Resource Conservation Service
Technical Release 55 (NRCS TR-55) Tabular method to calculate discharge
hydrographs. Peaks of those hydrographs for the 1, 2, and 10-year storms are
reported in Table 3.10. These values will be used to evaluate residence time,
adequacy, and size the conveyance downstream of the grass channel.
The length of the project along Route 652 is approximately 1,200’. Since the
proposed channel cross-section and longitudinal slope is consistent along the
1000
@=
A10 + 5B + 10CD − 10 CD. + 1.25CD B F.9 G (3.6)
where:
÷ IJKL,KMN KJNK
P = Rainfall (inches), (1.0” in Virginia)
Qa = Runoff volume (watershed inches), equal to
1000
@=
X10 + 5 1 L, + 10 0.51 L, − 10 0.51 L, + 1.25 0.51 L, 1 L, " Y
F.9
.
@ = 94
4 $ = 4Z CD (3.7)
All of the variables are known in the above equation with the exception of 4Z . To
determine its value, first the initial abstraction must be computed using the
equation:
200
!D = −2
@
(3.8)
200
!D = − 2 = 0.13 L,RℎN\
94
Read the unit peak discharge, 4Z , from Exhibit 4-II of the SCS TR-55 Handbook
(1986). Reading the chart yields a value of 925 cfs/mi2/in.
cfs
925 h l 12L,
4 =] mi2 b c 1.1 KR eg
2,024 ft3
) -
k
$
in 640 KRV dL . g 43,560 PQV
k 1 PQ
1.1 KR × S 1 KRW
f j
4 $ = 0.81 RP\
0.81 RP\ PQ
'= = 0.36
6.9 PQ × 0.33 PQ \
This velocity is less than the maximum velocity of 1 fps required and therefore is
an acceptable design.
PQ
> = 540' = 540 \NR )0.36 - = 194 PQ
\
The total length of the swale will be a minimum of 1,194’, which includes the
length adjacent to the project (1,000’) and the length downstream of the last
inflow location (corresponding to the termination of the project). If an existing
receiving channel exists downstream that approximates or exceeds the proposed
channel cross-section, then the downstream 194’ of channel will not be required.
The peak 10-year flow at the most downstream location is 4.79 cfs, as shown in
Table 3.9. To facilitate maintenance (mowing), the side slopes of the channel
will be 3:1. Ditch computations to verify adequacy for conveyance of the 10-year
storm shall meet guidelines shown in the VDOT Drainage Manual, latest edition.
Step 3 - Seeding
The grass chosen should be able to withstand both wet and dry periods. The
combination should provide low maintenance, tolerance of moisture conditions,
and be tolerant of high salt concentrations during the winter months. For
compliance with methods specified in the VDOT Special Provision for Grass
Channels (2014) temporary E&S controls are required during construction of the
grass channel area to divert stormwater away from the grass channel area until it
is completed and permanently stabilized. These may include diversions,
temporary stormwater conveyance, or other standard methods for temporary
diversion of runoff around disturbed areas. Special protection measures such as
erosion control fabrics may be needed to protect vulnerable side slopes from
erosion during the construction process.
Soil compost amendments are used to improve the retention and infiltration
characteristics of post-construction or in situ soils through deep tilling and
composting. This allows heavily compacted post-construction fill or existing
hydrologic soil classification (HSG) B, C, or D soils to be remediated in order to
be suitable for receiving runoff from rooftop disconnections, grass channels and
vegetated filter strips. Requirements shown herein are modifications to
specifications found in Virginia Stormwater Design Specification No. 4, Soil
Compost Amendment, Draft, (DCR/DEQ 2013) for specific application to VDOT
projects.
Compost amendments are suitable for compacted soils that been placed during
construction, and in situ soils belonging the HSG C or D. Constraints on use of
amendments are further defined in following sections.
4.2.4 Utilities
Amendment areas may be placed above existing or proposed utilities. A
minimum of 1.5’ clearance to top of utility line should be provided. However, keep
in mind that if the utility needs to do its own maintenance at some point in time,
the excavation may disrupt the benefit of the compost amendments, especially if
the excavated amended soil is not use as backfill or if the surface is
subsequently compacted. Therefore, it is probably wise to avoid amending soils
above utility lines if at all possible.
Table 4.2 Runoff Coefficients for Use for Different Pervious Areas
Virginia Stormwater Design Specification No. 4, Soil Compost Amendment, Draft, (DCR/DEQ
2013)
Hydrologic Soil Undisturbed Disturbed Restored and
Group 1 2 3
Soils Soils Reforested
A 0.02 0.15 0.02
B 0.03 0.20 0.03
C 0.04 0.22 0.04
D 0.05 0.25 0.05
Notes:
1
Portions of a new development site, outside the limits of disturbance, which are
not graded and do not receive construction traffic.
2
Previously developed sites, and any site area inside the limits of disturbance as
shown on the E&S Control plan.
3
Areas with restored soils that are also reforested to achieve a minimum 75% forest
canopy
= × 8 × 0.0031 (4.1)
where:
The design example found in Section 2.4 (Sheet Flow to Vegetated Filter Strips)
requires that HSG soils are compost-amended for compliance. Based on
information given in Section 2.4, the total impervious area draining to the bed is
0.32 acres, made up of a widened lane, and the existing pavement section to the
crown. The area of the bed itself is a minimum of 35’ wide by 1,000’ in length,
encompassing an area of 0.80 acres. Therefore, the IC/SA ratio used in Table
4.3 is computed as:
Using Table 4.3, the IC/SA ratio can be compared to given table values and
linearly interpolated to determine the incorporation depth. Table 4.3 indicates
that for an IC/SA of 0, the incorporation depth for HSG D soils is 10”, while an
IC/SA of 0.50 yields an incorporation depth of 12”. Interpolation allows
computation of actual required incorporation depth:
12 L, − 10 L,
× 0.4 + 10 L, = nn. o pqrstu
0.50 − 0.0
Once the depth of the amendment has been computed, the estimated volume of
compost in cubic yards is computed using Equation 4.1 as:
v
= 1,000 PQ × 35 PQ × 11.6 L,RℎN\ × 0.0031 = n, xyz {|
PQ . ∙ L,
Therefore, 1,259 cubic yards of compost will be required to be tilled into the
amendment area to an average depth of 11.6”.
Permeable pavements are surfaces that allow for rapid filtration of rainfall
through voids in pavement surfaces to a subsurface stone storage layer for
discharge or infiltration. The result is a decrease in the effective impervious area
of the site. The reservoir layer is designed to provide adequate structural support
as well as sufficient storage for the design treatment volume. Permeable
pavement should be designed to treat runoff that falls directly on the pavement
and adjacent impermeable surfaces; however, treatment of adjacent pervious
areas should be limited to the extent possible. Requirements shown herein are
modifications to specifications found in Virginia Stormwater Design Specification
No. 7, Permeable Pavement (DCR/DEQ, 2013), for specific application to VDOT
projects. Note that although limited Level 2 criteria is shown in this
specification for consistency with DEQ specifications, currently VDOT does
not allow the use of Level 2 designs for permeable pavement.
Permeable pavement applications used for VDOT projects are limited in nature
due to restrictions in recommended use for high speed and high volume traffic
areas in extreme weather conditions. Permeable pavements typically are used
only for parking applications. Prior to use of permeable pavement in a road
application, VDOT shall be consulted to confirm acceptance of use.
5.2.6 Setbacks
Although setbacks to structures are not applicable on many VDOT installations,
projects at district or area headquarters, rest areas or park-and-ride facilities may
propose permeable pavement in the vicinity of existing or proposed structures.
Setbacks are dependent upon the surface area of the permeable installation.
Requirements are as follows:
• 250-1,000 ft2 : 5’ down-gradient, 25’ up-gradient
• 1,000-10,000 ft2: 10’ down gradient, 50’ up-gradient
• >10,000 ft : 2
25’ down gradient, 100’ up-gradient
In cases where setbacks listed above cannot be met, those setbacks can be
reduced if an impermeable liner is used to encase the installation, and with
express permission from VDOT.
Due to the potential for contamination, a minimum setback of 100’ from all water
supply wells shall be enforced. In areas having a higher risk for ground water
contamination, ground water mapping should be used to determine
interconnectivity of groundwater systems to wells on surrounding properties.
However, considering that maintenance of the utility lines will require excavation
through the permeable pavement, and that it is unlikely that the utility contractor
will backfill properly and replace the permeable pavement (due to the limited size
of the backfill area, it is highly recommended that areas over utility lines be
avoided for permeable pavement installations. Alternatively, VDOT should
carefully monitor utility repairs under permeable pavement installations for
appropriate quality control in replacing the pavement materials.
Typical structural designs for surface layers will include Porous Asphalt Mix
(PAM) 9.5 and 19.0 components in thicknesses as specified through the design
guidance set forth in the VDOT Special Provision for Permeable Pavement
(2014). For parking applications, typical surface application will be 1.5” PAM-9.5
with underlying 3” PAM-19.0.
B× × + B× ~
I =
}
•€ ×
(5.1)
~
I
where:
}
B
= Depth of stone reservoir layer (feet)
= Rainfall depth (feet); Level 1 = 0.08’
= Contributing drainage area (ft2)
= Composite runoff coefficient for contributing area
~
•€
= Area of permeable pavement (ft2)
= Porosity of stone layer (0.4)
The permeability of the pavement surface and that of the gravel media is very
high. However, the permeable pavement reservoir layer will drain increasingly
slower as the storage volume decreases (i.e., the hydraulic head decreases). To
account for this change, a conservative stage discharge should be established
for routing the stone reservoir. The underdrains can serve as a hydraulic control
for limiting flows, or an external control structure can be used at the outlet of the
system.
5.3.3 Pretreatment
Pretreatment is typically not required for permeable pavement systems.
However, pretreatment may be required if the pavement receives runoff from
adjacent pervious areas. For example, a gravel filter strip can be placed along
the receiving edge of the permeable pavement section to trap sediment particles
before they reach the permeable pavement surface.
5.3.5 Underdrain
Underdrains shall be installed in an underdrain trench, with typical dimensions of
12” by 12” (see detail on VDOT SWM-5, Permeable Pavement (2014)). The
underdrain shall be 6” Schedule 40 PVC, with a minimum slope of 0.5%.
Installation details are found in VDOT SWM-5, Permeable Pavement (2014), and
specifications regarding installation are found in the VDOT Special Provision for
Permeable Pavement (2014).
• Protecting the Bottom of the Reservoir Layer. There are two options to
protect the bottom of the reservoir layer from intrusion by underlying soils.
The first method involves covering the bottom with a barrier of choker
stone and sand. In this case, underlying native soils should be separated
from the reservoir base/subgrade layer by a thin 2” to 4” layer of clean,
washed, choker stone (ASTM D 448 No. 8 stone) covered by a layer of 6”
to 8” of course sand.
The second method is to place a layer of filter fabric on the native soils at
the bottom of the reservoir. Some practitioners recommend avoiding the
use of filter fabric, since it may become a future plane of clogging within
the system; however, designers should evaluate the paving application
and refer to AASHTO M288-06 for an appropriate fabric specification.
AASHTO M288-06 covers six geotextile applications: Subsurface
Drainage, Separation, Stabilization, Permanent Erosion Control, Sediment
Control and Paving Fabrics. However, AASHTO M288-06 is not a design
guideline. It is the engineer's responsibility to choose a geotextile for the
application that takes into consideration site-specific soil and water
conditions. Fabrics for use under permeable pavement should, at a
minimum, meet criterion for Survivability Classes (1) and (2). Permeable
filter fabric is still recommended to protect the excavated sides of the
reservoir layer, in order to prevent soil piping.
The required site data from Table 5.3 is input into the VRRM Spreadsheet for
Redevelopment (2014), resulting in site data summary information shown in
Table 5.4.
Based on site data described above, the total phosphorus reduction required for
the entire site is 1.08 lbs/yr (Table 5.4). The estimated removal in the
bioretention component (not shown) is 0.91 lbs/yr. In order to provide the
remaining treatment, a Level 1 permeable pavement system is proposed. The
0.20 acres of impervious area for the Level 1 permeable pavement area is
entered into the Runoff Reduction Spreadsheet Drainage Area tab. The
estimated phosphorus removal reported by the spreadsheet for the permeable
pavement treatment area is 0.25 lbs/year (Table 5.5).
Table 5.5 Summary of Output from VRRM Summary Tab for Permeable Pavement
Treatment Area
Total Impervious Cover Treated (acres) 0.20
Total Turf Area Treated (acres) 0.00
Total TP Load Reduction Achieved in D.A.A (lb/yr) 0.25
Thus, combined with the phosphorus removal from the bioretention component
(0.91 lbs/year), the permeable pavement system will be sufficient to meet water
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
VDOT Drainage Manual for appropriate levels of protection and design
requirements related to erosion and flood protection. However, hydrologic
computations are necessary to compute overflow conveyance structures.
Values for the 1-, 2-, and 10-year 24-hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 36.6289, Long -80.9873), those values are shown in Table 5.6.
Curve numbers used for computations should be those calculated as part of the
runoff reduction spreadsheet (Virginia Runoff Reduction Spreadsheet for
Redevelopment, 2014). For runoff draining to the permeable pavement, results
from the runoff reduction spreadsheet are shown in Table 5.7, and result in
adjusted curve numbers of 94, 94 and 94 for the 1, 2 and 10-year storms,
respectively. Note that although areas draining to the bioretention facility would
also result in volume reduction and adjusted curve numbers, that the bioretention
portion should be entered as a separate drainage area in the RRM spreadsheet
in order to properly segregate the design parameters in order to design the
storage system and overflow for the permeable pavement system.
Table 5.7 Adjusted CN from Runoff Reduction Channel and Flood Protection
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 2.26 2.78 4.15
RVDeveloped (in) with Runoff Reduction 1.83 2.35 3.73
Adjusted CN 94 94 94
Based on the input parameters, a Level 1 design, and using Equation 5.1, the
required depth of the reservoir layer is calculated as:
The depth of the system’s underdrain trench should be installed along the end of
the storage reservoir, parallel to the gutter pan (see Figure 5.1). Dimensions of
stone trench shall be 12” x 12” x 144’ (width of 16 parking spaces). As specified
in section 5.3.5, the pipe shall be perforated and constructed using 6” schedule
40 PVC at the minimum slope of 0.5%. Perforated underdrain stubouts shall
extend out into the permeable pavement section a distance of 10’ perpendicular
to the underdrain main line (see detail, Figure 5.1). Spacing between stubouts
shall be maintained at 20’ on center. Computations should be completed to
verify that the underdrain system draws down the reservoir within a 48-hour
period.
