Clydeport Mooring Guidelines Jun 21
Clydeport Mooring Guidelines Jun 21
Clydeport Mooring Guidelines Jun 21
June 2021
INDEX
INTRODUCTION AND BACKGROUND
Item Description Page
1.0 General Overview 1
2.0 Harbour Authority Responsibilities 1
3.0 Risk Assessment 1
4.0 Communications 2
5.0 Training 3
6.0 Personal Protective Equipment (PPE) 3
7.0 Rope Handling 6
RESPONSIBILITIES AND EQUIPMENT/INFRASTRUCTURE
8.0 Berth Owners and Operators
8.1 Responsibilities 9
8.2 Shoreside Infrastructure 10
8.3 Mooring Arrangements 11
8.4 General Safety – Berths 13
9.0 Commercial Operators
9.1 Responsibilities 14
9.2 Self-Mooring 14
9.3 Vessel’s Mooring Equipment 14
9.4 Mooring Plans and the Master/Pilot Exchange 14
10.0 MOORING GUIDANCE
10.1 Heaving Lines 16
10.2 Damage, Incidents and Near Misses – Reporting 18
10.3 Mooring and Unmooring – Best Practice 18
10.4 Mooring Boat Operations 21
10.5 Unmooring 21
10.6 Barges 22
10.7 Additional Guidance for Ship’s Masters and Pilots 22
APPENDICES
A LEGAL BACKGROUND 23
B INDUSTRY GUIDANCE 24
INTRODUCTION AND BACKGROUND
The mooring and unmooring of vessels is potentially a hazardous activity. It is also an operation which
demands a high degree of teamwork. To be both efficient and safe, all involved must be properly trained
and equipped, and must have a clear understanding of the contribution made by others, as well as their
own role and responsibilities.
These Guidelines describe established good practice for the safe and efficient mooring and unmooring of
vessels and is published for all involved, be they Line Handlers, boatmen, tug crews, ship’s staff, masters,
pilots or berth operators.
Organisations should make reference to the legal background and industry guidance references detailed
in Appendix A and B to this document.
The Harbour Authority’s responsibility for mooring falls under Regulation 5 of the Dock Regulations 1988
which states that “Dock operations shall be planned and executed in such a manner as to ensure so far as
is reasonably practicable that no person will be exposed to danger” (1988).
Further, the Port Marine Safety Code places an obligation on harbour authorities to ensure that mooring
parties meet the industry’s competence standards and have access to appropriate training including
mooring processes and procedures referenced in their Marine Safety Management System.
Clydeport, as Statutory Harbour Authority (SHA), may license line handlers under the terms of the Clyde
Port Authority Confirmation Act 1965, as amended.
Risk assessments form the basis of safe harbour operations, both ashore and on water. Organisations are
required to prepare risk assessments for mooring operations, involving those carrying out the task. All
activities taking place within the harbour area should be risk assessed to ensure risk is reduced to ALARP
(as low as reasonably practicable). Those involved in mooring of vessels should be aware of the content
of such risk assessments relating to the work they are carrying out.
Dynamic risk assessment (DRA) is undertaken when carrying out a form of activity – whether routine or
unusual. This process assists the individual to effectively assess the unfolding situation. Responses can
be altered moment by moment to meet the risk. Examples of using a DRA and dealing with the
unexpected might be;
It is essential that good communications are established between all those involved in
mooring/unmooring of vessels within the port. All participants should be aware of their individual role.
VHF communication is considered to be the primary means of communication and is a vital component of
safe mooring operations. However, berth operators not employing Clyde Pilots may use an agreed
alternative means of communication between the vessel and the mooring supervisor. It is essential that
those on board the vessel, in the mooring boats and on the berth (both fore and aft of the vessel) are able
to communicate effectively. Once communications have been established and tested, mooring personnel
should keep transmissions to a minimum and should normally only call when in doubt, or in an emergency.
Berthing operations should be conducted on one dedicated VHF channel. VHF communications should be
established early with all involved in the mooring operation. Line Handlers, Coxswains, Tug Masters and
the Berth Operator should all be briefed on the mooring/unmooring plan and their role in it.
