PRE-COMMISSIONING FORMAT FOR TRANSFORMER

I. GENERAL DETAILS
DETAILS
Sub-Station: Sholoshahar 132kV GIS Substation
LOA No. :PGEP/IDB/PGCB/SS Make: SIEMENS
Sr. No.: I110202-02 Type: Dyn1
Year of Manufacture: 2019 Rating: 80/120MVA
Voltage Ratio : 132/34.5kV Cooling Type: ONAN/ONAF
Type of Neutral Grounding: Solid Oil Make: Power oil
Oil type: Naphthenic Oil quantity: 36kl
Quantity of Radiator: 18 Date of Receipt at site: 7 March-2020
Date of Starting of Erection: 03 Dec Date of Completion of Erection and Oil filling:
2020 29 Dec 2020

II. CHECK LIST OF ELECTRICAL TESTS CARRIED OUT FOR


TRANSFORMER

Testing Kit Details


Sl.
Name Of Test Date Of Last
No. Make
Calibration
1 Frequency Response Analysis Omicron
2 Voltage Ratio Test Omicron
3 Vector Group Test & Polarity Check N/A
4 Magnetic Balance Test (Not applicable for 1- N/A
ø)
5 Magnetization Current of Windings N/A
6 Short Circuit Impedance Test N/A
7 Insulation Resistance Measurement KOYRITSU
8 C & Tanδ Measurement Of Bushings & Omicron
Windings
9 Measurement of Winding Resistance Omicron
10 Oil Test Results YUNENG
11 Operational Tests and Checks of OLTC & N/A
Cooling Equipments
12 Protection And Alarm Tests N/A

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

III. PRE-COMMISSIONING CHECKS:

Sl. Status Deficiencies, If


Description Of Activity
No. Yes No Any
1 ICT and its Auxiliaries are free from visible defects on
Yes
physical Inspection
2 All fittings as per out line General Arrangement Drawing Yes
3 Check Main Tank has been provided with double earthing Yes
4 Check neutral is grounded through separate connections.
Ensure metallic requirements as per specification (e.g. Cu)
in earthing strips used
5 Check that Marshalling Box, T/C Driving Gear, Diverter, Yes
Radiator Bank Pump & Fan Motor etc. has been earthed
6 Check leveling of Transformer and its accessories Yes
7 Erection Completion Certificate along with list of No
outstanding activities reviewed
8 Any Paint removed / scratched in transit has been touched Yes
up
9 Bushings are clean and free from physical damages Yes
10 Oil level is correct on all Bushings Yes
11 Check oil leakage through any Joints / Valves etc. Yes
12 Check oil drain valves are properly closed and locked Yes
13 Check oil level in Main / OLTC Conservator tank Yes
14 Check OTI and WTI pockets and replenish the oil, if Yes
required
15 Check all valves for their opening & closing position. Yes
16 Check the colour of the breather silica gel Yes
17 Check availability of oil in the breather cup Yes
18 Check all rollers are locked and tack welded with rails Yes
(wherever applicable)
19 Check tightness of bolt if main unit placed directly on Yes
foundation and not on rollers
20 Check busing test tap is grounded Yes
21 Check that pressure relief valve is correctly mounted Yes

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

22 Ensure unused secondary cores of Bushing CT’s, if any, has Yes


been shorted
23 Check that Buchholz Relay is correctly mounted with arrow Yes
pointing towards conservator
24 Ensure all Power and Control cable Terminals are tightened Yes
25 Check that air has been released from the Radiators and their Yes
headers/OLTC Buchholz relay/Main tank/tank/Bushing
turrets etc
26 Check that CC-CL & G are shorted Yes
27 Check that all radiator bank valves on top and bottom Yes
headers are open
28 Change over operation of AC supply from source- I to Yes
source-II checked
29 Check the flanges of bushing & OLTC for any crack after Yes
fixing
30 Calibration of OTI & WTI performed as per procedure Yes
31 Ensure RTCC is commissioned and kept in service In progress
32 Ensure Remote OTI and WTI data transfer to control room In progress
is taking place
33 Ensure On-Line DGA is commissioned N/A
34 Ensure On-Line Dry out system is commissioned N/A

Signature: Signature:

Name: Name:

Designation: Designation:

SIEMENS-STI (Commissioning. Team)


Members:

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

IV. PRECOMMISSIONING TESTS AFTER READINESS OF THE TRANSFORMER

1. Frequency Response Analysis (FRA)

Sl. No Description Yes No Remarks


1 Carried out after completion of all commissioning Yes
activities
2 Factory FRA test report in soft form available at site Yes
3 Interpretation of test results carried out Yes
4 Test results matching with the factory results Yes

Note: - Measurement to be carried out at Minimum, Maximum and Nominal Tap.

