Code of Practice For Access and Working Scaffolds
Code of Practice For Access and Working Scaffolds
€35
Code of Practice for Access and Working Scaffolds
Table of Contents
Foreword 1
1.0 Introduction 3
1.1 Background 3
1.7.2 Designers 11
1.7.4 Contractors 13
1.7.5 Workers 14
1.8 Illustrations 15
1.9 Definitions 15
i Health and Safety Authority
Code of Practice for Access and Working Scaffolds
2.3.1 Layout 29
3.2 Materials 36
3.2.2 Standards 36
3.2.3 Transoms 36
3.2.4 Ledgers 37
3.2.5 Couplers 37
3.3 Stability 37
3.3.1 Foundations 38
ii
Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.3.2 Ties 40
3.3.2.4 Returns 46
3.3.4 Bracing 48
3.4.1 Decking 54
3.4.2 Toe-Boards 54
3.5 Guard-Rails 55
3.6.2 Sheeting 55
3.6.3 Fans 56
iii
Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.8.2 Signs 63
3.9.5 Stability 66
3.9.7 Bracing 67
3.9.8 Castors 67
3.10.3 Lightning 71
iv
Health and Safety Authority
Code of Practice for Access and Working Scaffolds
5.2 Modification 76
5.3 Maintenance 77
6.0 Dismantling 78
6.1 Stability 78
7.0 Competence 79
7.1.1 Training 80
7.1.2 Experience 81
v
Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Foreword
The Health and Safety Authority (by virtue of section 60 of the Safety, Health and
Welfare at Work Act 2005), following consultation with the statutory Advisory
Committee on Construction Safety (referred to as the Construction Safety Advisory
Committee), the Construction Industry Federation, the Irish Congress of Trade
Unions and the general public (through the Authority’s website), and with the
consent of Mr Billy Kelleher TD, Minister of State at the Department of Enterprise,
Trade and Employment, publishes this Code of Practice entitled “Code of Practice
for Access and Working Scaffolds”.
The aim of this Code of Practice is to provide practical guidance to scaffold erectors,
contractors and users of scaffolding on the requirements and prohibitions set out in
the relevant statutory provisions.
In particular, but not exclusively, this Code of Practice provides practical guidance
as to the observance of the provisions of:
This Code of Practice comes into effect on 1st January 2009. Notice of publication
was published in the Iris Oifigiúil of 2nd December 2008. It replaces the Code of
1 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Practice for Access and Working Scaffolds issued by the Authority in 1999 in
accordance with the Safety, Health and Welfare at Work Act 1989.
61. (1) Where in proceedings for an offence under this Act relating to an
alleged contravention of any requirement or prohibition imposed
by or under a relevant statutory provision being a provision for
which a code of practice had been published or approved by the
Authority under section 60 at the time of the alleged
contravention, subsection (2) shall have effect with respect to
that code of practice in relation to those proceedings.
Robert Roe
Assistant Chief Executive Officer and Secretary to the Board
2 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
1. Introduction
1.1. Background
The Code of Practice for Access and Working Scaffolds was first published in 1999.
The Code was the result of a joint initiative by the Health and Safety Authority, the
Construction Industry Federation and the Irish Congress of Trade Unions to
improve the standard of scaffolding. It was drafted in consultation with the
organisations represented on the Advisory Committee on Construction Safety.
This revised edition of the Code of Practice takes into account technical progress
and recent changes to health and safety legislation.
The Code gives recommendations and practical guidance on the erection, use,
inspection and dismantling of simple access and working scaffolds. It also gives
recommendations and practical guidance on the training and instruction of those
erecting, dismantling and using scaffolds.
The Code deals mainly with system scaffolds as these are the most common
scaffolds used in Ireland. It also contains outline guidance on the erection of basic
tube and fitting scaffolds. The Code does not give detailed recommendations or
guidance on special scaffolds such as cantilever, truss-out or slung scaffolds.
The previous Code was in line with the recommendations of BS 5973, 1993: Code
of practice for access and working scaffolds and special scaffold structures in steel.
This standard was withdrawn in 2004 and replaced by I.S. EN 12811 Part 1, 2004:
Temporary works equipment – Scaffolds – Performance requirements and general
design.
The main changes in I.S. EN 12811 Part 1, 2004 from BS 5973, 1993 include:
the definition of six service load classes, some with partial area loads;
3 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
the definition of seven width classes or “ranges” whose minima range from
0.6m to 2.4m. The range of each class is typically 0.3m. Compliance with the
requirements of this clause precludes the use of ledger bracing, which is
generally used on tube and fitting scaffolds;
the requirement that the gaps between platform units do not exceed 25mm;
the requirement for a minimum unimpeded area along the full length of the
working area;
a reduction in the number of working platforms in use for light duty, general
purpose and heavy duty scaffolds. When in use a scaffold is considered to
have one platform with 100% of the service load and one adjacent platform
(above or below) with 50% of the service load;
in the absence of wind, a scaffold shall have applied at the working area, on
every bay, a notional horizontal load applied separately parallel and
perpendicular to the bay;
tie patterns and their design are not included in this code of practice. For
tube and fitting scaffolds, refer to the design standards for an appropriate tie
pattern. For proprietary or system scaffolds, follow the erection manual from
the scaffold manufacturer.
4 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The requirements for façade scaffolds are dealt with in I.S. EN 12810 Part 1, 2004:
Façade scaffolds made of prefabricated components – Part 1: Products
specifications and I.S. EN 12810 Part 2, 2004: Façade scaffolds made of
prefabricated components – Part 2: Particular methods of structural design.
Falling from a height is one of the most common causes of accidental death and
serious injury in the construction industry. Scaffolding that is adequately erected
and maintained can prevent many such accidents.
System scaffolding has become the most common type of scaffolding in use due to
its ease of erection, ease of use and reduced labour requirements. A system
scaffold is a scaffold made of prefabricated elements and designed and
manufactured in accordance with I.S. EN 12810 Part 1, 2004 or an equivalent
standard. Each type of system scaffolding consists of a range of components such
as standards, ledgers, transoms and base plates and has its own specific erection
requirements.
5 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Tube and fitting scaffolding is constructed from steel tubing and several types of
couplers. Properly constructed, it forms a robust structure since the ledgers and
standards are usually continuous across several bays or lifts.
6 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Where the risks cannot be avoided, a risk assessment should be performed. The
risk assessment should be based on the hazards in relation to the specific scaffold,
e.g. adjacent overhead power lines, poor ground conditions or vulnerability to
vehicle impact. It should assess how serious the risks are.
The risk assessment should take account of the nature of the work to be carried
out, the loads and the height from which falls may occur.
The person undertaking the risk assessment needs to consider two aspects of the
scaffold:
the likelihood that someone could be injured during the erection, use or
dismantling of the scaffold; and
The greater the likelihood and/or severity will result in an increased risk that
someone could be injured.
Appropriate precautions should then be taken to control the risk and to prevent
injury. These precautions should be detailed in the safety statement and/or the
safety and health plan as appropriate.
Throughout the risk assessment process full account should be taken of the General
Principles of Prevention, which are contained in Schedule 3 of the Safety, Health
and Welfare at Work Act 2005 and reproduced in Table 1. These general principles
set out a hierarchy of control measures that apply to all places of work.
7 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The risk assessment for most scaffolding erection, use and dismantling will show
that the level of risk is high unless there is a good standard of planning, design,
equipment, training, supervision and checking to ensure safety.
8 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The main duty holders for any project involving scaffold structures include
suppliers, project supervisor for the design process (PSDP), designers of scaffold
structures, project supervisor for the construction stage (PSCS), contractors and
workers.
9 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
10 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
preparing a written safety and health plan for any project where construction
will take more than 500 person days or 30 working days or where there is a
Particular Risk and deliver it to the client prior to tender;
preparing a safety file for the completed structure and giving it to the client;
1.7.2. Designers
Designers of permanent structures and temporary scaffolds have duties which
include:
identifying any hazards that their design may present during construction
and subsequent maintenance;
taking account of any existing safety and health plan or safety file;
where no PSDP has been appointed, informing the client that a PSDP must be
11 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
appointed; and
appointing a safety adviser where there are more than 100 persons on site;
notifying the Authority and the client of non-compliance with any written
directions issued.