All persons engaged in work must be trained and assessed as competent for the role they are required to
perform by a competent person. These persons must have the physical capabilities required for each task
being undertaken.
Line Handlers must, through appropriate training, be made fully aware of the dangers of the quayside
environment and the task.
Supervisors should be trained, competent and experienced in the areas of work that they are supervising,
and/or have access to relevant competent advice and assistance.
Trainee Line Handlers require a high level of supervision until their competence is proven.
In addition, mooring personnel working on board mooring boats should have knowledge, as appropriate,
of mooring boat handling and machinery.
Refresher training is recommended at appropriate intervals to ensure all personnel involved in mooring
operations maintain currency of knowledge and are updated with any changes to procedure.
PPE for line handlers should be determined following risk assessment. As a general guide, PPE should be
fitted properly to the individual and may include a lifejacket or buoyancy aid, safety helmet (with chinstrap
worn), safety footwear (non-slip sole is recommended), hi-visibility clothing and gloves (providing a good
grip). Consideration should be given to waterproof clothing for all weather conditions. Some terminals
may require additional PPE, e.g. eye protection in dusty environments or where fuel or chemicals are
handled. In particular, lifejackets should always be worn and maintained in accordance with the
manufacturer’s instructions.
Line Handlers should be encouraged to check each other’s PPE is worn correctly.
https://www.youtube.com/watch?v=m-CmyKdy3MU
Regular servicing of lifejackets is vital and should be carried out in line with the manufacturers
recommendations. Service records should always be retained by the organisation.
Line handlers must be proficient rope handlers. The following illustrations show how to coil a rope
correctly and describe useful knots. These are key skills which should be incorporated into training plans
for Line Handlers.
By coiling rope properly, you can easily pick it up and use it as a heaving line quickly without having to
wind it up. A coil of rope is also less likely to snag, knot and cause injury.
A bowline creates a very secure loop in the end of a piece of rope or line. When under load it does not
slip and is difficult to untie.
2. RUNNING BOWLINE
The running bowline is simply a bowline, tied as above but around its own standing part, thus forming a
noose as in Image 3.
Usually used to tie a heaving line to a mooring rope tail or any smaller rope to a thicker rope.
Usually used to tie a heaving line to a mooring rope tail or any smaller rope to a thicker rope.
Useful knot to make something fast such a securing a coiled heaving line when not in use.
8.1 Responsibilities
Mooring is a “dock operation” as defined in the Health and Safety Executive Approved Code of Practice
and Guidance for Safety in Docks. The responsibility for planning mooring operations lies with the Berth
Operator.
The Berth Operator of a jetty or mooring buoy is also responsible for conducting a formal risk assessment
of the mooring operation at the berth and for ensuring that all equipment provided is fit for purpose and
well-maintained. In addition, good housekeeping of operational berths is vital with work areas kept clear
of hazards.
Where a large, new or unusual vessel is expected, careful planning should be carried out in advance. This
exercise should consider the following:
The Berth Operator, as the owner/operator of the fixed mooring infrastructure is responsible for the
condition of the berth, equipment and the need to ensure its suitability for the intended use. All
infrastructure and equipment is required to be of sufficient strength and assured accordingly. Such
mooring equipment includes but is not limited to:
• Bollards
• Fenders
• Quay/berth infrastructure
• Quick Release Hooks
• Pontoons
• Quay Ladders
• Capstans
• Mooring Buoys
• Swing Moorings/Buoys
• Any other equipment used to facilitate mooring
The berth operator should ensure that an appropriate, and documented, inspection, monitoring and
maintenance regime is in place to ensure that all mooring components are in a serviceable condition. It
is advisable to keep under review the safe capacity of existing mooring equipment, bearing in mind that
commercial vessels are generally increasing in size. Older bollards for example may no longer be fit for
purpose for modern vessels due to additional forces and it is advisable to test them to determine their
current SWL.
Berth Operators should ensure an appropriate person or supervisor is available on the jetty to oversee
the mooring operation.
The number of personnel employed in any mooring operation should be determined with due regard for
the size of the vessel, the prevailing operational circumstances, the weather, and the state of tide.