The overflow structure for this application will be a single DI-3A sump inlet at the
lower end of the parking lot. Capacity for this overflow structure should be
verified for the 10-year storm to determine adequacy. As seen in Table 5.8, the
overflow peak for the 10-year storm is 1.17 cfs.
The interception capacity of the DI-3A curb inlet operating as a weir can be
calculated using Equation 9.10 of the VDOT Drainage Manual as shown below:
where:
6
= Length of curb opening, ft
I
= Width of local depression, ft
= Depth of water at curb from a point where the normal
pavement cross slope would intercept the curb face, ft
The depth of allowable ponding = 8(0.0208) = 0.17’, which extends 8’ into the
adjacent parking space.
Using a factor of safety of 2, the depth of ponding is less than 1” below the top of
curb, or (2x(0.17’) < 0.42’).
If d/h<1.2, where h is the opening of the curb inlet then the inlet is in weir control.
With the factor of safety, the depth, d, is 0.34’ (4”) as shown above. From
specifications, the opening of the curb inlet is 5”. Therefore, d/h=4/5=0.80.
Since 0.8 < 1.2 then operation under weir control is confirmed.
Equation 9.10 from the VDOT Drainage Manual, and the length of the opening of
a DI-3A of 2.5’ is used to compute the flow capacity of a DI-3A:
Because the theoretical capacity is greater than the design flow, 2.78 cfs > 1.17
cfs, then a DI-3A may be used as the overflow. Otherwise, the design would
need to be upsized to use a DI-3C sump curb inlet. The proposed outlet pipe
from the DI-3A manhole is a 12” RCP pipe at 1.0% slope. Using Manning’s
equation, the pipe full capacity of a 12” reinforced concrete pipe at 1% slope is
3.57 cfs; therefore, the system will be adequate to convey the 10-year overflow.
The structural design of the surface and intermediate pavement sections are not
shown. Based on geotechnical analysis, CBR testing, and the expected
pavement loading, these two components have been determined to be 1.5” of
PAM 9.5 and 3.0” of PAM 19.0. As computed above, the reservoir layer (stone
bedding) will be just over 10”, at 0.84’. See VDOT Special Provision for
Permeable Pavement, 2014 for additional specification and design elements
related to permeable pavement systems.
Due to the nature of the practice, infiltration facilities are applicable to a wide
variety of projects, including linear highway projects. Infiltration practices are
typically subdivided into three categories: micro-infiltration (250 to 2,500 ft2),
small-scale infiltration (2,500 to 20,000 ft2), and conventional infiltration (20,000
to 100,000 ft2). Specific criteria generally associated with each category are
found in Table 6.2. A typical configuration and various cross-sections typically
associated with infiltration facilities are found in Figures 6.1 to 6.4.
6.2.6 Soils
Soils in the infiltration area are required to have infiltration tests in accordance
with the VDOT Special Provision for Stormwater Miscellaneous (2014), and
performed using the ASTM D 2434 Tube Permeameter Method. A field-tested
infiltration rate of 0.5 in/hr or greater is required for use of infiltration practices on
VDOT projects.
6.2.7 Setbacks
In order to prevent damage by seepage, infiltration practices should not be
hydraulically tied into base stone in pavement cross section or connected to
structure foundations. Setbacks from adjacent roads and structures are found in
Table 6.2 for each scale of infiltration practice. Setbacks from wells shall be a
minimum of 100’, and setbacks from septic drainfields shall be a minimum of 50’.
Infiltration practices shall be installed a minimum of 5’ down gradient of utility
lines. When located near down-gradient slopes of 20% or greater, infiltration
practices shall be located a minimum distance of 200’ from those slopes.
Infiltration practices must be set back at least 25’ from roadways to prevent
potential frost heaving of the road pavement.
6.3.1 Sizing
The measured infiltration rate on site shall be in accordance with Virginia
Stormwater Design Specification No. 8, Infiltration Practices, Draft (DCR/DEQ,
2013), and VDOT Special Provision for Infiltration Practices (2014).
Actual dimensions are determined from Equations 8.1 to 8.4 of the Virginia
Stormwater Design Specification No. 8, Infiltration Practices, Draft (DCR/DEQ,
2013). For convenience, those equations are reproduced below.
where:
P
)2- Q„
I =
Dƒ
η × 12
(6.2)
where:
After calculation with Equation 6.1 or 6.2, Table 6.4 shall be used for
comparison. The allowable depth that is less (Equations 6.1/6.2 or Table 6.4)
shall be used for final design.
Once the depth has been chosen, the surface area is computed using either
Equation 6.3 for surface basins or Equation 6.4 for subsurface basins:
where:
I
from upstream practices (ft3)
P
= Infiltration depth (feet), cannot exceed maximum allowable
Q‰
= Measured infiltration rate (inches/hr)
= Time to fill the infiltration facility (2 hours)
1V "P × Q
1 = Šη×I +ˆ 2 ‰ Š
12‹
†‡~ (6.4)
where:
6.3.2 Pretreatment
Pretreatment, including minimum pretreatment volume, required for infiltration
practices is as specified in Table 6.6.
6.3.4 Drawdown
Drawdown should typically be complete in 36 to 48 hours.
6.3.6 Porosity
Porosity, used in Equations 6.2 and 6.4, should be assumed to be 0.4; however,
if additional storage in the form of subsurface pipes or similar structures are
used, the porosity coefficient may be adjusted, as appropriate.
• Filter Fabric - Geotextile filter fabric should not be installed along the
bottom of infiltration practices. Experience has shown that filter fabric is
prone to clogging, and a layer of coarse washed stone (choker stone) is a
more effective substitute. However, permeable filter fabric must be
A Level 2 infiltration basin is being proposed to treat runoff from a 1.25 acre
addition (120 new parking spaces) to a park and ride lot near the U.S. 311 and
Interstate 81 interchange in Salem, VA. The hydrologic classification of on-site
soils is a mix of HSG B and HSG D soils. Infiltration tests indicate that the HSG
B soils are suitable for infiltration. Post-development conditions within the
disturbed area indicate 1.05 acres of impervious area, and 0.20 acres of
managed turf. Summaries of these parameters are found in Table 6.7. The time
of concentration to the infiltration practice has been computed as 6 minutes. The
project site does not exhibit a high or seasonally high groundwater table or
indicate the presence of bedrock, based on geotechnical tests performed on-site.
Due to the scale of the facility, it is classified as “conventional infiltration”
according to the impervious treatment areas shown in Table 6.2. In this case,
because there will be over 40 new parking spaces, the site is considered a
stormwater hotspot. Therefore, a Level 1 sand filter will be installed to provide
additional pretreatment prior to infiltration. Full design of the sand filter
pretreatment is not shown in this example. The user is directed to the Section 10
for computational methodology used to size the Level 1 sand filter pretreatment
cell.
The required site data from Table 8.2 is input into the VRRM Spreadsheet for
New Development (2014), resulting in site data summary information shown in
Table 6.8.
In this case, the total phosphorus reduction required is 1.87 lbs/yr (Table 6.8).
The estimated removal is 2.30 lbs/yr; therefore, the target has been met.
Values for the 1-, 2-, and 10-year 24-hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 37.3170, Long -80.0553), those values are shown in Table 6.10.
Curve numbers used for computations should be those calculated as part of the
runoff reduction spreadsheet (Virginia Runoff Reduction Spreadsheet for New
Development, 2014). For this site, results from the runoff reduction spreadsheet
are shown in Table 6.11, and result in adjusted curve numbers of 84, 85 and 87
for the 1, 2 and 10-year storms, respectively.
Table 6.11 Adjusted CN from Runoff Reduction Channel and Flood Protection
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.93 2.45 3.94
RVDeveloped (in) with Runoff Reduction 1.18 1.70 3.19
Adjusted CN 84 85 87
Site data and adjusted curve numbers are used in the Natural Resource
Conservation Service Technical Release 55 (NRCS TR-55) Tabular method to
calculate discharge hydrographs. (Note that other hydrologic methodologies
are suitable-see VDOT Drainage Manual, Hydrology for guidance).
Resulting peaks of hydrographs for the 1-, 2-, and 10-year storms are reported in
Table 6.12. These values can be used to size the conveyance downstream of
the infiltration practice.
The measured infiltration rate at the site is 1.2 in/hr. Based on guidelines by
DEQ, a factor of safety of 2 will be applied to this infiltration rate. Therefore, the
design rate will by 0.6 in/hr. The facility will be a subsurface facility; therefore,
the maximum depth is calculated using Equation 6.2 as:
Six inches of temporary surface storage will be used above ground for use during
larger storms. However, due to the presence of an over drain at the top of the
stone reservoir layer (see VDOT SWM-6, Type I), this surface area cannot be
used as part of the treatment volume. An initial assumed depth of the facility is
taken as 75% of the maximum depth. Therefore, Equation 6.4 is evaluated using
an assumed reservoir depth of 4.5’ to determine surface area as:
•c 1V "1.2 L, × 2ℎJe ”
4,162PQ 0 • 2 ℎJ ‘ “
1 = Š
0.4 × 4.5 PQ + • 12“ = 2,312 PQ
.
• “
Ž ’
Because the assumed depth (4.5’) does not exceed the maximum allowed depth
of 6’, and the calculated surface area of the facility does not exceed the available
area in the HSG B soils, the design is appropriate. Therefore, the facility will
have a bed area of 2,312 ft2 and a stone reservoir depth of 4.5’.
Step 4 - Pretreatment
Parking lot runoff drains directly to a gravel diaphragm that runs along the edge
of the proposed pavement to introduce stormwater runoff into a small perimeter
grass channel, where it is conveyed into the pretreatment sediment forebay,
spilling into the sand filter cell. The minimum sand filter treatment volume is
calculated to be 0.50 (due to hotspot restrictions) of the infiltration practice,
which is 2,081 ft3. However, VDOT, in conversations with the City of Salem, has
determined that maximum removal of hotspot contaminants from this site is
desired; therefore the entire treatment volume will be treated through the sand
filter prior to entering the infiltration bed. Sizing of the sediment forebay and
sand filter will be according to guidelines found in Section 10, but are not shown
in this example.
Due to width constraints, the final dimensions of the facility will be 26.6’ wide and
90’ long. The vertical cross section shall conform to the VDOT SWM-6 Infiltration
Practices (2014) detail for a Type I Infiltration Practice. The surface shall consist
of 3” of river stone. The stone reservoir shall have a depth of 3.83’, consisting of
VDOT #1 open graded course aggregate. Below this, an 8” filtration layer
consisting of grade A VDOT fine aggregate shall be installed. Finally, directly
above the bed, a 4” choker layer of #8 stone shall be installed. Note that due to
the location of the overflow drain (VDOT SWM-6), the surface layer of river stone
and the top 4” of VDOT #1 stone in the reservoir layer cannot be used as part of
the storage volume calculation.
Discharges for design storms are found in Table 6.12. Per the requirements of
VDOT SWM-6 Infiltration Practices (2014), an overflow weir shall be installed to
allow outflow of design storms. In this case, a weir shall be installed at a 6”
elevation above the surface (river stone) of the infiltration bed, with a base width
of 3’ and side slopes of 3:1. The overflow structure must be evaluated based on
design peaks.
Using a 4” perforated riser exiting the bed at a 1.0% slope at invert 1704.50’, and
an overflow weir with crest of 1705.58’ (see geometry above), a rating curve can
be generated using standard hydrologic modeling software. Once the rating
curve is developed, hydrologic routing calculations can occur. Abbreviated
routing results for the 2- and 10-year design storms are found is Tables 6.14 and
6.15, respectively.
The infiltration rate of the facility has been converted to a constant outflow rate of
0.032 cfs by using an adjusted infiltration rate of 0.6 in/hr (half of measured rate)
and the bed surface area (2,312 ft2). This infiltration rate must be implemented as
part of the routing to compensate for exfiltration during the course of the runoff
event. Note that the 2-year storm is completely contained within the facility until
the subsurface storage volume is overwhelmed and the overdrain is activated.
The 2-year storm overflow peak computed using this method is 0.39 cfs. Note
that this is partially due to the additional storage available above the level of the
overdrain and under the crest of the overflow weir.
Note that routing the 10-year storm using this method results in a peak of 4.34
cfs, vs. the peak of 6.35 cfs that is calculated using the adjusted curve numbers.
During the design, the VDOT project manager and VDOT Hydraulics shall be
consulted to determine the methodology to be used for final analysis. The
receiving channel downstream of the overflow weir must be evaluated for
adequacy using standard methodologies, such as the Manning equation.
Bioretention practices form a class of both filtration and infiltration BMPs whose
function is to improve the quality of stormwater runoff by means of adsorption,
filtration, volitilization, ion exchange and microbial decomposition. The soil media
and stone bed also contribute to partial volume reduction as calculated through
the runoff reduction methodology. In the most general sense, a bioretention
BMP can be thought of as a modified infiltration area comprised of a specific mix
of trees, plants, and shrubs intended to mimic the ecosystem of an upland (non-
wetland) forest floor. There are two categories of bioretention BMP: basins and
filters.
7.2.11 Floodplains
Bioretention facilities shall not be located in 100-year floodplains as designated
on applicable FEMA flood maps for the project area.
7.2.12 Access
It is vital to provide adequate access to the BMP site. Site access must be safe
and must provide enough room and appropriate gradients (ideally 4H:1V or
flatter) for construction vehicles to install the BMP and for crews and equipment
to perform maintenance. Ideally, access should include a dedicated easement
that guarantees right-of-entry. Access requirements for underground versus
above-ground BMPs are slightly different.
Storage depth is the sum of the porosity (•) of the soil media and gravel layers multiplied by their
Deeded Maintenance O&M Plan (VDOT maintains per BMP Maintenance Manual)
1
Coefficients in front of each correspond with void ratios associated with each
layer as defined in Virginia DEQ Stormwater Design Specification No.9, (2013, et
seq).
A × − 'Z G
1 =
18
(7.2)
= volume coefficient (1.0 for level 1 design and 1.25 for level 2 design);
Figure 7.3 Basin Geometry Relating Shortest and Longest Flow Paths.
Virginia DEQ Stormwater Design Specification No. 9, 2013
Common overflow structures include domed risers, grate or slot inlets (such as
DI-7), and weir structures. Budget, site aesthetics, and maintenance will govern
the selection of the overflow structure. The sizing of the overflow structure must
consider the flow rate for the design storm of interest, typically the 10-year runoff
producing event. The crest or discharge elevation of the overflow structure
should be set an elevation of 6” to 12” above the elevation of the filter bed. A
typical riser overflow structure is shown in Figure 7.4.
Typically, one of six planting templates should be used to maintain the function
and appearance of a bioretention bed. The six most common bioretention
templates are as follows:
• Turf. This option is typically restricted to on-lot micro-bioretention
applications, such as a front yard rain garden. Grass species should be
selected that have dense cover, are relatively slow growing, and require
the least mowing and chemical inputs (e.g., fine fescue, tall fescue).
• Perennial garden. This option uses herbaceous plants and native
grasses to create a garden effect with seasonal cover. It may be employed
in both micro-scale and small scale bioretention applications. This option
is attractive, but it requires more maintenance in the form of weeding.
• Perennial garden with shrubs. This option provides greater vertical form
by mixing native shrubs and perennials together in the bioretention area.
This option is frequently used when the filter bed is too shallow to support
tree roots. Shrubs should have a minimum height of 30”.
• Tree, shrub and herbaceous plants. This is the traditional landscaping
option for bioretention. It produces the most natural effect, and it is highly
recommended for bioretention basin applications. The landscape goal is to
simulate the structure and function of a native forest plant community.
• Turf and tree. This option is a lower maintenance version of the tree-
shrub-herbaceous option 4, where the mulch layer is replaced by turf
cover. Trees are planted within larger mulched islands to prevent damage
during mowing operations.
• Herbaceous meadow. This is another lower maintenance approach that
focuses on the herbaceous layer and may resemble a wildflower meadow
or roadside vegetated area (e.g., with Joe Pye Weed, New York Ironweed,
sedges, grasses, etc.). The goal is to establish a more natural look that
may be appropriate if the facility is located in a lower maintenance area
(e.g., further from buildings and parking lots). Shrubs and trees may be
incorporated around the perimeter. Erosion control matting can be used in
lieu of the conventional mulch layer.
The goal is to provide a planting plan that will provide cover for the filter surface
in a short amount of time. Plants should be tolerant and able to withstand
periods of inundation and drought. Species more tolerant of wet conditions
should be located towards the center of the bed, with those less tolerant toward
the perimeter. If trees are used, a spacing of approximately 15’ on center, and
density of approximately one tree per 250 ft2 is suggested. Shrubs should be
planted approximately 10’ on center, and herbaceous vegetation should be
planted at 1 to 1.5’ on center. Where trees and shrubs are recommended
(typically Level 2 designs), the designer should consider the long-term growth
habit of the plants – trees can dominate a facility and require extensive
A bioretention basin design is being proposed to treat runoff from a 3,000’ long
section of a lane widening project along I-81 in Montgomery County Virginia.
The current shoulder in the area that will be disturbed includes 1.10 acres of
impervious (gravel and paved) area [0.80 acres overlaying HSG B soils and 0.30
acres overlaying HSG C soils]. Note that the milled areas on the remaining lanes
are not counted in the disturbed area for calculations. In addition there is 1.20
acres of turf covered shoulder that drains to the area (0.90 acres in HSG B soils
and 0.30 acres in HSG C soils) within the area of disturbance. The proposed
widening will add an additional 0.40 acres of impervious area (total 1.10 acres
HSG B and 0.40 acres HSG C), and reduce turf area post-development to 0.80
acres (0.60 acres HSG B and 0.20 acres HSG C). See Table 7.3 for disturbed
area characteristics.
The time of concentration for the BMP location subarea has been calculated to
be 12 minutes. Geotechnical investigations reveal compacted soil with a high
clay content. Lab test confirm that infiltration cannot be performed at this
location. The project site does not exhibit a high or seasonally high groundwater
table.
The required site data from Table 7.3 is input into the VRRM Spreadsheet for
Redevelopment (2014) to compute load reductions for a linear project, resulting
in site data summary information shown in Table 7.5. Note that using the
redevelopment spreadsheet, the required reduction for linear projects is
computed as the sum of the Post-Redevelopment Load and the Post-
Development Load minus 80% of the Predevelopment Listed load.
Step 2 - Select Candidate BMP and Enter Information into Drainage Area
Tab
A Level 1 bioretention has been selected as the candidate BMP for treatment of
captured runoff. The land cover characteristics from Table 7.4 is input into the
VRRM Spreadsheet for Redevelopment (2014) drainage area tab, resulting in
site data summary information shown in Table 7.6.
Values for the 1-, 2-, and 10-year 24- hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 37.1538, Long -80.3265), those values are shown in Table 7.7.
For the 1-, 2-, and 10-year 24-hour storms, adjusted curve numbers supplied by
the VRRM spreadsheet should be used for conveyance and overflow sizing
related to the proposed BMP.
For this site, results from the runoff reduction spreadsheet are shown in Table
7.8, and result in adjusted curve numbers of 83, 84 and 85 for the 1-, 2- and 10-
year storms, respectively.
Table 7.8 Adjusted CN from Runoff Reduction Channel and Flood Protection Sheet
1-year storm 2-year storm 10-year storm
RVDeveloped (in) with no Runoff Reduction 1.22 1.64 2.89
RVDeveloped (in) with Runoff Reduction 0.93 1.35 2.59
Adjusted CN 83 84 85
Input data obtained in Tables 7.7 and 7.7 is used in the Natural Resource
Conservation Service Technical Release 55 (NRCS TR-55, 1986) Tabular
method to calculate discharge hydrographs. Peaks of those hydrographs for the
1-, 2-, and 10-year storms are reported in Table 7.9. These values will be used
to size the overflow structures and downstream conveyance from the
bioretention.
The depth of the facility’s planting soil should be a minimum or 24”, as specified
in Table 7.2. While this is the minimum allowed, the minimum should not be
exceeded except under special circumstances (such as site area constraints),
and should be discussed with VDOT during design. Site grading and placement
•I, GI, and 11I in Equation 7.1 as 2’, 1’, and 0.5’, respectively, yields a storage
Because the proposed design is for a Level 1 facility, using standard values of
depth of 1.40’.
= 3,746 PQ 0
The basin minimum surface area is determined through use of Equation 7.2.
A1.0 × 3,746PQ 0 − 0G
1 = = 2,676 sq. ft
1.40 ft
Note in the above calculation that the upstream treatment volume was assumed
to be 0. A coefficient of 1.0 is used when multiplying by the treatment volume
since this is a Level 1 facility. If this were part of a treatment train, the volume
treated by the upstream BMP would be subtracted from the treatment volume.
In order to prevent short circuiting, for a Level 1 design, the SFP/L ratio is
required to be 0.30 or greater. In order to determine an initial estimate of the
width and length of the basin to meet this ratio, the following calculations can be
If the overflow structure is centered lengthwise (0.5>) along the perimeter of the
basin opposite the inflow (side of facility opposite the road shoulder), then a
6
second equation relating the two parameters is:
= 0.30
0.5>
> = 133.6 ft
6=20 ft
This volume can be achieved through many geometric configurations, and should
be evaluated to best fit the site grades, channel cross sections, etc. If stone or
rip-rap is included within the calculated pre-treatment volume section, the
designer must ensure that only voids within the rip-rap are used to calculate
available volume.
Step 6 - Underdrains
Underdrains will be designed in accordance with the VDOT Special Provision for
Stormwater Miscellaneous (2014). Based on specification in that document,
underdrains shall be 6” rigid Schedule 40 PVC with 4 rows of 3/8” (9.5 mm) holes
with a hole spacing of 3.25 +/- 0.25”. A non-woven geotextile fabric shall be
installed over the top of the underdrain, extending 2’ to either side prior to
installation of the stone layers. Filter fabric shall be non-woven and shall have
0.08” thick equivalent opening size of #80 sieve, and maintain 125 GPM/ft2 flow
rate and meet ASTM D-751 (Puncture strength of 125 lbs), ASTM D-1117
(Mullen Burst Strength of 400 PSI, and ASTM D-1682 (tensile strength of 300
lbs).
The Virginia Stormwater Design Specification No. 10, Dry Swale, Draft
(DCR/DEQ, 2013) lists several dry swale applications, including road medians
and shoulders, in commercial setbacks, parking lots, and along buildings to
accept and treat runoff from roofs. Due to the linear nature of the practice and
the relatively high pollutant removal efficiency, dry swales are applicable on a
wide array of transportation related projects.
Dry Swales can be an important part of the stormwater quality treatment train,
but they require special design considerations to minimize maintenance.
Otherwise, they can become a maintenance burden, particularly if sediment
accumulates within the channel or if flows cause erosion within the channel.
Good design can eliminate or at least minimize such problems.
Also, while check dams or inter-channel berms may be useful flow control
devices, they can also increase the maintenance burden, clogging quickly with
sediment and debris that must be removed to ensure conveyance of design
flows. Therefore, only use these devices when they are absolutely necessary.
When a dry swale is proposed the designer must consider a number of site
constraints to ensure that the practice is applicable to the suggested use.
Soil conditions do not endorse nor preclude the use of dry swales; however, they
do determine if a liner must be installed. Therefore, in situ soil infiltration rate is a
critical design element in a dry swale for a level 2 design since the underdrain is
situated above the stone sump. When such a facility is proposed, a subsurface
analysis and permeability test is required in support of a level 2 design. The
required subsurface analysis should investigate soil characteristics to a depth of
no less than 3’ below the proposed bottom of the engineered media. Data from
the subsurface investigation should be provided to the Materials Division early in
the project planning stages to evaluate the final design characteristics of the
proposed facility.
8.2.9 Wetlands
When the construction of a dry swale is planned in the vicinity of known
wetlands, the designer must coordinate with the appropriate local, state, and
federal agencies to identify wetlands boundaries, their protected status, and the
feasibility of BMP implementation in their vicinity.
8.2.10 Floodplains
Dry swales should not be located in 100-year floodplains for project areas as
defined by applicable FEMA flood maps.
Equation 8.1 describes the dry swale design equivalent subsurface storage
depth as:
Coefficients in front of each correspond to the void ratio associated with each
et seq). In a typical Level 1 design, the depths for these two layers (•I and –I)
layer, as defined in Virginia DEQ Stormwater Design Specification No.10, (2013,
are 1.5’ and 0.25’, respectively, which yields an effective subsurface storage
depth of 0.5’; however, equation 10.1 should be used to calculate the design-
specific equivalent storage depth if a situation results in the modification of the
standard design.
2’ and 1’, respectively, which yields an equivalent storage depth of 0.90’. Again,
Equation 8.1 should be used to calculate the actual equivalent depth if a
situation results in the modification of this standard design.
Equation 8.2 below is used to calculate the required surface area, SA, of the
Level 1 and Level 2 swales described above. If the dry swale includes check
dams to decrease the effective swale longitudinal slope, or to simply create
storage volume, it is recommended that the designer estimate the design width of
the swale, compute the storage volume retained by the check dams (' , and
subtract it from the BMP design treatment volume, , of Dry Swale. This will be
an iterative computation if the design width of the Dry Swale is different from that
which is used to estimate the surface storage.
Equation 8.2 describes the calculation of the required minimum dry swale
A −' G
surface area as:
1 =
18
(8.2)
1 =
where:
surface area (ft2)
= computed treatment volume (ft3), Section 1, Equation 1.1 ( = 1.0
'ss =
for Level 1 and 1.1 for level 2)
18 =
volume of surface storage (ft3)
storage depth (ft), as computed by Equation 8.1.
Check dams may also be used for velocity reduction. Velocities in dry swales
should not exceed 3 fps to prevent erosion. Typical check dam spacing to
achieve effective swale slopes may be found in the Section 3, Table 3.3.
8.3.7 Drawdown
Drawdown of the treatment volume should occur within a 6 hour period. Filtration
may be accomplished through the soil media mix or in situ soils with verified
adequate permeability. This drawdown time can be achieved by using the soil
media mix specified in the VDOT Special Provision for Dry Swales (2014) and an
underdrain along the bottom of the swale, or native soils with adequate
permeability, as verified through testing.
8.3.8 Underdrains
Underdrains shall be installed in accordance with material, size, and installation
specifications found in the VDOT Special Provision for Stormwater Miscellaneous
(2014), VDOT Special Provision for Dry Swales (2014), and VDOT Standard
Detail SWM-8: Dry Swales (2014).
• Grass Filter Strips: Runoff entering a dry swale as sheet flow may be
treated by a grass filter strip. The purpose of the grass filter strip/energy
dissipation area is to reduce the erosive capabilities of runoff prior to its
entrance into the bioretention area. The recommended length of the grass
filter strip is a function of the land cover of the contributing drainage area
and its slope. The recommended minimum length of the grass filter strip
should not be less than 10’ when using the maximum side slope of 5:1.
An alternative design may be used that integrates road shoulders,
requiring a 5’ minimum grass filter strip at 20:1 (5%), that is combined with
3:1 (or flatter) side slopes of the swale to provide pre-treatment.
8.3.11 Overflow
The dry swale shall be designed to convey the 10-year storm within the banks
with a minimum of 3” of freeboard. Overflow from the dry swale may discharge
into an overflow structure (such as a VDOT Standard DI-7), and overflow
channel, or an overflow pipe. Discharge of overflow shall be to an adequate
channel per state and local requirements.
Salt tolerant grass and plant species should be used in order to withstand
concentrations of deicing solution used to treat roads during the winter.
This section presents the design process applicable to dry swales serving as
water quality BMPs. The pre- and post-development runoff characteristics are
intended to replicate stormwater management needs routinely encountered on
VDOT projects. The hydrologic calculations and assumptions presented in this
section serve only as input data for the detailed BMP design steps. Full
hydrologic discussion is beyond the scope of this report, and the user is referred
to Chapter 11 of the Virginia Stormwater Management Handbook, 2nd Edition,
Draft (DCR/DEQ, 2013) for details on hydrologic methodology.
A Level 1 dry conveyance swale design is being proposed to treat runoff from a
2,100’ long section of a road improvement project along I-64 near Waynesboro.
The longitudinal slope along this section of I-64 is approximately 1.5%. Runoff
from the crown to the side of the expansion for this section of the project can be
redirected to a BMP location having a total cumulative contributing drainage area
(at the downstream end of swale) of 2.30 acres. The current lane (on BMP side
of crown) and shoulder represent 1.40 acres of impervious area (1.00 acres
overlaying HSG B soils and 0.40 acres overlaying HSG C soils). In addition
there is 0.90 acres of turf covered shoulder that drains to the area (0.60 acres in
HSG B soils and 0.30 acres in HSG C soils).