12 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
For example the PSCS should ensure that arrangements are in place to
communicate the requirements of the scaffold users to the scaffold erectors.
1.7.4. Contractors
Contractors, including sub-contractors and specialist scaffolding contractors, have a
very significant range of responsibilities under the relevant statutory provisions.
These duties include:
providing the PSCS with information required for the safety file, for
forwarding to the PSDP;
reporting accidents to the Authority and to the PSCS where an employee can
not perform his or her normal work for more than three days;
complying with site rules and the safety and health plan and ensuring that
their employees comply;
appointing a safety officer where there are more than 20 persons on a site or
more than 30 employed in total directly by the contractor;
13 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
All contractors using a scaffold must be satisfied that an inspection has been
undertaken, as required. This can be achieved by looking at the report of
inspections.
1.7.5. Workers
Under the relevant statutory provisions, workers, including scaffold erectors, have
responsibilities such as:
14 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Scaffold erectors should ensure that, at the time of handing over the scaffold to the
contractor, the scaffold is fit for its intended purpose and is in a safe and stable
condition.
Any subsequent alteration that may be required during the use of the scaffolding
should only be undertaken by a trained and competent scaffolder.
1.8. Illustrations
The illustrations used in this Code of Practice show a type of system scaffold that is
in common use in Ireland. The illustrations are intended to apply to simple access
and working scaffolds in general. They do not supersede or replace the illustrations
or arrangements contained in the system manufacturer’s erection instructions.
The illustrations are schematic and in some cases may not show all of the
scaffolding components. For example toe-boards have been omitted in some
figures for clarity.
Scaffolding erectors and users must refer to the appropriate European standard and
the manufacturer’s instructions.
1.9. Definitions
For the purposes of this Code of Practice, the following definitions apply (see also
Figure 3).
Base plate is a plate used for spreading the load in a standard over a greater area.
15 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Node is a theoretical point where two or more members are connected together.
Platform unit is a unit (prefabricated or otherwise) that supports a load on its own
and that forms the platform or part of the platform and may form a structural part
of the working scaffold.
Right angle coupler is a coupler used for connecting two tubes crossing at a right
angle.
Sleeve coupler is a coupler used for joining two tubes located co-axially.
Swivel coupler is a coupler used for connecting two tubes crossing at any angle.
Working area is the sum of the platforms in one level, which provides an elevated
safe place for people to work on and to have access to their work.
System width (SW) is the maximum width class of Table 1 of I.S. EN 12811-1,
2004 that can be realised between the standards.
17 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Butting tube is a tube that butts up against the façade of a building or other
surface to prevent the scaffold moving towards that surface.
Castor is a swivelling wheel secured to the base of a vertical member for the
purpose of mobilising the scaffold.
Check coupler or safety coupler is a coupler added to a joint under load to give
security to the coupler(s) carrying the load.
End guard-rail is a guard-rail placed across the end of a scaffold or used to isolate
an unboarded part of the scaffold.
Joint pin is an expanding fitting placed in the bore of a tube to connect one tube
to another coaxially (see also Spigot).
Knee brace is a brace across the corner of an opening in a scaffold to stiffen the
angles or to stiffen the end support of a beam.
Movable tie is a tie that may be temporarily moved for the execution of work.
Non-movable tie is a tie that will not be moved during the life of a scaffold, as
18 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Reveal pin is a fitting used for tightening a reveal tube between two opposing
surfaces.
Reveal tie is the assembly of a reveal tube with wedges or screwed fittings, and
pads, if required, fixed between opposing faces of an opening in a wall together
with the tie tube.
Scaffold board is a softwood board generally used with similar boards to provide
access, working platforms and protective components such as toe-boards on a
scaffold.
Sole board is a timber, concrete or metal spreader used to distribute the load from
a standard or base plate to the ground.
Spigot is an internal fitting to join one tube to another coaxially (see also Joint
pin).
Spigot pin is a pin placed transversely through the spigot and the scaffold tube to
prevent the two from coming apart.
Sway transom is a transom extended inwards in contact with a reveal or the side
of a column to prevent the scaffold moving sideways.
Fragile surface means a surface, including fittings that would be liable to fail if a
person’s weight were to be applied to it in reasonably foreseeable circumstances.
19 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Supporting structure means any structure used for the purpose of supporting a
working platform and includes any plant used for that purpose.
(a) in the course of obtaining access to or egress from any place, except by a
staircase in a permanent place of work, or
(b) at or below ground level, from which, if measures required by this Part
were not taken, an employee could fall a distance liable to cause personal
injury and any reference to carrying out work at height includes obtaining
access to or egress from such place while at work.
20 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
21 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The high rates of activity and change on construction sites, together with the high
level of risk associated with scaffolding work, require a correspondingly high level
of safety management to prevent accidents and ill health. The five steps listed in
this section provide a practical template for the systematic management of
scaffolding operations.
22 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
list who is responsible for choosing the type of scaffold to be used on site and
give a procedure for determining the situations where a scaffolding design
would be required;
23 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The written plan should deal with the assembly, use and dismantling of the
scaffold. The plan may be in the form of a standard plan supplemented by
information on the particular scaffolding in question. The plan should be kept on
site in the Safety and Health Plan.
A copy of the plan, including any instructions it may contain, must be kept available
to persons concerned in the assembly, use, dismantling or alteration of scaffolding
until it has been fully dismantled.
The planning process involves the contractors who will use the scaffolding, the
scaffolding designer and the scaffolding erector. The planning process should
address the following areas.
24 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Site survey
Where they do not have prior knowledge of the site, a competent person or
scaffolder should undertake, on behalf of the scaffolding contractor, a survey
of the location where the scaffolding is to be erected. The survey should be
carried out before the design or erection of the scaffold and should consider
the risks that exist on site.
Recommendations
Where a scaffolder makes reasonable recommendations to the contractor in
relation to the scaffold, the contractor should implement these. If a
contractor fails to fully apply the recommendations given by a competent
scaffolder, then the contractor may be contravening the requirements of the
Safety, Health and Welfare at Work Act 2005.
25 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The written plan is transformed into action during the implementation stage.
Successful implementation requires that the following issues be addressed.
Responsibilities
Individual responsibilities should be clearly communicated by the contractor
and the scaffolder. Persons should be given the authority and resources to
carry out their responsibilities and individuals should be held accountable for
their successes or failures in performing their duties.
Communication
Relevant information relating to design, scheduling, loading etc. or contained
in safety statements or the safety and health plan should be communicated
to those who need that information. For example those performing periodic
safety inspections need to know the maximum design imposed load and tie
spacing, and those erecting the scaffold need to have copies of the system
scaffold erection instructions available.
Documentation
Appropriate documentation must be kept available on site. Such
documentation will include safety statements, safety and health plans,
scaffolding plans and inspection records, e.g. “Report of results of
inspections of Work Equipment for Work at a Height” (see Appendix C). Any
defect or issue noted in a scaffolding inspection record must be signed off as
rectified when the particular item is attended to and made safe.
Where defects are found they should be rectified. The root cause of serious or
recurring defects should be identified and corrective action taken to prevent further
recurrence.
The review stage helps to make each job a learning experience so that the next job
can be performed more effectively. The following questions should be asked:
Was the implementation adequate so that the job was completed as planned?
Were the planned checks carried out and did the necessary corrective action
take place?
28 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
2.3.1. Layout
The initial layout will have a significant impact upon the safety of the completed
scaffold. When considering the layout the following points should be remembered.
The scaffold should be laid out so as to reduce the gap between the structure
and the scaffold to a minimum, except where guard-rails will be erected
adjacent to the structure.
