Problem Solving M7
Problem Solving M7
Network Diagram
Find the least time required to complete the whole project and identify the critical activities.
How is the project completion time affected if?
a. Activity F is delayed by 3 days?
Because Activity F is one of the critical activities, if it is delayed by 3 days, the
project's overall duration would increase by 3 days, therefore instead of 38 days, the
total project duration will be 41 days. This is because Activity F is on the critical path,
which suggests that crucial activities, as opposed to non-critical activities, will have a
major impact on the project's completion timetable.
Project Network
Critical Path = Path with the Longest Time to Complete the Project
Critical Path = 1-3-5-7-8-9-11
3. Draw a network diagram for the following project and find the critical path and critical
activities and project duration.
15 Days
Start 0 0 0 0 0
A 2 0 5,000 0 5,000
D 6 0 1,704 0 1,704
E 5 2 4,000 2,000 8,000
J 7 0 11,620 0 11,620
Finish 0 0 0 0 0
12 days
Start 0 0 0 0
A 2 0 5,000 5,000
C 5 0 3,135 3,135
D 6 0 1,704 1,704
E 5 0 4,000 4,000
G 6 0 876 876
H 4 0 864 864
I 5 0 6,615 6,615
J 7 0 11,620 11,620
Finish 0 0 0 0
Path
1. How much will be the additional cost if the project is to be completed in 15 days? What
activities need to be crashed?
There will be no additional expense if we pursue the activities of A-D-J and B-E-J
because they are already covered by the 15-day working week. However, because
activities A-C-J-I, A-C-H-J, and B-F are on the critical path, they will be crashed,
resulting in an additional cost of 13,546.50 for the project.
2. Can the project be completed in 12 days? Why/Why not? If it can, what activities need
to be crashed at what additional costs?