In all circumstances, sufficient personnel should be provided to ensure that individual Line Handlers or
Boatmen are not exposed to undue risk, and that the operation can be conducted safely and efficiently.
Due regard should also be given to the size, weight and scope of mooring lines to be handled. The practice
of mooring/unmooring using a single Line Handler ashore is strongly discouraged, except where the size
of the vessel and weight of mooring lines are such that the person concerned is not at risk.
Mooring Boat Crew and Line Handlers should be ready for work with mooring boats fully manned and
equipment checked in good time. Communications should be established with the vessel or Pilot.
Equipment requiring testing includes but is not limited to the following:
The mooring party supervisor should confirm, with the Berth Operator, the required mooring plan, and
any specific positioning requirements. VHF contact should be established with the vessel in good time to
check communications and confirm the plan and timings. The berthing arrangements should also be
agreed including any non-standard arrangements from the Pilot or Master. In complex situations, it may
be necessary for the supervisor to board the vessel in order to discuss arrangements with the
Pilot/Master.
It should be ascertained in advance whether fibre or wire moorings are to be used in order to ensure that
sufficient persons are available ashore to facilitate mooring.
Any specific requirement in respect of vessel position should be made known to the Mooring Supervisor,
who will relay the information to the Master or Pilot.
All equipment at the berth required for mooring should be checked before the operation commences.
Defects should be reported to the Mooring Supervisor and, if appropriate to the vessel Master or Pilot.
Shore cranes must be in the correct position for vessel berthing, ensuring that booms do not protrude
beyond the jetty. Cranes not required for loading/discharge, and other potential obstructions, should be
moved well clear so as not to obstruct bridge wings and bow flare.
Shore cranes should not be moved during berthing/unberthing operations, nor as the vessel is
approaching the berth.
Bridge position signs or manifold connection flags (prominent and illuminated at night) should be used on
the jetty to assist in positioning a vessel before landing.
Consideration should be given to provision of rope guides or running bars (where small ships are led to lie
alongside over low water) to reduce the risk of chaffed lines.
Ladders on jetties and dolphins should be properly maintained and checked regularly.
Mooring dolphins should be provided with appropriate safety rails and safetyn equipment.
At night and during poor visibility, the work area should be adequately lit.
Mooring bollards not available for use should be boxed over or painted red. Bollards which become
unusable for whatever reason should be reinstated to full serviceable condition as soon as possible and
should be clearly identified as out of service.
All persons engaged in the mooring operation should wear appropriate PPE.
A means of de-icing jetties and dolphins should be available for use as required.
Lifesaving equipment, capable of being used at all states of the tide, should be positioned at appropriate
intervals on a jetty.
Disposition of bollards should be such that not more than 2 moorings have to be placed on a bollard at
any one time. Recommend that berth owners make an assessment of the adequacy of the bollards to
deal with loads arising from more than 2 lines per bollard if required.
9.1 Responsibilities
Responsibility for co-ordinating a mooring operation lies with whoever has the conduct of the vessel, be
that the Master or the Pilot. It is not the task of those providing mooring assistance.
When berthing and un-berthing, it is the duty of the Master and Pilot to ensure that the vessel is handled
in a safe and controlled manner, having due regard to the safety of those on the berth, in mooring boats,
and the vessel’s crew. Care should be taken that undue strain is not put on springs or other mooring lines
and consideration should be given to the use of tugs over and above the recommended requirement in
adverse weather conditions.
9.2 Self-Mooring
Self-mooring is potentially a very dangerous activity and, in general, self-mooring and berthing of
commercial vessels is discouraged.
Regulation 4 of the Merchant Shipping (Means of Access) Regulations 1988 requires that access to and
from the shore be provided in a safe manner. The Merchant Shipping Act 1995 (Part IV) is also relevant
in this regard.
The mooring of vessels using members of the crew only, is considered to be potentially dangerous and
thus not an approved practice on the Clyde for vessels over 24 metres LOA. Shore Line Handlers should
normally be employed to undertake the mooring operation.
In only very exceptional individual circumstances will self-mooring be approved by the Port Authority, and
will require a full Risk Assessment and Method Statement from the vessel operator as required by the
Management of Health and Safety at Work Regulations 1999.