Scaffolding contractors must specify the system of scaffolding in use, and provide
copies of the manufacturer’s guidelines to the Contractor and the Project Supervisor
for the Construction Stage (PSCS).
Where the contractor intends to load materials onto the scaffold by crane or
29 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
All other forms of scaffold, including special scaffolds, should be subject to design
and calculation by a competent designer.
Sections 6 and 10 of I.S. EN 12811 Part 1, 2004 provide technical data for the
structural design of scaffolds.
For illustrative purposes, typical examples where design and calculation may be
necessary include:
system scaffolds erected in areas where the wind pressure exceeds that
specified in I.S. EN 12810 Part 1, 2004 or where the design wind speed
exceeds that specified by the scaffolding manufacturer;
system scaffolds where the maximum height, tie spacing, imposed loads, bay
widths or number of working lifts exceeds the manufacturer’s
recommendations;
scaffolds where the tie or anchorage capacity is less than 6.25kN (637kg);
tube and fitting scaffolds where the height exceeds 50m for unsheeted
scaffolds and 25m for sheeted scaffolds;
scaffolds where the bottom transoms or ledgers have been omitted to allow
pedestrian access;
scaffolds where the first line of ties is more than 4m above the base of the
scaffold;
scaffold buttresses;
30 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
scaffolds where the allowable bearing pressure of the ground may not be
adequate to support the scaffold.
Refer to Appendix E for a range of guidance documents on the use of I.S. EN 12811
Part 1.
The PSDP and the PSCS should, at an early stage, seek the co-operation of building
designers in permitting the attachment of non-movable ties to the building
structure where such attachment is reasonably practicable.
31 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
erection or block laying at the edges of concrete floor slabs, the platform
should be maintained as close as practicable to the working level.
Where movable ties are provided, replacement ties should be installed before
existing ties are removed to facilitate plasterers, glaziers or other trades.
32 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The information should include the use for which the scaffold has been designed or
tested, and any information necessary to ensure that the scaffolding may be
erected, dismantled and used safely. The supplier should provide a complete set of
instructions that are sufficient to ensure the safe erection, use and dismantling of
the scaffold.
Scaffolding contractors must specify the system of scaffolding in use, and provide
copies of the manufacturer’s guidelines to the contractor and the PSCS.
conditions for use of the equipment, including instructions for its safe use
33 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3. Erection of Scaffolds
3.1. Safe Erection and Dismantling
The scaffolding contractor should carry out a risk assessment relating to the type of
scaffolding operations to be conducted at the site. The safety statement of the
scaffold erection contractor and, where appropriate, the site safety and health plan
should identify the hazards that erecting a scaffold on the site is likely to present
and specify the necessary precautions.
The Safety, Health and Welfare at Work (Construction) Regulations 2006 and the
Safety, Health and Welfare at Work (General Application) Regulations 2007 require
persons at work to be protected from the danger of falling, either by the provision
and use of collective safeguards such as adequate working platforms and guard-
rails or, where this is not practicable, by the provision and use of safety nets or
personal protective equipment such as suitable fall arrest systems (incorporating
safety harnesses, lanyards and anchorages).
The General Principles of Prevention (see Section 1.7) set out the hierarchy of
control measures that designers, contractors and employers should implement.
Collective safeguards should be specified in the safety statement and/or safety and
health plan. These will normally include, where possible, the use of ladders or stairs
and the placing of decking and guard-rails on each platform before scaffolders go
onto it or else as soon as practicable. Where scaffolders will be working on a
standard-width scaffold for only a very short time, they may work off a three-
board-wide platform provided that guard-rails are installed immediately following
the installation of the boards.
Where the necessary collective safeguards will be inadequate during certain phases
of the work, personal protective equipment, e.g. nets, fall arrest systems, should
be used to supplement the collective safeguards.
34 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
cantilever scaffolds;
truss-out scaffolds;
slung scaffolds;
work in confined spaces such as sewers, deep excavations, lift wells and
shafts, deep basements or sumps, where rescue may be required; and
Other workers and the public should be effectively excluded from the work areas by
signs and/or solid barriers. Where persons cannot be excluded from the working
area, they should be protected by the provision of properly constructed sheeting or
fans.
35 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.2. Materials
3.2.1. Scaffolding Provider’s Inspection Prior to Use
Scaffolding materials should be inspected by the scaffolding provider, prior to their
use on site. This inspection can be carried out before the materials are delivered to
the site. An area should be set aside for damaged or defective materials.
Signs should be erected indicating that the material is defective and is not to be
used. A checklist is provided in Appendix B (Checklist 01: Inspection of Scaffolding
Materials Before Use) to assist this examination.
3.2.2. Standards
Standards are upright members that transmit the vertical loads of the scaffold to
the foundations. The spacing of system scaffolding standards should follow the
recommendations in the manufacturer’s erection instructions.
For tube and fitting scaffolds, the service loads for working areas is provided in
Table A1 in Appendix A.
3.2.3. Transoms
Transoms are horizontal members normally in the direction of the smaller
dimensions of the working scaffold. Intermediate transoms may be required to
support the scaffold platform between main transoms.
The lowest transom should be installed as close as possible to the bottom of the
36 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.2.4. Ledgers
Ledgers are horizontal members normally in the direction of the larger dimension of
the working scaffold. Ledgers also support any intermediate transoms. The load-
carrying capacity of the scaffold will be significantly reduced where it is not possible
to place the first ledger at the base of the standards (see Section 3.2.3). Tube and
fitting ledgers should be joined with sleeve couplings positioned no more than one-
third of the bay length from a standard and staggered on alternate lifts.
3.2.5. Couplers
Couplers are devices used to connect two tubes. Couplers are used in conjunction
with system scaffolds mainly for the attachment of ties, plan bracing and cross
(ledger) bracing. The proper use of appropriate couplers is therefore important to
the stability of the scaffold. Couplers, when new, should comply with the
requirements of the relevant European Standard.
I.S. EN 74 Part 1, 2005: Couplers, spigot pins and baseplates for use in falsework
and scaffolds – Part 1: Couplers for tubes – Requirements and test procedures
specifies four classes of couplers (see Table A3 in Appendix A).
The characteristic values of the resistances for couplers are listed in Table A4 in
Appendix A. These values only apply to couplers marked with EN 74 and, where
appropriate, ‘A’ or ‘B’.
3.3. Stability
A scaffold is a temporary structure that is subjected to a wide range of loading
during erection, use and dismantling. It should support its own dead load; live
loads from construction materials, workers and tools; dynamic loads from material
placement; and wind loads.
Where failures occur, large areas of scaffolding can suddenly collapse. Scaffolds can
collapse because of poor construction or misuse leading to them being loaded
beyond their safe capacity to support the load.
37 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.3.1. Foundations
The foundations of a scaffold should be adequate to support the load imposed by
each standard and the scaffold as a whole throughout the life of the scaffold.
Other surfaces
Metal base plates should be used where there is a hard asphalt or similar
surface with sufficient bearing capacity. Where the bearing surface is soil,
compacted gravel, tarmacadam, hardcore, paving slabs or similar, sole
boards of timber or another suitable material should be used. Where the
surface has been disturbed or back-filled, or is soft, it should be compacted.
The contractor should prepare the ground in advance of the scaffolding being
erected. The scaffolder should seek written confirmation from the contractor as to
the bearing pressure. Guidance on allowable bearing pressures for various soils and
fill materials is given in BS 5975, 1996: Code of practice for falsework.
38 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Special precautions may be necessary to ensure the stability of the scaffold where
the ground slope exceeds 1 vertical to 10 horizontal.
Where excavations will affect only one standard, the load may be transferred to
adjacent standards by using proprietary beams or A-frames. The adjoining
standards should not be overloaded.
39 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.3.2. Ties
General
Ties connect the scaffold to the structure being built. Ties perform a dual function:
they stabilise the entire scaffold to prevent it from falling towards or away
from the building; and
There are a number of different tie types. Those types of tie that are non-movable
should be chosen, where reasonably practicable, as they present fewer difficulties
with maintenance or interference. Non-movable ties are assumed to be cast or
drilled into the structure and will not need to be moved until final dismantling of the
scaffold.