Geotechnical investigations reveal compacted soil with a high clay content. Lab
tests confirm that infiltration rates necessary for a Level 1 design a at this
location. The project site does not exhibit a high or seasonally high groundwater
table.
The required site data from Table 8.2 is input into the VRRM Spreadsheet for
Redevelopment (2014) to compute load reductions for this linear project,
resulting in site data summary information shown in Table 8.3. Note that using
the redevelopment spreadsheet, the required reduction for linear projects is
computed as the sum of the Post-Redevelopment Load and the Post-
Development Load minus 80% of the Predevelopment Listed load.
It is important to note that the values in Table 8.2 are only the values for the
disturbed area of the project. Although other run-on areas (2.30 acres total) were
described in the problem statement, they are not part of the disturbed area, and
should not be entered as such in the VRRM Spreadsheet to compute required
reductions (Table 8.3).
The drainage area is for this outfall is roughly symmetrical, with flow approaching
a common central discharge point from both directions. The Level 1 dry swale
will be used to treat runoff from one direction only (a total of 1.20 acres) for water
quality compliance. Note that the VRRM Spreadsheet will warn the user that the
area (1.20 acres) exceeds the disturbed area (1.05 acres); however, it is
acceptable to treat adjacent run-on area as part of the project. Appropriate data
for post-development conditions is input into the VRRM Spreadsheet Drainage
Area tab, yielding compliance results summarized in Table 8.4.
In this case, the total phosphorus reduction required is 1.12 lbs/yr. The
estimated removal is 1.17 lbs/yr; therefore, the target has been met.
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
VDOT Drainage Manual for appropriate levels of protection and design
requirements related to erosion and flood protection. However, hydrologic
computations are necessary to compute peaks to design components of the Dry
Swale. In particular, the 10-year 24-hour design storm is used to size the
rectangular notch is check dams.
Values for the 1-, 2-, and 10-year 24-hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 38.0522, Long 78.9162), those values are shown in Table 8.5.
For the 1-, 2-, and 10-year 24-hour storms, adjusted curve numbers supplied by
the VRRM spreadsheet should be used for conveyance and overflow sizing
related to the proposed BMP.
Table 8.6 Adjusted CN from Runoff Reduction Channel and Flood Protection Sheet
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.49 2.27 3.74
RVDeveloped (in) with Runoff Reduction 1.16 1.94 3.41
Adjusted CN 87 88 89
Because the proposed design is for a Level 1 facility, using standard values of •I
and GI in Equation 8.1 as 1.5’ and 0.25’, respectively, yields an equivalent
storage depth of 0.48’.
18 = 0.25 •„ + 0.40 –„
Although not required (due to the low slope of 1.5%), check dams will be installed
to increase surface storage and decrease the required width of the dry swale.
Based on the check dam spacing table in Section 3, Table 3, to achieve an
effective channel slope of 1.0%, a spacing of 67’ to 200’ should be used if the
actual channel slope is 1.5%. If 3:1 side slopes are assumed, the surface storage
volume may be approximated by:
™. 6
'˜ = ) + ™-
1 2
(8.3)
calculated by:
The notch weir length should be a minimum of 1’ less (6” clearance on each side)
The weir should also be centered in the check dam. An assumed ℎ of 0.50’ (6”)
than the channel bottom width to reduce the chance of erosion to channel banks.
and the C2F discharge of 4.92 cfs (Table 8.7) is used in rearranged Equation 8.4
to compute weir length:
Adding 1’ clearance to the notch weir length (to prevent erosion), yields a
minimum bottom width of ~5.1’. Therefore, 5.1’ will be used as the assumed
bottom width for surface storage computations.
The surface storage requirement is based on volume behind check dams, and
must initially be calculated by assuming the number of check dams necessary for
the application. If nine check dams are assumed, then the length of dry swale
media bed is estimated as 67’ (distance between dams) x 9 (dams), or
approximately 603’. The 67’ distance assumption stems from the spacing criteria
shown in Section 3, Table 3.3, which suggests of spacing of 67’ when on a 1.5%
swale slope to decrease the effective slope to 0%. If the media bed is assumed
to extend across the entire width of the channel bottom, the required minimum
surface storage can be calculated as:
The 2,118 ft3 is divided between storage areas behind each proposed check
is equivalent to '˜ from Equation 8.3. Substituting into that equation, and
dam. The volume calculated above after being divided by 9 dam areas (235 ft3)
assuming an effective check dam height, ™ , of 12” (1’), the required minimum
surface storage volume, '˜ is computed as:
™. 6 1.0 PQ . 6
235 PQ 0 = ) + ™- = ) + 1.0 PQ-
1 2 0.015 2
This value confirms the assumed channel width that was based on the weir
length calculated by Equation 8.4 (with 1’ added for erosion clearance) of 5.1’.
Therefore, the assumption of 9 check dams is valid, and produces sufficient
surface storage for the design.
The final treatment bed will encompass an area along the channel of 600’ x 5.10’,
with 9 check dams spaced evenly at 67’ intervals. A 4.1’ wide weir will be
centered in each check dam with a crest elevation of 12” above channel bottom,
and height of 6”. The total height of the check dam will be the maximum
allowable height of 18” (Figure 8.6).
Step 5 - Pre-treatment
Pre-treatment requirements will be met through the use of a grass filter for sheet
flow. The filter is shown in Figure 10.3 as the 5’ 20:1 shoulder along the
pavement, with a 3:1 slope to the bottom of the swale. No other pre-treatment is
required for this installation.
Step 8 - Seeding
The grass chosen should be able to withstand both wet and dry periods. The
user is directed to the Virginia Erosion Control Handbook (1992) permanent
seeding chapter for guidance. The selected seed mix combination should provide
low maintenance, tolerance of moisture conditions, and be tolerant to high salt
concentrations during the winter months.
Wet swales are effectively a hybrid treatment device that is a cross between a
swale and a constructed wetland. The purpose of the practice is to intercept the
high groundwater table and detain runoff. Wet swales provide pollutant removal
though gravitational settling, pollutant uptake, and microbial activity.
The Virginia Stormwater Design Specification No. 11, Wet Swales, Draft
(DCR/DEQ, 2013) describes wet swales as well-suited for use in linear
applications to treat highway or residential street runoff.
Wet Swales can be an important part of the stormwater quality treatment train,
but they require special design considerations to minimize maintenance.
Otherwise, they can become a maintenance burden, particularly if sediment
accumulates within the channel or if flows cause erosion within the channel.
Good design can eliminate or at least minimize such problems.
Also, while check dams or inter-channel berms may be useful flow control
devices, they can also increase the maintenance burden, clogging quickly with
sediment and debris that must be removed to sustain design flows. Therefore,
only use these devices when they are absolutely necessary, because they make
the maintenance worker’s job more difficult.
When a wet swale is proposed the designer must consider a number of site
constraints to ensure that the practice is applicable to the suggested use.
9.2.7 Wetlands
When the construction of a wet swale is planned in the vicinity of known
wetlands, the designer must coordinate with the appropriate local, state, and
federal agencies to identify wetlands boundaries, their protected status, the
feasibility of BMP implementation in their vicinity, and potential permit
requirements.
Actual dimensions are determined from the requirement to capture and treat the
(treatment volume) remaining from upstream runoff reduction practices (if
any). Treatment credit is applied to both the permanent wet storage below the
normal pool level and any temporary storage created through the installation of
check dams or other features.
The design must also demonstrate that on-line wet swales also have sufficient
capacity above the to safely convey the 10-year design storm and be non-
erosive during both the 2-year and 10-year design storms. When a Wet Swales
is used as an off-line practice (Level 2 design), a bypass or diversion structure
must be designed to divert the large storm (e.g., when the flow rate and/or
volume exceeds the water quality Treatment Volume) to an adequate channel or
conveyance system.
Design guidance shown in Sections 3.3.1, 3.3.2, and 3.3.4 of Section 3, Grass
Channels, should be used for design of pre-treatment and swale geometry.
Check dams may also be used for velocity reduction. Velocities in wet swales
should not exceed 3 fps to prevent erosion.
Keep in mind that the first cell created by a series of check dams will function, at
least to some degree, as a pre-treatment forebay, allowing sediment to settle out
of the stormwater prior to the runoff moving further down the swale. This first cell
should be one thing checked during maintenance inspections, to ensure design
capacity is being maintained so the cell performs properly in its pollution removal
function.
9.3.6 Overflow
The wet swale shall be designed to convey the 10-year storm within the banks
with a minimum of 3” of freeboard. The downstream end of the wet swale may
discharge into an overflow structure (such as a VDOT Std DI-7), and overflow
channel, or an overflow pipe.
This section presents the design process applicable to wet swales serving as
water quality BMPs. The pre- and post-development runoff characteristics are
intended to replicate stormwater management needs routinely encountered on
VDOT projects. The hydrologic calculations and assumptions presented in this
section serve only as input data for the detailed BMP design steps. Full
hydrologic discussion is beyond the scope of this report, and the user is referred
to Chapter 11 of the Virginia Stormwater Management Handbook, 2nd Edition,
Draft (DCR/DEQ, 2013) for details on hydrologic methodology.
A Level 1 wet swale design is being proposed to treat runoff from a 1,500’ long
section of a road improvement project along Route 620 in Isle of Wight County.
The longitudinal slope along the proposed redesign of this section of Route 620
is very flat (approximately 0.8%). The proposed project includes removal of
approximately 1,500 LF of road to grade a series of vertical curves (humps) that
do not meet VDOT’s current design standards. This will require complete
removal of the current pavement cross-section, regrading of subgrade, and
replacement of the pavement section with a width matching the existing
pavement. Runoff from the centerline crown to each side of the road can be
directed to wet swales on either side of the road. Calculations shown are for a
single side (south side of road) only. The current lane (on BMP side of crown)
and shoulder represent 0.40 acres of impervious area (all overlaying HSG C
soils). In addition there is 1.20 acres of turf covered shoulder that drains to the
BMP treatment area (0.80 acres in HSG C soils and 0.40 acres in HSG D soils).
A summary of the data is found in Table 9.3. In the post-development condition,
the time of concentration has been calculated to be 9 minutes.
The required site data from Table 9.3 is input into the VRRM Spreadsheet for
Redevelopment (2014) to compute load reductions for this linear project,
resulting in site data summary information shown in Table 9.4. Note that using
the redevelopment spreadsheet, the required reduction for linear projects is
computed as the sum of the Post-Redevelopment Load and the Post-
Development Load minus 80% of the Predevelopment Listed load.
The entire disturbed area drains to the proposed location of the BMP. Due to the
presence of high groundwater, a Level 1 wet swale is proposed as the treatment
BMP. Appropriate data for post-development conditions is input into the VRRM
Spreadsheet Drainage Area tab, yielding compliance results summarized in
Table 9.5.
In this case, the total phosphorus reduction required is 0.30 lbs/yr. The
estimated removal is 0.30 lbs/yr; therefore, the target has been met.
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
VDOT Drainage Manual for appropriate levels of protection and design
requirements related to erosion and flood protection. However, hydrologic
computations are necessary to compute peaks to design components of the Wet
Swale. In particular, the 10-year 24-hour design storm is used to size the
rectangular notch is check dams.
Table 9.7 Adjusted CN from Runoff Reduction Channel and Flood Protection Sheet
[No Reduction for Wet Swale BMP]
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.34 1.86 3.56
RVDeveloped (in) with Runoff Reduction 1.34 1.86 3.56
Adjusted CN 82 82 82
Sizing of wet swales follow similar procedures to those using to size grass
where:
÷ IJKL,KMN KJNK
P = Rainfall (inches), (1.0” in Virginia)
Qa = Runoff volume (watershed inches), equal to
2,381PQ 0 12L,
CD = ) - = 0.41 L,
43,560 PQV 1 PQ
1.6 KR S 1 KRW
1000
@=
X10 + 5 1 L, + 10 0.41 L, − 10 0.41 L, + 1.25 0.41 L, 1 L, " Y
F.9
.
@ = 92
4 $ = 4Z CD (9.2)
All of the variables are known in the above equation with the exception of 4Z . To
determine its value, first the initial abstraction must be computed using the
equation:
200
!D = −2
@
(9.3)
200
!D = − 2 = 0.17 L,RℎN\
92
Read the unit peak discharge, 4Z , from Exhibit 4-II of the SCS TR-55 Handbook
(NRCS, 1986). Reading the chart yields a value of 855 cfs/mi2/in.
4 $ = 0.88 RP\
The length of the project along Route 620 is approximately 1,500’. Since the
proposed channel cross-section and longitudinal slope is consistent (0.8%) along
the entire length, the channel will be evaluated for compliance at the most
downstream end.
Based on the requirements set forth in Section 3, Grass Channels, the Manning
‘n’ coefficient is 0.2 for a depth of up to 4”. Based on geotechnical observations,
it is estimated that a seasonally high groundwater table will intersect with the
bottom 4” of the swale during a portion of the year. Because specifications allow
treatment credit to be applied to both the permanent volume (as well as
temporary storage, if any) the initial assumption will be that treatment can occur
in the first 4” of depth. The estimated width may be calculated through
modification of Equation 3.3 (Section 3, Grass Channels), reproduced below
for convenience.
Using the discharge (0.88 cfs), the flow depth (0.33’), and the channel width
(8.4’), velocity can now be approximated using Section 3, Equation 3.4 as:
0.88 RP\ PQ
'= = 0.32
8.4 PQ × 0.33 PQ \
This velocity is less than the maximum velocity of 1 fps required, and is therefore
is an acceptable design.
The minimum swale length is calculated using Section 3, Equation 3.5 as:
PQ
> = 540' = 540 \NR )0.32 - = 173 PQ
\
For maintenance purposes, VDOT prefers grass and other herbaceous varieties
to be planted in wet swales, instead of trees and shrubs. See Stormwater
Specification 13, Constructed Wetland, Draft (DCR/DEQ, 2013) for a list of
acceptable plant species.