2. Voltage Ratio Test. HV / LV

Calculate
Voltages (kV) Measured Ratio
d Ratio
Tap 1U-1W/2U-2N 1V-1U/2V-2N 1W-1V/2W-2N
HV LV HV/LV
%Erro
Ratio %Error Ratio %Error Ratio
r
1 145.20 34.5 7.2897 7.2748 -0.20 % 7.2745 -0.21 % 7.2744 -0.21 %
2 143.55 34.5 7.2068 7.1943 -0.17 % 7.1938 -0.18 % 7.1937 -0.18 %
3 141.90 34.5 7.1240 7.1136 -0.15 % 7.1130 -0.15 % 7.1131 -0.15 %
4 140.25 34.5 7.0412 7.0327 -0.12 % 7.0324 -0.12 % 7.0323 -0.13 %
5 138.60 34.5 6.9583 6.9524 -0.09 % 6.9522 -0.09 % 6.9518 -0.09 %
6 136.95 34.5 6.8755 6.8714 -0.06 % 6.8712 -0.06 % 6.8710 -0.07 %
7 135.30 34.5 6.7927 6.7909 -0.03 % 6.7910 -0.02 % 6.7909 -0.03 %
8 133.65 34.5 6.7098 6.7103 0.01 % 6.7099 0.00 % 6.7098 0.00 %
9 132.00 34.5 6.6270 6.6295 0.04 % 6.6291 0.03 % 6.6292 0.03 %
10 130.35 34.5 6.5441 6.5487 0.07 % 6.5491 0.08 % 6.5483 0.06 %
11 128.70 34.5 6.4613 6.4682 0.11 % 6.4686 0.11 % 6.4679 0.10 %
12 127.05 34.5 6.3785 6.3877 0.15 % 6.3879 0.15 % 6.3875 0.14 %
13 125.40 34.5 6.2956 6.3069 0.18 % 6.3073 0.19 % 6.3069 0.18 %
14 123.75 34.5 6.2128 6.2263 0.22 % 6.2265 0.22 % 6.2262 0.22 %
15 122.10 34.5 6.1300 6.1455 0.25 % 6.1453 0.25 % 6.1454 0.25 %
16 120.45 34.5 6.0471 6.0650 0.30 % 6.0647 0.29 % 6.0649 0.29 %
17 118.80 34.5 5.9643 5.9843 0.34 % 5.9843 0.34 % 5.9843 0.33 %

Note:
1. The variation of result should be within ± 0.5 % from specified values (i.e. factory test result)
( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

2. Measurement to be done by Automatic Turns ratio meter

3. Vector Group Test & Polarity Checking

a. Vector Group Checks for 3Φ Transformer Formation.

Short 1U and 2U Terminals and apply 380 V. 3-phase supply to HV Terminals

Voltage Measured Terminals Voltage


Terminals
(Volts) Measured (Volts)
1U-1V 374.5 1V-2W 389.0
1V-1W 379.5 1V-2V 299.1
1W-1U 371.5 1U-1W 371.7
1W-2W 290.1 1U-2N 55.7
1W-2V 290.3 2N-1W 314.0

Conditions: 1) 1W-2W ≈ 1W-2V


2) 1V-2W >1V-2V
3) 1U-1W ≈ 1U-2N+2N-1W

Vector group Dyn1 is confirmed and polarity verified

4. Magnetic Balance Test:

a) From HV side: ( Apply 3 phase AC supply Tap 9b)


1U-1W(V) 1V-1U(V) 1W-1V (V)
366.1 300.7 61.0
270.5 362.8 91.7
135.6 230.5 368.1

b) From LV side: (Apply 1 phase AC supply Tap 9b)


2U-2N (V) 2V-2N (V) 2W-2N (V)
211.2 178.2 30.2
113.3 221.4 108.2
29.3 191.8 221.6

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

Note:
i. When outer phase is excited, voltage induced in the center phase shall be 50 to 90% of the applied voltage.
However, when the center phase is excited then the voltage induced in the outer phases shall be 30 to 70%
of the applied voltage.