Ties should resist movement towards the building and away from the building.
Where a tie cannot resist movement towards the building, e.g. through ties, long
bolts and wire ties, the tie should be supplemented by other measures, e.g. tubes
butted against the building.
The vertical interval between ties should be determined in the scaffolding design
and communicated to the scaffolding erector. In the case of system scaffolds,
reference should be made to the manufacturer’s instructions.
Scaffolds of normal width of 1.25m should not be erected 4m higher than the
highest line of ties, unless the scaffold has been cross braced between ledgers
(cross bracing) and the ties and scaffold are capable of taking the extra loads.
40 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
These anchorages, which are cast or drilled into the permanent structure, can
usually be left in place until the scaffold is being dismantled. They are not subject
to the degree of interference associated with, for example, through ties. These
anchorages and their components should have a safe working capacity of at least
6.25kN (637kg) in both tension and compression.
A sample of anchors to be used shall be tested to a load between 1.2 and 1.5 times
the required tensile load. In the case of ties requiring 6.1kN tensile capacity, this
means a test load of 9.2kN (where a tie load of 12.2kN is required the proof load
equals 18.3kN). It is assumed that the allowable load of the anchor is in all cases
greater than or equal to the working load. The pass criterion is that no significant
movement of the anchor is apparent; a visual check is sufficient.
A minimum of 3 anchors shall be tested and at least 5% (1 in 20) of the total job
(see Table 2). If any anchors fail to satisfy this test requirement then the reason
for failure should be investigated and the rate of proof testing at least doubled, i.e.
at least 6 tests and 1 in 10 overall.
If significant numbers of anchors fail this test, then the overall safety margin is in
doubt and the specification and installation method should be reviewed before the
scaffold is passed for use.
Site tests should be carried out by suitably competent personnel (other than the
actual installer of the fixings tested) using a test meter with a gauge calibrated
within the last twelve months to an accuracy of >95%. Test equipment should apply
the load through suitable couplers and be arranged such that the reaction loads are
taken sufficiently far from the anchor so as not to influence the result, typically this
means ensuring the feet of the bridge do not rest on the masonry unit being tested.
41 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Most cavity walls, cladding panels and many parapets and other architectural
features will be unsuitable for the attachment of anchorages. Where refurbishment
work is being undertaken, the capacity of the building fabric to withstand the
anchorage loads should be assessed.
A ring bolt may be used by passing a scaffold tube through the ring and connecting
it to the scaffold.
The exposed length of ring-bolt shank or other bolts should be kept short and it
should not be extended beyond what is permitted in the manufacturer’s written
recommendations for bolts in compression. Where no written recommendations are
available, the capacity of the tie in compression should be established by testing.
43 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
44 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
45 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Where reveal ties are used, a greater number of ties are required. Where
practicable, no more than 50% reveal ties should be used unless they are
supplemented by permanent bolted or cast-in anchorages and a high level of
maintenance.
3.3.2.4. Returns
Where a system scaffold is continually and correctly returned around the corner of
a building, it can be regarded as being equal to a tie to the first pair of standards in
each direction from the quoin (e.g. the ties can commence from the second pair of
standards back from the return). It should be noted that if a correct and continuous
return is not in place, then each elevation should be regarded as separate and must
then be tied at each end. Plan bracing of ledgers would be required to provide tying
to adjacent standards.
46 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
47 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Many system scaffolds require every standard to be tied and for the first level of
ties to be no more than 4m above the base plate. Where this is required but is not
possible for an individual standard, the manufacturer may permit plan or cross
bracing to be provided between ties to give stability to the untied standard. Such
bracing will transfer more load to the existing ties, these ties should be able to
resist the increased loading and at least two couplers should provide restraint in
each direction at both the scaffold and the wall end of the tie.
3.3.4. Bracing
Bracing is required to stiffen the scaffold and prevent it from swaying. In system
scaffolds swaying can cause instability, weld deterioration and can over stress the
standards. Refer to the manufacturer’s erection manual for specific requirements
for bracing.
In tube and fitting scaffolds, each plane of the scaffold should be braced by
installing diagonal tubes that divide it into a complete series of triangles from the
bottom to the top of the scaffold. The braces should be fixed as close as possible to
the standard–ledger intersections. Refer to Table A4 in Appendix A for the
48 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
(A) a series of parallel diagonal tubes placed one above the other;
The scaffold should incorporate one type of façade bracing (see Figure 13).
Tube and fitting scaffolds should be braced at least every 5 bays, unless movement
along the building is prevented by other means.
49 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
the height of the scaffold is 4m or more above the last line of ties.
Where ledger bracing is installed for the above reasons, the loads on the adjacent
ties will be increased. The system manufacturer’s instructions should be consulted
to determine whether ledger bracing is required.
50 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
51 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Ledger bracing should be installed on tube and fitting scaffolds. Brace alternate
pairs of tube and fitting standards, ensuring that the bracing forms a complete
series of triangles from bottom to top of the scaffold. Install the bracing from
ledger to ledger or from standard to standard. For tube and fitting scaffolds, brace
each pair of standards where the bracing is installed from the inside ledger to the
guard-rail of the lift below to allow access along a boarded lift.
When clear access is required on base lifts of tube and fitting scaffolds, the cross
bracing may be omitted on the base lift provided the first lift does not exceed
2.7m, or the lift is knee braced. In either case, the loading capacity of the scaffold
will be reduced.
Missing ties
Where an individual tie cannot be installed at the manufacturer’s
recommended spacing, plan bracing may be used to help span the extended
distance between the adjacent ties. Note that the loading on the ties will be
increased.
Lateral loading
Where loading bays are connected to the scaffold, the bays should be wing
plan braced off the scaffold.
52 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Where a person could fall a distance liable to cause personal injury, the working
platform should be of the widths given in Table A5, Appendix A.
53 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.4.1. Decking
Decking may consist of timber boards or proprietary decking units. Where timber
boards are used they should comply with I.S. 745, 1986 Machine-graded home-
grown timber scaffold boards or BS 2482, 1981 Specification for timber scaffold
boards. The scaffold boards should not exceed the spans given in Table A2 in
Appendix A. These spans may need to be reduced to accommodate heavy loading.
The transoms of many system scaffolds are constructed to provide a secure support
for standard-length boards.
Where the transoms do not positively restrain the boards from moving or tipping,
the boards should be installed so that they overhang the transoms by at least
50mm but by no more than 4 times their thickness. Boards that are nominally
38mm thick and less than 2.13m long should not be used unless they are positively
restrained to prevent moving or tipping.
The use of the scaffold should be monitored so as to ensure that the manner in
which the works are being undertaken is not damaging the working platform, e.g.
through the use of abrasive wheels on scaffold boards.
3.4.2. Toe-Boards
Toe-boards help prevent materials from falling and they also help prevent persons
falling between the guard-rail and platform. Toe-boards and end toe-boards should
be fixed to all working platforms where a person could fall a distance liable to cause
personal injury. The toe-boards should have a height of at least 150mm above the
platform and they should be securely fixed to the standards.
Account should be taken of the extra load imposed by cantilever brackets on the
inside line of standards. Fitting cantilever platform brackets will generally reduce
the working platform service load and reduce the allowable number of boarded lifts
and working lifts.
3.5. Guard-Rails
Guard-rails should be provided on all working platforms, including boarded trestles,
where a person could fall a distance liable to cause personal injury. Part 4 of the
Safety, Health and Welfare at Work (General Application) Regulations 2007 details
the requirements for guard-rails. The height of the guard-rail should be at least
950mm above the working platform.
3.6.2. Sheeting
Sheeting may consist of netting, corrugated sheets or timber sheets. It should be
fixed securely to prevent materials from passing through the sheeting. Sheeting
should be inspected regularly, particularly after strong winds. Sheeting will
55 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
significantly increase the wind loading on a scaffold and on the ties and tie
couplers.