Stormwater filters are used to collect and treat runoff from small, highly
impervious areas. These practices treat runoff by providing a pretreatment
chamber that slows and settles larger particles from runoff, and then through a
secondary treatment filter which provides an underdrain for discharging the
treated stormwater into a downstream conveyance system. Although filters are
moderately efficient at removal of pollutants, the practice affords no reduction in
the computed stormwater volume leaving the site. Stormwater filters are best
applied on sites where nearly 100% of the contributing drainage area is
impervious to limit the potential of clogging due to sediment laden runoff from
erosion on permeable surfaces. Linear stormwater filters are very suitable for
highway projects and may be designed as a series of filters. In practice, on
linear projects, the layout of filter practices will be very similar to dry swale
configurations. Requirements shown herein are modifications to specifications
found in Virginia Stormwater Design Specification No. 12, Filtering Practices,
Draft (DCR/DEQ, 2013), for specific application to VDOT projects. Table 10.1
describes a summary of stormwater functions provided by filtering practices.
Typical configurations of filters used for highway projects include surface filters
and perimeter sand filters, shown in Figures 10.1 and 10.2, respectively.
Surface filters, although similar in design to bioretention, several differences
include: impermeable filter fabric lining bottom of facility, an underdrain is always
present, surface cover is gravel, sand, or turf (no other plants), media is one
hundred percent sand, and the filter includes an upstream dry or wet settling
basin/chamber. Perimeter sand filters are typically precast systems that include
inlet grates, a sedimentation chamber, and the media filter bed, with underdrain.
Although very practical for highway projects due to the relatively small size and
linear nature, the overall dimensions will limit the contributing area that may be
treated by the device. Manufactured Treatment Devices (MTDs) may also be
allowed by VDOT on a case by case basis. Information regarding specific MTD
structures shall be submitted to VDOT Materials Division for acceptance during
design.
10.3.1 Sizing
For preliminary sizing and space planning, a general rule of thumb is that surface
filters will occupy an area ranging between 2%-3% of the contributing drainage
area, while perimeter sand filters or MTDs may be 1% or less.
Actual dimensions are determined from Equations 10.1 and 10.2 (below), from
the Virginia Stormwater Design Specification No. 12, Filtering Practices, Draft
(DCR/DEQ, 2013)
The required filter surface area size is determined by the following equation:
where:
‰ = area of the filter surface (ft2)
10.3.2 Pretreatment
Pretreatment is always required upstream of filters to remove trash, capture
coarse sediment, and provide for even flow distribution into the filter bed at near
zero velocity. The pretreatment volume is required to be a minimum of 0.25 .
For surface filters, the pretreatment (sediment forebay cell) shall conform to the
PT-1 Detail in VDOT SWM-PT, Pretreatment (2014) [see Figure 10.3]. Flow
entering surface cells directly from paved areas may require a pretreatment
gravel diaphragm in accordance with PT-2 in VDOT SWM-PT, Pretreatment
(2014) to insure that flow enters the cell as sheet flow. As required, a grass filter
strip at least 15’ long and meeting the requirements of VDOT SWM-2, Sheet
The check dam used to create the pretreatment forebay through separation from
the main filter bed shall be constructed in accordance with the VDOT SWM-CD,
Type 2 (2014) [Figure 10.4].
10.3.4 Dewatering
Filters shall be designed to dewater in less than 40 hours after a runoff producing
storm event.
Surface cover for underground sand filters (Level 2 only) shall consist of a 4”
choker layer meeting the requirements of Part II.(e) of the VDOT Special
Provision for Filtering Practices (2014) placed over a non-woven geotextile filter
fabric conforming to the requirements of the VDOT Special Provision for
Stormwater Miscellaneous (2014).
This section presents the design process applicable to stormwater filters serving
as water quality BMPs. The pre- and post-development runoff characteristics are
intended to replicate stormwater management needs routinely encountered on
VDOT projects. The hydrologic calculations and assumptions presented in this
section serve only as input data for the detailed BMP design steps. Full
hydrologic discussion is beyond the scope of this report, and the user is referred
to Chapter 11 of the Virginia Stormwater Management Handbook, 2nd Edition
(DCR/DEQ, 2013) for details on hydrologic methodology.
A Level 1 perimeter sand filter is being proposed to treat runoff from 1.05 acre
park and ride lot near the U.S. 460 and Interstate 81 interchange in
Christiansburg, VA. The hydrologic classification of on-site soils is HSG B. Post-
development conditions within the disturbed area indicate 0.95 acres of
impervious area, and 0.10 acres of managed turf. Summaries of these
parameters are found in Table 10.3. The time of concentration to the filtering
practice has been computed as 8 minutes. The project site does not exhibit a
high or seasonally high groundwater table or indicate the presence of bedrock,
based on geotechnical tests performed on site.
The required site data from Table 10.3 is input into the VRRM Spreadsheet for
New Development (2014), resulting in site data summary information shown in
Table 10.4.
Information should now be entered in the Drainage Area tab of the spreadsheet
using the proposed treatment train with sheet flow to vegetated filter strip to a
Level 1 filter. Appropriate data for post-development conditions is input into the
VRRM Spreadsheet Drainage Area tab, yielding compliance results summarized
in Table 10.5.
In this case, the total phosphorus reduction required is 1.67 lbs/yr. The
estimated removal is 1.68 lbs/yr; therefore, the target has been met.
Information from Table 10.3 is used in conjunction with Equation 1.2 and Table
1.1 (both from Section 1) to calculate for the post-development
condition.
= × %!" + $
×% "+ %
× %&"
Once the has been calculated, the Treatment Volume for the 1.0”
runoff through the facility can be directly computed using Equation 1.1 (from
Section 1) for a Level 1 facility.
Because the filter is part of a treatment train, and the vegetated filter strip results
in a runoff reduction of 1,638 ft3 of runoff as calculated by the VRRM
spreadsheet, the total treatment volume above can be reduced by that amount:
Values for the 1-, 2-, and 10-year 24- hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 37.1342, Long -80.3722), those values are shown in Table 10.6.
Curve numbers used for computations should be those calculated as part of the
runoff reduction spreadsheet Virginia Runoff Reduction Spreadsheet for New
Development (2014). For this site, results from the runoff reduction spreadsheet
are shown in Table 10.7, and result in adjusted curve numbers of 89, 89 and 90
for the 1-, 2- and 10-year storms, respectively. Note that the volume reduction
achieved is from the vegetated filter pretreatment, and that no volume reduction
is achieved through use of the filtering practice.
Table 10.7 Adjusted CN from Runoff Reduction Channel and Flood Protection
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.69 2.16 3.51
RVDeveloped (in) with Runoff Reduction 1.25 1.72 3.07
Adjusted CN 88 89 90
Using a media depth of 12” (1.0’), and a surface ponding depth average of 1’
(note that the maximum head is 2’), the required filter area is calculated using
Equation 10.1 as:
1,716 PQ 0 1.0 PQ
= = 147 ft .
‰
PQ
)3.5 - 1.0 PQ + 1.0 PQ 1.67 IK¨\
IK¨
Step 5 - Pretreatment
The parking lot runoff drains directly to a gravel diaphragm that runs along the
edge of the proposed pavement to introduce stormwater runoff to the vegetated
filter strip as sheet flow. The diaphragm is installed according to detail SWM-PT,
PT2, and the vegetated filter strips according to guidelines set forth in Section 2
of this manual. Runoff then is concentrated into a small perimeter grass channel,
where it is conveyed into the pretreatment sediment forebay. The minimum
forebay size is calculated as 0.25 , which is 429 ft3. However, due to limitations
in storage above the sand bed for this particular facility, the sediment forebay is
increased in size to allow ponding of approximately 1,400 ft3 of surface runoff
upstream of the rock check dam separating the pretreatment cell from the
treatment filter.
The depth of the facility’s filtering media should be a minimum of 12” and typically
a maximum of 18”. As stated above, a depth of 12” is used for this design
example. Limitations in available surface storage for head, limitations in
discharge elevation, and long-term maintenance needs and costs will be typical
driving factors that must be weighed in determining depth of media.
2.50
2.34 cfs
2.00
1.50
1,716 cubic feet
Flow (cfs)
1.00
0.50
0.00
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000
Cumulative Volume (cubic feet)
For the 10-year storm, if a similar curve is plotted (not shown), the treatment
volume will intersect the curve prior to the hydrograph peak of 4.31 cfs.
Therefore, the 10-year peak of 4.31 cfs should be used to determine the
adequacy of the downstream manmade conveyance system. Discharges to
natural systems will require additional analysis for the 1-year storm to meet the
requirements of 9VAC25-870-66 of the Virginia Administrative Code. Although,
there is an additional discharge related to the filter underdrains, based on the
Adequacy of the DI-7 to convey the peak discharge with the available head
should be verified using applicable nomographs in the VDOT Drainage Manual
(latest edition). VDOT Figure 9C-14 is used to determine flow capacity of a DI-7
in a sump. For this example, the DI-7 crest is set at 1’ above the filter bed
surface (maximum ponding depth), with a height of 1.0’ between DI-7 crest and
top of berm. Flow is computed through use of the VDOT 9C-14 nomograph, as
shown in Figure 10.6. Evaluation of the 10-year peak (Figure 10.6) shows that
a head of approximately 0.46’ above the DI-7 crest is needed to convey the 10-
year storm. Since this is less than the 1.0’ height to top of berm, the system is
adequate for the 10-year storm, even if partially clogged.
The discharge pipe from the DI-7 manhole will be sized to convey the 10-year
discharge without surcharge. The designer should use nomographs in the VDOT
Step 8 - Underdrains
Step 9 - Seeding
Constructed stormwater wetlands fall into a structural BMP category having the
capacity to improve the quality of stormwater runoff in much the same manner as
retention and enhanced extended detention basins. Like these impounding
facilities, stormwater wetlands are seeded with a diverse mix of aquatic and
emergent vegetation, which plays an integral role in the pollutant removal
efficiency of the practice. Wetland BMPs improve the quality of runoff by
physical, chemical, and biological means. The physical treatment of runoff
occurs as a result of decreased flow velocities in the wetland, thus leading to
evaporation, sedimentation, adsorption, and/or filtration. Chemical treatment
arises in the form of chelation (bonding of heavy metal ions), precipitation,
chemical adsorption, and microbial activity. Biological treatment occurs via
uptake of nutrients and other constituents into plant tissue.
Typical details for plan and profile views of constructed wetlands are shown in
Figures 11.1 and 11.2. Due to the water balance requirements for maintaining
vegetative species found in wetlands, applications on linear sites can be
challenging. Therefore, their used by VDOT will typical be limited to non-linear
sites or interchanges. However, linear wetland cells and regenerative
conveyance systems are well suited to treat runoff within swales located along
roads.
11.2.6 Setbacks
Generally, edges of wetlands should be 20’ from the right of way line, 25’ from
foundations, 50’ from septic drainfields, and 100’ from wells. Variations from
these requirements shall be requested and approved through the District Office,
prior to integration in Contract Documents.
11.2.7 Karst
Typically, constructed wetlands should not be implemented in karst areas due to
the risk of sinkhole formation and groundwater contamination. However, if a
geotechnical investigation shows at least a 3’ separation between the bottom of
the wetlands and bedrock, the practice can be implemented with approval from
the District Office, and with the installation of an impermeable liner (clay or,
preferably, geosynthetic) meeting the specifications shown in Table 11.3. If a
constructed wetland is used in karst terrain, then shallow, linear and multiple-cell
wetland configurations are preferred. Deeper wetland configurations, such as a
pond/wetland system and the ED wetland have limited application in karst terrain.
11.2.9 Soils
The implementation of constructed stormwater wetlands can be successfully
accomplished in the presence of a variety of soil types. However, when such a
facility is proposed, a subsurface analysis and permeability test is required. The
required subsurface analysis should investigate soil characteristics to a depth of
no less than 3’ below the proposed bottom of the wetland. Data from the
subsurface investigation should be provided to the Materials Division early in the
project planning stages to evaluate the feasibility of such a facility on native site
soils.
• Clogging Reduction. If the low flow orifice clogs, it can result in a rapid
change in wetland water elevations that can potentially kill wetland
vegetation. Therefore, designers should carefully design the flow control
structure to minimize clogging, as follows:
o A minimum 3” diameter orifice is recommended in order to minimize
clogging of an outlet or extended detention pipe when it is surface fed.
It should be noted, however, that even a 3” orifice will be very
susceptible to clogging from floating vegetation and debris.
o Smaller openings (down to 1” in diameter) are permissible, using
internal orifice plates.
o All outlet pipes should be adequately protected by trash racks, half-
round CMP, other anti-clogging measures, or reverse-sloped pipes
extending to mid-depth of the micro-pool.
Constructed wetlands are designed based on three major factors: (1) the
desired plant community (an emergent wetland – Level 1 design; a mixed
wetland – emergent and forest; or an emergent/pond combination – Level 2
design); (2) the contributing hydrology (groundwater, surface runoff or dry
weather flow); and (3) the landscape position (linear or basin).
Constructed wetlands shall typically fall within one of three categories, as defined
in the Virginia Stormwater Design Specification No. 13, Constructed Wetland,
Draft (DCR/DEQ, 2013). These are:
• Constructed Wetland Basin – Level 1 (1.0 x Treatment Volume [ ])
• Constructed Multi-Cell Wetland – Level 2 (1.5 )
• Constructed Multi-Cell Pond/Wetland Combination – Level 2 (1.5 )
To avoid performance issues, the facility must be sized properly for the target
Treatment Volume. However, oversizing the storage provided in the BMP, as
compared to what is required to achieve the BMP’s performance target, can
decrease the frequency of maintenance needed and, thus, potential life-cycle
costs. Oversizing, where feasible, can also help VDOT achieve its broader
pollution reduction requirements associated with its DEQ MS4 Permit and the
Chesapeake Bay TMDL. Oversizing options are likely to involve the adjustment
of detention times and may require prior approval by DEQ.
Note that the one year channel protection detention and detention volume depth
above normal pool shall not exceed 1’. Typically, the 1-year storm volume will
drive this requirement since it is likely that the will be less than the 1-year
storm volume. The maximum water level fluctuation during routing of the
treatment volume and/or the 1-year storm is limited to 12”. A weir or other outlet
control structure may be used to ensure that this maximum is not violated (see
VDOT Detail SWM-11: Constructed Wetlands (2014)).
Routing of the treatment volume requires that the water level fluctuations not
exceed 8”. Further, a maximum of 12” fluctuation in water level is allowed during
routing of the 1-year storm volume through the constructed wetland.
8 ×
8B = & × − ² − !@& − ²1
©ª«¬ª-®¯°
‚ ±D}„
(11.1)
where:
• High Marsh: Approximately 70% of the cell surface area should have
elevations ranging between -6” to +6” relative to the normal pool
elevation).