Masters are advised to note their obligations under the various regulations applying to this practice. It
must be stressed that that Master of a vessel who authorises self-mooring, remains personally
responsibility for the safety of its crew.
The Master should ensure that all mooring equipment is tested and ready for use ahead of arrival into
port. This includes but is not limited to winches and capstans and mooring lines to be prepared and ready
for use. Ship’s crew must be trained and competent to conduct mooring operations.
A copy of the ship’s General Arrangement plan and availability of ship’s lines should be provided in
advance to the port. A mooring plan generated by the port is then shared with the ship or its agent prior
to arrival.
Mooring plans should define breast, spring, head and stern lines. Where adverse weather is expected
consideration should be given to placing additional lines.
Line arrangements are crucial when securing a vessel against a structure such as a quay or berth. They
should be arranged in such a manner that it reduces the vessel’s movement against the berth, allowing
for tidal and wind forces whilst alongside.
The weighted end of a heaving line is usually formed into a knot known as a “monkey’s fist”. It is this knot
which gives weight to the line, but other knots or small sand bags can be used. The weight of the monkey’s
fist should be sufficient to allow the line to be thrown into the wind but should not be heavy enough to
cause injury should it inadvertently hit someone.
Occasionally, a ship may try to increase the weight of the heaving line by attaching things such as shackles,
bolts, metal bars etc. There have also been numerous reports of additional weights being placed inside
the monkey’s fist, such as heavy bolts. This practice is not acceptable and if these are found the linesman
should NOT accept the line and should report it immediately to their supervisor.
Dangerously weighted heaving lines are a serious hazard. Ship’s crew and Line Handlers should be aware
of the dangers.
The MCA has produced the following Safety Bulletin on Dangerously Weighted Heaving Lines and this
should be shared with all Line Handlers.
Any defects or damage to a berth or its infrastructure found before or occurring during the berthing
operation should be reported as soon as possible to the Berth Operator, the Master or Pilot of the vessel,
and to Clydeport via Estuary Radio.
Mariners are reminded that incidents or near misses should be reported to Clydeport, using the Marine
Incident Report Form available at https://www.peelports.com/marine-information?port=clydeport
(Publications and Forms folder).
Following consultation with experienced Line Handlers on the Clyde, the following has been identified as
best practice for line handling:
• Some vessels are occasionally using dangerously weighted heaving lines, which can cause injury. A
weighted line should not be accepted. Line Handlers should wear safety helmets, including wearing
chin straps at all times. Ship’s crew should be warned before heaving lines are thrown back onto a
ship.
• Badly maintained or defective mooring lines can be dangerous and should not be used. Where a Line
Handler sees that a defective line has been supplied, the situation should be reported immediately to
the vessel, which should provide a replacement.
• Line Handlers should keep clear of the jetty edge when hauling lines ashore. Lines under tension
should not be walked along a jetty. The weight should always be taken by one person whilst another
walks a slack line up the jetty. Line Handlers should be alert to the dangers posed by vehicles and
cranes moving in the vicinity.
• All mooring lines on a bollard should be “dipped” to facilitate prompt and easy release. Lines should
only be dipped when slack, and when the weight of the line is held by another person or stopper.
Where two Line Handlers are so engaged, careful co-ordination between them is essential as the
weight of the line is transferred to the bollard. Once a line has been placed on a bollard, slack should
be taken in order to keep the line clear of the water. Lines should only be tensioned on the specific
instruction of the Master or Pilot.
• Wire ropes are prone to snagging, particularly near the splice. Mooring gangs should be alert to this
risk and should take appropriate precautions.
• Forward and aft springs should not normally be put onto the same bollard, but if this is unavoidable,
they should always be dipped.
• In some circumstances, the Master or Pilot may instruct that breast lines are not to be run until the
vessel is alongside and in position.
• Line Handlers should not leave the berth until all lines have been made fast, and the Master and Pilot
are satisfied that the vessel is securely alongside and have indicated their agreement for the mooring
gang to stand down. Heaving lines and messengers should be returned to the ship or Berth Operator.
