Schedule B New
Schedule B New
(Schedule-B)
Description of Project
1. DESCRIPTION OF PROJECT
Start End
Elevation Slope Length Radius
Chainage Chainage
(m) % (m) (m)
(m) (m)
South 2353.745
0.00 - 1794.428 1.470 -
Portal m
North
- 4487.590 1780.735 -2.000 1775.027 -
Portal
Vertical 1821.960
2337.570 2487.570 - 150.000 4319.576
Curve (max)
1.4 Portals:
At the ends of the tunnel (portal zones) gentle curves should be designed in plan view
providing sufficient visibility as recommended by Indian IRC: SP:91-2019. For the
tunnels proposed adequate alignment solutions at the portals are chosen with respect to
the geological and topographical ground conditions and requirements on approach road.
S. Section Radius
ID Chainage (m) Easting (m) Northing (m)
No. Length (m) (m)
ST Straight Line
1.10 Superelevation
The current tunnel alignment is planned to rise from the South portal with a
gradient of 1.47% for a length of 2337.570m approx. followed by a vertical curve
(Crest) of 150.000m approx. in length and 4319.576m radius. The tunnel then
climbs down for a length of 1775m approx. with a radius of 2.000%.
A summary of all required alignment elements from Indian and International
Standards are given in Table 4 and compared with the proposed alignment
elements
Alignment Elements:
2. DESIGN SPECIFICATIONS
Mussoorie tunnel is designed for multi-radius twin tube unidirectional tunnel of length
4.487 km approximately. The design criterion for tunnel cross-section is considered
as per Indian Standards IRC: SP: 48, IRC: SP: 73 for Roads, and IRC: SP: 91 for
road tunnels. Tunnel utilities are designed as per IRC: SP: 91-2019. Tunnel design
and its approach are elaborated in Volume-II Design Report.
The proposed unidirectional twin-tube road tunnel cross-section is planned to
accommodate the horizontal and vertical traffic clearances and other required
utilities. Both tunnel tubes are designed to incorporate two traffic lanes. The table
below details the guidelines as per IRC SP 91 for the features to be accommodated
in the cross section.
The utilities planned above are shown in figure displaying typical cross-section of
Mussoorie tunnel. Some of the standard requirements considered in this cross
section are discussed hereafter.
The tunnels are planned as twin tubes enabling unidirectional traffic in each tube.
The tunnel alignment is of 4.487 km in length. For tunnels of length more than
1500m, IRC: SP:91 recommends adopting unidirectional twin tube tunnels to
overcome the limitations of bi-directional single tube tunnels. The traffic study
carried out in Mussoorie also demands a twin-tube tunnel to accommodate the
projected traffic.
The tunnel design is not provided with shoulder since both sides have clearance
of 0.5m of edge strips and is protected with a kerb on the edges.
Plain 10,000
Rolling 8500
Subgrade (mm)
Lay-byes of dimensions 3.5m width and 30m length are planned at every 500m
opposite to cross passages. The planned lay-bye dimension is a feasible
alternative to codal provisions, considering industrial practices. Additional refuge
vehicular parking or parking lay-byes are not provided in the tunnel cross-
section.
Schedule-B
(Value Addition Works)
Annex – I
(Schedule-B)
Description of Two - Laning
1. TUNNELS
End
S. Start Chainage Length Proposed
Location Chainage
No. (km) (m) Rehabilitation
(km.)
Nil
New 2-lane
ITBP Rock Single tube
1 0+000 4+488 4488 1x11.5m
temple area Unidirectional
Tunnel
New 2-lane
ITBP Rock Single tube
2 0+000 4+488 4488 1x11.5m
temple area Unidirectional
Tunnel
The tunnels shall be single tube (1x2-lane) configuration as per the chainages
mentioned in the above table. The tunnel cross section shall be 2 lanes as per
TCS enclosed in Appendix B-I of Schedule B.
Other tunnel ancillary works not limited to drainage, water proofing, tunnel
illumination including electrical distribution panels sub-station on either north or
south sides portal of each tunnel, including O&M Centre and service utility
building, furnishing, signage’s, emergency facilities, etc. shall be provided as
specified in IRC: SP:84-2019, IRC: SP:91-2019 and specification as per
schedule-D.