• Low Marsh: This zone contains storage at -6” to -18” below the normal
pool elevation. This zone is not considered to be an effective wetland
zone and should provide a short transition between high marsh and deep
pools. Maximum slopes in this transition zone from the deep pool to the
high marsh should be 5H:1V (or preferably flatter). Biodegradable erosion
control fabric should be used to prevent erosion of this zone during
construction, to prevent erosion or slumping due to difficulty in quickly
establishing vegetative cover.
11.3.8 Micro-topography
Variations in topography resulting in small variations in elevation are used to
create the various regions described above. At least two of the following design
features must be integrated into a Level 2 design:
1. Tree peninsulas, high marsh wedges, or rock filter cells installed
perpendicular to primary flow path.
2. Tree islands above both the normal pool and maximum extended
detention zone, formed by coir fiber logs.
3. Inverted root wads or large wood-based debris.
4. Gravel diaphragms within high marsh zone(s).
5. Internal weirs/baffles made of cobble with sand backfill, gabion baskets, or
stabilized earthen berms.
Other forms of pre-treatment for sheet flow and concentrated flow at minor inflow
points should be designed consistent with pre-treatment criteria found in Section
6.4 of Stormwater Design Specification No. 9: Bioretention.
11.3.13 Embankment
The top width of the embankment should be a minimum of 10’ in width to provide
ease of construction and maintenance. The design of the dam should be in
accordance with Appendix A: Earthen Embankments of the Introduction to the
New Virginia Stormwater Design Specifications, as posted on the Virginia
Stormwater BMP Clearinghouse web site:
https://www.swbmp.vwrrc.vt.edu/wp-content/uploads/2017/11/Introduction_App-
A_Earthen-Embankments_03012011.pdf
Design the principal spillway with acceptable anti-flotation, anti-vortex and trash
rack devices. The spillway must generally be accessible from dry land. Refer to
Appendix B: Principal Spillways of the Introduction to the New Virginia
Stormwater Design Specifications, as posted on the Virginia Stormwater BMP
Clearinghouse web site:
https://www.swbmp.vwrrc.vt.edu/wp-content/uploads/2017/11/Introduction_App-
B_Principal-Spillways_03012011.pdf
The required site data must be input into the VRRM Spreadsheet for
Redevelopment (2014), to determine the required load reduction of phosphorus
for this linear site. Note that using the redevelopment spreadsheet, the required
reduction for linear projects is computed as the sum of the Post-Redevelopment
Load and the Post-Development Load minus 80% of the Predevelopment Listed
load. Although the total contributing drainage area is defined by components
listed in Table 11.4, the area that is used to calculate water quality improvements
Output from the RRM Summary Spreadsheet is shown in Table 11.6, and
indicates that the required removal load is 3.20 lbs/yr. Although a Level 1
constructed wetland treating only the disturbed area does not meet the
requirement (only resulting in a net removal of 2.05 lbs/yr), an analysis performed
by inputting and treating the full drainage area to the constructed wetland,
including treatment of the two additional (undisturbed) lanes and the remaining
upstream drainage area, results in a load reduction of 6.77 lbs/year as indicated
in Table 11.7. This is achieved by input of the post-development land use given
in Table 11.4 in to the Drainage Area tab of the spreadsheet, and treating the
area with a Level 1 constructed wetland.
Table 11.7 Summary of Output from VRRM Site Data Tab for Full Treatment Area
Total Impervious Cover Treated (acres) 5.81
Total Turf Area Treated (acres) 1.70
Total TP Load Reduction Achieved in D.A. A (lb/yr) 6.77
Hydrologic computations for required design storms for flood and erosion
compliance must be computed to verify that design components meet guidelines.
Table 11.9 Unadjusted CN from Runoff Reduction Channel and Flood Protection
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 1.41 1.91 3.50
RVDeveloped (in) with Runoff Reduction 1.41 1.91 3.50
Adjusted CN 85 85 85
This volume should be distributed proportionally to total volume for each inlet
location based on runoff generated from a 1” rainfall. For this design, a single
inlet will introduce flow from the impervious and turf portions of the project (from
the I-295 lanes and shoulder), and a secondary inlet will introduce flow from the
AP − !D G.
C=
P − !D + 1
(11.2)
where:
C
P
= runoff (inches)
1
= rainfall (inches)
!D
= potential maximum retention after runoff begins (inches)
= initial abstraction (inches) = 0.2 1
1000
1= − 10
@
(11.3)
1000 .
Substituting Equation 11.3 into Equation 11.2 yields:
XP − 0.2 @ − 10 Y
C=
1000
B + 0.8 @ − 10
(11.4)
Equation 11.4 can now be used with computed curve numbers for the road and
forest components using information from the channel and flood protection tab of
the Runoff Reduction Spreadsheet to compute runoff for each from a 1” rainfall.
1000 L, .
X1 L, − 0.2 − 10 L, Y
C¸ = 85 = 0.17 inches
D„ 1000 L,
1 L, + 0.8 − 10 L,
85
1000 L, .
X1 L, − 0.2 77 − 10 L, Y
C% = = 0.05 inches
€ 1000 L,
1 L, + 0.8 − 10 L,
77
Using the drainage area ratios of each, the proportion of the total sediment
forebay volume that should be used for each inlet area is calculated as:
7.51 KRJN\
1&¸ D„ 0.17 L, ×
= 15.3 KRJN\ = 0.083 ≅ 3.3
1&% € 7.79 KRJN\ 0.025 1
0.05 L, ×
15.3 KRJN\
The deep pool should have a volume of approximately 25% of the design
treatment volume. Therefore, the deep pool volume ('„ ) is calculated as:
The deep pool volume listed above includes the volume of the sediment
forebays, calculated above as 3,449 ft3. The remaining 2,299 ft3 will be split
evenly between the central pool and the micro-pool at the outlet/overflow
location.
This Level 1 BMP will be designed to hold 50% of the treatment volume above
the wet pool elevation for an extended drawdown of at least 24 hours. Therefore,
the remainder of the treatment volume not in the storage area above the wet pool
(50%) and in the deep pools (25%) is 25%.
Assuming average deep pool depths of 48”, the surface area of the deep pools
are estimated as:
5,748 PQ 0
= 1,437 PQ .
4 PQ
Initially, the designer must assume surface area ratios (or percentages)
corresponding to each component of the constructed wetland (deep pools, high
marsh, and low marsh). Initially, assuming that the deep pools contain
approximately 8% of the total surface area each, enables computation of an
initial estimate of total surface area.
1,437 PQ .
= 17,963 PQ .
0.08
Approximately 70% of the cell surface area should have elevations ranging
between -6” and +6” (measures relative to the normal pool) as high marsh areas.
The low marsh area is initially estimated as the remaining 22% of the total area,
or 3,952 ft2.
Assuming an average low marsh depth of 1’, and an average submerged high
marsh depth of 0.25’, with the surface areas of the high marsh and low marsh
components as computed above, the estimated volume of submerged storage in
these areas can be calculated as:
Because this estimate is slightly less than the required 5,748 ft3, minor
adjustments to yield the necessary volume must be made to the grading plan. It
is assumed that the adjustment will be made in the low marsh area, with an
adjusted volume during final design of 4,176 ft3, but that the assumed surface
area of 3,952 ft2 can be carried forward in computations.
Summaries of the surface area and volume components of the various zones are
found in Tables 11.11 and 11.12, respectively. Note that only 50% of the volume
is shown in Table 11.12 since the 24-hour extended drawdown volume that is
temporarily stored above the permanent pool comprised 50% of the treatment
volume.
After determining the required surface areas and storage volumes, the stage-
storage relationship can be created. This curve is necessary for routing design
storm hydrographs through the BMP to determine adequacy. Table 11.13
presents the stage-storage relationship for this constructed wetland. The floor
elevation of the wet pools has been measured to be at approximately elevation
48’, above mean sea level, with the permanent pool set at 52’.
The proposed facility is designed to store 50% of the treatment volume above the
permanent pool. The elevation corresponding to the treatment volume of 22,992
ft3 is approximately 52.72’ (see Table 11.12). The volume above the permanent
pool elevation (52.00’) is required to have a drawdown of at least 24 hours. In
addition, the 1-year 24-hour storm should have a maximum ponding depth of less
than 1’, or a maximum elevation of 53.0’. It is recommended that the designer
use hydraulic design software that has the ability to model a multi-stage
structure. It is typical that many iterations may be necessary to meet multiple
criteria related to the design.
Routing calculations showing the maximum depth of the 1-year 24-hour storm
are shown in Table 11.15. Note that during routing calculations it is assumed
that the starting pool elevation is at the permanent pool elevation of the facility
(52’). The maximum elevation of the 1-year 24-hour storm as shown in Table
11.14 is 52.97’, which is lower than the maximum allowed elevation of 53.00’.
The conveyance pipe providing outfall from the riser structure is a 30” RCP pipe
at 2.0% slope. The discharge pipe has been designed to convey the 10-year
outflow to a point of adequate discharge (calculations for adequacy not shown).
Modified puls routing calculations of the 10-year 24-hour post-development storm
using the outlet structure and rating curves developed above result in a peak
elevation of 53.36’ and a peak outflow of 42.31 cfs. See abbreviated set of
routing calculations for 10-year storm in Table 11.16. An emergency spillway for
conveyance of the 100-year storm should be designed with a crest elevation of
approximately 53.40’. The 100-year storm elevation is required to have a
maximum elevation less than 4’ above the maximum pool elevation, or 56.00’.
Calculations for the 100-year storm yield a peak elevation of 53.99’ if a 20’ wide
emergency spillway is installed at 53.40’ (calculations not shown).
To ensure that the wetland permanent marsh does not become dry during
extended periods of low or absent inflow, the designer must perform a water
balance calculation. Equation 11.1, discussed previously, includes a brief
analysis of minimum pool depths related to drought conditions. The minimum
deep pool depth recommended is 22”. The deep pools in this analysis are
proposed at 48”, which exceeds the minimum depth for drought conditions.
A secondary analysis is performed for the anticipated low flow conditions. For
Hopewell, Virginia, the month with the lowest average precipitation is February,
at 3.19”. Using this average rainfall, Equation 11.1 is evaluated as:
15.3 KR × 0.41
8B = 3.19 L, × − 8 L, − 7.2 L, − 6 L, = 28 L,RℎN\
0.41 KR
This exceeds the recommended minimum deep pool depth (22”) during drought
conditions.
Step 9 - Landscaping
A wet pond is a basin that retains a portion of its inflow in a permanent pool so
the basin is typically wet, even during non-runoff producing periods. Generally,
stormwater runoff is stored above the permanent pool, as necessary, to provide
flood control and/or downstream channel protection. Wet ponds are capable of
providing downstream flood control, water quality improvement, channel erosion
control, and the reduction of post-development runoff rates to pre-development
levels.
Typically, wet ponds are difficult to incorporate on VDOT projects due to the area
required for the footprint of the facility. Also, because wet ponds provide no
runoff reduction credit, they should be used only if additional water quality
improvement credit is required after all other options are exhausted.
Requirements shown herein are modifications to specifications found in Virginia
Stormwater Design Specification No. 14, Wet Pond (DCR/DEQ, 2013), for
specific application to VDOT projects.
Wet ponds can be an important part of the stormwater quality treatment train, but
they require special design considerations to minimize maintenance. Otherwise,
they can become a maintenance burden, particularly if sediment accumulate or if
flows cause erosion. Good design can eliminate or at least minimize such
problems.
It is important to design wet ponds within the limits established for CDAs. Too
much or too little runoff can result in performance issues and the need for
subsequent repairs or reconstruction.
12.2.9 Karst
Wet ponds are not recommended for installation in or near karst areas. If the
geotechnical report indicates that less than 3’ of vertical separation exists
between the bottom of the pond and the underlying soil/bedrock interface, a wet
pond should not be used due to the risk of sinkhole formation.. Exceptions may
be granted by VDOT. If ponds are employed in karst areas, the following criteria
must apply:
• A minimum of 6’ of unconsolidated soil material exists between the bottom
of the basin and the top of the karst layer.
• Maximum temporary or permanent water elevations within the basin do
not exceed 6’.
• Annual maintenance inspections must be conducted to detect sinkhole
formation. Sinkholes that develop should be reported immediately after
they have been observed, and should be repaired, abandoned, adapted or
observed over time following the guidance prescribed by the appropriate
local or state groundwater protection authority
• A liner is installed that meets the requirements outlined in Table 12.2
below.
12.2.12 Floodplains
The construction of a wet pond within floodplains is strongly discouraged. When
this situation is deemed unavoidable, critical examination must be given to
ensure that the proposed basin remains functioning effectively during the 10-year
flood event. The structural integrity and safety of the basin must also be
evaluated thoroughly for 100-year flood conditions as well as the basin’s impact
on the characteristics of the 100-year floodplain. When basin construction is
proposed within a floodplain, construction and permitting must comply with all
applicable regulations under FEMA’s National Flood Insurance Program.
The wet pond is designed to manage the design treatment volume within a
permanent pool, multiple pool cells, or a combination of the permanent pool and
extended detention storage. The design shall be based on the treatment volume
of the contributing drainage area, less any volume treated (and reduced) by
upstream BMPs to determine the permanent pool volume, as well as any other
pond features (forebays, etc.).
Length/Width ratio OR Flow path = 2:1 or Length/Width ratio OR Flow path = 3:1 or
more; Length of shortest flow path / overall more;
length 4 = 0.5 or more Length of shortest flow path/overall length4 =
0.8 or more
Standard aquatic benches Wetlands more than 10% of pond area
Turf in pond buffers Trees, shrubs, and herbaceous plants in pond
buffers; Shoreline landscaping to discourage
geese
No Internal Pond Mechanisms Aeration (preferably bubblers that extend to or
near the bottom or floating islands
1
Runoff volume reduction can be computed for wet ponds designed for water reuse and
upland irrigation.
2
Extended Detention may be provided to meet a maximum of 50% of the Level 2 Treatment
Volume; Refer to Design Specification 13 for ED design
3
At least three internal cells must be included, including the forebay
4
In the case of multiple inflows, the flow path is measured from the dominant inflows (that
comprise 80% or more of the total pond inflow)
5
Due to groundwater influence, slightly lower TP and TN removal rates in coastal plain, CSN
Technical Bulletin No. 2. (2009)
Sources: CSN (2009), CWP and CSN (2008), CWP (2007)
For Level 2 designs, the storage volume is divided into multiple cells (Table
12.3), of which one cell can be a sediment forebay. Typically, other cells related
to a Level 2 design consist of deep pools and wetland cells (see Section 11,
Constructed Wetlands). Typically, the pool configuration is designed to maximize
hydraulic residence time in order to boost the sediment and pollutant removal
functioning of the facility. This includes design elements such as incorporation of
long flow paths and relatively shallow depths through a portion of the facility. In
Level 2 facilities, the allowed extended detention volume cannot exceed a depth
of 12” above the permanent pool elevation; however, additional storage volume
can extend to 5’ above the permanent pool when providing storage for
downstream channel and flood protection. Non-erodible berms or simple weirs
should be used instead of pipes to separate multiple pond cells.
where:
DP = Average design depth of the permanent pool, inches
ET = Summer evapotranspiration rate, inches (assume 8”)
INF = Monthly infiltration loss (assume 7.2 @ 0.01 in/hr)
RES = Reservoir of water for a factor of safety (assume 24”)
MB = Measured baseflow rate to the pond, if any (convert to inches)
Translating the baseflow to inches refers to the depth within the pond. Therefore,
the following equation can be used to convert the baseflow, measured in cubic
feet per second (ft3/s), to pond-inches:
where:
The internal slope of the pond bottom should be at least 0.5% to 1% to ensure
flow proceeds within the facility toward the outlet structure.
The ratio of the shortest flow path (from closest inlet to the outlet structure)
should be a minimum of 0.5 for Level 1 designs and 0.8 for Level 2 designs. If
these requirements cannot be met, the drainage area contributing to the closest
inlet may not constitute more than 20% of the total contributing drainage area to
the wet pond.
12.3.7 Benching
All pools with a depth of 4’ or greater shall employ safety and aquatic benches.
A safety bench (intended to reduce the risk of someone falling into the pond) with
a minimum width of 10’ should be employed just above the permanent pool
elevation. The cross slope shall be approximately 2%. Slopes below the bench
should not exceed 3H:1V. If pond side slopes above the permanent pool are
less than 5H:1V, benching is not required.
Aquatic benches (shallow areas just inside the perimeter of the normal pool that
promote growth of aquatic and wetland plants and also provide a safety feature)
shall be employed around the perimeters of forebays, micropools, and wetland
pools. Depth shall range between 0 and 18”. A 10’ minimum width is required
for forebays, micropools and deep pools.
“The foundation material under the dam and the material used for the
embankment of the dam should be an AASHTO Type A-4 or finer and/or meet
the approval of the Materials Division. If the native material is not adequate, the
foundation of the dam is to be excavated and backfilled a minimum of 4’ or the
amount recommended by the VDOT Materials Division. The backfill and
embankment material must meet the soil classification requirements identified
herein or the design of the dam may incorporate a trench lined with a membrane
(such as bentonite penetrated fabric or an HDPE or LDPE liner). Such designs
shall be reviewed and approved by the VDOT Materials Division before use.”
The design of the dam should employ a homogenous embankment with seepage
controls or zoned embankments, or similar design in accordance with
recommendations of the VDOT Materials Division.
12.3.12 Embankment
The top width of the embankment should be a minimum of 10’ in width to provide
ease of construction and maintenance. The design of the dam should be in
accordance with Appendix A: Earthen Embankments of the Introduction to the
New Virginia Stormwater Design Specifications, as posted on the Virginia
Stormwater BMP Clearinghouse web site:
https://www.swbmp.vwrrc.vt.edu/wp-content/uploads/2017/11/Introduction_App-
A_Earthen-Embankments_03012011.pdf
A concrete cradle shall be used under the pipe to prevent seepage through the
dam. The cradle shall begin at the riser or inlet end of the pipe, and run the full
length of the pipe.
The design must specify an outfall that will be stable for the maximum (pipe-full)
design discharge (the 10-year design storm event or the maximum flow when
surcharged during the emergency spillway design event, whichever is greater).
The channel immediately below the pond outfall must be modified to prevent
If a gravity based drawdown system is not feasible, such as in areas with high
groundwater conditions, a pump wet well shall be provided for incorporation of
temporary pumps required to draw down the permanent pool for maintenance
activities.
A clay liner meeting the specifications shown in Table 12.3 should have a
minimum thickness of 12” with an additional 12” layer of compacted soil above. If
the pond is being constructed in Karst terrain, the liner must conform to criteria in
Table 12.4.
12.3.20 Landscaping
A landscaping plan must be provided that indicates the methods used to
establish and maintain vegetative coverage in the pond and its buffer. Minimum
elements of a plan include the following:
• Delineation of pondscaping zones within both the pond and buffer
• Selection of corresponding plant species
• The planting plan
• The sequence for preparing the aquatic and safety benches (including soil
amendments, if needed)
• Sources of native plant material
For more guidance on planting trees and shrubs in Wet Pond buffers, consult the
following:
• Cappiella et al (2006)
• DCR/DEQ's Riparian Buffer Modification & Mitigation Guidance Manual,
available online at:
http://www.deq.virginia.gov/Portals/0/DEQ/Water/Publications/RiparianBuf
ferManual.pdf
• Appendix E: Landscaping of the Introduction to the New Virginia
Stormwater Design Specifications , as posted on the Virginia Stormwater
BMP Clearinghouse web site:
https://www.swbmp.vwrrc.vt.edu/wp-
content/uploads/2017/11/Introduction_App-E_Landscaping_03012011.pdf
The required disturbed area data from Table 12.8 is input into the VRRM
Spreadsheet for Redevelopment (2015), resulting in site data summary
information shown in Table 12.7.
Table 12.7 Summary of Output from VRRM Site Data Summary Tab
Site Rv 0.71
Post-development TP Load (lb/yr) 125.69
Total TP Load Reduction Required (lb/yr) 97.92
It is important to note again that the values entered in the VRRM spreadsheet
(Table 12.6) are only the values for the disturbed area of the project. Although
other areas (105.00 acres total) drain to the proposed facility as described in the
problem statement, they are not part of the disturbed area, and should not be
entered as such in the VRRM Spreadsheet to compute required reductions.
Information for the full drainage area (Table 12.5) is then entered into the
Drainage Area tab of the VRRM Spreadsheet. A Level 2 wet pond is chosen for
the treatment BMP, and information is entered in the appropriate cells of the
spreadsheet, resulting in summary output shown in Table 12.8.
Table 12.8 Summary of Output from VRRM for Level 2 Wet Pond
Total Impervious Cover Treated (acres) 59.80
Total Turf Area Treated (acres) 34.20
Total TP Load Reduction Achieved in D.A. A (lb/yr) 109.25
In this case, the total phosphorus reduction required is 97.92 lbs/yr. The
estimated removal is 109.25 lbs/yr; therefore, the target has been met.
= × %!" + $
×% "
Once the has been calculated, the Treatment Volume for the 1.0”
runoff through the facility can be directly computed using Equation 1.1 for a
Level 2 facility.
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
VDOT Drainage Manual for appropriate levels of protection and design
requirements related to erosion and flood protection. However, hydrologic
computations are necessary to compute peaks to design components of the Wet
Pond.
Values for the 1-, 2-, and 10-year 24-hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site, those values are shown in Table 12.9. Curve numbers used for
computations should be those calculated as part of the Runoff Reduction
Spreadsheet (Virginia Runoff Reduction Spreadsheet for Redevelopment, 2014),
which in this case are unadjusted. The resulting unadjusted curve numbers for
all return periods are reported in the channel and flood protection tab of the
VRRM spreadsheet, with a value of 84, as shown in Table 12.10.
A sediment forebay will be included on the inflow side of the project. The
majority of runoff (>90%) will enter the facility from a single direction. Volume of
the sediment forebay is required to be designed to be a minimum of 0.25” of
runoff per impervious acre of contributing drainage area, or:
1 PQ 43,560 PQ
'³´µdN &³JN¶K¨ = 0.25 in ) - × 59.8 ac ) - = 54,268 PQ 0
12 L, 1 KR
As a Level 2 wet pond, the facility is required to either use multiple pools to store
the treatment volume below the permanent pool elevation, or provide extended
detention for up to 50% of the treatment volume (24-hour minimum drawdown)
within 1’ above the permanent pool. For this site, the second option will be used
to meet the requirements. In order to have some indication of elevations and
storage, the first step is to create a storage elevation table (Table 12.13) from
topographic data. The desire is to use existing site grades for the facility, to the
extent possible, in order to limit disturbance and earthwork required at the wet
pond site.
Initially, there are two particular elevations that need to be derived from the
stage-storage relationship. They are the elevation corresponding to the
treatment volume (8.0 acre-ft), and that corresponding to 50% of the treatment
volume (4.0 acre-ft). Based on linear interpolation, the elevation corresponding
to 50% of the treatment volume is 2027.34’, and that corresponding to the
treatment volume is 2029.03. Because the extended detention storage volume
cannot exceed 1’ (12”) above the permanent pool, a 50%-50% split is not
possible since 2029.03’ – 2027.34’ is 1.69’. Therefore, the permanent pool
elevation will be set at 2028.1’, which corresponds to a volume of 5.26 acre-ft.
Therefore, the permanent pool will store 66% of the volume, and the extended
detention portion will temporarily store the remaining 34%.
The proposed facility will be designed to store 34% of the treatment volume
above the permanent pool. The volume above the permanent pool elevation is
required to have a drawdown of at least 24 hours. It is recommended that the
designer use hydraulic design software that has the ability to model a multi-stage
structure. It is typical that many iterations may be necessary to meet multiple
criteria related to the design. Because these computations are not normally done
by hand, detailed orifice and grate sizing computations are not shown in this
document. If hand calculations are performed, the user is directed to the VDOT
Drainage Manual for detailed guidance on orifice and grate sizing calculations.
10
8
Discharge (cfs)
0
2024 2026 2028 2030 2032 2034 2036
Elevation (feet)
Next, drawdown (or empty time) calculations must be performed to ensure that
the selected orifice size meets the minimum drawdown of 24 hours for the
extended detention volume. Drawdown calculations using pond routing software
(employing the Modified Puls routing technique) are shown in Table 12.14.
Based on these calculations, the extended drawdown requirement is met. At this
point, the designer may wish to increase the orifice size in order to decrease the
drawdown time to a point closer to the 24-hour minimum; however, additional
channel protection requirements requires that discharge limitations must be
determined prior to increasing the orifice size.
To ensure that the wet pond does not become dry during extended periods of low
or absent inflow, the designer must perform a water balance calculation.
Equation 12.1 calculates a recommended minimum pool depth to ensure that
adequate pool volume will remain during drought conditions. The minimum deep
pool depth (prior to calculation) as recommended is 22”. The deep pools in this
Although there is minimal base flow into the wet pond area, it is negligible for
most of the year, and assumed to be 0, which is conservative. The equation
above evaluates to a minimum deep pool depth of 39.2”.
The total length of the facility along the flow path from the inflow to the outflow
point is 515’. The maximum width is 165’. Both of these measurements are
taken at the elevation of the permanent pool. The ratio evaluates to 515:165, or
3.12:1. Therefore, the Level 2 requirement of 3:1 or higher ratio has been
achieved.
Due to the direction of flow, the short circuiting ratio is not an issue for this wet
pond implementation since a very small percentage of the flow enters the pond
near the outlet.
Two requirements must be achieved for the Level 2 design. First, a minimum 10’
aquatic bench must be provided around the perimeter of the facility. Second, a
minimum of 10% of the pond surface area (at the permanent pool elevation) must
be wetland. The perimeter of the contour at the permanent pool elevation
(2028.1’) is 1,378’, and the area is 83,372 ft2. If the 10’ aquatic bench is
employed, the area will be approximately 13,207 ft2 (note that this is slightly less
than 1,378’ x 10’ since the 10’ offset is into the wet pool area), which should be
evaluated using CAD software. This area can be used to compute the wetland
areal coverage and determine if additional wetland area is required. The
percentage evaluates as:
13,207PQ .
× 100 = 15.8%
83,372PQ .
Therefore, additional wetland area is not required above that required for the
aquatic bench.
Many wet ponds and extended detention facilities have control structures that are
within the zone of saturation, which requires a full buoyancy analysis. In this
case, control structures are designed to be away from the main pool, and
embedded in the embankment outside the zone of saturation; therefore a
Step 12 - Landscaping
Specific guidance on plant species suitable for each zone can be found in the
Virginia DEQ Stormwater Design Specification No. 13, Constructed Wetland
(2013). Invasive species such as cattails, Phragmites, and purple loosestrife
should be avoided.
13.2.9 Karst
The presence of Karst topography places even greater importance on the
subsurface investigation. Implementation of extended detention facilities in Karst
regions may greatly impact the design and cost of the facility, and must be
evaluated early in the planning phases of a project. Construction of stormwater
management facilities within a sinkhole is prohibited. When the construction of
such facilities is planned along the periphery of a sinkhole, the facility design
must comply with the guidelines found in Chapter 5 of this Manual and
DCR/DEQ’s Technical Bulletin #2 “Hydrologic Modeling and Design in Karst.”
13.2.10 Wetlands
When the construction of an extended detention facility is planned in the vicinity
of known wetlands, the designer must coordinate with the appropriate local,
state, and federal agencies to identify the wetlands’ boundaries, their protected
status, and the feasibility of BMP implementation in their vicinity. In Virginia, the
Department of Environmental Quality (DEQ) and the U.S. Army Corps of
Engineers (USACOE) should be contacted when such a facility is proposed in
the vicinity of known wetlands.
13.2.12 Floodplains
The construction of extended detention facilities within floodplains is strongly
discouraged. When this situation is deemed unavoidable, critical examination
must be given to ensure that the proposed basin remains functioning effectively
during the 10-year flood event. The structural integrity and safety of the basin
must also be evaluated thoroughly under 100-year flood conditions as well as the
basin’s impact on the characteristics of the 100-year floodplain. When basin
construction is proposed within a floodplain, construction and permitting must
comply with all applicable regulations under FEMA’s National Flood Insurance
Program.
To avoid performance issues, the facility must be sized properly for the target
Treatment Volume. However, oversizing the storage provided in the BMP, as
compared to what is required to achieve the BMP’s performance target, can
decrease the frequency of maintenance needed and, thus, potential life-cycle
costs. Oversizing, where feasible, can also help VDOT achieve its broader
pollution reduction requirements associated with its DEQ MS4 Permit and the
Chesapeake Bay TMDL. Oversizing options are likely to involve the adjustment
of detention times and may require prior approval by DEQ.