3.6.3. Fans
Fans normally consist of an inclined support extending from the building and
covered in decking. Fans are often the most suitable method of protecting
pedestrian traffic areas and access points into the structure.
The loads imposed on a scaffold by a fan, i.e. dead load, impact load and wind
load, are usually substantial. The top of the fan should be tied to the scaffold where
it is tied to the permanent structure and the bottom tube of the fan should be
propped against the structure.
Figure 17 shows two different arrangements for protection fans. Type 1 is where
the fan is at a lift level. For Type 2 the fan is detailed at a lower level, in order to
pass under a boarded lift. Note that in both cases additional toe-boards should be
used to prevent material rolling off the fan.
56 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Sufficient access points should be provided so that workers may easily gain access
to their place of work.
ladder access towers, fixed to the outside of the scaffold, should be erected,
where practicable;
the top of ladder stiles should be securely fixed to the scaffold by lashings;
the ladder should be set, where practicable, at an angle of not more than 4
vertical to 1 horizontal;
the ladder should extend at least 1m above the landing point or some other
adequate handhold should be provided;
58 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
59 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Figure 19: Example of Stair Access Towers (toe-boards omitted for clarity)
60 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The type of loading bay required will vary depending on the chosen method for
transporting materials around the site and loading materials onto the scaffolding. A
loading bay designed for use by a teleporter is different to a loading bay for use
with a crane (see Figures 20 and 21).
61 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Refer to the system manufacturer’s instructions for the erection of loading bays.
Loading bays should be diagonally braced on all four sides or braced in compliance
with the system manufacturer’s recommendations. Where the internal façade
bracing hinders access onto the scaffold from the loading bay, the brace may be
placed on the main scaffold adjacent to the loading bay or in accordance with the
system manufacturer’s recommendations. Issues that require consideration
include:
62 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Plan bracing should be installed from the outside corner of a loading bay to
the main access scaffold and the main scaffold should be tied to the building
with supplementary ties opposite these braces at intervals not exceeding 3m.
3.8.2. Signs
Easily comprehensible signs showing the safe working load, for each working lift,
should be placed on scaffolds and loading bays.
Figure 22: Example of Sign for Working Platform with UDL of 2.5 kN/m2
Warning signs must also be erected on a scaffold that is not available for use,
including during its assembly, dismantling or alteration and, where appropriate, the
scaffolding should be protected, by barriers or other suitable means, from
unauthorised access or use.
63 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Type C: Stairway or
Stairladder Tower
Type D: Frame Access
Tower
(Courtesy of PASMA)
I.S. EN 1004, 2005: Mobile access and working towers made of prefabricated
elements – Materials, dimensions, design loads, safety and performance
requirements gives minimum specifications for standard mobile prefabricated
towers with platform heights from 2.5m to 8.0m when used externally and 2.5m to
12.0m when used internally.
Advanced Guard-Rails
This method uses an additional set of equipment allowing guard-rails to be
placed ahead of the platform from the safety of the level below so that
collective fall prevention measures are in place before the operative stands
on the platform (see Figure 24 – toe-boards omitted for clarity).
(Courtesy of PASMA)
65 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
(Courtesy of PASMA)
3.9.5. Stability
The conditions of use of the tower and environmental forces such as wind can
adversely affect tower stability. Where the conditions of use or the wind forces are
likely to be different from those covered by the manufacturer’s instructions or this
Code, or where the tower is erected in a location exposed to high winds, the
overturning forces should be calculated by a competent person. Appropriate
measures should be taken to ensure that the tower has a factor of safety against
overturning of at least 1.5 in any direction (see Section 2.3.2).
66 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
3.9.7. Bracing
Prefabricated towers should be braced in accordance with the manufacturer’s
instructions. Where the tower is constructed of tube and fitting components, it
should be adequately braced on all four sides and be braced in plan at every
alternate lift.
3.9.8. Castors
Castors should be fitted with adequate brakes and they should be securely fixed to
each leg of the tower to prevent accidental uncoupling.
67 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
From July 2009 the Safety, Health and Welfare at Work (Construction)
(Amendment) Regulations 2008 require persons who erect mobile towers to have
successfully completed the FETAC (or recognised equivalent) course and to be in
possession of a FÁS Construction Skills Certification Scheme (CSCS) card for mobile
tower scaffolds. A basic or advanced scaffolder is already deemed to be competent
to erect mobile towers.
Competent supervision should be provided to ensure that towers are safely erected,
checked and used.
The tower should not be moved with workers or materials anywhere on the tower.
It should be moved manually, pushing the tower at or near the base. Mechanical
means should not be used to push towers.
The castors should always be locked, except when moving the tower. Chocks
should be used where there is any doubt about the adequacy of the brakes.
The access tower should be inspected and form GA3 (see Appendix C), or some
68 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The manufacturer’s instructions should be followed and the tower should not be
assembled to a height above that recommended by the manufacturer for the
specified stabilisers or outriggers, which must be installed correctly and at the
appropriate point in the assembly sequence.
Towers outside are usually exposed and are therefore subject to wind forces.
Frequently towers with a height to least base dimension ratio greater than 3.5 are
unstable in locations exposed to high winds. For these circumstances, the wind
forces should be calculated and the tower restrained by kentledge or guys, to give
a factor of safety against overturning of 1.5 in any direction.
In calculating the height to base ratio, measure the height from ground level to the
working deck or top lift and measure the base width as the least base dimension,
centre to centre, of the shortest side of a rectangular tower.
69 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
The erection and removal of scaffolding in the vicinity of overhead lines can present
particular risks as scaffolding materials are normally good conductors of electricity,
are handled manually and may have the potential to come into contact with or
come within arcing distance of the live overhead line conductors. Furthermore,
once scaffolding has been erected, work activities being carried out on the
scaffolding can present similar safety risks, especially while materials are being
handled or long handle tools are being used. Risks can also arise in windy
conditions from live conductors blowing towards or making contact with the scaffold
and thereby making the entire scaffold assembly live.
The ESB Networks/HSA Code of Practice for Avoiding Danger from Overhead
Electricity Lines gives practical guidance on how to carry out work safely in the
vicinity of overhead lines. Any party who has a responsibility for design, erection,
dismantling or use of scaffolding near overhead electricity lines should refer to it
(see Appendix E). It gives the appropriate “Hazard Zone” and “Exclusion Zone”
dimensions that apply for the different voltage levels of overhead lines. In
situations where any part of the scaffold, if erected, would be within the “Hazard
Zone” for the line voltage involved (i.e. normally 6m for lines supported on single
wood pole or steel pole supports), ESB Networks should be consulted in advance to
agree the arrangements necessary to facilitate the scaffolding.
In the particular case of LV overhead lines (i.e. where the voltage is less than
1,000 volts), it may be feasible for ESB Networks to replace bare, open wire
conductors with insulated, aerial bundled conductors or to temporarily insulate the
conductors by applying approved temporary shrouding and other protection to the
70 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
conductors to facilitate scaffolding and certain work activities within the “Hazard
Zone” of such lines.
3.10.3. Lightning
Scaffolds on the roofs of high buildings or associated with some topographical
features are susceptible to being struck by lightning. Such scaffolds should be
earthed.
The public should be excluded from the area around the work during scaffold
erection, modification and dismantling. This requirement may involve getting
permission to close streets or footpaths while the scaffold is being erected or
dismantled. Where the public cannot be excluded, effective physical protection
should be provided to prevent persons being struck by falling tools or materials.
71 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
ensuring there are no projections that may injure people or damage their
clothing;
Where ledger bracing is omitted from the bottom lift up to a height of 2.7m
(typically for scaffolding erected on a footpath), the scaffold must either be tied at
the top of the bottom lift or stabilised by other means, such as outside rakers. Ties
should be fitted at alternate standards.
72 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
73 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
clearly identifying the areas of the scaffold that have been handed over;
clearly stating the maximum capacity of the loading bays and working
platforms and the tie spacing;
inspecting the entire area of the scaffold before it is taken into use. The
scaffold inspection checklist given in Appendix B (Checklist 02: Inspection of
Scaffolding in Use) or another suitable checklist may be used;
preparing a report of the inspection, e.g. using form GA3 “Report of results
of inspections of Work Equipment for Work at a Height” (see Appendix C) or
similar. A copy of the report should be retained on site; and
Figure 27 outlines the steps that a scaffolder should follow when handing over the
control of the scaffold to the end-user.
74 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
75 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Users should:
5.2. Modification
Uncontrolled modification of a scaffold, particularly if carried out by persons without
adequate competence, can lead to instability and an increased risk of persons
falling from the scaffold. Modifications to ties, bracing, ledgers, transoms and
decking should be identified, requested and made in good time (see Section 2.5).
Only competent persons who have been trained and are experienced in this kind of
76 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
5.3. Maintenance
The scaffold should be maintained in a safe condition for the entire period of its use
(see Section 2.5).
modification;
77 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
6. Dismantling
Dismantling a scaffold can place large loads on the scaffold unless the work is
planned to keep the amount of material stored on the scaffold to a minimum. The
work should be planned so that the scaffold remains stable, workers are prevented
from falling from the scaffold and others are protected from the risk of falling
materials.
6.1. Stability
The scaffold should be examined to ensure that the foundation is adequate and that
all ties and braces are in position and are effective.
Any defects found in the scaffold should be made good before commencing
dismantling.
Prominent warning notices should be placed and access to the danger zone should
be prevented.
78 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
7. Competence
The risks associated with the erection, use and dismantling of scaffolding are
potentially very high. Persons given the task of erecting, altering, using or
dismantling scaffolding should have the necessary competence to perform their
tasks safely, as outlined in Figure 28.
79 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
In the case of scaffolding, close personal supervision is intended to ensure that the
trainee’s safety is protected at all times and that the skills necessary to safely
complete the job are comprehensively communicated and demonstrated. To
achieve this, the supervising scaffolder must ensure that the trainee scaffolder can
be organised, directed, observed, communicated with and monitored at all times.
In considering the nature, scale and complexity of the scaffolding activities, the
scaffolding contractor must at all times ensure that the trainee scaffolder is
undertaking work that is within his or her training, knowledge, experience and
capabilities.
A competent person is a person who has been fully trained, has acquired the
necessary knowledge and practical experience and has received the necessary
instructions for the erection, alteration or dismantling of the type of scaffold.
7.1.1. Training
Formal training is required for those who erect, substantially add to, alter or
dismantle a scaffold. The training should include instruction on any risks involved.
The extent of training required will depend on the type of work normally
undertaken and on the type of scaffold. The minimum acceptable standard of
training is the approved FÁS Construction Skills Certification Scheme (CSCS) for
Basic Scaffolders, or an equivalent training programme accredited by FÁS.
Scaffolding activities beyond the range of general access scaffolds require the
erector to be trained to an advanced level.
80 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
7.1.2. Experience
A competent and experienced person should supervise the erection, alteration or
dismantling of a scaffold. The person should be experienced in the kind of work
being undertaken.
(Courtesy of FÁS)
Employers, contractors and project supervisors for the construction stage should
satisfy themselves that persons erecting scaffolding have the necessary training by
seeking evidence of FÁS certification or an equivalent qualification accredited by
FÁS.
While it is relatively easy to inspect for certain defects such as missing guard-rails,
81 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
an untrained person may not be able to form an opinion on the stability of the
scaffold.
Those performing simple scaffold inspections should have received at least one day
of formal training in scaffold inspection and be competent. Extra training is required
for the inspection of complex scaffolds.
This training may be provided as part of the site-specific induction that all persons
who are likely to use the scaffold, either for access or as a working platform, should
receive.
are able to recognise when a scaffold is complete, e.g. full boarding, guard-
rails and toe-boards present;
know the maximum loading capacity of the scaffold working platforms and
loading towers (the training should provide specific comprehensible examples
relating to the materials in use on the site);
use the designated access points and do not climb the scaffold.
82 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Equipment operators such as crane drivers and telescopic fork-truck drivers as well
as signallers (banksmen) should be competent and have received training,
assessment and certification. FÁS or FÁS-approved providers offer training courses
for equipment operators and assess, certify and register trained operators. Other
appropriately qualified bodies may apply to FÁS for accreditation of courses.
Lifting equipment operators should be informed of the safe working load of the
scaffold working platforms and loading bays. Comprehensible examples relating to
the materials in use on the site should be provided. It may be necessary to review
the information provided if the materials or scaffold layout change.
Excavation close to the scaffold can undermine it. Excavator operators should be
informed of the minimum distances that they should observe when excavating in
the vicinity of the scaffold.
83 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Appendix A
84 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Access and working scaffolds may be specifically designed and constructed for any
particular distributed or point load and for a variety of purposes. Table A1 lists the
six distributed load classes specified in I.S. EN 12811 Part 1. The requirements for
concentrated and partial area loads are also included. Further details of these can
be found in Table 3 of I.S. EN 12811 Part 1.
In the absence of wind, in addition to vertical imposed loads, I.S. EN 12811 Part 1
requires a notional horizontal load applied to each bay of the scaffold of not less
than 2.5% of the total uniformly distributed service load on that bay or 0.3kN,
whichever is greater. It should be separately applied parallel and perpendicular to
the bay at the level of the working platform.
Reference should also be made to clause 6.2.9 of I.S. EN 12811 Part 1 for the
design load combinations to be used. If the specifier quotes no load rating, it is
recommended that the selection be made from either Table A1 in this Code of
Practice or from Table 3 in I.S. EN 12811 Part 1.
The following tables are derived from I.S. EN 12811 Part 1, 2004 and I.S. EN 74
Part 1, 2005.
85 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
86 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
87 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
88 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Appendix B
Example
Checklists
89 Health and Safety Authority
Checklist 1:
Inspection of Scaffolding Materials Before Use
Use this checklist to verify and record that scaffolding materials that are delivered to site are in an acceptable
condition; before they are incorporated into the temporary structure.
Site: Reference:
Base Plates
Base Jacks
Standards
Ledgers
Transoms
Intermediate Transoms
Swivel Couplers
Sleeve Couplers
Scaffold Tube
Diagonal Brace
Bridging Ledgers
Anchorage / Ties
Brick Guards
Sheeting / Netting
Other Component
Source: Health and Safety Authority's Code of Practice for Access & Working Scaffolds (2008)
Checklist 2:
Inspection of Scaffolding in Use
Use this checklist while inspecting scaffolding that is in use. Record all defects observed and arrange for a
a competent scaffolder to rectify the defects (note when completed). This can help you complete form GA3.
Site: Reference:
Date
Item Defect and Location (use gridlines or references)
Corrected
Foundations
Sole Boards
Standards
Ledgers
Transoms
Facade Bracing
Plan Bracing
Cross Bracing
Guard Rails
Toe Boards
Unauthorised Alterations
Other (traffic/public/electricity)
Observations
Source: Health and Safety Authority's Code of Practice for Access & Working Scaffolds (2008)
Certificate:
Handover of Scaffolding to User
Use this certificate to record the particulars of the scaffolding that you have erected and communicate the
capacity of the scaffolding to the User.
Site: Reference:
We have: (tick when done) You must: (tick to confirm you uderstand)
Erected the scaffolding in accordance with the Make sure that the scaffolding is used in
details above and our quotation:___________ accordance with the details above
Inspected the scaffolding in accordance with Not alter the scaffolding or overload the
our scaffolding inspection procedures scaffolding during use
Inspected the scaffolding and completed GA3 Make arrangements to have the scaffolding
Form, or similar (attached) inspected at least every 7 days (see GA3 form)
Signed: Signed:
Scaffolding Erector; or Scaffolding User; or
Scaffolding Company Contractor
Source: Health and Safety Authority's Code of Practice for Access & Working Scaffolds (2008)
Code of Practice for Access and Working Scaffolds
Appendix C
93 Health and Safety Authority
GA3 - Report of Results of Inspections of: * Must specify details of any matters
identified that could give rise to a
risk to the safety or health of any
Work Equipment for Work at a Height employee.