It should be noted that the minimum drifting scheme has to be adopted as per
the specifications and drawings but shall be revised (by EPC contractor) based
upon the geological findings of the ground and if required the stages shall be
increased to achieve the desired excavation stability and hence the provisioning
of resources shall be accounted for any such requirements.
1.3 The details of the distribution of rock- mass conditions on the Basis of
Rock Mass Rating are as below:
Characteristics
per site visit
Design Chainage respective rock Class as per
RMR rating (%)
Rock
From Total RC
To (Ch.) RC1 RC3 RC4 RC5 RC6
(Ch.) (m) 2
Moderately
1.4 Based on the surficial study during the field survey the geological study
along the tunnel alignment, the support measures recommended are as
follows:
Notes:
• The Above details of the tunnel have been prepared as per the field survey and
geological/geotechnical investigation.
• RC1, RC2, RC3, RC4, RC5 & RC6 are rock classes based on. Marinos’12, Marinos ’07 &
Bieniawski’89 rock mass classifications and tunnel behaviour types.
• SC A, SC B, SC C, SC D, SC E & SC F are the tunnel support categories applicable to different
types of rock classes mentioned in the table.
• Above details for the tunnel support system has been prepared as per the Geological data
collected from the field visit and detailed geotechnical investigation done along the tunnel
alignment and portal areas. This shall form Geotechnical Baseline Report (GBR) and any
variation in tunnel support system due to deviation from the Geotechnical Baseline report as
change of scope under the provision of the Article 13 of the EPC Contract agreement.
• RC1, RC2, RC3, RC4, RC5 & RC6 indicates classification based on Geological Mapping and
detailed geotechnical investigation. Six types of Tunnel Support have been designed for the
Tunnel (SC1 to SC6). Cost Matrix for working out the financial implication on account of
change in support pattern due to deviation from geotechnical baseline report as change of scope
under the provision of Article 13 of EPC Contract Agreement has already been mentioned.
• Provisions for Probe holes: In case of poor geological conditions, if required, where the
geological data collected during actual excavation so warrants, advance probe holes by
percussion or core drilling, as required, shall be drilled ahead of the tunnel faces to locate any
gas, flowing mass of rock, auriferous strata, geological disturbances (15-20 m length).
1.5 The Summary Details of the Support system of Tunnel is indicated in the
table below.
TYPE
Support
Classification
A B C D E F
Cost Variation P1 P2 P3 P4 P5 P5
Matrix
Classification
Rock Mass
83 60 47 37 25 19
Rating (RMR)
Head / Head /
Excavation Full Full Full
Head / Bench Bench / Bench /
Method Face Face Face Invert Invert
Extra
Excavation
- 25 50 150 300 350
Thickness
(mm)
Face Sealing - - 20 20 50 50
Bottom
- - - - 200 200
Sealing
Pipe Pipe
Fore Roofing 12 Roofing
Poling/Umbrella m long, 12 m
arch 4m long, 114 mm long,
Auxiliary Support - - - dia single
76 mm dia 114
overlap as layer mm dia
round length single
layer
Parameters Specifications
No. Of Targets 5
2. Multipoint Extensometers
Parameters Specifications
Displacement 50 mm
transducer range
Displacement 0.01 mm
transducer resolution
3. Pressure Cells
Parameters Specifications
Accuracy 0.5% FS
4. Strain Meter
Parameters Specifications
Sensitivity 1 μ strain
Parameters Specifications
Parameters Specifications
Parameters Specifications
Data Transfer The data transfer to Web DAS should occur through
Wireless Monitoring Gateway powered by AC and DC
power supply.
Vibrating Wire Wireless Sensor Node (VWWSN) for local logging and
Wireless Monitoring
Protection IP68
VW interface
connector
Specifications for
Sensor Node
9. Monitoring Software
Parameters Specifications
Software Modules
Expectations
Data Storage Database SQL database, open to 3rd Party Software Integration
Alarming Functionality The software shall send automated Alerts and Alarms
to define sets of conditions including tolerances for
displacement at any point via SMS and email to
specified stakeholders based on user defined
thresholds.
The software shall send the reports automatically to
multiple people or groups of people and at different
schedules to different groups with acknowledgement.
Protection & Access The Password shall be protected for access with 3
Control levels of privileges (incl. password lost option).