Designers should use the BMP design treatment volume, TvBMP (defined as the
treatment volume based on the contributing drainage area, TvDA, minus any
volume reduced by upstream runoff reduction practices) to size and design the
wet features and extended detention volume. If additional detention storage is
proposed for channel protection and/or flood control, designers should use the
adjusted curve number reflective of the volume reduction provided by the
upstream practices as well as the ED Pond (Level 2) to calculate the developed
condition energy balance detention requirements. (Refer to Chapter 11 of the
Virginia Stormwater Handbook, 2nd Edition, Draft (DCR/DEQ 2013)).
“The foundation material under the dam and the material used for the
embankment of the dam should be an AASHTO Type A-4 or finer and/or meet
the approval of the Materials Division. If the native material is not adequate, the
foundation of the dam is to be excavated and backfilled a minimum of 4’ or the
amount recommended by the VDOT Materials Division. The backfill and
embankment material must meet the soil classification requirements identified
herein or the design of the dam may incorporate a trench lined with a membrane
(such as bentonite penetrated fabric or an HDPE or LDPE liner). Such designs
shall be reviewed and approved by the VDOT Materials Division before use.”
If the basin embankment height exceeds 15’, or if the basin includes a permanent
pool, the design of the dam should employ a homogenous embankment with
seepage controls or zoned embankments, or similar design in accordance with
the recommendations of the VDOT Materials Division.
13.3.7 Embankment
The top width of the embankment should be a minimum of 10’ in width to provide
ease of construction and maintenance.The design of the dam should be in
accordance with Appendix A: Earthen Embankments of the Introduction to the
New Virginia Stormwater Design Specifications, as posted on the Virginia
Stormwater BMP Clearinghouse web site:
https://www.swbmp.vwrrc.vt.edu/wp-content/uploads/2017/11/Introduction_App-
A_Earthen-Embankments_03012011.pdf
13.3.9 Benching
A safety bench (intended to reduce the risk of someone falling into the pond) with
a minimum width of 10’ should be employed just above the high water elevation.
The cross slope shall be approximately 2%. Sloped below the bench should not
exceed 3H:1V.
Aquatic benches (shallow areas just inside the perimeter of the normal pool that
promote growth of aquatic and wetland plants and also provide a safety feature)
shall be employed around the perimeters of forebays, micropools, and wetlands
pools. Depth shall range between 0 and 18”. A 4’ minimum width is required for
forebays, and 6’ for micropools.
The internal slope of the pond bottom should be at least 0.5% to 1% to ensure
flow proceeds within the facility toward the outlet structure.
For a Level 2 facility the basis is required to have a length to width ratio of 3:1 or
greater, with the widest point typically observed at the outlet end. For a Level
The shortest flow path (distance from closest inflow point to outlet structure) must
be used to calculate the ratio of this distance to the overall flow (maximum)
length in the facility. For a Level 1 facility, this ratio must be 0.4 or higher. This
ratio is increased to a minimum value of 0.7 for a Level 2 design. If these ratios
cannot be met, the inflow locations violating these ratios should not contain more
than 20% of the contributing drainage area.
A clay liner meeting the specifications shown in Table 13.3 should have a
minimum thickness of 12” with an additional 12” layer of compacted soil above. If
the pond is being constructed in Karst terrain, the liner must conform to criteria in
Table 13.4.
A concrete cradle shall be used under the pipe to prevent seepage through the
dam. The cradle shall begin at the riser or inlet end of the pipe, and run the full
length of the pipe.
The design must specify an outfall that will be stable for the maximum (pipe-full)
design discharge (the 10-year design storm event or the maximum flow when
surcharged during the emergency spillway design event, whichever is greater).
The channel immediately below the pond outfall must be modified to prevent
erosion and conform to natural dimensions in the shortest possible distance.
Outlet protection should be provided consistent with guidelines established in the
VDOT Drainage Manual (2014).
13.3.19 Landscaping
A landscaping plan must be provided that indicates the methods used to
establish and maintain vegetative coverage within the ED Pond and its buffer.
Minimum elements of a plan include the following:
• Delineation of pond-scaping zones within both the pond and buffer
• Selection of corresponding plant species
• The planting plan
• The sequence for preparing the wetland bed, if one is incorporated with
the ED Pond (including soil amendments, if needed)
• Sources of native plant material
• The landscaping plan should provide elements that promote diverse
wildlife and waterfowl use within the stormwater wetland and buffers.
• The planting plan should allow the pond to mature into a native forest in
the right places, but yet keep mowable turf along the embankment and all
access areas. The wooded wetland concept proposed by Cappiella et al.,
(2005) may be a good option for many ED Ponds.
• Woody vegetation may not be planted or allowed to grow within 15’ of the
toe of the embankment nor within 25’ from the principal spillway structure.
• A vegetated buffer of native plants that requires minimal maintenance
should be provided that extends at least 25’ outward from the maximum
water surface elevation of the ED Pond. Permanent structures (e.g.,
buildings) should not be constructed within the buffer area. Existing trees
should be preserved in the buffer area during construction.
• The soils in the stormwater buffer area are often severely compacted
during the construction process. The density of these compacted soils can
be so great that it effectively prevents root penetration and, therefore, may
lead to premature mortality or loss of vigor. As a rule of thumb, planting
holes should be three times deeper and wider than the diameter of the
root ball for ball-and-burlap stock, and five times deeper and wider for
container-grown stock.
• Avoid species that require full shade, or are prone to wind damage. Extra
mulching around the base of trees and shrubs is strongly recommended
as a means of conserving moisture and suppressing weeds.
The required site data from Table 13.5 is input into the VRRM Spreadsheet for
Redevelopment (2014), resulting in site data summary information shown in
Table 13.7.
It is important to note that the values in Table 13.5 are only the values for the
disturbed area of the project. Although other areas (combining to 23.60 acres
total) were described in the problem statement (Table 13.6), they are not part of
the disturbed area, and should not be entered as such in the VRRM Spreadsheet
to compute required reductions.
Table 13.8 Summary of Output from VRRM Site Data Tab for Full Treatment Area
Total Impervious Cover Treated (acres) 4.60
Total Turf Area Treated (acres) 19.00
Total TP Load Reduction Achieved in D.A. A (lb/yr) 5.16
In this case, the total phosphorus reduction required is 3.70 lbs/yr. The
estimated removal is 5.16 lbs/yr; therefore, the target has been met.
= × %!" + $
×% "
Once the has been calculated, the Treatment Volume for the 1.0”
runoff through the facility can be directly computed using Equation 1.1 for a
Level 2 facility.
Hydrologic computations for required design storms for flood and erosion
compliance are not shown as part of this example. The user is directed to the
VDOT Drainage Manual for appropriate levels of protection and design
requirements related to erosion and flood protection.
Values for the 1-, 2-, and 10-year 24- hour rainfall depth should be determined
from the National Oceanographic and Atmospheric Administration (NOAA) Atlas
14 and entered into the “Channel and Flood Protection” tab of the spreadsheet.
For this site (Lat 37.2978, Long -79.9586), those values are shown in Table 13.9.
Curve numbers used for computations should be those calculated as part of the
runoff reduction spreadsheet (Virginia Runoff Reduction Spreadsheet for
Redevelopment, 2014). For runoff draining to the ED facility, results from the
runoff reduction spreadsheet are shown in Table 13.10, and result in adjusted
curve numbers of 66, 67 and 67 for the 1-, 2- and 10-year storms, respectively.
Table 13.10 Adjusted CN from Runoff Reduction Channel and Flood Protection
1-year 2-year 10-year
Storm Storm Storm
RVDeveloped (in) with no Runoff Reduction 0.43 0.70 1.67
RVDeveloped (in) with Runoff Reduction 0.38 0.65 1.62
Adjusted CN 66 67 67
Due to the location of this ED facility, all runoff enters the facility at a single
forebay location. If multiple inlets were used along the perimeter, then the
various sediment forebays would be sized proportional to the runoff volume
entering each. For sizing methodology, see design problem in Section 11,
Constructed Wetlands.
Of the total 5,619 ft3 of required forebay storage, 80% (4,495 ft3) will be in a
sediment forebay, and 20% (1,124 ft3) will be in the micropool at the outlet
structure location.
Approximately 70% of the cell surface area should have elevations ranging
between -6” and +6” (measured relative to the normal pool) as high marsh areas.
The remaining 30% of the constructed wetlands area should have depths ranging
from -6” to -18” below the permanent pool. Since the total volume of the
constructed wetlands is known, the surface area may be approximated as:
³QK´ '³´µdN = 0.70 × NJKMN 8N»Qℎ ™LMℎ + 0.30 × NJKMN 8N»Qℎ >³¼ ∗ JNK
JNK = 19,717PQ .
Note that this is only an approximation and should be verified through creation of
a storage elevation curve. The average depth for the high marsh area is taken
as the average between the normal pool and 6” in depth (0.25’), while that of the
low marsh is taken as the mean of the low marsh depth range, or 1’.
Surface areas of the deep pools (sediment forebays and micropool), assumed to
have an average depth of 4’, is approximated from the volume computed in Step
2 as:
5,619 PQ 0
= 1,405 PQ .
4 PQ
Therefore, the total estimated surface area of the facility permanent pool is the
sum of 19,717 ft2 and 1,405 ft2, or 21,122 ft2 (0.48 acres). Note that the VRRM
process requires the wet pond areas to be calculated as impervious areas in the
VRRM spreadsheet. This likely means that design is an iterative process—
unless the area for the detention facility is known at the beginning of design. For
purposes of this example, this impervious area of the wet pool is assumed to be
included in the impervious area shown in Table 13.5.
Summaries of the surface area and volume components of the various zones are
found in Tables 13.12 and 13.13, respectively. Note that only 40% of the
volume is shown in Table 13.13 since the 24-hour extended drawdown volume
that is temporarily stored above the permanent pool comprised 60% of the
treatment volume.
After determined the required surface areas and storage volumes, the stage-
storage relationship can be determined. This curve is necessary for routing
design storm hydrographs through the BMP to determine adequacy. Table
13.14 presents the stage-storage relationship for this ED facility. The floor
elevation of the wet pools has been measured to be approximately elevation
1130’, above mean sea level.
The proposed facility is designed to store 60% of the treatment volume above the
permanent pool. The elevation corresponding to the treatment volume of 37,462
ft3 is approximately 1135.04’ (see Table 13.14). The volume above the
permanent pool elevation (1,134.00’) is required to have a drawdown of at least
36 hours. It is recommended that the designer use hydraulic design software
that has the ability to model a multi-stage structure. It is typical that many
iterations may be necessary to meet multiple criteria related to the design.
Because these computations are not normally done by hand, detailed orifice and
grate sizing computations are not shown in this example. If hand calculations are
performed, the used is directed to the VDOT Drainage Manual for detailed
guidance on orifice and grate sizing calculations.
To ensure that the wetland permanent marsh does not become dry during
extended periods of low or absent inflow, the designer must perform a water
balance calculation. Equation 11.1 (Section 11) calculates a recommended
minimum pool depth to ensure that adequate pool volume will remain during
drought conditions. The minimum deep pool depth as recommended is 22”. The
deep pools in this analysis are proposed at 48”, which exceed the minimum
depth for drought conditions.
23.6 × 0.35
8B = 2.87 L, × − 8 L, − 7.2 L, − 6 L, = 28 L,RℎN\
0.48
This analysis shows that the design pool depth of 48” is expected to be
adequately maintained (drawing down to 28”) even during the month with the
lowest average precipitation. If the equation is evaluated for the average July
precipitation of 4.06” of rainfall, the estimated maintainable pool depth is 49”.
The first step is to compute the buoyant force acting on the riser. The buoyant
force is a function of the volume of water displaced by the riser. The calculation
presented here also assumes that the basin ground is saturated, thus including
the buoyant force of the volume of water displaced below grade by the riser
footing. A VDOT SWM-1 is used in this design example.
Due to the use of the SWM-1 trash rack and the 30” outfall culvert, a 5’ inner
diameter (6’ outer) manhole will be used. Displacement of water volume from the
riser crest (DI-7 elevation) is calculated using the volume of the manhole [from
base (typically invert minus 8”)] to maximum storm depth. In this case, the total
height is 1135.50’ (DI-7) minus 1128.33’ (base), or 7.17’.
'„ = ¾ 3PQ .
7.17PQ = 202.73 PQ 0
The unit weight of water is 62.4 lb/ft3, with the buoyant force computed as:
´¶
&¿Z = 202.73 PQ 0 × 62.4 = 12,650 ´¶
ÀD}
PQ 0
The downward force is computed by calculating the summing the weights of the
manhole, grates, and SWM-1 used for the structure.
´¶
Weight of manhole riser:
&€ = 5.84PQ A¾ 3PQ .
− ¾ 2.5PQ . G × 150 = 7,568 ´¶
€
PQ 0
The weight of the SWM-1 trash rack is approximately 120 lbs, and the weight of
the DI-7, Type 1 grate and top is approximately 2,000 lbs.
Finally, the concrete weight lost due to the presence of the 4.5” orifice must be
´¶
subtracted:
& = 0.5PQ A¾ 0.1875 PQ . G × 150 = 8.3 ´¶
PQ0
€‰
2,829 ´¶ + 7,568 ´¶ + 120 ´¶\ + 2,000 ´¶\ − 8.3 ´¶\ = 12,509 ´¶\
Because this weight is less than the buoyant force (with applied safety factor) of
15,813 lbs, additional weight must be added. The simplest method of providing
this additional weight is to add additional concrete to the bottom of the manhole.
If the manhole is ordered with additional depth (below the invert out), the invert
may be placed on site with A3 concrete filling the base of the manhole up to the
invert out elevation. This will provide the additional ballast necessary to
counteract the buoyant force. The additional depth needed can be directly
calculated using the difference in forces and the interior radius of the manhole
(5’) as:
Therefore, when ordered, the interior manhole invert should be 1127.88 or less,
and concrete will be placed in the bottom up to the pipe invert out of 1129.00.
Step 10 - Landscaping
Specific guidance on plant species suitable for each zone can be found in the
Virginia Stormwater Design Specification No. 13, Constructed Wetland
(DCR/DEQ, 2013). Invasive species such as cattails, Phragmites, and purple
loosestrife should be avoided.
Schueler, T. 2008. Technical Support for the Baywide Runoff Reduction Method.
Chesapeake Stormwater Network. Baltimore, MD.
www.chesapeakestormwater.net