• On occasions when it is necessary for a Line Handler to board a vessel underway to assist in the
mooring operation, embarkation should be via a correctly rigged pilot ladder. Such Line Handlers
must report their presence on board to the vessel Master and remain under the direction of the
Master or Pilot throughout their time on board the vessel.
At times, the weight of a manoeuvring ship is taken on a single mooring line. Line Handlers must be aware
of snap back zones as very high loads come onto such ropes. Similar loads can be produced by the ship’s
mooring winches when heaving on ropes or wires. Personnel must keep clear of the snap back zone
whenever mooring lines are tensioned.
Mooring/Line Handling Boats used within Clydeport are required to register with the Port Authority, be
declared as “fit for purpose” by the operator, carry the appropriate safety equipment and be equipped
with effective VHF radios. They should be sufficiently powerful to handle the size and weight of any
mooring lines. Ideally, mooring boats should be substantial steel vessels, designed for mooring/line
handling operations and be fitted
with equipment appropriate for the
safe handling of ropes/wires.
Care should be taken at all times to keep mooring boats clear of vessel propellers and tugs assisting in the
mooring/unmooring operation. The Coxswain in charge of a boat should not allow it to come close to the
stem or stern without having first obtained clearance from the Master or Pilot via VHF radio.
Whenever possible, lines should always be run straight forward and aft. Once made fast to a bollard or
buoy, heaving should not commence until the boat Coxswain has signallled that the boat is safe and clear.
Mooring lines should be lowered into the boat and flaked down such that they can be readily hauled up
the side of the jetty or dolphin. Mooring lines should be securely lashed in the boat before the boat
proceeds to the jetty or dolphin, and in a manner which facilitates quick release in event of an emergency.
A suitable cutting instrument should be immediately available in case of emergency. Lines should not be
allowed to enter the water, particularly in the vicinity of propellers or thrusters.
Where a strong on-shore wind or tidal set exists, extreme caution should be taken by all involved to ensure
that a mooring boat does not get trapped between the vessel and the jetty. In circumstances where such
risk potentially exists, close liaison between the Coxswain in charge of the mooring boat and the Master
or Pilot is essential.
A Coxswain in charge of a mooring boat should alert the Master or Pilot via VHF as soon as he considers
that the situation is becoming dangerous. He should also take whatever avoiding action he deems
necessary to ensure the safety of personnel.
Where there is a risk of the mooring boat being trapped between the vessel and the jetty, consideration
should be given to running springs to the jetty using heaving line/messenger from the ship.
10.5 Unmooring
Unmooring should not commence until the ship or shore gangway has been properly secure, or brow
landed.
No mooring line should be slackened or released except on the specific instruction of the Master or Pilot.
Likewise, slackened lines should not be released until advised by the Master or Pilot as such lines may still
be required for warping purposes.
Line Handlers should be aware that added tension can be put on a mooring line during an unberthing
operation, and especially when using engines to “spring off”. Extra strain can also be put on mooring lines
when using tugs, or when wind and tide are setting the vessel away from the berth.
A mooring line should never be let go under tension. Once a line has been released from a bollard or
hook, it should be walked clear of any obstruction, unless it has been released using a triggered slip hook.
All personnel in the vicinity should stand well clear.
When releasing a mooring line, care should be taken to hold it by the side of the eye, and to avoid hands
getting between the line and the hook or bollard.
When releasing a dipped rope, sufficient slack should be pulled through the eye of any other ropes, so
that the eye of the line to be released may be pulled over the top of the hook or bollard. This will facilitate
clearing any subsequent jam as and when the line is put under tension.
Where a mooring is badly jammed, it may be necessary to slacken briefly other lines on the same bollard,
whilst taking care not to release them.
When releasing mooring lines at the stern, including after breast lines and back-springs, they should be
controlled and if possible kept clear of the water to reduce the risk of fouling propellers. Berths can
sometimes provide messenger lines to assist the process. They should not be released until the onboard
mooring team confirm they can immediately haul onboard.
10.6 Barges
The mooring/unmooring operation of a barge remains at all times under the control of the Bargemaster
and/or Pilot. All involved should only take instructions from the Bargemaster or Pilot.
Anchors should be cleared away and winches and capstans should have been checked before arrival at
the berth.
