PMP Math Formulas
PMP Math Formulas
PV=FV/(1+ i)n
Present value of money You enter info here Formula components
Future value 158,000 158000
Interest 0.06 1.06
Years 6 1.41851911
Rounded decimal Enter nothing here 1.419
Present value $ 111,346.02
Future Value
FV=PV x (1+ i)n
Future value of money You enter info here Formula components
Present value 265,000 265000
Interest 0.06 1.06
Years 4 1.26247696
Rounded decimal Enter nothing here 1.262
Future value $ 334,430.00
Net Present Value You enter info here Year Formula components
Project Investment -100000 0 $ (100,000.00)
Return year 1 50000 1 $ 47,169.81
Return year 2 35000 2 $ 31,149.88
Return year 3 65000 3 $ 54,575.25
Return year 4 80000 4 $ 63,367.49
Return year 5 125000 5 $ 93,407.27
Net Present Value $ 189,669.70
Three-Point Estimate
Optimistic 20
Most likely 60
Pessimistic 90
Estimate 57
Budget at completion
Actual costs
Earned value
Planned value
Cost variance
Schedule variance
Cost performance index
Schedule performance index
Estimate at completion
Estimate to complete
To-complete performance index (BAC)
To-complete performance index (EAC)
Variance at completion
$ 750,000.00
25%
32%
$154,000
750,000
154,000
187,500
240,000
33,500
-52,500
1.22
0.78
616,000
462,000
0.94
1.22
134,000
Formula Results
EAC=AC+Bottom-up ETC NA
EAC=AC+(BAC-EV) 716,500.00
EAC=BAC/CPI 616,000.00
EAC=AC+[(BAC-EV)/(CPI x SPI)] 745,360.00
Communications Channels
n(n-1)/2
Number of stakeholders 1004
n-1 1003
Multiplication 1007012
Division and result 503506
Risk event Probability Impact Ex$V
A 0.6 -45,000 -27000
B 0.2 -30,000 -6000
C 0.7 -12,000 -8400
D 0.5 -45,000 -22500
E 0.2 -37,000 -7400
F 0.25 45,000 11250
G 0.6 -23,500 -14100
38000
26450
Point of Total Assumption
PTA=[(Ceiling Price – Target Price)/Buyers Share Ratio] + Target Cost