Name of person (or company) for whom the inspection was carried out:
Day to day management of the scaffolding is the responsibility of the contractor responsible for the site.
GA3 - Report of Results of Inspections of:
Work Equipment for Work at a Height NOTES
This form may be used to assist in compliance with the Safety Health and Welfare at Work (General Application) Regulations 2007 Regulation 119 – Inspection
of Work Equipment in relation to scaffolds, guard-rails, toe-boards, barriers or similar means of protection, fixed and mobile working platforms, nets, airbags
or other collective safeguards for arresting falls, personal fall protection systems, work positioning systems, rope access and positioning techniques, fall
arrest systems, work restraint systems and ladders. This is not an approved or statutory form. Reports of Inspection may be produced in other formats. This
form does not substitute for reports of thorough examination of lifting equipment that may be required under other statutory provisions (see GA1 and GA2).
Safety, Health and Welfare at Work (General Application) Regulations, 2007 - Part 4 - Regulation 119
119. (1) An employer shall ensure that, as regards work equipment to which Regulations 101 to 114 apply—
(a) where the safety of the work equipment depends on how it is installed or assembled, it is not used after installation or assembly in any
position unless it has been inspected in that position,
(b) without prejudice to paragraphs (a) and (c), work equipment exposed to conditions causing deterioration which is liable to result in
dangerous situations is inspected—
(i) at suitable intervals, and
(ii) where exceptional circumstances have occurred that are liable to jeopardise the safety of the work equipment, as soon as
practicable following these exceptional circumstances, and
(2) A person carrying out an inspection of work equipment to which paragraph (1)(c) applies shall—
(a) promptly prepare a report containing the particulars as set out in Schedule 5, and
(b) within 24 hours of completing the inspection, provide the report, or a copy thereof, to the person on whose behalf the inspection was
carried out.
(3) An employer receiving a report under paragraph (2) shall keep the report or a copy of the report—
(a) at the site where the inspection was carried out until the construction work is completed, and
(b) the result of an inspection under this Regulation is recorded and kept available for inspection by an inspector for 5 years from the date
of inspection.
Day to day management of the scaffolding is the responsibility of the contractor responsible for the site.
Code of Practice for Access and Working Scaffolds
Appendix D
Weights of
Typical Building Materials
96 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
97 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
98 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Table D5: Additional Weight of a Boarded Lift (with imposed service load)
One Bay Long
(this includes the additional weight of one boarded lift: the boards, the
toe-board, the principle and intermediate guard-rails, fittings and the
service imposed load on the lift. The figures do not include weight of the
scaffold itself, which is given in Table D4)
99 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Appendix E
Information Sources
100 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Statutory Provisions
www.hsa.ie
Irish Standards
www.nsai.ie | www.standards.ie
I.S. EN 39, 2001 Loose steel tubes for tube and coupler
scaffolds – technical delivery conditions
101 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
I.S. EN 10210 Parts 1 & 2, 2006 Hot finished structural hollow sections of
non-alloy and fine grain steels
I.S. EN 12385 Parts 1 & 2, 2002 Steel wire ropes – Safety – General
requirements
102 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
British Standards
www.bsonline.bsi-global.com
104 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
TG20:05 Guide to Good Practice for Scaffolding with Tube and Fittings
Other
105 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Index
A
access see also ladders; staircase access towers
definition of 19
mobile elevated work platforms 41
points of 56, 57–60, 67, 72
preventing 12, 36, 54, 63, 71–72
towers 58, 64–69, 64illus., 79
accidents, reporting of 12
advanced scaffolders 79, 80
aluminium towers 64, 69
anchorages 30, 41–43, 46 see also ties
definition of 15
asphalt surfaces 38
assembly see erection
assessment, definition of 18
availability of competent scaffolders 32, 77
B
barriers 25, 35, 36, 54, 63, 67, 72
base jacks
definition of 15
use of 39
base plates
definition of 15
positioning of 39
use of 37, 38, 39, 67
basements 35
basic scaffolders 79, 80
baskets, work out of 35
bay length 21illus.
bearing pressures 38
birdcage scaffolds, definition of 16
blocks
incorrect use of 39
loading bays for 60
weight of 98
boards see also decking
definition of scaffold 19
dimensions of 54, 86, 97
missing 6
weight of 97, 98, 99
106 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
C
cantilever brackets 32, 54–55
definition of 18
cantilever loading bays 35
cantilever scaffolds 35
castors
definition of 18
use of 67, 68
certification 81
check couplers, definition of 18
checklists 89–91
cladding see also sheeting
definition of 16
clients, duties of 10
107 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
Code of Practice for Avoiding Danger from Overhead Electricity Lines 70, 104
collapse, causes of 6, 15, 37–38, 83
collective protective measures 8, 34 see also barriers
competence 23, 24, 26–27, 79–83
availability of on site 32, 77
definition of 80, 81
design 29
erection 26, 68, 79, 80
inspection 32, 81–82
modification 15, 32, 76–77, 79, 80, 81, 82
supervision 81
components, definition of 17, 21illus.
defective 14, 27, 28, 36, 76, 78
requirements for 5
weights of 96–99
concrete surfaces 38
configuration, definition of 17
confined spaces 35
connection device, definition of 17
Construction Regulations 9, 12, 23, 24, 34, 711
guidance to 104
Construction Skills Certification Scheme (CSCS) cards 12, 13, 68, 79, 80, 81illus.
contractors
duties of 7, 10, 13–14, 70, 76, 80, 81, 82
policy preparation 23
safety statements 13
control measures see General Principles of Prevention
corners 46
couplers
check 18
classes of 87
definition of 16
parallel 16, 87
resistance values 87
right angle 16, 43illus., 87
safety see check couplers
sleeve 17, 37, 87
supplementary 19
swivel 17, 51illus., 87
use of 37, 48
weight of 97
cranes for loading materials 29–30, 61, 62illus., 63, 83
cross bracing see ledger bracing
D
debris netting see sheeting
108 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
E
egress, definition of 19
electrical dangers 67, 70–71 see also overhead power lines
element, definition of 17
end guard-rails 53illus.
definition of 18
end toe-boards 53illus., 54
definition of 18
equipment
definition of working 20
operators, information/training for 63, 83
portable electrical 71
selection of 29
erection 34–73
competence in 26, 68, 79, 80
planning for 24–26
protection of public during 71–72
risk assessment 7, 8
safety issues 34–36, 70
scheduling of 31
erectors, duties of 10, 14–15, 70
ESB Networks 70, 71, 104
evacuation 59
excavations
position in relation to 31, 39, 83
protective measures for 32, 35
exclusion zones 70
109 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
F
façade bracing 49, 49illus.
definition of 18, 21illus.
façade scaffolds 5
fall arrest systems see personal protective equipment
falling objects 54, 55–57, 71, 78
falls from height 34–36, 65, 78
fans 35, 56, 57illus.