5) Magnetization Current Test

a) Apply 1 Phase, AC supply on LV Terminal and keep HV open

Tap Position Voltage Applied Current Measured (mAmps)


(Volts)
2U – 2N 211.2 U - PH 33.4
NORMAL 2V – 2N 221.4 V - PH 25.4
2W - 2N 221.6 W - PH 34.9

b) Apply 3 Phase, AC supply on LV Terminal and keep HV open

Tap Position Voltage Applied Current Measured (mAmps)


(Volts)
2U – 2V 377.8 U - PH 23.6
NORMAL 2V – 2W 381.2 V - PH 13.9
2W – 2U 385.2 W - PH 24.3

c) Apply 3 Phase, AC supply on HV Terminals and keep LV open

Tap Position Voltage Applied Current Measured (mAmps)


(Volts)
  1U – 1V 380.1 U - PH 2.4
LOWEST 1V – 1W 378.7 V - PH 2.4
  1W -1U 374.1 W - PH 4.0
1U – 1V 365.5 U - PH 3.0
NORMAL 1V – 1W 377.5 V - PH 2.7
1W -1U 377.7 W - PH 4.5
  1U – 1V 378.0 U - PH 2.9
HIGHEST 1V – 1W 383.3 V - PH 3.5
  1W - 1U 378.2 W - PH 4.9

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

6) Short Circuit Impedance Test - HV TO LV

Top Oil Temperature: 33 °C

Apply 3 Phase, AC supply on HV Terminals and keep LV short.

Tap
Voltage Applied Current Measured (Amps)
Position
(Volts)
  1U – 1V 377.7 1U 9.8 2U 41.3
LOWEST 1V – 1W 382.2 1V 9.9 2V 41.9
  1W -1U 375.8 1W 9.9 2W 42.4
1U – 1V 377.7 1U 12.2 2U 47.1
NORMAL 1V – 1W 382.5 1V 12.5 2V 47.7
1W -1U 375.6 1W 12.4 2W 48.5
  1U – 1V 384.3 1U 15.5 2U 53.7
HIGHEST 1V – 1W 386.5 1V 15.8 2V 54.2
  1W - 1U 380.3 1W 15.7 2W 55.2

% Impedance Calculation

a) Lowest Tap

HV Current (Measured value) = ( Applied voltage * Rated HV current)/ Impedance Voltage

Impedance voltage = Rated HV voltage * Impedance

Impedance = ( Applied Voltage * Rated HV current)/( Rated HV voltage* HV measured current)


Impedance = (379.57*477.15) / (145200*9.87)
= 0.1263
% Impedance = 0.1263*100

% Impedance = 12.63

b) Normal Tap

Impedance = ( Applied Voltage * Rated HV current)/( Rated HV voltage* HV measured current)


Impedance = (378.6*524.86) / (132000*12.37)
= 0.1217
( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

% Impedance = 0.1217*100

% Impedance = 12.17

c) Highest Tap

Impedance = ( Applied Voltage * Rated HV current)/( Rated HV voltage* HV measured current)


Impedance = (383.7*583.18) / (118800*15.67)
= 0.1202
% Impedance = 0.1202*100

% Impedance = 12.02

7) Insulation Resistance Measurement


a) Insulation Resistance Measurement of Windings (Using 5000 V Megger)

Top Oil Temperature: 35 ºC


IR Value (GΩ)
Dielectric
Polarization
Absorption
Index
Main Winding Coefficient
15 sec 60 sec 600 sec PI= 600 Sec /
DAI= 60 Sec /
60 Sec
15 Sec

Combination for Power transformer


9.53 13.6 45.5
a) HV / LV 1.42 3.34
b) HV / E 12.8 19.7 34.4 1.53 1.74
8.16 15.0 35.7
c) LV / E 1.83 2.38

b) Core Insulation Test (after oil Circulation)

Shorting link between Core - Core Clamp & Tank to be removed and IR value to be taken by applying
1000 V DC
Top Oil temperature: 35 °C

Terminals Insulation Value

Core/Frame >2GΩ

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

Core/Tank >2GΩ

Frame/Tank >2GΩ

Note:
i. Permissible value > 500 MΩ
ii. Ensure shorting of Core - Frame & Tank after the completion of the testing

8) Capacitance And Tanδ Measurement

a) Capacitance And Tanδ Measurement Of Bushings

BUSHING DETAILS

HIGH VOLTAGE SIDE


Details
R–Ø Y–Ø B–Ø
Make TRENCH FRANCE SAS TRENCH FRANCE SAS TRENCH FRANCE SAS
Type COT 650-1250 L300 COT 650-1250 L300 COT 650-1250 L300
Sl. No. 19B4550 19B4551 19B4549
Ambient Temperature: 35 °C

Test Capacitance (pF) Tan δ(%)


Bushing
Voltage Test Mode Site Value Factory Site Value Factory
Location
kV in pF Value (%) Value
5 UST 268.68 N/A 0.317 N/A
1U
10 UST 268.68 269.95 0.316 0.00332
5 UST 270.30 N/A 0.324 N/A
1V
10 UST 270.06 273.03 0.325 0.00373
5 UST 270.36 N/A 0.322 N/A
1W
10 UST 269.77 271.65 0.233 0.00342