All mooring lines not on tension winches or drums should be coiled or flaked neatly on deck ready for use.
Before bringing a mooring boat under the bow to collect a line, the ship’s anchors should have been
secured, it not in use or being prepared for use. Similarly, a mooring boat should not be allowed under
the stem or stern whilst thrusters and engines present a hazard. Boats should keep well clear of a dredged
anchor.
Where there is an on-shore wind or tidal set, particular care should be taken to ensure that the mooring
boats are well clear before allowing the vessel to settle onto the berth. The running of lines should be
monitored carefully. Attentive watch should be maintained on the appropriate VHF channel. Where the
berth configuration and size of vessel permits, consideration should be given to running springs using
heaving lines from the ship instead of using mooring boats.
When paying out mooring lines from the ship, care should be taken to avoid excessive weight for the Line
Handlers by keeping the bight to a minimum and under control.
Ship’s mooring lines should not normally be used for towing operations except in an emergency or where
a proper risk assessment has been carried out. Where such use is authorised, extreme caution should be
taken to ensure that the size and condition of the line are suitable and that it is kept slack and under
control when lowering to the tug and making fast. Crew should stand well clear and be alert to the
possibility of the hawser coming under sudden tension or a parted line snaking or recoiling.
Care should be taken to ensure that the vessel is moored in the correct position, and as required by the
Berth Operator, before mooring personnel are stood down.
Appropriate lifesaving equipment should be supplied onboard the vessel at the mooring stations and
should be available for immediate use.
When running mooring lines ashore, they should normally be passed via the mooring boat crew, unless
otherwise instructed by the Master or Pilot.
The Master and Pilot of a vessel equipped with controllable pitch propellers or stern thrusters should be
aware of the inherent dangers which exist in relation to after mooring lines.
The Pilot should not leave the bridge or break communication with the Coxswain/Line Handlers until the
mooring operation is complete.
This appendix identifies relevant legislation relating to mooring operations and associated activities. By
adhering to the legislation and guidance, safe practices develop and liabilities can be better managed. All
organisations involved in mooring operations are encouraged to be familiar with, and consider how best
to incorporate, their legal obligations within mooring practices.
Regulation 4 of the Merchant Shipping (Means of Access) Regulations 1988 requires that access to and
from the shore be provided in a safe manner. The Merchant Shipping Act 1995 (Part IV) is also relevant
in this regard.
Section 3 – General duties of employers and self-employed to persons other than their employers.
Section 8 – Duty not to interfere with or misuse things provided pursuant to certain provisions.
This regulation places duties on people and companies who own, operate or have control over work
equipment. PUWER also places responsibilities on business and organisations whose employees use work
equipment, whether owned by them or not.
Port Marine Safety Code (PMSC) 2016 and the Guide to Good Practice (GtGP) 2018
Harbour Authorities have the powers in byelaws and directions to regulate the mooring of vessels in the
Harbour. The Marine Safety Management System should detail the use of these powers.
This document was jointly created between the Health and Safety Executive (HSE) and Port Skills and
Safety (PSS). It is aimed at companies operating in the UK ports industry with responsibility for the safe
design, construction, operations, management, maintenance of ports and terminal facilities and activities
to allow said organisations to make improvements within the ports industry.
The ship owner/Master has a responsibility to ensure a safe means of access and egress. SIP014 gives
further guidance on this.
This Marine Guidance Note considers the whole operation rather than the individual safety aspects,
details, and specific areas of interest considered during risk assessments for mooring operations.
This Code is published by the Maritime and Coastguard Agency (MCA) and endorsed by the National
Maritime Occupational Health and Safety Committee, UK Chamber of Shipping, Nautilus International and
the National Union of Rail, Maritime and Transport Workers (RMT) as best practice guidance for improving
health and safety on board ship. It is intended primarily for merchant seafarers on UK-registered ships.
The Code is addressed to everyone on a ship regardless of rank or rating, and to those ashore responsible
for safety, because the recommendations can be effective only if they are understood by all and if
everyone cooperates in their implementation. Those not actually engaged in a job in hand should be
aware of what is being done, so that they may avoid putting themselves at risk or causing risk to others
by impeding or needlessly interfering with the conduct of their work.