FÁS 68, 80, 81, 83, 104
foundations 6, 26, 32, 38–39, 67 see also ground conditions
fragile surfaces, definition of 19
frame access towers 64illus.
free-standing towers 41, 64–69
functions of scaffolding 5
G
GA3 form 93–95
use of 4, 10, 14, 68, 74, 75, 76, 77
gangways see access points
gaps see safe distances
General Application Regulations 9, 23, 24, 34, 55, 93, 95
definitions in 19–20
guidance to 104
General Principles of Prevention 7, 8
ground conditions 7, 24, 26, 38, 39, 67
GRP (glass reinforced plastic) towers 64, 69
guard-rails 34, 53illus., 55, 58, 65, 66, 67
definition of 18
temporary removal of 6, 32, 63, 77
H
handover certificates 92
handover procedures 14, 42, 74–75, 92
harnesses see personal protective equipment
hatches see trapdoors
hazard zones 70, 71
hazards 6, 7, 25, 26, 34–36, 64, 71
responsibility for identification of 11, 13, 25
headroom classes 4
Health and Safety Authority, notifications to 12, 13
Health and Safety Executive (UK) 104–105
height 40, 50, 76
height to base ratio 69
helmets see personal protective equipment
hirer’s duties 33, 36
hoarding licences 72
hoardings, protective 37, 72
110 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
I
implementation stage 26–27
incomplete scaffolding/towers 36, 54, 69, 74, 77
induction 13, 32, 82
inspection 27–28, 77
before use 14, 36, 74–75, 76, 77, 90
checklists 89–91
competence in 32, 81–82
during use 72, 75, 76, 77, 91
reports 74, 76, 77, 93–95
I.S. EN 39 101
I.S. EN 74 37, 85, 101
I.S. 745 54, 102
I.S. EN 1004 65, 69, 102
I.S. EN 1298 65, 102
I.S. EN 12810 4, 5, 29, 30, 102
I.S. EN 12811 3–4, 5, 6, 17, 29, 30, 48, 79, 85, 97, 103
J
joint pins, definition of 18
K
kentledge, definition of 18
knee braces, definition of 18
L
ladders
access 34, 36, 58–60, 59illus., 64illus., 67, 72
definition of 20
landings 58
lateral loading 52
layout 29
ledger bracing 4, 40, 48, 50, 51illus., 52, 72
definition of 18
ledgers
definition of 16, 21illus.
modifications to 76
positioning of 37
legal duties 1–2, 7, 9–15, 23, 24, 77
lighting 72
lightning 71
lines, definition of 20
loading bays 26, 30, 35, 60–63, 61illus., 62illus.
loading capacity, impacts on 37, 39, 52, 55, 56, 78, 83 see also stability
loading charts 63
111 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
M
maintenance 22, 32, 77
planning for 32
manhole covers, position in relation to 29, 39
manufacturer’s duties 33
manufacturer’s guidelines 29
materials
defective 14, 27, 28, 36, 76, 78
loading 60–61, 63
loose 36
requirements for 5
weights of 63, 83, 96–99
mobile access towers
assembly/dismantling of 64–65, 65illus., 66illus., 68, 79
inspection of 68–69
preventing falls from 65–66
stability of 66–67
types of 64–65, 64illus., 69
use of 68–69
mobile elevated work platforms 35, 41
modifications 76–77
competence in 15, 32, 76–77, 79, 80, 81, 82
planning for 32
protection of public during 71–72
modular system, definition of 16
movable ties
definition of 18, 21illus.
use of 32, 40
N
National Access and Scaffolding Confederation (UK) 105
112 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
O
overhead power lines 7, 34, 64, 67, 70–71
overloading 6, 37, 38, 39, 60, 76, 83 see also stability
P
parallel couplers 87
definition of 16
parking, adjacent 72
pedestrian traffic 35, 37, 55, 56, 72, 73illus.
performance standards 25, 27
permanent works, influence of 29, 31
personal fall protection system, definition of 20
personal protective equipment (PPE) 8, 14, 25, 34–35, 66
plan bracing 40, 46, 48, 52, 52illus., 63 see also bracing in horizontal plane
definition of 19
planning stage 24–26
platform units, definition of 16
platforms 4, 53–55, 67
definition of 16, 20
width of 34, 53, 88
policy, scaffolding 23–24
Prefabricated Access Suppliers’ and Manufacturers’ Association (UK) 105
project supervisors (construction), duties of 7, 10, 12–13, 70, 81, 82
project supervisors (design), duties of 7, 10, 11, 23, 70, 82
protection fans see fans
protective measures 8, 14, 25, 34–37, 54, 55–56, 63, 72
public safety 35, 55, 56, 71–73
R
rakers 46, 47illus., 72
definition of 19
raking tubes see rakers
ramps see access, points of
register of qualified scaffolders 81
rescue procedures 35
restricting access 12, 36, 54, 63, 71–72
returns 46
reveal pins 44, 45illus.
definition of 19
113 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
S
safe distances
between platform units 4
between scaffolding and building 29, 54
between scaffolding and underground hazards 29, 31, 39, 83
between scaffolding and overhead power lines 70
Safe Pass 12, 79
safety advisers 12
safety and health plans 24
preparation of 11
protective measures in 7, 8, 25, 35, 37
risk assessment in 34, 70
Safety Awareness cards 12, 13
safety couplers see check couplers
safety files, preparation of 11
safety nets 8, 34
safety officers 13
safety representatives 12, 13
safety signs see warning notices
safety statements
communication of 27
contractors’ 13
protective measures in 7, 25, 35
risk assessment in 34, 70
Safety, Health and Welfare at Work Act 2005 9, 12, 24, 25
General Principles of Prevention 7, 8
guidance to 104
Safety, Health and Welfare at Work (Construction) (Amendment) Regulations 2008
68
Safety, Health and Welfare at Work (Construction) Regulations 2006 9, 12, 23, 24,
34, 711
guidance to 104
Safety, Health and Welfare at Work (General Application) Regulations 2007 9, 23,
24, 34, 55, 93, 95
definitions in 19–20
guidance to 104
114 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
T
teleporters for loading materials 29–30, 61, 61illus., 63
temporary buildings and roofs 35
testing
anchorages 41–42, 43
requirements for 5
3T method 65–66, 66illus.
through access 72, 73illus. see also pedestrian traffic
through the trapdoor method 65–66, 66illus.
through ties 43, 44illus.
definition of 19
ties 40–52, 43illus.
capacity of 30
definition of 17
function of 40
impact on stability 38
missing 52
modifications to 32, 76
movable 18, 21illus., 32, 40
non-movable 18, 21illus., 40
patterns 4, 47–48, 48illus.
positioning of 40, 48illus., 48, 72
reveal 19, 44, 45illus., 46
through 19, 43, 44illus.
tube and fitting scaffolds 48
unauthorised removal of 15, 38
timber packing 44, 45illus.
toe-boards 53illus., 54, 55, 56, 58, 67
definition of 19
omission in illustrations 15
temporary removal of 77
towers
access 41, 58, 64–69, 64illus., 79
staircase access 59, 60illus., 64illus.
traffic, adjacent 72
trainee scaffolders 79, 80
training 8, 26–27, 33, 35, 68, 76, 79, 80, 82, 83
transoms
definition of 17, 21illus.
intermediate 36
in loading bays 62
modifications to 76
positioning of 36–37, 54
116 Health and Safety Authority
Code of Practice for Access and Working Scaffolds
sway 19
trapdoors 58, 65–66, 67
truss-out scaffolds 35
tube and fitting scaffolds
bracing 47–48, 49, 52, 67
positioning of sleeve couplings 37
requirements for 6, 85–88
service loads for 86
ties 48
tubes
butting 18, 40, 43
weight of 97
types of scaffolding 5–6
U
underground services 29, 35, 39
users
duties of 10, 14–15, 76
needs of other 32
information for 26–27, 33, 63, 76, 82, 83
V
vehicle impact 7, 72, 77
voltage of portable tools 71
W
Walker, H. B. 105
walkways 35
warning notices 25, 35, 36, 54, 63, 67, 69, 72, 74, 78
water, work near 35
weather 27, 71, 77 see also lightning; wind
weights of materials 63, 83, 96–99
welfare facilities 12
wells 35
width classes 4
wind, effects of 30, 47, 53, 55–56, 66, 67, 69, 70
work at height, definition of 20
work equipment, definition of 20
workers see users
working area, definition of 17
working platforms 4, 53–55, 53illus., 67
definition of 20
width of 34, 53, 88
working scaffold, definition of 17
117 Health and Safety Authority
Scaffolding Cover 2 21/8/08 03/09/2008 16:28 Page 1
CODE OF PRACTICE
FOR ACCESS AND
WORKING SCAFFOLDS