Capacitance And Tanδ Measurement Of Windings Temperature: 30 °C

HIGH TAN DELTA


TEST TEST CAPACITANCE
VOLT
VOLT MOD
AGE
AGE E Site Value Factory Value Site Value Factory Value
ON In nF (pF) (%)
5 KV 9.457 N/A 0.0972 N/A
HV
UST
Side 10 KV 9.457 9112.0 0.0835 0.00200

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

5 KV 12.77 N/A 0.140 N/A


GST
10 KV 12.77 12784.0 0.141 0.002123
5 KV 3.316 N/A 0.374 N/A
GSTg
10 KV 3.317 3672.0 0.467 0.00244
5 KV 9.1469 N/A 0.169 N/A
UST
10 KV 9.1194 9112 0.190 0.00200
5 KV 25.65 N/A 0.206 N/A
LV
GST
Side 10 KV 25.56 25544.0 0.201 0.00267
5 KV 16.50 N/A 0.249 N/A
GSTg
10 KV 16.50 16431.0 0.233 0.00304

9) Measurement Of Winding Resistance (In mΩ)

Temperature (t): 30 °C

a) HV Winding

Measured Winding Resistance Winding Winding


Tap Avg. Resistance/Ph Resistance/Ph
Position 1U – 1W 1V – 1U 1W – 1V Resistance/Ph at 75°C (Site at 75°C(Fat
(Rt) value) value)
1 441.16 443.69 444.34 664.59 777.44 777.11
2 435.32 437.82 438.46 655.8 767.16 767.03
3 429.65 432.11 432.72 647.24 757.14 756.94
4 423.92 426.41 426.99 638.66 747.11 746.93
5 418.21 420.68 421.29 630.09 737.08 736.91
6 412.62 415.02 415.71 621.67 727.23 726.99
7 406.95 409.31 409.98 613.12 717.23 717.00
8 401.30 403.64 404.34 604.64 707.31 707.03
9 394.56 396.68 397.16 594.2 695.10 694.90
10 401.22 403.58 404.25 604.52 707.17 706.97
11 406.91 409.33 409.95 613.1 717.21 716.92
12 412.62 415.03 415.68 621.66 727.22 726.89
13 418.33 420.79 421.43 630.27 737.29 736.87
14 424.15 426.59 427.23 638.98 747.48 747.00
15 429.81 432.33 432.95 647.54 757.49 757.00
16 435.55 438.39 438.71 656.32 767.77 767.02
17 441.26 443.85 444.45 664.78 777.66 777.09

b) LV Winding
( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

Measured Winding Resistance Winding Winding


Tap Resistance/Ph Resistance/Ph
Avg.
Position 2U – 2N 2V – 2N 2W – 2N at 75°C(Site at 75°C(Fat
Resistance/Ph
value) value)
9b 10.89 10.88 10.88 10.88 12.72 12.71

Measured Winding Resistance Winding


Tap
Avg. Resistance/Ph at
Position 2U – 2V 2V – 2W 2W – 2U
Resistance/Ph 75°C
9b 21.71 21.76 21.74 21.73 25.42

NOTE: Formula for calculating the resistance at 75°C: R75 = Rt (235+75)/ (235+t),
Where Rt = Resistance Measured At Winding Temperature t.

11. Operational Tests and Checks of OLTC & Cooling Equipment’s

a) Test On OLTC

STATUS
SL.
DESCRIPTION NOT REMARKS
NO
OK OK
1 Visual inspection of equipment Yes  
2 Hand Operation at all Taps Yes    
3 Complete wiring of Circuit Yes
4 Limit switch Yes
5 Over Running Device Yes
6 Break System Yes
7 Remote Panel Wiring In Progress
8 Over load device of driving motor Yes    
9 Local operation (electrical) Yes
10 Remote operation (electrical)   In Progress
11 Tap position indicator Yes
12 Step by step contactor Yes
13 Out of step relay Yes
14 OLTC Continuity Test Yes

b) Checking of cooling Equipment’s

STATUS
SL. No DESCRIPTION NOT
OK
OK
1 Rotation direction of Pumps Yes
2 Rotation direction of Fans Yes
( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation:
SIEMENS Doc.No. GP TP NSW LPT STI CS/ 02/ B/ dated
01.08.2019

12. Protection And Alarms

SET FOR
SL.NO DEVICE
ALARM TRIP
1 Excessive winding temperature Yes
2 Excessive oil temperature Yes
3 Oil flow failure  Yes
4 Pressure relief valve  Yes
5 Main tank Buchholz relay  Yes
6 OLTC Buchholz relay  Yes
7 Fan failure  Yes
8 Low oil level (MOG)  Yes
9 On line DGA N/A

( Siemens ) (PGCB)
Signature: Signature:
Name: Name:
Designation: Designation: